About this opportunity
The State of Utah Division of Purchasing, conducting through Wildlife Resources, is requesting bids under IFB BD26-74 for wetland dike maintenance and bank stabilization on approximately 400 linear feet of eroding dike in Penrose, Utah, with bids due June 11, 2026 and all work to be completed by June 30, 2026.
The scope requires repair of significant erosion damage, restoration of structural integrity, and installation of protective armoring. Work includes crest repair to uniform 12-foot width; pipe correction and realignment; slope stabilization to 3:1 ratio on both sides with proper compaction in 6-inch lifts and benching; application of 4 inches of compacted 1-inch minus road base with 2% crown to the top surface; and installation of 6- to 10-inch fractured angular rock armoring at minimum 12-inch thickness extending at least 2 feet below standard water line. Estimated quantities: 240–260 cubic yards of fill dirt, 60–70 cubic yards of pit run road base, and 375–400 cubic yards of slope riprap. Contractors must source and deliver all materials, handle site preparation and cleanup, and cover all mobilization costs.
Contractor eligibility requires a minimum of five years' experience performing similar work in Utah, current insurance in the state, and possession or ability to secure all necessary equipment including data-logging GPS capability. A pre-work conference is mandatory before groundwork begins. Contractors must maintain equipment mobilized and dedicated to the project until all phases are 100% complete and guarantee pricing through June 30, 2026.
The contract term runs from award until June 30, 2026. Award will be made to the lowest cost responsive and responsible vendor. Responses must be submitted electronically through the U3P platform. Vendors may not commence work, purchase materials, or enter subcontracts until receiving a fully executed purchase order or contract.
Opportunity text
Issuing Procurement Unit: State of Utah Division of Purchasing Conducting Procurement Unit: Wildlife Resources The purpose of this IFB is to enter into a contract to provide: Perform maintenance and bank stabilization on approximately 400 linear feet of dike to repair significant erosion damage, restore structural integrity, and install protective armoring to prevent further degradation in Penrose, Utah. Work must be completed and invoice submitted by June 30th, 2026. It is anticipated that this IFB will result in a single contract award to the lowest cost responsive and responsible vendor. Length of Contract: From time of award until June 30th, 2026. Vendor must guarantee its pricing for the duration of the project.
Files
| File | Type | Posted |
|---|---|---|
| 1-Vendor Prerequisites - IFB Agency.pdf | ||
| 2-ATT B Scope of Work BD26-74 Dike Maintenance FY26.pdf |