WY FLAP US212(8) Beartooth Highway
Awarded Award Notice Posted
- Solicitation number
- DTFH6816B00026
- Agency
- Federal Highway Administration Department of Transportation
- Awarded
- to Oftedal Construction, Inc.
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- DTFH6817C00015 Federal contract award
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- Not on record
- Place of performance
- Park County, Wyoming, United States
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
Added: Sep 12, 2016 10:47 am Modified: Jan 25, 2017 8:21 pmTrack Changes
Project Details: This project includes reconstruction of 3.773 km of roadway on Park County Road US 212, otherwise called Beartooth Highway.
Type of Construction: grading, concrete bridge, culverts, concrete headwalls, riprap, aggregate base course, and paving, traffic control, public information
The route is currently 5.4-6.1 m (18-20 feet) in width the proposed project will increase the roadway width to 9.0 m (30 feet) for the length of project.
The existing asphalt surface is severely degraded and the existing drainage is under hydraulic capacity for the entire project. The proposed project includes drainage improvements by the addition of new culverts and the construction of a concrete bridge over the Little Bear Creek. The proposed project will also address safety items in regard to roadway width, clear zone, signing, and striping.
Estimated total cost is between $12 - $15 million.
Update #1 ·
Added: Sep 12, 2016 10:47 am
This is not an Invitation for Bid, plans and specs are not available. Advertisement is tentatively planned for November '16 and will be Full and Open Competition.
Non-Mandatory Contractor Site Visit for the WY FLAP 212(8) Beartooth Highway project.
September 27th 10:00am at the Top of the World Store parking lot. Store is located on Beartooth Highway. No RSVP is required.
Project Details: This project includes reconstruction of 3.773 km of roadway on Park County Road US 212, otherwise called Beartooth Highway.
Type of Construction: grading, concrete bridge, culverts, concrete headwalls, riprap, aggregate base course, and paving, traffic control, public information
The route is currently 5.4-6.1 m (18-20 feet) in width the proposed project will increase the roadway width to 9.0 m (30 feet) for the length of project.
The existing asphalt surface is severely degraded and the existing drainage is under hydraulic capacity for the entire project. The proposed project includes drainage improvements by the addition of new culverts and the construction of a concrete bridge over the Little Bear Creek. The proposed project will also address safety items in regard to roadway width, clear zone, signing, and striping.
Attached at 95% Plan Sheets A1 and A6 for informational purposed for the Site Visit. The entire 100% Plan Sheets will be posted with the Solicitation.
Estimated total cost is between $12 - $15 million.