Z1DA--Exterior Cleaning Program for Buildings, Rooftops, Windows, and Parking Garages at Orlando VA Healthcare System (OVAHCS) facilities
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 36C24822Q0084
- Agency
-
Veterans Integrated Service Network 8
Veterans Health Administration, Department of Veterans Affairs
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 561790 Other Services to Buildings and Dwellings
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks a contractor to provide exterior cleaning services at four Department of Veterans Affairs medical facilities in Orlando, Florida. The contractor will plan, develop and implement cleaning of buildings, rooftops, windows and parking garages totaling over 1 million square feet of building space and more than 5,400 windows. Services must be performed in accordance with approved industry standards. The base period of performance is January 1, 2022 through December 31, 2022 with four optional one-year extensions. Proposals are due by December 22, 2021. Evaluation criteria will consider technical approach, past performance and price.
The NAICS code for this requirement is 561790 for exterior building services. There is no set-aside designation. The place of performance encompasses four locations in central Florida with a total budget estimated between $500,000-$1,000,000 annually. The solicitation was issued by the Department of Veterans Affairs Network Contracting Office 8 and seeks to continue exterior cleaning services currently provided by several incumbent contractors at the medical centers and campuses.
Notice text
3 versions
Update #3 · Latest ·
Page 2 of 2
CONTINUATION PAGE
Q6. Rooftop square footage and window count.
A6. (revised response from A00001) Updated the figures for Lake Nona VAMC, Viera VAHCC, & Lake Baldwin VAMC. The figures for the Lakemont Campus are unchanged.
VA Facility
Rooftop
(estimated total sqft all bldgs)
Window
(estimated counts all bldgs)
Lake Nona VAMC
812,312
5,100
Viera VAHCC
178,218 + 87,000 for carports
268
Lake Baldwin VAMC
255,000
400
Lakemont Campus
52,000
350
Q7. At Lake Nona, when were the rooftop tiedowns last certified? When were the tiedowns last inspected?
A7. (revised response from A00001) The suspended maintenance & rooftop fall protection anchorage system was last certified 09/04/2018. No annual inspections of the suspended maintenance & rooftop fall protection anchorage system have been performed since the certification in September 2018. Contractors will be required to provide their own fall protection system.
Q46. Do the parking garage floors require hot pressure wash?
A44. Yes. This will be incorporated into the PWS for the pressure washing of the garage floors.
The Contractor will pretreat (Pretreat will be required for any stains bigger than 2 x 2 ) all floors with a biodegradable cleaner and pressure wash the area with a pressure cleaner capable of producing a minimum of 220-degree water. The Contractor will remove vehicle and Biologic stains which include but not limited to (Oil, fluids, dirt, food and build) Contractor will recover and filter the water with a water recovery system. Contractor is responsible for removing and disposing of all waste materials collected in accordance with federal, state and local regulations to include all disposal costs and fees.
Q47. Will the Government consider discounts?
A47. Yes. The Government will consider discount terms. For example, a discount for early payment (2%, Net 10 or 1%, Net20). Another example, in the event the Government completes annual inspections and maintains certification of the suspended maintenance & rooftop fall protection anchorage system making available for use by the contractor, the contractor may offer discounted pricing terms.
Update #2 ·
Page 2 of 2
CONTINUATION PAGE
Q1. Is this a new effort or was there an incumbent?
A1. The Government is treating this requirement as a new effort. The scope of work included in this solicitation has increased/expanded significantly when compared to work previously performed at the Lake Nona VAMC.
Q2. Can you please provide the current vendor that s been providing service for this project?
A2. No vendor currently providing services.
Q3. Is this a new requirement, or is this identical to the past contract??
A18. see response for Q1.
Q4. How many elevators are available to gain access to the roof of the main building at Lake Nona VAMC?
A4. There are (2) elevators available to access the rooftop of the main building. The south elevator was used/shown to transport attendees of the site visit up to the rooftop and the west elevator was used/shown to return everyone to the ground floor.
Q5. Is there access to water for cleaning of the rooftops?
A5. Yes. Spigots and hydrants provide access to water. In areas where spigots are located inside the building(s), e.g. the 5th floor roof access area at Lake Nona, the contractor is to ensure hose connections are leak-free.
Q6. Rooftop square footage and window count.
A6. The VA provides the following information:
VA Facility
Rooftop
(estimated total sqft all bldgs)
Window
(estimated counts all bldgs)
Lake Nona VAMC
650,000
5,100
Viera VAHCC
147,000
100
Lake Baldwin VAMC
255,000
100
Lakemont Campus
52,000
350
Q7. At Lake Nona, when were the rooftop tiedowns last certified? When were the tiedowns last inspected?
A7. The suspended maintenance & rooftop fall protection anchorage system was last certified 09/04/2018. We are researching when the most recent annual inspection was completed. Further clarification will be provided.
Q8. Do all facilities have certified/ load tested and annually inspected anchors on the roof as required by OSHA 1910.27 Sub Part D, Walking Working Surfaces? Can these be provided?
A8. Only Lake Nona Campus has tie-downs and safety cables. See response for Q7 regarding certification & inspection dates for Lake Nona facility. The contractor may review certification(s) & inspection(s) prior to performance.
Q9. Are there anchors on the rooftops of the at the Lake Baldwin VAMC (4-story building) or the 3-story building at the Lakemont Campus?
A9. No.
Q10. All of the top sail is to be cleaned as well, correct?
A10. Yes.
Q11. Are there hooks or tiedowns on the super-structure (sail) at the Lake Nona VAMC?
A11. This area is equipped with tie-downs and safety cables.
Q12. There are several roofs with no tie offs, will these still be cleaned per the contract?
A12. Yes.
Q13. Are contractors expected to clean rooftops with terracotta roof tiles?
A13. Yes.
Q14. At the Lake Nona VAMC, is the Fisher House tile or metal roof and can it be walked on?
A14. The roof is tile & can be walked on.
Q15. Is your department requiring a certain cleaning solution that we apply to the exterior building and rooftop, or is it up to the contractor as long as it s industry standard?
A15. Proposed cleaning solutions are up to contractor.
Q16. What type of chemicals can be used?
A16. Reference Section B.3 Performance Work Statement (PWS), paragraph 3.3.3. All products (i.e. cleaners) used must be eco-friendly.
Q17. It is our understanding that Chlorine-based products nor their derivatives are to be used on this project since it is a Leeds certified building. Therefore, we cannot use with the following chlorine derivatives, bleach, sodium hypochlorite, sodium chloride, sodium hydroxide, hydrogen peroxide with KOA activator, sodium bicarbonate, sodium magnesium, benzoyl peroxide, chlorine dioxide, Sodium chloride, brand names, soft wash, Joe Max, 30 Second-cleaner, Clorox, Mold Armor, simply Green Oxy, wash safe roof wash, coenzo2 clean.
A17. Yes, the Lake Nona facility is a LEEDS certified building. Chlorine derivative products are not to be used in performance of any work resulting from this solicitation.
Q18. Is the contractor expected to remove stains on buildings caused by the irrigation system?
A18. These areas will be included in the work and cleaned; however, the Government realizes the staining is a result and will continue with the current irrigation system. A best effort shall be made to lessen staining marks. (This question was asked at Lake Baldwin VAMC where there is noticeable staining of the building exterior due to the irrigation system.)
Q19. Is the contractor expected to clean the air handlers on rooftops?
A19. No, the contractor is not to clean air handlers on rooftops and shall take special care around equipment when performing services.
Q20. Viera - Are the air handlers and piping on the roof included in the scope of this contract. Normally, the installer/manufacturer is responsible for cleaning.
A20. see response for Q19.
Q21. Is it a squeegee finish for windows and does that apply to all windows?
A21. The Government will evaluate each contractor s proposed approach to meet or exceed the requirements of the solicitation. A squeegee finish for windows is acceptable.
Q22. A substantial number of windows have over-spray from sealant that was applied to the exterior building. This over-spray sealant cannot be removed by standard window cleaning. Is this sealant to be removed or part of a separate one-time contract in the future?
A22. The Government will evaluate each contractor s proposed approach to meet or exceed the requirements of the solicitation. A squeegee finish for windows is acceptable. Vendors may include separate pricing for restoration services to remove over-spray as an addendum (or added option of services) to their initial quote(s).
Q23. Does each facility have a designated point of contact?
A23. Upon award, Contracting Officer Representative(s) (COR) will be appointed to administer the contract within their authority. Each COR may be responsible for more than one site. A copy of the COR delegation letter, outlining each COR s authority and area of responsibility, will be provide to the awardee.
Q24. What is the Limitation On Subcontracting (LOS).
A24. In the case of a contract for services (except construction), the contractor will not pay more than 50% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs as set forth in 852.219-10. Any work that a similarly situated VIP-listed subcontractor further subcontracts will count towards the 50% subcontract amount that cannot be exceeded. Please refer to applicable VAAR 852.219-77 and 13 CFR 125.6 for additional information.
Q25. Does the work include the perimeter fences?
A25. Yes, the exterior cleaning program includes perimeter fences as well as any block wall and concrete/block posts in line with the perimeter fence, see definitions within the PWS at paragraph 4.13 Structures ...surrounding walls/perimeter walls & columns... are to be included.
Q26. Does the work include the perimeter fences?
A26. see response for Q25.
Q27. It is our understanding the no walls or ceilings to be cleaned in the Garages, just the floor/road surfaces.
A27. The removal of cobwebs from the walls and ceilings of the (16) parking garage levels and (4) stairwells is required. Power washing work will only apply to the floor/road surfaces within the garage.
Q28. At Lake Nona, there appears to be a heavily soiled canvas on the interior roof sections is that to be cleaning as well?
A28. Yes.
Q29. It is our understanding that we can power clean roof with unit not to exceed 2,000psi, correct?
A29.Yes, 2000 psi or less is acceptable.
Q30. Lake Baldwin Facility - It is our understanding that the roofs cannot be power washed, correct?
A30. Correct due to material use on the roof, power washing cannot be performed.
Q31. Lakemont Campus - It is our understanding that the roofs cannot be power washed, correct?
A31. Correct due to material use on the roof, power washing cannot be performed.
Q32. It is our understanding that the outside of the buildings cannot be powered sprayed because the material is comprised of soft sandstone, correct?
A32. Correct, power washing cannot be performed.
Q33. The perimeter fence, front/back security entrances and all vertical columns are within the scope of this contract, correct?
A33. Yes. See response for Q25.
Q34. The new construction (Training Building) and the Fisher house are within the scope of this contract, correct?
A34. Yes, both buildings are within the scope of the contract.
Q35. Do sidewalks include curbs, road gutters, and car stops?
A35. All sidewalks, curbs, road gutters are to be cleaned. Car stops within the parking garages are to be cleaned. The cleaning of car stops in parking lots is not required.
Q36. Since it has been two years since the last cleaning, there will be a heavy accumulation of pigeon feces. That requires special removal requirements per OSHA since it is considered HAZMAT. Is that to be removed per the contract requirements?
A36. The intent of this requirement is to provide a (full) Exterior Building Cleaning Program which may require the removal of pigeon feces, as well as dirt, grimes, stains, and pollutants.
Q37. Bee/hornet is prevalent. Will these be removed prior to execution of this contract?
A37. The government regularly sprays for bees, hornets, & other insect nests at all facilities but our reach is only so high. In the event bees or similar pests hinder operations, the government is willing to discuss with the contractor possible solutions and equitable adjustment through a supplemental agreement and modification.
Q38. Lake Baldwin Facility - Bee/hornet is prevalent. Will these be removed prior to execution of this contract?
A38. See response for Q37
Q39. Lakemont Campus - Bee/hornet is prevalent. Will these be removed prior to execution of this contract?
A39. See response for Q37
Q40. Viera - Rust spots at entrance appear to be battery acid spillover. This requires special attention and may not be removable, is this in the scope of this contract?
A40. Clean to the best of your ability and we understand these areas may not be able to be removed.
Q41. Viera - The parking carports are all topped with solar panels. Are these in the scope of the contract? If so these need special attention per manufactures guidelines to ensure that warranty is not voided.
A41. Yes, they are part of the contract.
Q42. Lakemont Campus - Is the Sunshade Sail in the break area included in the scope of this contract?
A42. Yes, it is part of the contract.
Q43. Lakemont Campus - The parking lot is not included in the scope of this contract, correct? Only the entrance sidewalks that adjoin the facility are to be cleaned, correct?
A43. Asphalt parking lots are not part of the contract.
Q44. Is the contractor responsible for light poles, trash cans, landscape stones, fountains, signs around the property, flagpoles, monuments, outdoor chapel by the lake, dumpster pads, exit signs, basketball court, helicopter pads, café waterfall?
A44. Yes, the intent of the exterior cleaning program is to address all exterior areas on VA property. Light poles, trash cans, landscape stones, fountains, signs around the property, flagpoles, monuments, outdoor chapel by the lake, dumpster pads, exit signs, basketball court (maybe depends on the material), helicopter pads, café waterfall. If it can be cleaned, we like it to be cleaned.
Q45. When we clean the roof top, is it the government s responsibility to make sure the roof drains are not clogged before we start our services?
A44. Yes, the government will ensure roof drains are not clogged prior to services being rendered. When performing work, the contractor shall not sweep, spray, or wash any debris into roof drains. In the event of a clogged roof drain, the contractor shall notify the COR immediately for assistance.
Update #1 ·
Network Contracting Office 8 (NCO 8) in Orlando, Florida is soliciting businesses for an Exterior Cleaning Program of Buildings, Rooftops, Windows, and Parking Garages for VA facilities within the Orlando VA Healthcare System (OVAHCS).
The contractor shall plan, develop, and implement an exterior cleaning program for all OVAHCS buildings, structures, rooftops, walkways, and exterior windows. The designated areas are to be cleaned in their entirety (NOT spot cleaned). Best commercial practices shall be applied in the performance of work. All work shall be completed per approved and accepted industry standards throughout the duration of the contract. The Contractor shall furnish all labor, transportation, supplies, and equipment.
The NAICS Code is 561790 with a Size Standard of $8,000,000.00 in revenue.
Period of Performance:
Base Year: January 01, 2022 through December 31, 2022
Option Year 1: January 01, 2023 through December 31, 2023
Option Year 2: January 01, 2024 through December 31, 2024
Option Year 3: January 01, 2025 through December 31, 2025
Option Year 4: January 01, 2026 through December 31, 2026
Place of Performance:
Orlando VA Medical Center (VAMC) at Lake Nona, 13800 Veterans Way, Orlando, FL 32827
Lake Baldwin VAMC, 5201 Raymond St., Orlando, FL 32803
Lakemont Campus, 2500 S. Lakemont Ave., Orlando, FL 32814
Viera VA Health Care Center (VAHCC), 2900 Veterans Way, Viera, FL 32940
Contracting Office Address: Department of Veterans Affairs
Network Contracting Office 8 (NCO 8)
13800 Veterans Way
Lakemont Building, Room 221
Orlando, FL 32827-7401
Primary Point of Contact: Kurt Kramer
Contracting Officer, NCO 8
Kurt.Kramer@va.gov
Files
| File | Type | Posted |
|---|---|---|
| 36C24822Q0084 0002.docx | DOCX document | |
| 36C24822Q0084 0001.docx | DOCX document | |
| D.2 ATACHMENT 2 VAAR 852.219-77.pdf | ||
| D.3 ATACHMENT 3 FAR 52.209-7.pdf | ||
| D.1 ATTACHMENT 1 B.2 PRICE SCHEDULE.xlsx | XLSX spreadsheet | |
| WD 15-4555 Rev13 07-21-2021 Brevard.pdf | ||
| WD 15-4553 Rev16 07-21-2021 Orange.pdf | ||
| 36C24822Q0084_1.docx | DOCX document |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Z1DA--Exterior Cleaning Program for Buildings, Rooftops, Windows, and Parking Garages at Orlando VA Healthcare System (OVAHCS) facilities | Award Notice | |
| This notice | Solicitation | |
| Z1DA--Exterior Cleaning Program for Buildings, Rooftops, Windows, and Parking Garages at Orlando VA Healthcare System (OVAHCS) facilities | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| S201--semi-annual window cleaning | Veterans Integrated Service Network 22 | No set-aside | |
| S201--VANIHCS Window Cleaning - Engineering Service Fort Wayne and Marion Campuses | Veterans Integrated Service Network 10 | Service-Disabled Veteran-Owned Small Business | |
| S201--36C24127Q0017 Windows Washing Service Amendment 0001 | Veterans Integrated Service Network 1 | Service-Disabled Veteran-Owned Small Business | |
| Vent Hood Services | Air Combat Command | Total Small Business | |
| Window Cleaning and Maintenance | Headquarters Division | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity