About this opportunity

This solicitation seeks proposals to replace three mission essential systems at Building 600 of the Central Utility Plant on Schriever Air Force Base in Colorado Springs, Colorado. The 50th Civil Engineer Squadron is soliciting to replace (1) six transformers and associated equipment in the transformer yard, (2) eight roof-mounted exhaust fans and connected wall louvers, and (3) obsolete generator synchronizers, load controllers, and generator operator computer equipment. Proposals are due by January 31, 2020 at 1200 hours and will be evaluated for technical acceptability, with award made to the lowest priced technically acceptable offeror.

The solicitation is set aside for HUBZone small businesses and has a place of performance of 730 Irwin Ave # 83, Colorado Springs, CO 80912. The NAICS code is 238210 and PSC code is R499. The work must be completed within 365 days of notice to proceed at an estimated value between $2-5 million. Replacement of this aging infrastructure supporting critical energy and HVAC systems for Building 600 is required to maintain essential power generation capabilities for the Air Force base.

Notice text

7 versions

Update #7 · Latest ·

The Purpose of This Amendment Is:

  1. To execute RFP Amendment 006. This is Amendment 001 to the 1442. The first five amendments to the RFP were done outside of the CON-IT system.
  2. To execute Amendment 001 to the 1442. This is RFP amendment 006.The first five amendments to the RFP were done outside of the CON-IT system.
  3. Extend the revised proposals submission due date to 31 January 2020 at 1200 hrs.
  4. Post and incorporate RFI 005 responses.
  5. Incorporate Wage Determination CO20200002 03 January 2020.
  6. Post digital drawing for B600 Electrical & HVAC Upgrade.
  7. Incorporate Revised SOW 06 January 2020 (changes identified in SOW).
  8. Previous actions incorporated:
    1. RFP Amendment 001: Included RFI 001 Responses, drawings, site visit sign in sheet, SOW Addendum, and Manual Mode Transfer. See Amendment 001 on https://beta.sam.gov/opp
    2. RFP Amendment 002: Extended the proposal due dates. See Amendment 002 on https://beta.sam.gov/opp
    3. RFP Amendment 003: Included RFI 002 Responses and SOW Addendum. See Amendment 003 on https://beta.sam.gov/opp
    4. RFP Amendment 004: Included RFI 003 Responses, drawings, and MCC-1 AE Comments. See Amendment 004 on https://beta.sam.gov/opp
    5. RFP Amendment 005: Included RFI 004 Responses and revised the proposal due dates. See Amendment 005 on https://beta.sam.gov/opp
  9. All other Terms and Conditions remain the same.
Update #6 ·

Thr Purpose of Amendment 005 is to post responses to RFI 004 and extend the proposal due date to 16 October 2019 at 1200 MT.

Update #5 ·

Thr Pirpose of Amendment 005 is to post responses to RFI 004 and extend the proposal due date to 16 October 2019 at 1200 MT.

Update #4 ·

The purpose of Amendment 003 and 004 is to respond to and clarify RFIs.

Update #3 ·

The Purpose of Amendment 001 is to answer RFI questions and provide photos and documents as requested.
The Purpose of Amendment 002 is to extend the response date to 8 October 2019 at 1200 Mountain Time to allow the Government's technical expert adequate time to clarify answers to RFIs.

Update #2 ·

The Purpose of Amendment 001 is to answer RFI questions and provide photos and documents as requested.

Update #1 ·

The 50th Civil Engineer Squadron is seeking proposals to replace three mission essential systems in building 600, Central Utility Plant (CUP). (1) Replace the existing transformers, CT-1, CT-4, CT-7, CT-2, CT-5, & CT-8, common generator grounding resistor, interconnecting lines, and grounding system in the transformer yard. (2) Replace eight roof mounted exhaust fans connected to seven wall louvers controlled by thermostats located in the power generation system area. (3) Replace the existing obsolete models Woodward synchronizers, load controllers, custom PLC based generator controller, and the generator operator Human Machine Interface (HMI) computer and programming.

Files

File Type Posted
5 WD_CO20200002_ 01-03-2020.pdf PDF
4 B600 Upgrade drawing.pdf PDF
1 Solicitation Amendment - FA255019RA0100001.pdf PDF
2 GLEN18-1101_SOW_06Jan2020.pdf PDF
3 18-1101 RFI 005.pdf PDF
RFI_004.pdf PDF
3_-_Design_Drawings_PDF_Exhaust_Fans_AE_Comments.pdf PDF
RFI_003.pdf PDF
MCC-1_AE_Comments.pdf PDF
RFI_002.pdf PDF
GLEN_18-1107_SOW_Addendum_2.pdf PDF
Sign_In_Sheet.pdf PDF
Site_Visit_MFR.pdf PDF
Transfer_to_commercial_(with_load)_in_Manual_Mode_B600_2019.pdf PDF
GLEN_18-1107_SOW_Addendum.pdf PDF
RFI_001_18-1101_Answered.pdf PDF
Transformer_Pad.pdf PDF
Binder1RS1.pdf PDF
Exhaust_Fans_Electrical_One_Line.pdf PDF
Transfer_to_emergency_(with_load)_in_Manual_Mode_B600_2019.pdf PDF
4_-_Design_Drawings_PDF_Transformers_Replacement(RS).pdf PDF
5_-_Design_Guide_Version_March_2017.pdf PDF
00_Solicitation_-_FA255019RA010.pdf PDF
1_-_01_55_04_-_SAFB_Security_Requirements.pdf PDF
2_-_Design_Analysis_Exhaust_Fans_Redacted(RS).pdf PDF
8_-_SOW_Environmental_Supplement.pdf PDF
7_-_GLEN18-1101_AF_66_Form.xls XLS spreadsheet
3_-_Design_Drawings_PDF_Exhaust_Fans.pdf PDF
0_-_GLEN18-1101_SOW_10July19.pdf PDF
9_Wage_Determination.pdf PDF
Show all 30

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Synopsis_GLEN_18-1101 Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Repair Electrical Systems Wright-Patterson AFB, OH 45433 (Area A, Area B and all other properties owned by Wright-Patterson Air Force Base, Ohio) 45433 · NAICS 238210 AFLCMC Wright Patterson AFB No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity