Stilling basin repair, foster joseph sayers DAM, beech creek, PA

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W912DR20B0004
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Beech Creek PA 16822 USA

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks a contractor to repair the deteriorated concrete surfaces within the stilling basin at the Foster Joseph Sayers Dam in Beech Creek, Pennsylvania. The U.S. Army Corps of Engineers, Engineering District Baltimore is seeking to award a fixed price contract to conduct the repairs and improve flow characteristics. Key requirements include installing a temporary water diversion system capable of carrying 700 cubic feet per second, conducting 3D laser scans before and after construction, and monitoring the stilling basin throughout the project duration. Proposals were due by March 10, 2020.

This is a 100% small business set-aside identified under NAICS code 237990 for specialty trade contractors, with a place of performance in Beech Creek, PA. The solicitation includes five bids ranging from $3.19 million to $4.86 million, with a government estimate of $3.5 million. Work must be completed by designing and installing a temporary water diversion system to remain in place for a minimum of 28 days after concrete placement.

Notice text

5 versions

Update #5 · Latest ·

Abstract of Bids from bid opening on 10 MAR 2020 @ 11:00 AM EDT

Update #4 ·

Amendment 0002 - Update Wage Determination dated 2-28-20

Update #3 ·

Amendment 0001

Update #2 ·

FJ Sayers Stilling Basin Repairs site visit from 13 FEB 2020.

Update #1 ·

Foster Joseph Sayers Dam is located in Beech Creek, PA (Centre County), between State College and Lock Haven.  The purpose of this contract is to repair the deteriorated concrete surfaces within the stilling basin, and improve the flow characteristics.

The project consists but is not limited to the repair, construction and installation of the following:

  1. The area around the stilling basin is heavily used for fishing. The contractor shall erect temporary fencing and signage around the work area, sufficient to prevent pedestrian access into the work area. Temporary fencing and signage shall also be erected around the contractor’s staging area.
  2. For any required vehicular access to the south side of the stilling basin, due to the steep slopes, the contractor shall construct a temporary ramp with fill materials that shall be removed at the end of construction.
  3. A water diversion and dewatering system shall be designed by a registered Professional Engineer, and constructed to allow for controlling the upstream reservoir level and downstream river level. The water diversion system shall be designed to carry a design discharge of 700 cubic feet per second. Due to reservoir regulations, water diversion and dewatering shall not begin until 1 June. Dam flow shut downs cannot exceed 1 hour, with a waiting period of 1.5 hours between shut downs. The temporary water diversion shall remain in place and the basin shall remain dewatered for a minimum of 28 days after completion of concrete placement. The diversion system shall not be dismantled until approval of all work.
  4. The basin shall be monitored for movement by survey methods throughout the work.  Monitoring is required to detect any uplift of the basin or sideways movement of the walls. Several monitoring points shall be established and readings shall have an accuracy of 0.1 inch. Monitoring shall be required at one hour intervals during the initial dewatering of the basin, and at daily intervals thereafter, throughout the duration of the work. The contractor shall submit his monitoring plan for approval.
  5. Concrete repairs and geometric changes to the channel shall be constructed, for the purpose of improving the flow characteristics, so that the channel is no longer damaged by backward circulating riprap. Concrete repairs shall be by the placement of Silica Fume Concrete and epoxy coated reinforcing steel.
  6. Contractor to conduct 3D laser scanning (also referred to as High Definition Surveying ((HDS)), 3D Imaging, Terrestrial Scanning, and LIDAR) of the stilling basin slab and baffle blocks before and after demolition and following concrete placement to establish quantities for payment for demolition and placement of new concrete.
  7. Obtain the necessary permits to perform the work cited above. As a minimum, a permit from the Centre County Conservation District, will be required.
  8. For more details see the photographs and drawing below. The attached photographs and drawing are for information only. Please use the drawings issued with the solicitation for construction.

Files

Notice history

Notice Type Posted
Stilling basin repair, foster joseph sayers DAM, beech creek, PA Award Award Notice
This notice Latest solicitation Solicitation
Stilling basin repair, foster joseph sayers DAM, beech creek, PA Pre-Solicitation
Stilling basin repair, foster joseph sayers DAM, beech creek, PA Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
FY27 Euclid Creek Fishway Construction Euclid Creek Spillway Cleveland, OH, 44114 44114 · NAICS 237990 ENDIST Buffalo Total Small Business
Canonsburg-Houston, Pennsylvania, Local Protection Project (LPP) PL84-99 Rehabilitation Canonsburg-Houston, Strabane, Washington County, Pennsylvania 15317 · NAICS 237990 ENDIST Pittsburgh Total Small Business
Reserve basin maintenance dredging contract for sites at the phildelphia navy yard in the public works department pennsylvania area of responsibiliy Philadelphia, Pennsylvania 19112, United States · NAICS 237990 Naval Facilities Engineering Command No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors