Z2DA--657-21-117JB, Correct Deficiencies Identified During Triennial Testing Phase 2
Closed Pre-Solicitation Posted
A newer solicitation was posted. See the latest solicitation from .
- Solicitation number
- 36C25525R0041
- Agency
- Veterans Integrated Service Network 15 Veterans Health Administration, Department of Veterans Affairs
- Responses due
- Set-aside
- Service-Disabled Veteran-Owned Small Business
Opportunity facts
- NAICS code
- 238210 Electrical Contractors and Other Wiring Installation Contractors
- Place of performance
- St louis Jefferson Barracks 1 Jefferson Barracks Drive6 St. Louis MO 63125, United States
- Points of contact
-
- Jenna Hill jennifer.hill@va.gov (913) 946-1144
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of Veterans Affairs (VA) Veterans Health Administration is seeking a construction contractor to correct electrical deficiencies at the St. Louis Health Care System's Jefferson Barracks Division. The project involves removing and replacing electrical equipment in Buildings 18, 51, and 53, including transformers, panels, and automatic transfer switches, with specific requirements for equipment installation, safety protocols, and code compliance. Contractors must create a Gantt chart for project phasing, adhere to VA TIL specifications, follow OSHA safety regulations, and implement infection control protocols. The contract will be awarded using a Best Value-Tradeoff source selection method, with contractors required to be registered in SAM and VetCert. The response deadline is February 21, 2025, at 10:00 AM Central Time, with a specified response method and documentation requirements.
The opportunity is set aside exclusively for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under NAICS code 238210, with a size standard of $19 million. The estimated contract value ranges between $100-150 million, with a contract performance period of 150 calendar days after notice to proceed. Contractors must perform at least 25% of the work under the specified NAICS category and be prepared to handle complex electrical infrastructure modifications. The project involves critical electrical infrastructure upgrades, including replacing a 300kVA transformer at Building 18, relocating and replacing panels in Building 51's basement mechanical rooms, and replacing a 750kVA transformer at Building 53. Contractors will be responsible for proper disposal and recycling of removed equipment, with documentation required to demonstrate compliance with state and federal regulations.
Notice text
VA St. Louis Health Care System
Statement of Work: 657-21-117JB, Phase 2
Correct Deficiencies Identified During Triennial Testing
January 23, 2025
Purpose of Project:
The VA St. Louis Health Care System, Jefferson Barracks Division, will correct various electrical deficiencies in buildings 18, 51, and 53, and outside buildings 18, and 53.
Statement of Work:
The Construction firm must provide construction services as delineated in the Plans and Specifications. This project will correct deficiencies with some VA electrical equipment. New equipment shall have all the required working clearances, according to current electrical codes.
Building 18: Remove and replace outside 300kVA transformer T18-A, construct cast-in-place reinforced concrete pad, per plans and specifications, and manufacturer s recommendations.
Building 51:
Remove and replace Panels MDP-51A in Basement Mechanical Room BA101, construct cast-in-place reinforced concrete housekeeping pad, per plans and specifications, and manufacturer s recommendations.
Remove and replace Panels MSB-51A in Basement Mechanical Room BA100, construct cast-in-place reinforced concrete housekeeping pad, per plans and specifications, and manufacturer s recommendations.
Remove ATS-51A from Basement Mechanical Room BA101, and move to Basement Mechanical Room BA100, in Basement Mechanical area, construct cast-in-place reinforced concrete housekeeping pad, per plans and specifications, and manufacturer s recommendations.
Building 53: Remove and replace outside 750kVA transformer, construct cast-in-place reinforced concrete pad, per plans and specifications, and manufacturer s recommendations.
At the beginning of the project, the Contractor will create a Gantt chart or similar spreadsheet to indicate project phasing and supply it to the COR. The contractor shall be responsible for updating the spreadsheet as the project progresses.
All work shall comply with the VA TIL specifications.
All Contractor personnel shall wear the proper safety equipment required by all applicable VA Safety regulations and OSHA to accomplish this type of work.
All work shall comply with all VA health care provisions, such as ICRA (Infection Control Risk Assessment) provisions, ILSM, and all applicable State, National, and U.S. Federal Codes.
For all items removed by this Statement of Work, the Contractor shall be responsible for the safe and legal disposal or recycle of all items listed. The Contractor will have signed paperwork from the disposal site or recycle center indicating all removed items are disposed of properly and in accordance with all applicable State and Federal Codes and Laws.
All outside equipment installed through this project shall adhere to National Electrical Code (NEC) Outdoors section 10.26(F)(2).
Attachments
| File | Type | Posted |
|---|---|---|
| 36C25525R0041.docx | DOCX document |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Z2DA--657-21-117JB, Correct Deficiencies Identified During Triennial Testing Phase 2 | Solicitation | |
| Z2DA--657-21-117JB, Correct Deficiencies Identified During Triennial Testing Phase 2 | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity