Y1DA--528A6-26-611 Abate Asbestos Pipe Insulation - B76

Closed Solicitation Posted

Solicitation number
36C24226B0021
Agency
Responses due
Set-aside
Service-Disabled Veteran-Owned Small Business

Opportunity facts

NAICS code
562910 Remediation Services
Place of performance
Bath, New York 14810, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2 is soliciting bids for asbestos abatement and demolition services at the Bath Veterans Affairs Medical Center in Bath, New York. The scope of work includes the removal of approximately 200 linear feet of asbestos-containing material (ACM) pipe insulation from Building 76, including work in basement and crawl spaces with vertical runs extending to the second floor. The contractor must comply with all federal and state asbestos abatement regulations, including OSHA, EPA, and NESHAP standards, and must establish regulated work areas with negative air pressure systems, implement comprehensive worker protection protocols, and achieve final clearance testing with fiber levels at or below 0.01 f/cc. The procurement is evaluated based on technical compliance with the detailed specifications and master construction standards provided, along with price competitiveness. The bid submission deadline is December 17, 2025, at 12:30 PM EST, with bid opening scheduled for 1:00 PM EST the same day, and a pre-bid site visit was held on December 3, 2025.

This solicitation is a 100 percent set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs), and the estimated project cost falls between $25,000 and $100,000. No incumbent contractor is identified in the solicitation documents. The contractor must complete all abatement work within 30 calendar days from the Notice to Proceed, working during standard business hours (Monday through Friday, 8:00 AM to 4:30 PM) with potential off-tour work as directed by the Contracting Officer's Technical Representative to maintain continuous medical center operations. The work is located at Building 76 of the Bath VAMC at 76 Veterans Avenue, Bath, NY 14810, situated on a campus with over 30 buildings spanning more than 200 acres. Bidders must be registered in the System for Award Management (SAM), verified and certified as SDVOSBs, and must submit required documentation including the Buy American Certificate, Limitations on Subcontracting Certificate, and Vets4212 Report, with the NAICS code 562910 (Remediation Services) and a business size standard of $25 Million.

Notice text

4 versions

Update #4 · Latest ·

Abate Asbestos Pipe Insulation – B76

528A6-26-611

GENERAL PROJECT WORK SCOPE DESCRIPTION

Existing Conditions:

The Bath VAMC is located at 76 Veterans Avenue, Bath, NY 14810. The layout is a campus

with more than 30 buildings located on over 200 acres. Normal working hours are Monday – Friday

8:00am – 4:30pm. The Scope of this project includes but is not limited to the abatement of ACM

pipe insulation found within Building 76. Contactor shall follow all requirements and procedures set

by the local, state, and federal rule, regulation, and guidelines for the proper removal and disposal of

ACM. Building 76 being a fully operational Medical Center may restrict the hours of work and may

require off-tour work to ensure continuous operations of the facility as directed by the COR.

Contractor shall have 30 days from the award to complete all work.

Update #3 ·

Abate Asbestos Pipe Insulation – B76

528A6-26-611

GENERAL PROJECT WORK SCOPE DESCRIPTION

Existing Conditions:

The Bath VAMC is located at 76 Veterans Avenue, Bath, NY 14810. The layout is a campus

with more than 30 buildings located on over 200 acres. Normal working hours are Monday – Friday

8:00am – 4:30pm. The Scope of this project includes but is not limited to the abatement of ACM

pipe insulation found within Building 76. Contactor shall follow all requirements and procedures set

by the local, state, and federal rule, regulation, and guidelines for the proper removal and disposal of

ACM. Building 76 being a fully operational Medical Center may restrict the hours of work and may

require off-tour work to ensure continuous operations of the facility as directed by the COR.

Contractor shall have 30 days from the “Notice to Proceed” to complete all work.

Scope of Work:

1. Demolition:

a. Contractor is to provide all labor, material, equipment, supervision, to complete the

removal of approximately 200 LF of ACM insulation found on existing plumbing

from the crawl space and runs vertically through to the 2nd floor. Contractor is

required to dispose of all ACM at an approved location offsite. Clear exposure/wall

removal is to be completed by Medical Center maintenance shops prior to the start of

the abatement.

b. Part of scheduled abatement work is within basement/crawl space which is

considered a confined space.

2. Safety Measures:

a. Review and incorporate risk assessment and interim life safety plans and measures

into safety and construction planning.

i. Pre Construction Risk Analysis (PCRA) by VA

ii. Interim Life Safety Measures (ILSM) by VA

b. Generate and follow a safety plan and incorporate risk and life safety assessments.

3. Communication and Standards

a. All contract direction, changes, financials, and contract performance are the

responsibility of the VAMC Contracting Officer (CO).

b. Contracting Officers Technical Representative (COR) is responsible for the day-today

operations in project and the primary point of contact (POC) for the project.

i. Communications to/from VAMC

ii. Technical communications, submittals, RFI’s, change orders

iii. On site visits for construction and sub-contractors

iv. Construction coordination

c. Project is required to use Autodesk Construction Cloud Build Platform (ACC)

i. Bath VAMC will provide licensing, permissions, and online training for this

cloud-based tool at no cost to the contractors.

ii. Contractors are required to actively use Build on ACC for project

documentation and coordination.

iii. ACC is used for submittals, RFI’s, project communications and

documentation.

1. No contract financial information on ACC.

2. No personal identification information on ACC.

Code requirements:

The installed product must, at a minimum, be in accordance with all applicable codes

including Veterans Affairs standards which can be found at https://www.cfm.va.gov/til/. This will

include, but not be limited to: Department of Veterans Affairs Design Manuals, VA Publications,

and Construction Standards, National Fire Protection Code (NFPA), Life Safety Code, Underwriters

Laboratory (UL), International Building Code IBC, National Electric Code (NEC), the VA

Information Security Handbook 6500.6, Occupational Health and Safety (OSHA), and

Environmental Protection Agency (EPA) requirements (to include Mold Remediation in Schools and

Commercial Buildings). All work will be completed by certified individuals.

Contract Drawings: Please see attached.

Specifications: Please see attached.

General Requirements:

A. The contractor shall review the contract documents for conflicts. Where conflicts exist work

shall not proceed until the COR has been notified and has given direction.

B. Where incidental work is required to accomplish work shown on the drawings, this work is

implied and shall be included as part of the base bid.

C. Prior to any work commencing in an area, the contractor shall notify the COR of his intention to

work in the area and shall schedule a walkthrough with the COR to determine existing

conditions.

D. After the work, the existing work areas shall be returned to their original state before final

approval shall be given. After the completion of construction, the contractor shall completely

clean all surfaces of construction debris.

E. The contractor shall receive all deliveries of materials, equipment, tools, or other goods off

station, and bring them to the job site. The Bath VA shall not accept deliveries for project

purposes.

F. The contractor shall prepare and submit an excel spreadsheet submittal log listing all submittals

required. The worksheet shall be submitted by the contractor and reviewed and re-submitted as

necessary.

G. The contractor shall not proceed with any on-site work until the completion of the submittal

process or approval to proceed from the CO and COR without completion of the submittal

process. Not less than 14 calendar days shall be planned for COR review of each submittal. Resubmittals

shall be provided as required by the COR, and shall be treated as a new, separate

submittal.

H. Any non-lead time materials will only be paid for when installed.

I. Any items identified as punch list items will be fixed prior to project closeout.

J. Special care will be taken to secure tools and construction equipment during construction as this

facility has patients in it.

K. Work cleanliness must be adhered to throughout the project.

L. Sounds and vibrations must be kept to a minimum to avoid patient disruption. The COR

reserves the right to stop work if sound and vibrations are impacting patient living or employees.

M. Contractor staging area is east of railroad tracks, coordinate with COR.

N. Off tour work may be required to minimize the impact on Veterans and employees.

O. The contractor shall warranty all work including for 1 year from the date of acceptance.

Warranty shall include any labor or parts necessary to ensure complete functionality of the new

area.

P. The contractor shall plan accordingly to stage and store materials in the contractor’s designated

area shown.

Q. The contractor shall be responsible for coordinating any traffic interruption with the COR. The

contractor is responsible for providing interior pedestrian traffic control as well as any exterior

traffic control personnel as needed during the period of the performance.

Submittals:

Submittals are required for all items outlined in the specification and include but are not

limited to the submittals as shown in the submittal log.

Project Duration:

The total project duration for this project is not to exceed 30 days from the date of the NTP

issuance. This includes all processes starting with submission and approval of all submittals and

ending with final punch list c

Update #2 ·

Abate Asbestos Pipe Insulation – B76

528A6-26-611

GENERAL PROJECT WORK SCOPE DESCRIPTION

Existing Conditions:

The Bath VAMC is located at 76 Veterans Avenue, Bath, NY 14810. The layout is a campus with more than 30 buildings located on over 200 acres. Normal working hours are Monday – Friday 8:00am – 4:30pm. The Scope of this project includes but is not limited to the abatement of ACM pipe insulation found within Building 76. Contactor shall follow all requirements and procedures set by the local, state, and federal rule, regulation, and guidelines for the proper removal and disposal of ACM. Building 76 being a fully operational Medical Center may restrict the hours of work and may require off-tour work to ensure continuous operations of the facility as directed by the COR.

Contractor shall have 30 days from the “Notice to Proceed” to complete all work.

Update #1 ·

2

STATEMENT OF WORK (SOW):

SUMMARY:

This firm fixed price purchase order is for the provision of Abatement and Demolition Services the Buffalo VAMC located at 3495 Bailey Ave, Buffalo, NY 14215 to be completed within 21 days of award.

OVERVIEW:

All activities in this scope of work will be completed in Building 1 Room 625B.

Services are to include abatement and demolition of existing interior finishes,

All activities in this scope of work shall be done under abatement conditions.

REQUIREMENTS:

The Contractor shall provide personnel, material, services, and facilities to perform, accomplish, and deliver the required services detailed in this scope of work.

Asbestos abatement shall be performed in accordance with all federal and state regulations and PG 18 1 MASTER CONSTRUCTION SPECIFICATIONS; SECTION 02 82 11 TRADITIONAL ASBESTOS ABATEMENT.

SCOPE OF SERVICES:

The work to be performed shall be performed in Building 1, Room 625B and shall be completed within 21 days of award and shall include the following:

Demolish approximately 330 square feet of plaster ceiling in its entirety to include all wire mesh. There is known to be disturbed friable asbestos containing material (ACM) located on top of the plaster soffit and ceiling which shall be abated.

Abate approximately 50 linear feet of ACM Duplex pipe insulation and mudded joint fittings above the plaster soffit and ceiling.

Abate approximately 330 square feet of black floor mastic, the mastic is found to be non-ACM but fragments of ACM 12 x12 floor tile remain.

Abate all ACM inside two (2) radiators that is located on the backside of the metal baffles.

REQUIREMENTS:

Demolition and Abatement performed under this contract shall be performed in accordance with 10 NYCRR Part 73 and PG 18 1: MASTER CONSTRUCTION SPECIFICATIONS. Demolition and Abatement work shall include, but is not limited to, all labor, material, equipment, and supervision to perform the required demolition, abatement, encapsulation, and disposal. All asbestos containing material shall be demolished and abated mechanically, chemical abatement shall not be permitted.

Where the ACM recesses into the floor, ceiling, and adjacent walls, any remaining exposed ACM shall be encapsulated to prevent personnel exposure to any ACM during wall reconstruction.

Air monitoring services during abatement activities shall be provided by the VA.

CONTRACTOR QUALIFICATIONS:

The Contractor shall have an active New York State Department of Labor Asbestos Handling License.

All technicians working under this contract on abatement activities shall have an active New York State Department of Labor Asbestos Certificate with one of the following endorsements:

Asbestos Handler (worker)

Supervisor

PERSONAL PROTECTIVE EQUIPMENT (PPE):

The Contractor is responsible for obtaining/providing, inspecting, and maintaining any required Personal Protective Equipment (PPE) and access equipment (lifts, scaffolding, etc.) necessary to perform services identified in this scope of work.

GUIDING DOCUMENTS:

The following documents are applicable to this Scope of Work (SOW) to the extent specified herein. While every effort has been made to ensure the completeness of this list, document users are cautioned that they must meet all specified requirements of applicable documents, whether they are listed here or not.

01 00 00 GENERAL REQUIREMENTS

01 32 16.15 PROJECT SCHEDULES (SMALL PROJECTS)

01 35 26 SAFETY REQUIREMENTS

01 74 19 CONSTRUCTION WASTE MANAGEMENT

02 41 00 DEMOLITION

02 82 11 TRADITIONAL ASBESTOS ABATEMENT

02 82 13.19 FLOOR AND MASTIC ABATEMENT

HOURS OF COVERAGE:

The VAMC is a health care facility providing critical care 24 hours a day; as such disruptions in operations are not feasible and will need to be coordinated closely with the COR. Work shall take place during normal duty hours: Monday-Friday, 7:30am-3:30pm. Requests to conduct work on weekends and outside of normal duty hours must be submitted in writing at least seven (7) working days in advance of the anticipated work to the COR. If this new schedule is agreed upon, work can begin. The original written request will remain with all test documents along with any written agreements relative to the original requests.

The following are Federal Holidays observed by the facility and the Contractor shall not expect access to the VA Facility of VA employees on these dates unless notified otherwise by the COR. Preventive maintenance or other services are not to be scheduled on these dates:

New Year s Day

Martin Luther King, Jr. Day

Washington s Birthday

Memorial Day

Juneteenth

Independence Day

Labor Day

Columbus Day

Veteran s Day

Thanksgiving Day

Christmas Day

If it becomes difficult for the Contractor to complete services because of patient care related activities or security issues, the Contractor shall not be obligated to complete testing in the area of concern at the time of their scheduled visit. They will be obligated to complete their work at the time of the next scheduled visit to the facility. The final authority relative to this decision will be the COR. Unless fully absolved by the VA, Contractor shall be responsible for completing all work.

ACCESS:

Although the VAWNYHS campuses are public facilities, access to facility maintenance areas, electrical areas, mechanical areas, roof access, and certain other portions of the medical facility are restricted from the public. Accessing these areas may require advance notice, pre approval, and scheduling to gain entry.

All visits and access requests to the VAWNYHS under this scope of work shall be coordinated through the Contracting Officer Representative (COR) at least 1 week in advance.

IDENTIFICATION, PARKING, SMOKING, AND VAMC REGULATIONS/KEY CONTROL SAFETY:

All Contractor employees who have access to VA facilities are subject to the same level of investigation as VA employees. Security and badging process to be determined by COR.

Contractor employees shall always wear visible identification while on the premises of the VAMC.

It is the responsibility of the vendor to park in the appropriate designated parking areas. Information on parking is available from the VA Police Section. The VAMC will not invalidate or make reimbursement of parking violations of the vendor under any conditions.

Smoking is prohibited on VAMC property to include inside privately owned vehicles (POV) parked on VAMC property. Smoking shall only be allowed off VAMC property.

Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or municipal court.

The Contractor shall establish and implement methods of making sure all keys/key cards issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be included in the Quality Control Plan. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The Contractor shall immediately report any occurrences of lost or duplicate keys/key cards to the Contracting Officer.

In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the Contracting Officer, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of rekeying or the replacement of the lock or locks shall be deducted from the monthly payment due the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment due the Contractor. The Contractor shall prohibit the use of Government issued keys/key cards by any persons other than the Contractor s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer.

GENERAL REQUIREMENTS:

In the performance of this contract, the contractor shall take such safety precautions as the Contracting Officer may determine to be reasonably necessary to protect the lives and health of occupants of the building.

The Contracting Officer or designee shall notify the Contractor of any safety issues and the action necessary to correct the issues. Such Notice, when served to the Contractor or their representative at the work site shall be deemed sufficient for the corrective actions to be taken.

If the Contractor fails or refuses to comply promptly with notified safety deficiencies, the Contracting Officer may issue an order stopping all or part of the work and hold the Contractor in default.

No tools or equipment shall be left unattended.

All work areas must be clean at the close of the day and shall be left in the same condition as before work started.

KICK OFF MEETING AND SITE SURVEY:

This will be a joint meeting with both the abatement contractor and the air monitoring Consultant. The Contractor shall attend a Preconstruction Conference. In preparation for this meeting the Contractor shall submit:

An updated work plan that adds additional details based upon approved submittal information.

Revised or new Activity Hazard Analysis (AHA) based on approved submittals.

Any additional clarifying details about the work to be performed that have been updated bases upon the approved submittals.

Any action items resulting from this meeting shall be addressed prior to ordering any materials or beginning the actual construction work. This meeting shall comply with the terms of Section 3.1.2 of this SOW and the terms of PG 18 1 MASTER CONSTRUCTION SPECIFICATIONS; SECTION 01 35 26 SAFETY REQUIREMENTS (528 21 135); Article 1.6 Preconstruction Conference.

RECORDS MANAGEMENT:

Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government IT equipment and/or Government records.

Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the Freedom of Information Act.

Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.

The Government Agency owns the rights to all data/records produced as part of this contract.

The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.

Contractor agrees to comply with Federal and Agency records management policies, including those policies associated with the safeguarding of records covered by the Privacy Act of 1974. These policies include the preservation of all records created or received regardless of format (paper, electronic, etc.) or mode of transmission (email, fax, etc.) or state of completion (draft, final, etc.).

No disposition of documents will be allowed without the prior written consent of the Contracting Officer. The Agency and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. Records may not be removed from the legal custody of the Agency or destroyed without regard to the provisions of the agency records schedules.

Contractor is required to obtain the Contracting Officer s approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, this contract. The Contractor (and any sub-contractor) is required to abide by Government and Agency guidance for protecting sensitive and proprietary information.

RISK CONTROL:

The Contractor shall take all precautions necessary to protect persons and property from injury or damage during performance of this contract.

The Contractor shall be responsible for any injury to any Contractor Representative, or others, as well as for any damage to personal or public property that occurs during the performance of this contract that is caused by the contractor s fault or negligence.

11 of 15

3/11/2022

SUBMITTALS:

Data

Item

Type

Responsible

Party

Description

Date

Delivery

Qty

SOW

Ref

Spec Ref

Duration of Contract

1

Submittal

Contractor

Daily Status Report

Every Morning NLT 0800

email

NA

3.1.1

625B Abatement & Demolition

Kick off Meeting and Site Survey

2

Submittal

Contractor

Kickoff Meeting Agenda

Kickoff Meeting 5 Business Day(s)

email

NA

3.2.1

3

Submittal

Contractor

Work Plan (Draft)

Concurrent with Kickoff Meeting Agenda

email

NA

3.2.1

01 00 00;

1.7.G

4

Submittal

Contractor

Schedule, Gantt Chart (Draft)

Concurrent with Kickoff Meeting Agenda

email

NA

3.2.1

01 00 00,

1.7.G;

02 82 11,

2.4.1.A

Action

Contractor

Kickoff Meeting and Site Survey

NTP +5 Business Day(s)

In person @ VAMC

1

3.2.1

VAMC

Work Plan (Draft) Comments

Concurrent with Kickoff Meeting

VAMC

Schedule, Gantt Chart (Draft) Comments

Concurrent with Kickoff Meeting

5

Submittal

Contractor

Kickoff Meeting Minutes (Draft)

Kickoff Meeting +5 Business Day(s)

email

NA

3.1.2

VAMC

Kickoff Meeting Minutes (Draft) Comments

Receipt of Draft +3 Business Day(s)

6

Submittal

Contractor

Kickoff Meeting Minutes (Final)

Receipt of Comments +3 Business Day(s)

email

NA

3.1.2

Data

Item

Type

Responsible

Party

Description

Date

Delivery

Qty

SOW

Ref

Spec Ref

Submittals

7

Submittal

Contractor

Work Plan (Final)

NTP +5 Calendar Day(s)

email

NA

01 00 00,

1.7.G

8

Submittal

Contractor

Schedule, Gantt Chart (Final)

NTP +5 Calendar Day(s)

email

NA

01 00 00,

1.7.G;

02 82 11,

2.4.1.A

9

Submittal

Contractor

Employee Lists

NTP +5 Calendar Day(s)

email

NA

01 00 00,

1.6.A;

02 82 11,

2.4.1.B

10

Submittal

Contractor

Keys and lock combinations (doors, tool boxes,

equipment)

NTP +5 Calendar Day(s)

In person @ VAMC

2

01 00 00,

1.6.D

11

Submittal

Contractor

Electronic Security Memorandum

NTP +5 Calendar Day(s)

email

NA

01 00 00,

1.6.E

12

Submittal

Contractor

Vehicle registration

NTP +5 Calendar Day(s)

email

NA

01 00 00,

1.6.F

13

Submittal

Contractor

Accident Prevention Plan (APP)

Preconstruction Conference

5 Calendar Day(s)

email

NA

01 35 26,

1.4

14

Submittal

Contractor

Fire Safety Plan

Preconstruction Conference

5 Calendar Day(s)

email

NA

01 35 26,

1.14

15

Submittal

Contractor

Activity Hazard Analysis (AHA)

Preconstruction Conference

5 Calendar Day(s)

email

NA

01 35 26,

1.5

16

Submittal

Contractor

OSHA Training Certificates

Preconstruction Conference

5 Calendar Day(s)

email

NA

01 35 26,

1.8

Data

Item

Type

Responsible

Party

Description

Date

Delivery

Qty

SOW

Ref

Spec Ref

18

Submittal

Contractor

Certificate of Worker's Acknowledgment

Preconstruction Conference

5 Calendar Day(s)

email

NA

02 82 11,

2.4.1.B

25

Submittal

Contractor

Experience and Qualifications

Preconstruction Conference

5 Calendar Day(s)

email

NA

02 82 11,

2.4.1.H

VAMC

Submittal Reviews

Submittal Receipt +3Calendar Day(s)

Preconstruction Conference

28

Submittal

Contractor

Preconstruction Conference Agenda

Preconstruction Conference

5 Business Day(s)

email

NA

3.1.2

Action

Contractor

Preconstruction Conference

NTP +5 Calendar Day(s)

In person @ VAMC

3.2.3

01 35 26;

1.6

2

Files

Show all 12

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Y1DA--528A6-26-611 Abate Asbestos Pipe Insulation - B76 Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
F108--620-26-206 Asbestos Abatement Department of Veterans Affairs VA Hudson Valley Health Care Montrose, New York 10548, United States · NAICS 562910 Veterans Integrated Service Network 2 Service-Disabled Veteran-Owned Small Business
Z2DA--Renovate Space for Patient Care Improvements Asheville, North Carolina 28805, United States · NAICS 236220 Veterans Integrated Service Network 6 Service-Disabled Veteran-Owned Small Business
Y1DA--NRM-CONST 528-CSI-102 Urology Equipment Site Prep | FY27 NRM Buffalo, New York 14215, United States · NAICS 236220 Veterans Integrated Service Network 2 Service-Disabled Veteran-Owned Small Business
Building 13 Stair and Roof Replacement at Castle Point VAMC New York 12590, United States · NAICS 236220 Veterans Integrated Service Network 2 Service-Disabled Veteran-Owned Small Business
Y1DA--replace roofs and repair facades building 6 and 7 at the northport VA medical center project number: 632-23-112 Department of Veterans Affairs Northport VA Medical Center New York, New York 11768, United States · NAICS 236220 Veterans Integrated Service Network 2 Service-Disabled Veteran-Owned Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity