Spec Package Rev 1.pdf

PDF 426 KB Posted

Attached to
Z1DA--FISHER HOUSE RENOVATIONS
Solicitation number
36C24224B0019
Issued by

About this file

This document is a Solicitation for a construction project to renovate the interior of a Fisher House located at the Albany VA Medical Center in New York. The key details are:

The project scope includes renovating 7 bedrooms, the upstairs hallway, and first floor common areas. Work will include removing and replacing flooring, painting walls and ceilings, renovating bathrooms, and refinishing hardwood floors. The contractor will work with the Fisher House Interior Designer to select higher-end finishes and light fixtures to create a more comfortable atmosphere. The contractor shall provide all labor, materials, and travel necessary to complete the work within 90 calendar days after the Notice to Proceed, unless otherwise agreed to in writing with the Contracting Officer. Coordination with the government's Contracting Officer's Representative and use of good construction practices are required. Any unacceptable work must be immediately corrected by the contractor.

View the file

Other files

File Type Posted
36C24224B0019 0003.docx DOCX document
36C24224B0019 0002.docx DOCX document
36C24224B0019 0001.docx DOCX document
Spec package.pdf PDF
FAR 52.225-2 Buy American Certification.pdf PDF
FH Rm info and floor plans.pdf PDF
A-3 Drawing.pdf PDF
(P07) Wage Determination.pdf PDF
36C24224B0019.docx DOCX document
852.219-77 VA Notice of Limitations on Subcontracting.docx DOCX document
A-2 Drawing.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

04-01-22

01 74 19 - 1

SECTION 01 74 19

CONSTRUCTION WASTE MANAGEMENT

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies the requirements for the management of non-hazardous building construction and demolition waste.

B. Waste disposal in landfills shall be minimized to the greatest extent possible. Of the inevitable waste that is generated, as much of the waste material as economically feasible shall be salvaged, recycled or reused.

C. Contractor shall use all reasonable means to divert construction and demolition waste from landfills and incinerators, and facilitate their salvage and recycle not limited to the following:

D. Waste Management Plan development and implementation.

E. Techniques to minimize waste generation.

F. Sorting and separating of waste materials.

G. Salvage of existing materials and items for reuse or resale.

H. Recycling of materials that cannot be reused or sold.

I. At a minimum the following waste categories shall be diverted from landfills:

1. Soil.

2. Inerts (e.g., concrete, masonry, and asphalt).

3. Clean dimensional wood and palette wood.

4. Green waste (biodegradable landscaping materials).

5. Engineered wood products (plywood, particle board and I-joists, etc.).

6. Metal products (e.g., steel, wire, beverage containers, copper, etc.).

7. Sheathings

8. Cardboard, paper, and packaging.

9. Bitumen roofing materials.

10. Plastics (e.g., ABS, PVC).

11. Carpet and/or pad.

12. Gypsum board.

13. Insulation.

14. Paint.

15. Fluorescent lamps.

01 74 19 - 2

1.2 RELATED WORK

A. Section 02 41 00, DEMOLITION.

B. Section 01 00 00, GENERAL REQUIREMENTS.

1. //C. Lead Paint: Section 02 83 33.13, LEAD BASED PAINT REMOVAL AND

DISPOSAL.//

2. //D. Division 1 Sustainability specifications//

1.3 QUALITY ASSURANCE

A. Contractor shall practice efficient waste management when sizing, cutting and installing building products. Processes shall be employed to ensure the generation of as little waste as possible. Construction

/Demolition waste includes products of the following:

1. Excess or unusable construction materials.

2. Packaging used for construction products.

3. Poor planning and/or layout.

4. Construction error.

5. Over ordering.

6. Weather damage.

7. Contamination.

8. Mishandling.

9. Breakage.

B. Establish and maintain the management of non-hazardous building construction and demolition waste set forth herein. Conduct a site assessment to estimate the types of materials that will be generated by demolition and construction.

C. Contractor shall develop and implement procedures to recycle construction and demolition waste to a minimum of //50// // // percent.

D. Contractor shall be responsible for implementation of any special programs involving rebates or similar incentives related to recycling.

Any revenues or savings obtained from salvage or recycling shall accrue to the contractor.

E. Contractor shall provide all demolition, removal and legal disposal of materials. Contractor shall ensure that facilities used for recycling, reuse and disposal shall be permitted for the intended use to the extent required by local, state, federal regulations.

F. Contractor shall assign a specific area to facilitate separation of materials for reuse, salvage, recycling, and return. Such areas are to

01 74 19 - 3 be kept neat and clean and clearly marked in order to avoid contamination or mixing of materials.

G. Contractor shall provide on-site instructions and supervision of separation, handling, salvaging, recycling, reuse and return methods to be used by all parties during waste generating stages.

H. Record on daily reports any problems in complying with laws, regulations and ordinances with corrective action taken.

1.4 TERMINOLOGY

A. Class III Landfill: A landfill that accepts non-hazardous resources such as household, commercial and industrial waste resulting from construction, remodeling, repair and demolition operations.

B. Clean: Untreated and unpainted; uncontaminated with adhesives, oils, solvents, mastics and like products.

C. Construction and Demolition Waste: Includes all non-hazardous resources resulting from construction, remodeling, alterations, repair and demolition operations.

D. Dismantle: The process of parting out a building in such a way as to preserve the usefulness of its materials and components.

E. Disposal: Acceptance of solid wastes at a legally operating facility for the purpose of land filling (includes Class III landfills and inert fills).

F. Inert Backfill Site: A location, other than inert fill or other disposal facility, to which inert materials are taken for the purpose of filling an excavation, shoring or other soil engineering operation.

G. Inert Fill: A facility that can legally accept inert waste, such as asphalt and concrete exclusively for the purpose of disposal.

H. Inert Solids/Inert Waste: Non-liquid solid resources including, but not limited to, soil and concrete that does not contain hazardous waste or soluble pollutants at concentrations in excess of water-quality objectives established by a regional water board, and does not contain significant quantities of decomposable solid resources.

I. Mixed Debris: Loads that include commingled recyclable and non-recyclable materials generated at the construction site.

J. Mixed Debris Recycling Facility: A solid resource processing facility that accepts loads of mixed construction and demolition debris for the purpose of recovering re-usable and recyclable materials and disposing non-recyclable materials.

01 74 19 - 4

K. Permitted Waste Hauler: A company that holds a valid permit to collect and transport solid wastes from individuals or businesses for the purpose of recycling or disposal.

L. Recycling: The process of sorting, cleansing, treating, and reconstituting materials for the purpose of using the altered form in the manufacture of a new product. Recycling does not include burning, incinerating or thermally destroying solid waste.

1. On-site Recycling – Materials that are sorted and processed on site for use in an altered state in the work, i.e. concrete crushed for use as a sub-base in paving.

2. Off-site Recycling – Materials hauled to a location and used in an altered form in the manufacture of new products.

M. Recycling Facility: An operation that can legally accept materials for the purpose of processing the materials into an altered form for the manufacture of new products. Depending on the types of materials accepted and operating procedures, a recycling facility may or may not be required to have a solid waste facilities permit or be regulated by the local enforcement agency.

N. Reuse: Materials that are recovered for use in the same form, on-site or off-site.

O. Return: To give back reusable items or unused products to vendors for credit.

P. Salvage: To remove waste materials from the site for resale or re-use by a third party.

Q. Source-Separated Materials: Materials that are sorted by type at the site for the purpose of reuse and recycling.

R. Solid Waste: Materials that have been designated as non-recyclable and are discarded for the purposes of disposal.

S. Transfer Station: A facility that can legally accept solid waste for the purpose of temporarily storing the materials for re-loading onto other trucks and transporting them to a landfill for disposal, or recovering some materials for re-use or recycling.

1.5 SUBMITTALS

A. In accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and

SAMPLES, furnish the following:

B. Prepare and submit to the COR a written demolition debris management plan. The plan shall include, but not be limited to, the following information:

01 74 19 - 5

1. Procedures to be used for debris management.

2. Techniques to be used to minimize waste generation.

3. Analysis of the estimated job site waste to be generated:

a. List of each material and quantity to be salvaged, reused, recycled.

b. List of each material and quantity proposed to be taken to a landfill.

4. Detailed description of the Means/Methods to be used for material handling.

a. On site: Material separation, storage, protection where applicable.

b. Off site: Transportation means and destination. Include list of materials.

1) Description of materials to be site-separated and self-hauled to designated facilities.

2) Description of mixed materials to be collected by designated waste haulers and removed from the site.

a) The names and locations of mixed debris reuse and recycling facilities or sites.

b) The names and locations of trash disposal landfill facilities or sites.

c) Documentation that the facilities or sites are approved to receive the materials.

C. Designated Manager responsible for instructing personnel, supervising, documenting and administer over meetings relevant to the Waste

Management Plan.

D. Monthly summary of construction and demolition debris diversion and disposal, quantifying all materials generated at the work site and disposed of or diverted from disposal through recycling.

E. Target waste diversion rate by material and an overall diversion rate.

F. Final report documenting the results of implementation of the preconstruction waste management plan.

1.6 APPLICABLE PUBLICATIONS

A. Publications listed below form a part of this specification to the extent referenced. Publications are referenced by the basic designation only. In the event that criteria requirements conflict, the most stringent requirements shall be met.

01 74 19 - 6

B. U.S. Green Building Council (USGBC): LEED Green Building Rating System for New Construction

1. Green Building Initiative (GBI): Green Globes for New Construction

1.7 RECORDS

A. Maintain records to document the quantity of waste generated; the quantity of waste diverted through sale, reuse, or recycling; and the quantity of waste disposed by landfill or incineration. Records shall be kept in accordance with the LEED Reference Guide and LEED Template

PART 2 - PRODUCTS

2.1 MATERIALS

A. List of each material and quantity to be salvaged, recycled, reused.

B. List of each material and quantity proposed to be taken to a landfill.

C. Material tracking data: Receiving parties, dates removed, transportation costs, weight tickets, tipping fees, manifests, invoices, net total costs or savings.

PART 3 - EXECUTION

3.1 COLLECTION

A. Provide all necessary containers, bins and storage areas to facilitate effective waste management.

B. Clearly identify containers, bins and storage areas so that recyclable materials are separated from trash and can be transported to respective recycling facility for processing.

C. Hazardous wastes shall be separated, stored, disposed of according to local, state, federal regulations.

3.2 DISPOSAL

A. Contractor shall be responsible for transporting and disposing of materials that cannot be delivered to a source-separated or mixed materials recycling facility to a transfer station or disposal facility that can accept the materials in accordance with state and federal regulations.

B. Construction or demolition materials with no practical reuse or that cannot be salvaged or recycled shall be disposed of at a landfill or incinerator.

3.3 REPORT

A. With each application for progress payment, submit a summary of construction and demolition debris diversion and disposal including beginning and ending dates of period covered.

01 74 19 - 7

B. Quantify all materials diverted from landfill disposal through salvage or recycling during the period with the receiving parties, dates removed, transportation costs, weight tickets, manifests, invoices.

Include the net total costs or savings for each salvaged or recycled material.

C. Quantify all materials disposed of during the period with the receiving parties, dates removed, transportation costs, weight tickets, tipping fees, manifests, invoices. Include the net total costs for each disposal.

- - - E N D - - -

01-01-21

10 28 00 - 1

SECTION 10 28 00

TOILET, BATH, AND LAUNDRY ACCESSORIES

PART 1 - GENERAL

1.1 DESCRIPTION

A. SUMMARY:

1. Section Includes: Toilet and bath accessories at dressing rooms, toilets, baths, locker rooms and other areas indicated on drawings.

1.2 RELATED WORK

A. Section 09 30 13, CERAMIC/PORCELAIN TILING: Ceramic Toilet and Bath

Accessories.

1.3 APPLICABLE PUBLICATIONS

A. Comply with references to extent specified in this section.

B. American Society of Mechanical Engineers (ASME):

1. B18.6.4-98(R2005) Thread Forming and Thread Cutting Tapping

Screws and Metallic Drive Screws inch.

C. American Welding Society (AWS):

D10.4-86(2000)..........Welding Austenitic Chromium-Nickle Stainless

Steel Piping and Tubing.

D. ASTM International (ASTM):

A269/A269M-15a(2019)....Seamless and Welded Austenitic Stainless Steel

Tubing for General Service.

A312/A312M-19...........Seamless, Welded, and Heavily Cold Worked

Austenitic Stainless Steel Pipes.

A653/A653M-20...........Steel Sheet, Zinc-Coated (Galvanized) or

Zinc-Iron Alloy-Coated (Galvannealed) by the

Hot-Dip Process.

A666-15.................Annealed or Cold-Worked Austenitic Stainless

Steel Sheet, Strip, Plate, and Flat Bar.

A1011/A1011M-18a........Steel, Sheet and Strip, Hot-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low-Alloy with Improved

Formability, and Ultra-High Strength.

B30-20..................Copper Alloys in Ingot Form.

B75/B75M-20.............Seamless Copper Tube.

B221-14.................Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes.

10 28 00 - 2

B221M-13................Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes (Metric).

B456-17.................Electrodeposited Coatings of Copper Plus Nickel

Plus Chromium and Nickel Plus Chromium.

B824-17.................General Requirements for Copper Alloy Castings.

C1036-16................Flat Glass.

C1048-18................Heat-Strengthened and Fully Tempered Flat

Glass.

D635-18.................Rate of Burning and/or Extent and Time of

Burning of Plastics in a Horizontal Position.

F446-19.................Grab Bars and Accessories Installed in the

Bathing Area.

E. Federal Specifications (Fed. Spec.):

A-A-3002................Mirror, Glass.

FF-S-107C(2)............Screws, Tapping and Drive.

WW-P-541/8B(1)..........Plumbing Fixtures (Accessories, Land Use).

F. National Architectural Metal Manufacturers(NAAMM):

AMP 500-06..............Metal Finishes Manual.

1.4 SUBMITTALS

A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

B. Submittal Drawings:

1. Show size, configuration, and fabrication, anchorage and installation details.

2. Show mounting locations and heights.

C. Manufacturer's Literature and Data:

1. Description of each product.

2. Installation instructions.

D. Samples:

1. Full sized, complete assembly of each product specified.

2. Approved samples may be incorporated into project.

E. Certificates: Certify each product complies with specifications.

1. Soap dispensers: Certify soap dispensers are fabricated of material that will not be affected by liquid soap, aseptic detergents, and hexachlorophene solutions.

F. Operation and Maintenance Data:

1. Care instructions for each exposed finish product.

10 28 00 - 3

1.5 QUALITY ASSURANCE

A. Manufacturer Qualifications:

1. Regularly manufactures specified products.

1.6 DELIVERY

A. Deliver products in manufacturer's original sealed packaging.

B. Before installation, return or dispose of products within distorted, damaged, or opened packaging.

1.7 STORAGE AND HANDLING

A. Store products indoors in dry, weathertight facility.

B. Protect products from damage during handling and construction operations.

1.8 WARRANTY

A. Construction Warranty: FAR clause 52.246-21, "Warranty of

Construction."

PART 2 - PRODUCTS

2.1 MATERIALS

A. Aluminum: ASTM B221M (ASTM B221), Alloy 6063-T5 and Alloy 6463-T5.

B. Stainless Steel:

1. Plate Or Sheet: ASTM A666, Type 304, 0.8 mm (0.031 inch) thick unless otherwise specified.

2. Tubing: ASTM A269/A269M, Grade TP 304, seamless or welded.

3. Pipe: ASTM A312/A312M; Grade TP 304.

C. Steel Sheet: ASTM A653/A653M, zinc-coated (galvanized) coating designation G90.

D. Chrome Plating (Service Condition Number SC 2): ASTM B456.

E. Brass Castings: ASTM B30.

F. Copper:

1. Tubing: ASTM B75/B75M.

2. Castings: ASTM B824.

G. Glass:

1. ASTM C1036, Type 1, Class 1, Quality q2, for mirrors, and for mirror doors in medicine cabinets.

2. ASTM C1036, Type 1 Class 1 Quality q3, for shelves in medicine cabinets.

2.2 PRODUCTS - GENERAL

A. Basis of Design: Section 09 06 00, SCHEDULE FOR FINISHES.

B. Provide each product from one manufacturer.

10 28 00 - 4

C. Fed. Spec. WW-P-541/8B, Type IV, bars, surface mounted, Class 2, grab bars and complying with ASTM F446.

D. Fabricate from stainless steel or nylon coated steel, use one type throughout project:

1. Stainless steel: Grab bars, flanges, mounting plates, supports, screws, bolts, and exposed nuts and washers.

2. Nylon Coated Steel: Grab bars and flanges complete with mounting plates and fasteners.

2.3 SHOWER CURTAIN RODS

A. Stainless steel tubing, minimum 1.27 mm (0.050 inch) wall thickness, 32 mm (1-1/4 inch) outside diameter.

B. Flanges, stainless steel rings, 66 mm (2.6 inch) minimum outside diameter, with 2 holes opposite each other for 6 mm (1/4 inch) stainless steel fastening bolts. Provide set screw within curvature of each flange for securing rod.

2.4 CLOTHES HOOKS, ROBE OR COAT

A. Fabricate hook units from chromium plated brass with satin finish, or stainless steel, using 6 mm (1/4 inch) minimum thick stock, with edges and corners rounded smooth to thickness of metal, or 3 mm (1/8 inch) minimum radius.

B. Fabricate each unit as a double hook on a single shaft, integral with or permanently fastened to wall flange, provided with concealed fastenings.

2.5 TOWEL BARS

A. Fed. Spec. WW-P-541/8B, Type IV, Bar, Surface mounted; Class 1, towel.

B. Stainless steel, or chromium plated copper alloy.

C. Bar Length: 450 and 600 mm (18 and 24 inches.

D. Finish brackets and supports to match bar.

E. Fed. Spec. A-A-3002 metal frame; // chromium finished steel, // anodized aluminum, // or // stainless steel //.

F. Mirror Glass:

1. Minimum 6 mm (1/4 inch) thick.

2. Set mirror in a protective vinyl glazing tape.

G. Frames:

1. Channel or angle shaped section with face of frame minimum 9 mm

(3/8 inch) wide. Fabricate with square corners.

2. Metal Thickness 0.9 mm (0.035 inch).

3. Filler:

10 28 00 - 5

a. Where mirrors are mounted on walls having ceramic tile wainscots not flush with wall above, provide fillers contoured to conceal void between back of mirror and wall surface.

b. Fabricate fillers from same material and finish as mirror frame.

4. Attached Shelf for Mirrors:

a. Fabricate shelf of same material and finish as mirror frame.

b. Make shelf maximum 150 mm (6 inches) in depth, and extend full width of mirror.

c. Close ends and front edge of shelf to same thickness as mirror frame width.

d. Form shelf for aluminum framed mirror as integral part of bottom frame member.

e. Form stainless steel shelf with concealed brackets to attach to mirror frame.

H. Back Plate:

1. Fabricate backplate for concealed wall hanging from zinc-coated, or cadmium plated 0.9 mm (0.036 inch) thick sheet steel, die cut to fit face of mirror frame.

2. Provide set screw type theft resistant concealed fastening system for mounting mirrors.

I. Mounting Bracket:

1. Designed to support mirror tight to wall.

2. Designed to retain mirror with concealed set screw fastenings.

2.6 MEDICINE CABINETS

A. Fed. Spec. WW-P-541/8B, Type III Medicine cabinets, Style R, Recessed.

1. Mirror Glass: Minimum 5 mm (3/16 inch) thick. Set mirror in protective vinyl glazing tape.

2. Glass Shelves: Minimum 6 mm (1/4 inch) thick, with bulb-edges at front. Support shelves on adjustable aluminum brackets. Provide three shelves for each cabinet.

3. Cabinet Body: Fabricate from 0.9 mm (0.036 inch) thick sheet steel, with baked enamel finish, or 0.9 mm (0.036 inch) thick stainless steel. Form body in one piece, without seams, and with rounded inside corners.

B. Hinged Door:

1. Swing door.

2. Fabricate mirror door approximately 400 by 560 mm (16 by 22 inches).

10 28 00 - 6

3. Cabinet concealed when doors are closed.

4. Mirror Door Frame: Channel shape, 15 mm (0.060 inch) thick chromium plated brass, or 0.9 mm (0.036 inch) thick stainless steel.

5. Provide door with full length stainless steel piano hinge, magnetic or friction catches, rubber bumpers, and 90 degree restraining arm with spring type stop.

6. Toggle Bolts: For use in hollow masonry or frame construction.

7. Sex bolts: For through bolting on thin panels.

8. Expansion Shields: Lead or plastic for solid masonry and concrete substrate as recommended by accessory manufacturer to suit application.

9. Screws:

a. ASME B18.6.4.

b. Fed. Spec. FF-S-107, Stainless steel Type A.

C. Adhesive: As recommended by manufacturer to suit application.

PART 3 - EXECUTION

3.1 PREPARATION

A. Examine and verify substrate suitability for product installation.

1. Verify blocking to support accessories is installed and located correctly.

B. Verify location of accessories with Contracting Officer's

Representative.

3.2 INSTALLATION

A. Install products according to manufacturer's instructions and approved submittal drawings.

1. When manufacturer's instructions deviate from specifications, submit proposed resolution for Contracting Officer's Representative consideration.

B. Install grab bars according to ASTM F446.

C. Set work accurately, in alignment and where indicated, parallel or perpendicular as required to line and plane of surface. Install accessories plumb, level, free of rack and twist.

D. Install accessories to function as designed. Perform maintenance service without interference with performance of other devices.

E. Position and install dispensers, and other devices in countertops, clear of drawers, permitting ample clearance below countertop between devices, and ready access for maintenance.

10 28 00 - 7

F. Align mirrors, dispensers and other accessories even and level, when installed in battery.

G. Install accessories to prevent striking by other moving, items or interference with accessibility.

3.3 CLEANING

A. After installation, clean toilet accessories according to manufacturer’s instructions.

3.4 PROTECTION

A. Protect accessories from damage until project completion.

- - E N D - -

09 30 13 - 1

SECTION 09 30 13

CERAMIC/PORCELAIN TILING

A. This section specifies interior ceramic, porcelain and quarry tile, marble thresholds and window stools, terrazzo divider strips, waterproofing membranes for thin-set applications, crack isolation membranes, and tile backer board.

1.2 SUBMITTALS

A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT

DATA, AND SAMPLES.

B. Samples:

1. Base tile, each type, each color, each size.

2. Mosaic floor tile panels, 228 by 228 mm (9 by 9 inches), each type, color, size and pattern.

3. Paver tile, each size, type, color and pattern.

4. Quarry tile, each type, color, and size.

5. Porcelain tile, each type, color, patterns and size.

6. Wall (or wainscot) tile, each color, size and pattern.

7. Trim shapes, bullnose cap and cove including bullnose cap and base pieces at internal and external corners of vertical surfaces, each type, color, and size.

8. Therapeutic pool tile, panels 305 mm (12 inches) square, each type, size, color, typical lettering and special shapes.

C. Product Data:

1. Ceramic and porcelain tile, marked to show each type, size, and shape required.

2. Chemical resistant mortar and grout (epoxy and furan).

3. Cementitious backer unit.

4. Dry-set portland cement mortar and grout.

5. Divider strip.

6. Elastomeric membrane and bond coat.

7. Reinforcing tape.

8. Leveling compound.

9. Latex-portland cement mortar and grout.

10. Commercial portland cement grout.

11. Organic adhesive.

09 30 13 - 2

12. Slip resistant tile.

13. Waterproofing isolation membrane.

14. Fasteners.

D. Certification:

1. Master grade certificate, ANSI A137.1.

2. Manufacturer's certificates indicating that the following materials comply with specification requirements:

a. Chemical resistant mortar and grout (epoxy and furan).

b. Modified epoxy emulsion.

c. Commercial portland cement grout.

d. Cementitious backer unit.

e. Dry-set portland cement mortar and grout.

f. Elastomeric membrane and bond coat.

g. Reinforcing tape.

h. Latex-portland cement mortar and grout.

i. Leveling compound.

j. Organic adhesive.

k. Waterproof isolation membrane.

l. Factory back mounted tile documentation for suitability for application in wet area.

E. Installer Qualifications:

1. Submit letter stating installer’s experience.

1.3 DELIVERY AND STORAGE

A. Deliver materials in containers with labels legible and intact and grade-seals unbroken.

B. Store material to prevent damage or contamination.

1.4 QUALITY ASSURANCE

A. Installers to be from a company specializing in performing installation of products specified and have a minimum of three (3) years’ experience.

B. Each type and color of tile to be provided from a single source.

C. Each type and color of mortar, adhesive, and grout to be provided from the same source.

1.5 WARRANTY

A. Construction Warranty: Comply with FAR clause 52.246-21, “Warranty of

Construction”.

09 30 13 - 3

1.6 APPLICABLE PUBLICATIONS

A. Publications listed below form a part of this specification to the extent referenced. Publications are referenced in text by basic designation only.

B. American National Standards Institute (ANSI):

A10.20-06(R2016)........Safe Operating Practices for Tile, Terrazzo and

Marble Work

A108/A118/A136.1:2019...Installation of Ceramic Tile

A108.01-18..............Subsurfaces and Preparations by Other Trades

A108.02-19..............Materials, Environmental, and Workmanship

A108.1A-17..............Installation of Ceramic Tile in the Wet-Set

Method with Portland Cement Mortar

A108.1B-17..............Installation of Ceramic Tile on a Cured

Portland Cement Mortar Setting Bed with Dry-Set or Latex-Portland Cement Mortar

A108.1C-17..............Contractors Option; Installation of Ceramic

Tile in the Wet-Set method with Portland Cement

Mortar or Installation of Ceramic Tile on a

Cured Portland Cement Mortar Setting Bed with

Dry-Set or Latex-Portland Cement Mortar

A108.4-09...............Ceramic Tile with Organic Adhesives or Water

Cleanable Tile-Setting Epoxy Adhesive

A108.5-10 ..............Ceramic Tile with Dry-Set Portland Cement

Mortar or Latex-Portland Cement Mortar

A108.6-10...............Ceramic Tile with Chemical Resistant, Water

Cleanable Tile-Setting and -Grouting Epoxy

A108.8-10...............Ceramic Tile with Chemical Resistant Furan

Resin Mortar and Grout

A108.9-10...............Ceramic Tile with Modified Epoxy Emulsion

Mortar/Grout

A108.10-17..............Grout in Tilework

A108.11-18..............Interior Installation of Cementitious Backer

Units

A108.12-10..............Installation of Ceramic Tile with EGP (Exterior

Glue Plywood) Latex-Portland Cement Mortar

A108.13-16..............Load Bearing, Bonded, Waterproof Membranes for

Thin-Set Ceramic Tile and Dimension Stone

A108.14-10..............Paper-Faced Glass Mosaic Tile

09 30 13 - 4

A108.15-19..............Alternate Method: Paper-Faced Glass Mosaic Tile

A108.17-16..............Crack Isolation Membranes for Thin-Set Ceramic

Tile and Dimension Stone

A118.1-19...............Dry-Set Portland Cement Mortar

A118.3-13...............Chemical Resistant, Water Cleanable Tile-

Setting and –Grouting Epoxy and Water Cleanable

Tile-Setting Epoxy Adhesive

A118.4-19...............Modified Dry-Set Cement Mortar

A118.5-16...............Chemical Resistant Furan Mortars and Grouts

A118.6-19...............Standard Cement Grouts for Tile Installation

A118.7-1................High Performance Cement Grouts for Tile

Installation

A118.8-16...............Modified Epoxy Emulsion Mortar/ Grout

A118.9-19...............Cementitious Backer Units

A118.10-14..............Load Bearing, Bonded, Waterproof Membranes for

Thin-Set Ceramic Tile and Dimension Stone

Installation

A118.11-17..............EGP (Exterior Glue Plywood) Modified Dry-set

Mortar

A118.12-14..............Crack Isolation Membranes for Thin-Set Ceramic

Tile and Dimension Stone Installation

A118.13-14..............Bonded Sound Reduction Membranes for Thin-Set

Ceramic Tile Installation

A118.15-19..............Improved Modified Dry-Set Cement Mortar

A136.1-13...............Organic Adhesives for Installation of Ceramic

Tile

A137.1-17...............American National Standard Specifications for

Ceramic Tile

C. ASTM International (ASTM):

A666-15.................Annealed or Cold-Worked Austenitic Stainless

Steel Sheet, Strip, Plate and Flat Bar

A1064/A1064M-18a........Carbon-Steel Wire and Welded Wire

Reinforcement, Plain and Deformed, for Concrete

C109/C109M-20b..........Standard Test Method for Compressive Strength of Hydraulic Cement Mortars (Using 2 inch. or

[50-mm] Cube Specimens)

C241/C241M-15e1.........Abrasion Resistance of Stone Subjected to Foot

Traffic

09 30 13 - 5

C348-20.................Standard Test Method for Flexural Strength of

Hydraulic-Cement Mortars

C627-18.................Evaluating Ceramic Floor Tile Installation

Systems Using the Robinson-Type Floor Tester

C954-18.................Steel Drill Screws for the Application of

Gypsum Board on Metal Plaster Base to Steel

Studs from 0.033 in (0.84 mm) to 0.112 in (2.84

mm) in thickness

C979/C979M-16...........Pigments for Integrally Colored Concrete

C1002-18................Steel Self-Piercing Tapping Screws for the

Application of Panel Products

C1027-19................Test Method for Determining Visible Abrasion

Resistance of Glazed Ceramic Tile

C1127/C1127M-15.........Standard Guide for Use of High Solids Content, Cold Liquid-Applied Elastomeric Waterproofing

Membrane with an Integral Wearing Surface

C1178/C1178M-18.........Standard Specification for Coated Glass Mat

Water-Resistant Gypsum Backing Panel

C1325-19................Non-Asbestos Fiber-Mat Reinforced Cementitious

Backer Units

C1353/C1353M-20e1.......Abrasion Resistance of Dimension Stone

Subjected to Foot Traffic Using a Rotary

Platform, Double-Head Abraser

D1204-14(2020)..........Test Method for Linear Dimensional Changes of

Nonrigid Thermoplastic Sheeting or Film at

Elevated Temperature

D2240-15e1..............Test Method for Rubber Property – Durometer

Hardness

D2497-07(2018)..........Tolerances for Manufactured Organic-Base

Filament Single Yarns

D3045-2018..............Heat Aging of Plastics Without Load

D4397-16................Standard Specification for Polyethylene

Sheeting for Construction, Industrial and

Agricultural Applications

D5109-12(Withdrawn2020).Standard Test Methods for Copper-Clad

Thermosetting Laminates for Printed Wiring

Boards (recommend deletion)

D. Code of Federal Regulation (CFR):

09 30 13 - 6

40 CFR 59...............Determination of Volatile Matter Content, Water

Content, Density Volume Solids, and Weight

Solids of Surface Coating

E. Marble Institute of America (MIA)/ Building Stone Institute (BSI):

Dimension Stone Design Manual VIII-2016

F. Tile Council of North America, Inc. (TCNA):

Handbook for Ceramic Tile Installation (2020)G. TCNA DCOF AcuTest-

2012,Dynamic Coefficient of Friction Test

PART 2 - PRODUCTS

2.1 TILE

A. Comply with ANSI A137.1, Standard Grade, except as modified:

1. Inspection procedures listed under the Appendix of ANSI A137.1.

2. Abrasion Resistance Classification:

a. Tested in accordance with values listed in Table 1, ASTM C1027.

b. Class V, 12000 revolutions for floors in Corridors, Kitchens, Storage including Refrigerated Rooms

c. Class IV, 6000 revolutions for remaining areas.

3. Slip Resistant Tile for Floors:

a. Coefficient of friction, when tested in accordance with

ANSI A137.1 and measured per the TCNA DCOF AcuTest.

1) Equal to or greater than .42 for level interior tile floors that will be walked on when wet.

b. Tile Having Abrasive Grains:

1) Unglazed Ceramic Mosaic Tile: Abrasive grains throughout body of the tile.

2) Quarry Tile: Abrasive grains uniformly embedded in face at rate of approximately 7.5 percent of surface area.

c. Porcelain Paver Tile: Matte surface finish // with raised ridges spaced uniformly over tile surface //.

4. Mosaic tile may be mounted or joined by a resinous bonding material along tile edges.

5. Factory Blending: For tile with color variations, within the ranges selected during sample submittals blend tile in the factory and package so tile units taken from one (1) package show the same range in colors as those taken from other packages and match approved samples.

09 30 13 - 7

B. Unglazed Ceramic Mosaic Tile: Nominal 6 mm (1/4 inch) thick with cushion edges.

C. Unglazed Quarry Tile: Nominal 13 mm (1/2 inch) thick, square edges.

D. Glazed Wall Tile: Cushion edges, glazing.

E. Porcelain Paver Tile: Nominal 8 mm (5/16 inch) thick, with cushion edges. Porcelain tile produced by the dust pressed method are to be made of approximately 50 percent feldspar; the remaining 50 percent is to be made up of various high-quality light firing ball clays yielding a tile with a water absorption rate of 0.5 percent or less and a breaking strength of between 176 to 181 kg (390 to 400 pounds).

F. Trim Shapes:

1. Conform to applicable requirements of adjoining floor and wall tile.

2. Use slip resistant trim shapes for horizontal surfaces of showers shower curbs, drying area curbs, and seats.

3. Use trim shapes sizes conforming to size of adjoining field wall.

4. Internal and External Corners:

a. Square internal and external corner joints are not acceptable.

b. External corners including edges: Use bullnose shapes.

c. Internal corners: Use cove shapes.

d. Base to floor internal corners: Use special shapes providing integral cove vertical and horizontal joint.

e. Base to floor external corners: Use special shapes providing bullnose vertical edge with integral cove horizontal joint. Use stop at bottom of openings having bullnose return to wall.

f. Wall top edge internal corners: Use special shapes providing integral cove vertical joint with bullnose top edge.

g. Wall top edge external corners: Use special shapes providing bullnose vertical and horizontal joint edge.

h. For unglazed ceramic mosaic and glazed wall tile installed in portland cement mortar setting bed, use cove and bullnose shapes as applicable. When ceramic mosaic wall and base tile is required, use C Series cove and bullnose shapes.

i. For unglazed ceramic mosaic and glazed wall tile installed in dry-set portland cement mortar, latex-portland cement mortar, and organic adhesive (thin set methods), use cove and surface bullnose shapes as applicable.

j. For quarry tile work, use cove and bullnose shapes as applicable.

09 30 13 - 8

2.2 BACKER UNITS

A. Cementitious Backer Units:

1. Use in showers or wet areas.

2. Conform to ASTM C1325; Type A.

3. Use in maximum lengths available to minimize end to end butt joints.

2.3 JOINT MATERIALS FOR CEMENTITIOUS BACKER UNITS

A. Reinforcing Tape: Vinyl coated woven glass fiber mesh tape, open weave, 50 mm (2 inches) wide. Tape with pressure sensitive adhesive backing will not be permitted.

B. Tape Embedding Material: Latex-portland cement mortar complying with

ANSI A108.01.

C. Joint material, including reinforcing tape, and tape embedding material, are to be as specifically recommended by the backer unit manufacturer.

2.4 FASTENERS

A. Screws for Cementitious Backer Units.

1. Standard screws for gypsum board are not acceptable.

2. Minimum 11 mm (7/16 inch) diameter head, corrosion resistant coated, with washers.

3. ASTM C954 for steel 1 mm (0.033 inch) thick.

4. ASTM C1002 for steel framing less than 0.0329 inch thick.

B. Washers: Galvanized steel, 13 mm (1/2 inch) minimum diameter.

2.5 SETTING MATERIALS OR BOND COATS

A. Conform to TCNA Handbook for Ceramic Tile Installation.

B. Organic Adhesives: ANSI A136.1, Type 1.

C. Chemical-Resistant Bond Coat:

1. Epoxy Resin Type: ANSI A118.3.

2. Furan Resin Type: ANSI A118.5.

1. membrane systems do not provide for slopes to drain and will follow profile of floor.

D. Waterproofing Isolation Membrane:

1. Sheet System TCNA F122-14 (on-ground concrete) and TCNA F122A-14

(above-ground concrete).

2. Composite sheet consisting of ASTM D5109, Type II, Grade I

Chlorinated Polyethylene (CM) sheet reinforced on both sides with a non-woven polyester fiber.

09 30 13 - 9

3. Designed for use in wet areas as an isolation and positive waterproofing membranes for thin-set bonding of sheet to substrate and thin-set bonding of ceramic and porcelain tile or marble to sheet. Suited for both horizontal and vertical applications.

4. Conform to the following additional physical properties:

Property Units Results Test Method

Hardness

Shore A

Points 70-80 ASTM D2240

(10 Second

Reading)

Shrinkage Percent 5 maximum ASTM D1204

Brittleness No crack remains flexible at temperature

-37 degrees C

(-35 degrees F)

ASTM D2497

13 mm (1/2-inch)

Mandrel Bend

Retention of

Properties after Heat

Aging

Percent of original

80 Tensile

80 Breaking

80 Elongation

ASTM D3045,

90 degrees C

(194 degrees F) for 168 hours

5. Manufacturer’s standard sheet size with prefabricated or preformed inside and outside corners.

6. Sheet manufacturer’s solvent welding liquid or xylene and edge sealant.

2.6 GROUTING MATERIALS

A. Sand-Portland Cement Grout: ANSI A108.10, consisting of white or gray cement and white or colored aggregate as required to produce color indicated. // Zero VOC content. //

B. Standard Cement Grout: ANSI A118.6.

C. High Performance Tile Grout: ANSI A118.7 // with a VOC content of

65 g/L or less when calculated according to 40 CFR 59

(EPA Method 24) //.

1. Polymer Type: Ethylene vinyl acetate or acrylic additive, in dry, redispersible form, prepackaged with other dry ingredients.

2. Polymer Type: // Acrylic resin // // or // // styrene-butadiene rubber // in liquid-latex form for addition to prepackaged dry-grout mix.

09 30 13 - 10

D. Water-Cleanable Epoxy Grout: ANSI A118.3 //, with a VOC content of

65 g/L or less when calculated according to 40 CFR 59

(EPA Method 24) //.

1. Provide product capable of withstanding continuous and intermittent exposure to temperatures of up to 60 and 100 degrees C (140 and

212 degrees F), respectively, and certified by manufacturer for intended use.

2.7 PATCHING AND LEVELING COMPOUND

A. Portland cement base, polymer-modified, self-leveling compound, manufactured specifically for resurfacing and leveling concrete floors.

Products containing gypsum are not acceptable.

B. Provide a patching and leveling compound with the following minimum physical properties:

1. Compressive strength - 25 MPa (3500 psig) per ASTM C109/C109M.

2. Flexural strength - 7 MPa (1000 psig) per ASTM C348 (28 day value).

3. Tensile strength – 4.1 MPa (600 psi) per ANSI 118.7.

4. Density – 1.9.

C. Capable of being applied in layers up to 38 mm (1-1/2 inches) thick without fillers and up to 101 mm (4 inches) thick with fillers, being brought to a feather edge, and being trowelled to a smooth finish.

D. Primers, fillers, and reinforcement as required by manufacturer for application and substrate condition.

E. Ready for use in 48 hours after application.

2.8 WATER

A. Clean, potable and free from salts and other injurious elements to mortar and grout materials.

2.9 CLEANING COMPOUNDS

A. Specifically designed for cleaning masonry and concrete and which will not prevent bond of subsequent tile setting materials including patching and leveling compounds and elastomeric waterproofing membrane and coat.

B. Materials containing acid or caustic Material are not acceptable.

2.10 FLOOR MORTAR BED REINFORCING

A. ASTM A1064/A1064M welded wire fabric without backing, MW3 x MW3

(2 x 2-W0.5 x W0.5).

2.11 POLYETHYLENE SHEET

A. Polyethylene sheet conforming to ASTM D4397.

09 30 13 - 11

B. Nominal thickness: 0.15 mm (6 mils).

PART 3 - EXECUTION

A. Follow all Manufacturer’s instructions for installation and use of adhesive, Thin Sets and or Grout.

B. Tile in depressed slab areas may also be set in epoxy or furan mortar, dry-set or latex-portland cement mortar over "set-up" mortar fills.

C. For existing areas where floors cannot be cut for depressed mortar beds and a waterproof membrane is required, consider an elastomeric bond coat over an elastomeric membrane with waterproof isolation membrane system option.

D. Wall tile for wet areas such as showers and washing areas: Set tile over cementitious backer unit. Use portland cement mortar, dry-set portland cement mortar or latex-portland cement mortar, setting or bond coat as specified.

E. Thin-set tile can only follow slope of sub-floor or contour of walls as only a minimum amount of adjustment can be made.

F. Do not install building expansion joints in ceramic tile floors over water-proof membranes.

3.2 ENVIRONMENTAL REQUIREMENTS

A. Maintain ambient temperature of work areas at not less than

16 degrees C (60 degrees F), without interruption, for not less than 24 hours before installation and not less than three (3) days after installation.

B. Maintain higher temperatures for a longer period of time where required by manufacturer's recommendation and ANSI Specifications for installation.

C. Do not install tile when the temperature is above 38 degrees C

(100 degrees F).

D. Do not install materials when the temperature of the substrate is below

16 degrees C (60 degrees F).

E. Do not allow temperature to fall below 10 degrees C (50 degrees F) after third day of completion of tile work.

3.3 ALLOWABLE TOLERANCE

A. Variation in plane of sub-floor, including concrete fills leveling compounds and mortar beds:

1. Not more than 6 mm in 3048 mm (1/4 inch in 10 feet) from required elevation where portland cement mortar setting bed is used.

09 30 13 - 12

2. Not more than 3 mm in 3048 mm (1/8 inch in 10 feet) where dry-set portland cement, and latex-portland cement mortar setting beds and chemical-resistant bond coats are used.

B. Variation in Plane of Wall Surfaces:

1. Not more than 6 mm in 2438 mm (1/4 inch in 8 feet) from required plane where portland cement mortar setting bed is used.

2. Not more than 3 mm in 2438 mm (1/8 inch in 8 feet) where dry-set or latex-portland cement mortar or organic adhesive setting materials is used.

3.4 SURFACE PREPARATION

A. Patching and Leveling:

1. Mix and apply patching and leveling compound in accordance with manufacturer's instructions.

2. Fill holes and cracks and align concrete floors that are out of required plane with patching and leveling compound.

a. Thickness of compound as required to bring finish tile system to elevation shown on construction documents.

b. Float finish // except finish smooth for elastomeric waterproofing //.

c. At substrate expansion, isolation, and other moving joints, allow joint of same width to continue through underlayment.

3. Apply patching and leveling compound to concrete and masonry wall surfaces that are out of required plane.

4. Apply leveling coats of material compatible with wall surface and tile setting material to wall surfaces, other than concrete and masonry that are out of required plane.

B. Mortar Bed for Slopes to Drains:

1. Slope compound to drain where drains are shown on construction documents.

2. Install mortar bed in depressed slab sloped to drains not less than

3.2 mm in 305 mm (1/8 inch per foot).

3. Allow not less than 50 mm (2 inch) depression at edge of depressed slab.

4. Screed for slope to drain and float finish.

5. Cure mortar bed for not less than seven (7) days. Do not use curing compounds or coatings.

09 30 13 - 13

6. Perform flood test to verify mortar bed slopes to drain before installing tile. Contracting Officer Representative (COR) to be present during flood test.

C. Additional preparation of concrete floors for tile set with epoxy, or furan-resin is to be in accordance with the manufacturer's printed instructions.

D. Walls:

1. In showers or other wet areas cover studs with polyethylene sheet.

2. Use of cementitious backer unit is preferred in showers or other wet areas.

3. Where isolated tile panels are required on plaster or gypsum board walls apply adhesives.

4. Apply patching and leveling compound to concrete and masonry surfaces that are out of required plane.

5. Apply leveling coats of material compatible with wall surface and tile setting material to wall surfaces, other than concrete and masonry that are out of required plane.

E. Existing Floors and Walls:

1. Remove existing composition floor finishes and adhesive. Prepare surface by grinding, chipping, self-contained power blast cleaning or other suitable mechanical methods to completely expose uncontaminated concrete or masonry surfaces. Follow safety requirements of ANSI A10.20.

2. Remove existing concrete fill or topping to structural slab. Clean and level the substrate for new setting bed and waterproof membrane or cleavage membrane.

3. Where new tile bases are required to finish flush with plaster above or where they are extensions of similar bases in conjunction with existing floor tiles, cut channel in floor slab and expose rough wall construction sufficiently to accommodate new tile base and setting material.

3.5 CEMENTITIOUS BACKER UNITS

A. Remove polyethylene wrapping from cementitious backer units and separate to allow for air circulation. Allow moisture content of backer units to dry down to a maximum of 35 percent before applying joint treatment and tile.

B. Install in accordance with ANSI A118.9 except as specified otherwise.

09 30 13 - 14

C. Install units horizontally or vertically to minimize joints with end joints over framing members. Units with rounded edges; face rounded edge away from studs to form a “V” joint for joint treatment.

D. Secure cementitious backer units to each framing member with screws spaced not more than 203 mm (8 inches) on center and not closer than

13 mm (1/2 inch) from the edge of the backer unit or as recommended by backer unit manufacturer. Install screws so that the screw heads are flush with the surface of the backer unit.

E. Where backer unit joins shower pans or waterproofing, lap backer unit over turned up waterproof system. Install fasteners only through top one-inch of turned up waterproof systems.

F. Do not install joint treatment for seven (7) days after installation of cementitious backer unit.

G. Joint Treatment:

1. Fill horizontal and vertical joints and corners with latex-portland cement mortar. Apply fiberglass tape over joints and corners and embed with same mortar.

2. Leave 6 mm (1/4 inch) space for sealant at lips of tubs, sinks, or other plumbing receptors.

3.6 CERAMIC TILE – GENERAL

A. Comply with ANSI A108/A118/A136 series of tile installation standards applicable to methods of installation and TCNA Installation Guidelines.

B. Installing Mortar Beds for Floors:

1. Install mortar bed in a manner that does not damage cleavage or waterproof membrane; 32 mm (1-1/2 inch) minimum thickness.

2. Install floor mortar bed reinforcing centered in mortar fill.

3. Screed finish to level plane or slope to drains shown on construction documents, float finish.

4. For thin set systems cure mortar bed not less than seven (7) days.

Do not use curing compounds or coatings.

5. For tile set with portland cement paste over plastic mortar bed coordinate to set tile before mortar bed sets.

C. Setting Beds or Bond Coats:

1. Where recessed or depressed floor slabs are filled with portland cement mortar bed, set ceramic mosaic floor tile in either portland cement paste over plastic mortar bed or latex-portland cement mortar over cured mortar bed except as specified otherwise, ANSI A108-1C, TCNA System F121-14 or F111-14.

09 30 13 - 15

2. Set floor tile in elastomeric bond coat over elastomeric membrane per ANSI 108.13, TCNA System F122-14 where indicated on construction documents.

3. Set wall tile installed over concrete backer board in latex-portland cement mortar, ANSI A108.1B.

4. Set tile installed over gypsum board and gypsum plaster in organic adhesive, ANSI A108.1, TCNA System W242-14.

5. Set trim shapes in same material specified for setting adjoining tile.

D. Workmanship:

1. Lay out tile work so that no tile less than one-half full size is used. Make all cuts on the outer edge of the field.

2. Set tile firmly in place with finish surfaces in true planes. Align tile flush with adjacent tile unless shown otherwise on construction documents.

3. Form intersections and returns accurately.

4. Cut and drill tile neatly without marring surface.

5. Cut edges of tile abutting penetrations, finish, or built-in items:

a. Fit tile closely around electrical outlets, piping, fixtures and fittings, so that plates, escutcheons, collars and flanges will overlap cut edge of tile.

b. Seal tile joints water tight as specified in Section 07 92 00, JOINT SEALANTS, around electrical outlets, piping fixtures and fittings before cover plates and escutcheons are set in place.

6. Completed work is to be free from hollow sounding areas and loose, cracked or defective tile.

7. Remove and reset tiles that are out of plane or misaligned.

8. Floors:

a. Extend floor tile beneath casework and equipment, except those units mounted in wall recesses.

b. Align finish surface of new tile work flush with other and existing adjoining floor finish where indicated in construction documents.

c. In areas where floor drains occur, slope tile to drains.

d. Push and vibrate tiles over 203 mm (8 inches) square to achieve full support of bond coat.

09 30 13 - 16

9. Walls:

a. Cover walls and partitions, including pilasters, furred areas, and freestanding columns from floor to ceiling, with tile.

b. Finish reveals of openings with tile, except where other finish materials are indicated in construction documents.

c. Finish wall surfaces behind and at sides of casework and equipment, except those units mounted in wall recesses, with same tile as scheduled for room proper.

10. Joints:

a. Keep all joints in line, straight, level, perpendicular and of even width unless shown otherwise on construction documents.

b. Make joints 2 mm (1/16 inch) wide for glazed wall tile and mosaic tile work.

c. Make joints in quarry tile work not less than 6 mm (1/4 inch) nor more than 9 mm (3/8 inch) wide. Finish joints flush with surface of tile.

d. Make joints in paver tile, porcelain type; maximum 3 mm

(1/8 inch) wide.

3.7 PORCELAIN TILE INSTALLED WITH LATEX PORTLAND CEMENT BONDING MORTAR

A. Due to the denseness of porcelain tile use latex portland cement bonding mortar that meets the requirements of ANSI A108.01. Mix bonding mortars in accordance with manufacturer’s instructions. Provide liquid ratios and comply with dwell times during the placement of bonding mortar and tile.

3.8 THIN SET CERAMIC AND PORCELAIN TILE INSTALLED WITH DRY-SET PORTLAND

CEMENT AND LATEX-PORTLAND CEMENT MORTAR

A. Installation of Tile:…

This is the start of the file's text. The full file is on GovTribe.