About this opportunity
Paragraph 1:
This solicitation is for the renovation of the Fisher House located at the Samuel S. Stratton Albany VA Medical Center in Albany, New York. The Department of Veterans Affairs is seeking a contractor to provide all labor, materials, and travel necessary to renovate seven bedrooms, the upstairs hallway, and first-floor common areas. The scope of work includes removing and replacing flooring, painting walls and ceilings, renovating bathrooms, and refinishing hardwood floors. The contractor must work with the Fisher House Interior Designer to select appropriate finishes and fixtures to create a warm, comfortable atmosphere. The work must be substantially completed within 90 calendar days of receiving the notice to proceed, and the contractor will be expected to coordinate closely with the VA's Contracting Officer's Representative throughout the project.
Paragraph 2:
This solicitation is not set-aside for any specific business type. The NAICS code is 236220 (Commercial and Institutional Building Construction) and the PSC code is Y1ET (Construction of Buildings, Nonresidential). There is no incumbent contractor identified, and the government has not provided a specific award value or budget range. However, the solicitation states the contractor shall provide all labor, materials, and travel necessary to complete the renovation project. The place of performance is the Samuel S. Stratton Albany VA Medical Center in Albany, New York.
Notice text
4 versions
Update #4 · Latest ·
REVISION
RFI #1
Fisher House Project
(1) During the walkthrough it was discussed that the Interior Designer will be selecting furnishes for the Contractor to install: Please provide which materials are being provided by the VA and which materials the Contractor will be purchasing to allow accurate takeoff.
Answer: Specific fixtures, tile, flooring, paint colors, and any other such items will be selected and determined through the submittal process. Requirements that must be met are detailed in the specifications.
(2) Please clarify whether existing furniture will be removed from Fisher House and stored by the VA or whether Contractor will be responsible for moving all furniture from work areas and storing (and whether VA will provide storage or if Contractor is to provide storage).
Answer: We will turn over the entire space, furniture will be removed by the VA before work starts.
(3) Has there been any asbestos testing on tile and existing material; is there any asbestos expected in the Fisher House?
Answer: We are testing now, for bidding purposes assume no asbestos is present.
(4) From our understanding the current flooring is engineered so we cannot refinish. Will the current floor in the dining room be replaced with hardwood or LVT?
Answer: Dining room flooring is hardwood as is the rest of the first-floor common areas except kitchen.
(5) Are they provided with exact models and quantities in the RFI?
Answer:
(6) Will the shower be curb less for ADA accessibility?
Answer: Yes
(7) Will we be required to put up wall art, mirrors, decor accessories, etc.?
Answer: Yes
(8) Will vent caps get changed?
Answer: Yes
(9) Will we be required to remove all furniture/fixtures that are currently there?
Answer: All furniture will be removed by the VA
(10) If so, are they getting disposed of or stored?
Answer: N/A See (9)
(11) Are shop drawings required at the time of submission? If so, who will provide the plan?
Answer: No, but selected contractor will have to provide submittals for approval.
(12) How will payments be processed? (Net 30, after completion, or 20% deposit then rest of payment after completion)?
Answer: Progress payments will be authorized as per the percentage of completion according to the schedule of values.
(13) Please provide specifications or basis of design for:
a. Prefinished hardwood flooring. --- Must meet the NWFA/NOFMA International Standards for
Factory Finished Solid Wood Flooring
b. Ceramic floor tile. --- Spec Section 09 30 13
c. Wood trim. --- Spec Section 09 91 00
d. Light fixtures. --- Spec Section 26 51 00
e. Plumbing fixtures Spec Section 22 05 11 & Spec Section 22 40 00
f. Bathroom vanity--- Spec Section 22 40 00
g. Bathroom accessories Spec Section 10 28 00
h. Glass shower doors. ---Must be ADA compliant.
i. Refinishing hardwood floors. --- Spec Section 09 91 00
Update #3 ·
AMENDMENT 0002
The purpose of this amendment is to extend the bid opening date FROM April 04, 2024, TO April 17, 2024. Bids are due by 11:00am, and the bid opening will at 11:30am.
Update #2 ·
RFI #1
Fisher House Project
(1) During the walkthrough it was discussed that the Interior Designer will be selecting furnishes for the Contractor to install: Please provide which materials are being provided by the VA and which materials the Contractor will be purchasing to allow accurate takeoff.Â
Answer: Designer will be picking out fixtures, tile, paint colors, and any other decorative items needed to support the new furniture. They will need to know from the contractor what brands/price point they have included in your bid so they do not go over budget.
(2) Please clarify whether existing furniture will be removed from Fisher House and stored by the VA or whether Contractor will be responsible for moving all furniture from work areas and storing (and whether VA will provide storage or if Contractor is to provide storage).
Answer: The VA will NOT provide storage. Storage is on the contractor to provide.
(3) Has there been any asbestos testing on tile and existing material; is there any asbestos expected in the Fisher House?
Answer: We are testing now.
(4) From our understanding the current flooring is engineered so we cannot refinish. Will the current floor in the dining room be replaced with hardwood or LVT?
Answer: Dining room flooring is hardwood as is the rest of the first-floor common areas except kitchen.
(5) Are they provided with exact models and quantities in the RFI?
Answer: Designer will be picking out fixtures, tile, paint colors, and any other decorative items needed to support the new furniture. They will need to know from the contractor what brands/price point they have included in your bid so they do not go over budget.
(6) Will the shower be curb less for ADA accessibility?
Answer: Yes
(7) Will we be required to put up wall art, mirrors, decor accessories, etc.?
Answer: Yes
(8) Will vent caps get changed?
Answer: Yes
(9) Will we be required to remove all furniture/fixtures that are currently there?
Answer: Yes
(10) If so, are they getting disposed of or stored?
Answer: Disposition of items is yet to be determined.
(11) Are shop drawings required at the time of submission? If so, who will provide the plan?
Answer: No, but selected contractor will have to provide submittals for approval.
(12) How will payments be processed? (Net 30, after completion, or 20% deposit then rest of payment after completion)?
Answer: Progress payments will be authorized as per the percentage of completion according to the schedule of values.
(13) What material and fixtures will be purchased by the interior designer and what materials will be purchased by us?
Answer: See answer to question #1.
(14) Please provide specifications or basis of design for:
Prefinished hardwood flooring
Ceramic floor tile
Wood trim
Light fixtures
Plumbing fixtures
Bathroom vanity
Bathroom accessories
Glass shower doors
Refinishing hardwood floors
Answer: Designer will be picking out fixtures, tile, paint colors, and any other decorative items needed to support the new furniture. They will need to know from the contractor what brands/price point they have included in your bid so they do not go over budget.
Update #1 ·
NETWORK CONTRACTING OFFICE 2
Albany/Bath/Bronx/Canandaigua/Northport/Syracuse Medical Centers
Hudson Valley/New Jersey/New York Harbor Healthcare Systems
WNY Upstate New York Healthcare System
STATEMENT OF WORK
Fisher House Renovate
Bldg. 56 VAMC, 113 Holland Ave., Albany, NY
I. BACKGROUND AND PROJECT DESCRIPTION
The Samuel S. Stratton Albany VA Medical Center Fisher House is currently seeking to renovate the interior of the Fisher House.
The items for the Scope of Work in the Fisher house include, but not limited to the following:
Contractor shall provide all labor, materials, and travel to renovate seven (7) bedrooms this will include
Removing @2,700 sq ft of carpet and installing prefinished hardwood flooring.
Patch and paint @400 sq ft of ceilings
Patch and paint @12,000 sq ft of walls
Paint 20 doors.
Replace light fixtures
Install and finish @550 lin ft of baseboard and shoe base trim
Renovate existing bathrooms 1 in each room. To include
Remove existing tub enclosure.
Install walk in shower.
Install new shower trim kit
Tile @450 sq ft of floors
Install new vanity. (Handicap accessible in rooms 1 and 2)
Install new toilet
Install new faucet
Remove wallpaper (rooms 6 and 7)
Repair wallboard as necessary
Install new baseboard and shoe base trim
Paint @1,900sq ft of wall
Paint @400 sq ft of ceilings
Paint @9-bathroom doors
Install new bath accessories
Install new glass shower doors installed.
Contractor shall provide all labor, materials, and travel to renovate Upstairs hallway and first floor common areas. This will include.
Remove wallpaper and chair rail in Foyer and Dining Room
Patch and paint @1,300 sq ft of walls.
Patch and paint @500 sq ft of ceilings.
Refinish @1400 sq ft of hardwood flooring.
The contractor shall work with the Fisher House Interior Designer for appropriate selection of higher-end finishes and light fixtures to accomplish a warm, more comforting atmosphere to the area.
II. ADDITIONAL INFORMATION
The Contractor shall provide all labor, supervision, and materials necessary to perform the work as indicated in this scope of work, and project specifications attached. The Contractor shall make every effort to maintain the existing conditions that are not part of the project. In addition to following FAR 52.236-9, Protection of Existing, Structures, Equipment, Utilities, and Improvements the Contractor shall remove or alter existing work in such a manner to prevent injury or damage to any portions of the existing work, which is to remain. The Contractor shall repair or replace portions of the existing work, which have been altered or damaged during construction operations to match existing or adjoining work, as approved by the Contracting Officer and at no cost to the government. At the completion of operations, the existing work shall be in a condition equal to or better than that which existed before new work started.
The Contractor shall verify all existing conditions on the site and in the facility infrastructure that the proposed project may affect before the commencement of any construction. This includes but is not limited to, verifying the locations and elevations of existing utilities, verifying site items as shown on the any applicable project drawings and taking appropriate field measurements. The government will not be held responsible for bidding errors made or the failure to adequately inspect the job site for existing conditions, dimensions or to fully review manufacturer s information related to the project. All bidders are strongly encouraged to inspect the job site prior to submitting bids.
All discrepancies between the specifications and manufacturer s recommendations shall be brought to the attention of the Contracting Officer s Representative prior to the commencement of work. The Contractor shall abide by the Scope of Work regardless of whether or not a manufacturer calls for the task, level of preparation, etc. in question. The only exception is where the Contracting Officer agrees in writing that the item or task specifically voids a manufacturer s warranty and may be omitted. A credit for the work not performed may be due to the government in such circumstances at the discretion of the Contracting Officer.
For this project the C&A requirements do not apply, and that a Security Accreditation Package is not required.
III. SCHEDULES
The work shall be substantially complete no later than 90 calendar days after receipt of the Notice to Proceed unless otherwise agreed to in writing with the Contracting Officer. Provide the government a construction project timeline that includes but is not limited to submittal submission dates, start of construction, milestones, completion of construction, and final hand over to government for occupancy that is less than or equal to 90 calendar days.
IV. CONTRACTOR PERFORMANCE
Use good construction practices and standards in completing all work. All work shall be performed by laborers that are fully versed and experienced in the trade that they are employed to do. Coordination with the government, of project and scheduled items, shall be a regular occurrence, initiated by the Contractor.
The VA s Contracting Officer s Representative shall monitor all work done during the project duration. The Contractor will immediately correct any work that the Contracting Officer s Representative deems unacceptable or not in accordance with the plans or specifications.
Files
| File | Type | Posted |
|---|---|---|
| 36C24224B0019 0003.docx | DOCX document | |
| Spec Package Rev 1.pdf | ||
| 36C24224B0019 0002.docx | DOCX document | |
| 36C24224B0019 0001.docx | DOCX document | |
| (P07) Wage Determination.pdf | ||
| Spec package.pdf | ||
| FAR 52.225-2 Buy American Certification.pdf | ||
| A-3 Drawing.pdf | ||
| 36C24224B0019.docx | DOCX document | |
| FH Rm info and floor plans.pdf | ||
| 852.219-77 VA Notice of Limitations on Subcontracting.docx | DOCX document | |
| A-2 Drawing.pdf |
Show all 12
Notice history
| Notice | Type | Posted |
|---|---|---|
| Z1DA--fisher house renovations | Award Notice | |
| This notice | Solicitation | |
| Z1DA--fisher house renovations | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Z2DA--Renovate Space for Patient Care Improvements | Veterans Integrated Service Network 6 | Service-Disabled Veteran-Owned Small Business | |
| Z1DA--528A8-22-814 Consolidate Primary Care Reception | Veterans Integrated Service Network 2 | Service-Disabled Veteran-Owned Small Business | |
| C1DA--578-27-003 - Renovate A Section First Floor of Building 1 - Design FY27 | Veterans Integrated Service Network 12 | Service-Disabled Veteran-Owned Small Business | |
| Z2DA--612A4-27-018 | Replace B650 3rd and 2nd Flooring | Veterans Integrated Service Network 21 | Service-Disabled Veteran-Owned Small Business | |
| Y1DA--FY27 NRM | 619-24-103 | Replace Flooring & Repair Walls in Building 1 (VA-27-00012190) | Veterans Integrated Service Network 7 | Service-Disabled Veteran-Owned Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity