2 GLEN18-1101_SOW_06Jan2020.pdf
PDF 1 MB Posted
- Attached to
- Solicitation_GLEN_18-1101
- Solicitation number
- FA255019RA010
About this file
This solicitation seeks proposals to replace three mission essential systems at Building 600 on Schriever Air Force Base, including transformers, exhaust fans, and generator synchronizers. The transformers and common generator grounding resistor in the transformer yard will be replaced. Eight roof-mounted exhaust fans connected to seven wall louvers will also be replaced. Finally, obsolete Woodward synchronizers, load controllers, and generator controllers will be replaced with new digital models. Proposals are due from contractors to undertake this work for the 50th Civil Engineer Squadron at Schriever Air Force Base, replacing aging infrastructure supporting critical HVAC equipment.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Schriever Air Force Base
“Masters of Space, Home of the 50th Space Wing!”
STATEMENT OF WORK (SOW)
Project Number: GLEN18-1101
Repair Electrical-HVAC at Emergency Power Plant, B600
50 CES Project Manager:
Michael R. Mattson
Revisions 1 Corrections
1. Demolition Section (2.3.3), removed requirement to demolish conduit and cable between transformers and MVMC, MVMCC.
2. Demolition Section (2.3.3), Concrete slab and walkway shall be removed in transformer yard to ease replacement on conduits and grounding system.
3. Civil Section (2.4), added concrete slab and walkway replacement and specifications.
4. Electrical Section (2.5.1), Removed the replacement of interconnection cable and conduit between transformers and Switchgear MVMC, MVMCC. Clarified requirements for transformer outages.
06 Jan 2020
1 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
Table of Contents
BACKGROUND:
REQUIREMENTS:
PERIOD OF PERFORMANCE:
GENERAL:
WARRANTY:
SUBMITTALS:
ENVIROMENTAL REQUIRMENTS:
GEOGRAPHIC INFORMATION SYSTEM (GIS) DATA:
SECURITY REQUIRMENTS:
REFERENCES:
ATTACHMENTS:
PRE-AWARD RFI ANSWERS
PRE-AWARD RFI CLARIFICATIONS
GOVERNMENT POINTS OF CONTACT (POC):
2 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
BACKGROUND:
The 50th Civil Engineer Squadron is seeking proposals to replace three mission essential systems in building 600, Central Utility Plant (CUP). (1) Replace the existing transformers, CT-1, CT-4, CT-7, CT-2, CT-5, & CT-8, common generator grounding resistor, interconnecting lines, and grounding system in the transformer yard. (2) Replace eight roof mounted exhaust fans connected to seven wall louvers controlled by thermostats located in the power generation system area. (3) Replace the existing obsolete models Woodward synchronizers, load controllers, custom PLC based generator controller, and the generator operator Human Machine Interface (HMI) computer and programming.
1.1. Transformer and Common Generator Grounding.
The six (6) transformers provide electrical power for mission critical HVAC equipment such as chillers, water pumps, boiler, and cooling towers in CUP. The common generator grounding resistor prevents damage to the generators by minimizing fault currents during electrical faults because the medium-voltage (MV) generators are not designed to withstand full fault current during an electrical fault. The existing transformers, common generator grounding resistor, interconnecting lines, circuit breakers, grounding system and other components are 20 to 30 years over their life expectancies and are in need of immediate lifecycle replacement. Symptoms of failing transformer and common generator grounding resistor have been noticed such as abnormally high temperatures due to defects on the forced cooling fans, and oil leaks in gaskets and valves. In addition, recent installation of Variable Frequency Drives (VFD) on the chillers creates harmonic currents in the power supplying system requiring K-factor transformers. K-factor transformers are designed to withstand the heating effects of harmonic currents created by loads like VFDs.
It is essential to replace the transformers and common grounding resistor to ensure uninterrupted reliable power to the mission critical HVAC equipment and to prevent failure of the power generating system.
Refer to the transformer drawings, for specific design and requirements.
1.2. Replacement of Roof Exhaust Fans and Wall Louvers.
` Schriever AFB has seven (7) generators in the CUP that provide backup power to the base. There are eight
(8) roof mounted exhaust fans connected to seven (7) wall louvers that turn on when generator room temperature reaches a certain level. In 2009, three (3) of the generators were replaced with new Caterpillar generators. During startup testing, a high bearing temperature alarm was activated. Initial observations from Wagner Power Systems showed improper and insufficient air flow. Initial calculations also show that the existing exhaust fans may be too small to provide adequate airflow. It is essential to replace roof-mounted exhaust fans, wall louvers, louver actuators, and thermostats to maintain cool temperatures in the power generation area.
Refer to the exhaust fans design analysis and drawings, for specific design and requirements.
1.3. Replace of Generator Synchronizers and Load Controllers.
Generator Synchronizers connect emergency power generators to the utility grid through the process of line-synchronization which amounts to generating voltages and phase that match the grid so that the machine can be electrically connected. Load Controllers provide load control across the base electrical system by operating intertie circuit breakers over an Ethernet communication network to control complex generator system.
The existing Generator Synchronizers and Load Controllers are over 20 years old Woodward Generator Synchronizers and Load Controllers which have not been produced by the manufacturer for seven (7) years.
Repair parts for the equipment are no longer available. Some of the current synchronizers have failed resulting in Schriever AFB not being able to synchronize the seven generators with utility power. It is vital to update the equipment to provide fail-safe emergency power to the base critical missions in the absence of utility power. Replacement of nine (9) Woodward synchronizers and four (4) load controllers with new modern models, programming synchronizers and load controllers, and interconnection wiring updates are required to complete this modernization and replacement work.
1.4. Present Equipment Includes:
3 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
1.4.1. Generators:
Caterpillar Diesel (3 each), 8 years old
Model D3516
RPM 1800
KW 2650
Voltage 12,470
Voltage Regulator Caterpillar
Governor Caterpillar
Mirrlees Diesel (3 each), 36 years old
Model KP8 Major
RPM 600
KW 2300
Voltage 12,470
Voltage Regulator Basler SR8F
Governor Woodward EGB35P
Stewart & Stevinson Diesel (1 each), 30 years old
Model L20-645F4B
RPM 900
KW 2700
Voltage 12,470
Voltage Regulator SBSRN-HV
Governor Woodward EGB13P
1.4.2. Synchronizers and Controllers:
Caterpillar Generators (3 each):
Woodward Digital Synchronizer and Load Control (DSLC)
Caterpillar Speed Governor (Integrated into the Caterpillar package)
Caterpillar Fuel Actuators (Integrated into the Caterpillar package)
Caterpillar Voltage Regulators (Integrated into the Caterpillar package)
Mirrlees Generators (3 each):
Woodward Digital Synchronizer and Load Control (DSLC)
Woodward 723 PLUS Digital Speed Governor
Stewart & Stevinson Generator (1 each):
Woodward Digital Synchronizer and Load Control (DSLC)
Woodward 723 PLUS Digital Speed Governor
4 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
Utility Feeder Breakers (2): Woodward Master Synchronizer and Load Control (MSLC)
1.4.3. Communication Network:
LON network between the DSLCs, MSLCs, and 723 Plus controllers
MODBUS between various devices and the master PLC
Master Control and Annunciation PLC
Third-Party PLC provided by others, with interface for Schweitzer protective relays
1.5. All work to be conducted under this contract shall be done under the general conditions of the Statement of Work (SOW) contained herein and all applicable specifications and attachments.
REQUIREMENTS:
The Contractor shall provide all labor, materials, transportation, equipment, and supervision to replace the existing outdated aforementioned three systems in strict accordance with the contract documents. The Contractor shall include information on each type of equipment they are bidding (i.e. cut sheets from the manufacturer). The Contractor shall provide the Government with complete construction, and warranty for this project.
All applicable codes and regulations shall be followed as outlined in section ten (10) of this SOW.
2.1. Outage Board Meetings: Prior to the requested outage date, the Contractor’s Project Manager/Superintendent may be required to attend the Schriever AFB Outage Board meeting (meets weekly) to present and brief their outage request and coordinate issues related to the outage board and impact to other affected facilities and utility systems. Outage request shall be requested no later than two weeks prior to the outage date.
2.2. Construction schedule:
2.2.1. The construction schedule shall detail a plan for minimal risk and shut down during duration of work on the synchronizers, controllers, transformers, and exhaust fans. A detailed outage schedule and plan for power restoration will be required to be presented to, and approved by, the Utility Outage Board two weeks before outages may be performed.
2.2.2. All work on the generator synchronizers and controls shall be performed separately from the work on the transformer replacement, in order to minimize risk of large scale outages.
2.2.3. All work performed on the synchronizers shall be phased in such a way to minimize impact to the backup power capability system for the instillation.
2.2.4. All work performed on the transformers shall be phased in such a way to minimize impact to the power capability system for the instillation.
2.3. Demolition:
2.3.1. Demolition works shall be done in such ways that removal of any part of the equipment shall not impact the Base missions. The Contractor shall provide a demolition work plan for each of the three systems for the Government’s review and approval. Demolished systems must be disposed of by recycling the applicable components in accordance with the guidance listed in section 7.
2.3.2. Demolition of Exhaust Fan System
a. Remove and dispose of the roof-mounted exhaust fans and dampers as indicated on the contract design drawings.
b. Remove and dispose of the existing electrical disconnect, receptacles, and associated wire to the exhaust fans, as indicated on the contract design drawings.
5 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
c. Remove and dispose of the existing lightning protection air terminals and associated roof conductors using support brackets, as indicated on the contract design drawings.
d. Remove and dispose of the existing electric actuators on the wall louvers and associated wiring, as indicated on the contract design drawings.
e. Remove and dispose of the existing thermostats and associated wiring, as indicated on the contract design drawings.
2.3.3. Demolition of Transformers and Common Grounding Resistor
a. Remove and dispose of the existing transformers. Prior to removal of the transformers, the contractor shall coordinate with the Schriever AFB Environmental Section for oil draining and testing to ensure the oil is non-PCB containing. Contractor shall dispose of oil in accordance with appropriate environmental regulations.
b. Remove and dispose of the existing interconnecting cables from SWGR ‘A’ and ‘A1’ to the six transformers.
c. Remove and dispose of the existing interconnecting cables and conduits from the transformers to switchgears CIL.
d. Drawing ED-101 shows the removal of the interconnecting wire and conduit between Transformers CT-4, CT-5, and the Switchgear MVMC. This wire and conduit shall be protected in place and reused.
e. Drawing ED-101 shows the removal of the interconnecting wire and conduit between Transformers CT-6, CT-8, and the Switchgear MVMCC. This wire and conduit shall be protected in place and reused.
f. Remove and dispose of the existing common generator grounding resistor and interconnecting cables connecting Neutral switchgear and the common generator grounding resistor.
g. Remove and dispose of the concrete slabs and walkways in the transformer yard.
h. Remove and dispose of the existing ring ground system for transformers and common generator grounding resistor.
2.3.4. Demolition of Generator Synchronizers and Load Controllers
a. Removal of the synchronizer and controller equipment shall be done in phases to ensure that removal of any part of the equipment shall not impact the required Base emergency power capacity. Base emergency power must be maintained at all times. Coordinate with the 50 CES Construction Manager (CM) for the required Base emergency power when utility power is absent. Any work that may require an electrical outage must be coordinated with the CM at least 20 working days in advance. The Contractor shall provide a demolition work plan for the Government’s review and approval.
2.4. Civil:
2.4.1. Drawings PDF Transformers Replacement – Sheet CP-101, shows concrete pads to be protected in place, this is incorrect. Pads shall be removed and new pads installed for new equipment.
2.4.2. New concrete Pads for Transformers shall be sized to fit new equipment but must fit in existing transformer yard with proper spacing. Pads shall meet specifications as outlined below in 2.4.4 and 2.4.5.
2.4.3. Pour new concrete walkways in transformer yard as shown on drawing: Drawings PDF Transformers Replacement – Sheet CP-101. Expansion joints of the Concrete walkway shall be followed to match new pads.
2.4.4. Transformer Pad Concrete Material Specifications:
6 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
a. Composed of fine aggregate, coarse aggregate, Portland cement, and water so proportioned and mixed as to produce a plastic, workable mixture.
b. Fine aggregate: hard, dense, durable, clean, and uncoated sand.
c. Coarse aggregate: reasonably well graded from 3/16 inch to 1 inch.
d. Fine and coarse aggregates: free from injurious amounts of dirt, vegetable matter, soft fragments, or other deleterious substances.
e. Water: fresh, clean, and free from salts, alkali, organic matter, and other impurities.
f. Concrete associated with electrical work for other than encasement of underground ducts: 30 MPa 4000 psi minimum 28-day compressive strength unless specified otherwise.
g. Slump: Less than 4 inches. Re-tempering of concrete will not be permitted.
h. Exposed, unformed concrete surfaces: smooth, wood float finish.
i. Concrete must be cured for a period of not less than 7 days, and concrete made with high early strength Portland cement must be repaired by patching honeycombed or otherwise defective areas with cement mortar as directed by the Contracting Officer.
j. Air entrain concrete exposed to weather using an air-entraining admixture conforming to
ASTM C260/C260M.
k. Air content: between 4 and 6 percent.
2.4.5. Transformer Pad Construction Specifications:
a. Mount transformer on concrete slab as follows:
b. Unless otherwise indicated, provide the slab with dimensions at least 8 inches thick, with reinforcing 6 by 6 inches - W2.9 by W2.9 mesh placed uniformly 4 inches from the top of the slab.
c. Place slab on a 6 inch thick, well-compacted gravel base.
d. Install slab such that top of concrete slab is approximately 4 inches above the finished grade with gradual slope for drainage.
e. Provide edges above grade with 1/2 inch chamfer.
f. Provide slab of adequate size to project at least 8 inches beyond the equipment.
g. Stub up conduits, with bushings, 2 inches into cable wells in the concrete pad. Coordinate dimensions of cable wells with transformer cable training areas.
2.5. Electrical:
2.5.1. Replace Transformers and Common Grounding Resistor
a. Commissioning of the transformers shall be performed in accordance with all applicable codes as referenced in section 10 of this SOW. The plant manager or approved government representative shall be present.
b. Provide two (2) transformers rated at 1500 KVA, 12.47KV/480V, two (2) transformers rated at 3000 KVA, 12.47KV/4160V, and two (2) transformers rated at 5000 KVA, 12.47Kv/4160V.
Total of six (6) transformers are required, Cooper Power CA202003EN Series or equivalent with 9 K-factor rating. The transformers shall be copper-wound for both primary and secondary windings, dead-front, compartmentalized, load break elbow terminations, fused, loop-feed capable with 6 bushings, a single on-off switch, oil-immersed, and load break switches. Provide a spare conduit in the high voltage section extending 5ft (1.5 m) out from the transformer pad for each transformer. Provide bushing-mounted elbow type lightning arresters.
c. The transformers shall have copper bussing and windings, a minimum of four 2.5% taps (2+, 7 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
2- nominal voltage), and have minimum 9 K-factor rating. Transformer output voltage shall be verified at commissioning of system and load taps adjusted to provide +/- 2.5% of nominal.
Field testing, pre-energized, or manufacturer’s field service shall be required unless specifically stated otherwise.
d. The transformers shall be factory painted in Architectural Brown TR-0611-442 (or equivalent) per FEP. This color is the same as Munsell NEMA Brown 1.6YR 1.2/1.1. Shades that vary in any capacity from this color will not be acceptable.
e. All transformer pads shall have a counterpoise around the pad with two ground conductors bonding the transformer to the counterpoise. A ground rod at each corner shall be installed on the counterpoise. Provide 4/0 copper ring around the pads.
f. All transformers shall be marked from where they are fed and what they feed by white lettering on black placards. Additionally, primary/secondary voltages and KVA shall also be annotated on the placards.
g. Provide a new common generator grounding resistor, 100A, 60 Sec. This is a like-for-like replacement.
h. Provide new interconnecting cables and conduit as indicated on the project drawings and specifications Section 26 05 13.00 40, Medium Voltage Cable. All new interconnecting cables shall be installed in new schedule 40 PVC conduit 36 inch below grade and rigid metal conduit if installed above grade. All replaced conduit inside the building footprint shall be replaced with overhead conduit.
i. Interconnecting cables and conduit between Transformers CT-4, CT-5, and the Switchgear MVMC shall be protected in place and reused.
j. Interconnecting cables and conduit between Transformers CT-6, CT-8, and the Switchgear MVMCC shall be protected in place and reused.
k. Provide a new transformer ring ground system for the transformers and common generator grounding resistor as indicated on the project drawings.
l. Perform ground resistance test on the newly installed ring ground system for the transformers and common generator grounding resistor in accordance with MIL-HDBK-419A and NFPA 70 and provide test results in PDF format to the CO and CM. The resistivity of the new ring ground system shall be 3-ohm or less. If necessary, provide additional ground electrodes and/or soil treatment to achieve a 3-ohm resistivity for the transformer ring ground system.
m. Perform Dielectric-Absorption Tests, Medium-Voltage Tests, and Radiographic Tests on the newly installed interconnecting medium voltage cables in accordance with IEEE 400, “IEEE Guide for Field Testing and Evaluation of the Insulation of Shielded Power Cable Systems” and provide test results in PDF format to the CO.
n. Perform Acceptance Checks and Tests on the new transformers for an insulation power factor test and take an oil sample for a dielectric test, dissolved gas analysis, water-in-oil (Karl Fischer) test, oil acidity test, and PCB content determination in accordance with NETA ATS and provide test results in PDF format to the CO.
o. Provide temporary power and necessary support for 12.47 KV/480 V and 12.47 KV/4160 V services while each set of transformers are being replaced to ensure uninterrupted power to the CUP. Submit the temporary power plan for the Government’s review and approval.
p. Provide a detailed plan to minimize outages for transformer replacement. There is a primary and secondary transformer for each of the three sizes of transformers in this project. None should be out of service for more than 8 hours. This plan must be submitted and approved.
q. Perform selective short-circuit current and protective device coordination studies and provide study results and protective device settings in PDF format to the CO.
8 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
r. See “Design Drawings PDF Transformers Replacement” for detailed design of transformer replacement.
2.5.2. Generator Synchronizers and Load Controllers:
a. Commissioning of the synchronizers and load controllers shall be performed in accordance with all applicable codes as referenced in section 10 of this SOW. The plant manager or approved government representative shall be present.
b. Detailed controls sequence of operation and one line diagrams shall be provided.
c. Only one generator can be offline at a time work shall be scheduled to be completed on each generator in sequence.
d. Replace seven (7) generator breaker DSLC controllers with new Woodward DSLC-2 controllers or equivalent, as a basis of design.
e. Replace two (2) utility breaker controllers with new Woodward MSLC-2 controllers or equivalent, as a basis of design.
f. Replace the 723 PLUS speed governors on the Mirrlees and S&S engines with new Woodward 2301E controllers or equivalent, as a basis of design.
g. Replace the existing master PLC with a new ABB DCS based PLC. The new controller shall interface directly with our existing Schweitzer communication module interface, Schweitzer overcurrent protection relays, the 12.47kV relay and control system, the proposed new generator synchronization and load/governor controls, and new Human Machine Interface “HMI” operator interface computer. The new programmed PLC shall integrate all power system devices, including the DSLC-2s, MSLC-2s, 2301Es, and Schweitzer protective relays, into one system with a new HMI computer. This generic interface/computer system must be programmed to automatically transfer the utility power to operator specified generators when prime utility power is interrupted, and must then transfer the base power load from operator specified generators back to prime utility power once the utility power is restored. This process must be executed seamlessly without power interruption to the base load. The generators shall be able to synchronize with each other and to the utility at the command of the operator or a preprogrammed command sequence. Additionally, the user interface must allow technicians to observe and automatically record the instantaneous and real-time history status of the system via a graphical user interface (GUI) and retain a hard copy printout history for any operation point in time. The operator shall be able to make changes in the sequence of operation without having to learn PLC control language or any special programming language. The controls shall permit the operator to use a graphical keyed or touch screen to control and alter system operation. The system shall be placed in either a manual mode of operator control or in operator selected pre-programmed automated operation modes.
h. Replace all cabinet door meters, switches, and indicators with new high reliability digital display based components and manual switches.
i. Replace all interconnecting wire, and switches, between synchronizers, controllers, and the generators.
j. Re-design and replace the outdated generators synchronization, governor load controls, utility power transfer/synchronization, and “Lonworks” based power system communications networks with a modern “Modbus RTU” local communications system protocol communications network.
k. Provide engineering, project management, materials, scheduling, quality control, installation, programming, training, warranty, and commissioning services to execute the entire project.
l. Copies of all program and configuration files of all devices developed during system design and commissioning shall be provided to the Contracting Officer (CO) and 50 CES Construction
9 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
manager (CM).
2.6. Mechanical:
2.6.1. Replace Exhaust Fan System
a. Install new roof-mounted exhaust fans and dampers as indicated on the contract design drawings. Modify existing roof curbs and roofing, as necessary, for the new exhaust fans to be mounted properly and to maintain roofing warranty.
b. Provide connection to new roof top exhaust fan from existing motor control centers. Ground motor case of each fan.
c. Install new electrical disconnects, GFCI receptacles, and associated wire, to the exhaust fans, as indicated on the contract design drawings.
d. Install new lightning protection air terminals and roof conductors using support brackets and transition clamps as shown on the contract design drawings
e. Install new electric actuators on the wall louvers, new wall louvers and wiring, as indicated on the contract design drawings. Modify the linkages as necessary to accommodate new actuators such that the louvers may be 100% opened and closed.
f. Install new thermostats and associated wiring, as indicated on the contract design drawings.
g. Connect into the existing EMCS system such that exhaust fan status may be monitored.
h. Provide testing, adjusting, and balancing of exhaust fans and wall louvers.
i. See “Design Drawings PDFs Exhaust Fans” for detailed drawings of the exhaust fan replacement.
PERIOD OF PERFORMANCE:
3.1. All work shall be completed within 365 calendar days of the issuance of Notice to Proceed.
3.2. Normal operating hours are weekdays, 7:00 am to 5:00 pm MST. The Contractor must arrange and obtain approval from the Contracting Officer to schedule work and facility access outside these hours.
3.3. Traffic control measures and phasing shall allow for continuous access to all facilities and parking lots.
3.4. Contractor shall not work during any federal holidays.
3.5. Winter exclusions shall not be included in the performance period. Requests to alter these time limits shall be submitted to the Contracting Officer at least (10) working days in advance of the requested date.
GENERAL:
4.1. Existing Conditions: Contractor shall field verify conditions prior to start of work to confirm plans match existing conditions.
4.2. Work Clearance Request: The Contractor shall provide, valid maps clearly showing the location of areas needing work clearance and/or any infrastructure (road, utility lines, etc.,) that will need to be closed prior to work clearance being processed by 50 CES. Need by dates shall be submitted to the CES Project Manager 14 days before work may begin. If work is not completed within 90 days of the clearance approval a new request must be submitted. Initial making will be performed by government personnel. Once a permit is approved, the requestor/excavator will be required to maintain the utility markings until the work has been completed. Makings will be made using water-based paint. The permit will be invalid if the lines are no longer clearly marked in the area where work is being performed. A new permit will need to be submitted
10 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
and approved before any further work is completed. For extended excavations, the contractor shall cut grass and trim around fences within the construction and storage sites to maintain a maximum height of four inches. A copy of the approved permit must be on site at all times while excavation is occurring.
4.2.1. When excavating, personnel will hand dig within two feet of either side (four feet diameter total) of any marked utility line. If the utility is not found after hand excavation, the excavator will contact the appropriate 50 CES / 50 SCS (Comm) representative for a more precise location by calling CE customer Service at 567-2300. If the utility still cannot be found with the assistance of the CE/Comm representative, the excavation may proceed with caution in the area. Exceptions where power tools can be used are: (1) to remove existing pavement or floor surface if it has been determined that no utilities are in the pavement or floor or (2) to break the surface of the soil.
4.2.2. Should any of the coordination points indicate additional utility lines or structures to those already shown on the drawings, by sketch on the Contractor’s drawing or by field location marking, the Contractor shall be responsible for the protection of each of the indicated items. It is the responsibility of the Contractor to verify the exact location of all indicated utility lines and structures, and for the protection of the same, in the project work area. Should damage occur to any utility line or structure, the Contractor shall be responsible for the prompt repair of the damage to return the item to its original working condition.
4.2.3. If any utility is damaged, the excavator must immediately notify their project manager and CE Customer Service (567-2300) with the following information: (1) exact location, (2) type of utility damaged, (3) extent of damage, (4) name and phone number where personnel may be reached.
4.2.4. The excavator shall be held liable for any damage to utilities within the marked areas by construction equipment or materials, to include the cost of labor and materials for emergency responses.
4.2.5. Upon completion of the excavation project, the contractor shall remove all flags, stakes, and construction material for that project. Excavator will return the site to its original condition, remove all rocks, gravel, construction debris, or excess soil. Excavator will clean the site and lay seed as determined by the approving authority on the work clearance request.
4.2.6. Maps showing any new utility lines placed during excavation (if applicable) must be provided to 50 CES/CEN Geobase personnel at the completion of work.
4.2.7. Work during Utility Outages: The contractor shall have contingency plans for continuing work during utility outages caused by the contractor. The plan must also include procedures for promptly repairing utility breaks/interruptions made by the contractor.
4.2.8. Outage Board Meetings: Prior to the requested outage date, the Contractor’s Project Manager/Superintendent may be required to attend the Schriever AFB Outage Board meeting (meets weekly) to present and brief their outage request and coordinate issues related to the outage board and impact to other affected facilities and utility systems. Outage request shall be requested no later than two weeks prior to the outage date.
4.3. Traffic Control: The contractor is responsible for establishing a traffic control plan in accordance with Manual on Uniform Traffic Control Devices (MUTCD) and approved by 50 CES. Traffic control is the sole responsibility of the contractor. Traffic control plan shall be reviewed and approved by the government.
4.4. Restoration to Original Conditions: The contractor shall limit construction activities to those areas within the limits of disturbance. Any disturbance beyond these limits shall be restored to original condition by the contractor at the contractor’s expense.
4.5. Safety: The Contractor shall comply with all applicable Schriever AFB policies and regulations pertaining to safety, health, security, traffic control, fire prevention, and environmental protection. Contractor performing work must comply with EM 385-1-1, AR 385-10, OSHA 29 CFR 1910/1926, EPA & NFPA standards, all rehabilitation/environmental laws and regulations, all electrical work must comply with current NEC standards/comply with NFPA7E for electrical safety, HVAC must meet industrial hygiene ventilation standards, environmental dust suppression plan if required, asbestos air sampling/monitoring and
11 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
abatement plan as required, if applicable wet saw for cutting operations adhered to (silica hazard abatement plan), confined space permitting as required, required respiratory protection, HAZCOM/SDS/PPE, JHA compliance.
4.6. Fire Hydrants: The contractor shall coordinate with the Government Inspector prior to making any fire hydrant connections. A backflow preventer is required to be installed by contractor whenever a hydrant is used to supply water for construction site use.
4.7. Hot Work Permit: The contractor shall obtain hot work permits AF Form 592 prior to conducting any type of hot work or work that may emit sparks such as cutting metal, welding, etc. Permits are required before work may be commenced. It is the contractor's duty to timely obtain such permits.
4.8. Fill Material: Excess fill materials, including rock, gravel, broken concrete or asphalt, etc. shall be removed from the installation and disposed of in accordance with applicable state and local regulations, or as directed by the CO. Excess fill shall not be disposed of in any 100-year floodplain as regulated by County Land Use Department. Additional fill material shall be imported and delivered to the site from off the base grounds as a necessary part of the work. Material composition shall be subject to the requirements of Section 31 23 00, Excavation and Fill, in these specifications.
4.9. Contractor Vehicles: The company name shall be prominently displayed on all Contractor vehicles operated on Schriever AFB. The Contractor may obtain temporary vehicle entry passes needed to transport materials and equipment at Building 15, the Pass and ID Facility. The Contractor shall be equipped to present proof of insurance, driver’s license, vehicle registration, and other documentation as needed to obtain vehicle pass.
Entry to the restricted area of Schriever AFB will require a vehicle pass and additional clearances (i.e. for personnel) as described in section 01 55 04, Security Requirements for Schriever AFB.
4.10. Meetings: Time and place of meetings shall be determined by the CO.
4.10.1. Kick-off Meeting: Before work begins on this contract, the Contracting Officer will arrange for a meeting with the Contractor to discuss the contract in general, including administrative matters, project requirements, submittal procedures, approval and payment schedule, quality control expectations, request for proposal and TO procedures, traffic control, construction access requirements, as-built criteria, performance requirements, security procedures, accident prevention, safety, environment protection, and fire prevention briefings. The Contractor shall submit meeting minutes to the CO and CM.
The following contract requirements and procedures will be discussed during the Pre-Construction Conference, but are not limited to:
a. Project Schedule
b. Contractor Work Progress Reporting Plan
c. Quality Control Plan
d. Accident Prevention Plan
e. Environment Protection Plan
f. Contractor Submittals
g. Contractor Storage/Laydown Yard
h. Utility Outages
i. Government Furnished Information and Materials
j. The SAFB Operating Conditions and The Base Personnel’s Specific Concerns
k. Restricted Area Security Requirements
l. As-Built Drawings and O&M Manuals
12 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
m. The meeting orients the Contractor on Government procedures, contractual lines of authority, and administrative/construction matters. If the magnitude of the project warrants, the preconstruction conference may be held in two parts. The first part of the conference in this case will cover the SAFB operating conditions, the base personnel’s specific concerns, and the Restricted Area Security Requirements and the second component will cover local administrative features between the Government agencies and the Contractor.
n. The agenda of this conference will cover introductions, safety, design briefings (as applicable), user coordination, defense materials system, environmental protection, administrative/technical requirements, Government and Contractor organizations, anticipated critical items, access and security, and potential problem areas. The Contractor Quality Control (CQC) system, Health and Safety plan and Environmental Protection plan are typically discussed in separate meetings.
o. The Contractor shall prepare detailed minutes of the meeting to include items discussed. The original minutes are forwarded to the CO and CM for review with formal written concurrence typically requested within 5 business days. The CO, CM and Contractor sign final minutes of the Pre-construction Conference and the original is sent to the CO and CM.
4.10.2. Pre-Construction Site Survey
The Contractor, prior to the start of any on site construction activities, shall conduct a condition survey with the CO and CM, after which the Contractor shall note the condition of any structural damage that may exist immediately within or adjacent to work site.
4.10.3. Progress Meetings
Bi-weekly progress meetings shall be held. The contractor shall provide the weekly project schedule updates prior to the bi-weekly progress meeting for discussion. These meetings will cover the progress made in the past period and will include any pertinent issues which could affect future contract progress. The Contractor will be responsible for providing Progress Meeting Minutes within 1 business day of conclusion of the meeting.
The following items shall be covered:
a. Meeting Attendees and Contact Information
b. Project Percent Complete (Actual and Scheduled)
c. Schedule
d. Two Week Look Ahead
e. Material Submittals and Statuses
f. RFI’s and Statuses
g. Resolution of Existing Issues
h. New Business
4.11. Delivery & Warranty:
The Contractor shall complete all requirements prior to final inspection. Following final inspection, two electronic copies of as-built drawings, O&M Manuals, and warranties on CDs shall be delivered to the CO within fourteen (14) calendar days.
4.12. Pre-Final Inspection:
The Contractor shall conduct a pre-final walk through inspection with Base personnel and publish the pre-
13 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
final inspection findings in a pre-final inspection (punch list) report. The Contractor shall include a draft DD Form 1354, Transfer and Acceptance of Real Property to the Contracting Officer for review.
4.13. Final Inspection:
The Contractor shall conduct a final inspection with base personnel. The inspection shall concentrate on the items identified at the pre-final inspection and recorded in the pre-final inspection (punch list) report. A final inspection shall not be performed until the pre-final inspection (punch list) report has been resolved. At the final inspection, the Contractor shall present a completed DD Form 1354, Transfer and Acceptance of Real Property to the Base Civil Engineer (BCE) or other appropriate organization for signature and acceptance, if required.
4.14. Final acceptance:
Upon successful final testing in presence of the CO and CM, final electronic copies of “as-built” drawings submitted to CO, and approved site clean-up, the contractors work will be complete.
WARRANTY:
5.1. The warranty period shall commence no sooner than completion and receipt of all documentation. All hardware shall be warrantied for the duration of the Original Equipment Manufacturer (OEM) s’ warranty and installation warranty.
5.2. This warranty period shall cover 1 year warranty of labor and material. Warranty shall include procurement, installation, reinstallation, replace, and repair and cover all project components to include all new equipment, associated components, power and system controls, software, firmware, coding, training, service certification and licensing upgrades (See FAR Clause 52.246-21).
5.3. The Contractor shall warrant to the government all parts, components and devices comprising the working system upgrade for one (1) calendar year, beginning on the date of acceptance by the government.
5.4. During this warranty period, no cost shall accrue to the government for any discovered needed repairs or replacement of any components in the system, (including labor, parts acquisition, stocking charges, transportation or service calls), including components found to be damaged due to this work which is directly related to work and components repaired or replaced by the contractor.
SUBMITTALS:
In accordance with the AF Form 66 developed for this project.
6.1. Required Submittals: The contractor shall provide all materials, equipment and information submittals required by the Government for approval prior to the start of work, as listed in the submittal register, or attachments to this Statement of Work.
6.2. Color Selection: The materials requiring color selection shall be submitted as a package so colors and finishes can be coordinated. The contractor shall submit system configurations, manufacturer’s cut sheets and material information, along with the color data.
6.3. As-Built Drawings: See section 8 for As-built drawing requirements
6.3.1. The as-built drawings shall be submitted to the government in three parts:
a. Hard copy set, half size (17"x 22") or larger - 1 Copy
b. CD or DVD with PDF of files - 2 Copies
c. CD or DVD with all CADD drawing files - 2 Copies
14 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
6.3.2. PDF and CADD files may be on the same disk
6.3.3. All drawings must contain a proper title block with all project information, and final date for as-builts must be noted on each drawing.
6.3.4. The Contractor is required to maintain the digital drawings to Final As-built completion for turn in back to CES.
6.3.5. When contractor is given only a hard copy for which to build as-builts the Contractor is still required to furnish a digital version of final as-built.
ENVIROMENTAL REQUIRMENTS:
The contractor is responsible for adhering to all environmental protection, if applicable.
The Contractor must comply with the SAFB Overarching Environmental Specifications, which outlines provisions to help ensure Contractor compliance with environmental law. Contractor must provide Spill Prevention and Response Plan with every project.
7.1. ENVIROMENTAL ISSUES
7.1.1. Activities implemented, in whole or in part, with federal funds must comply with applicable legislation and regulations established to protect the human or physical environment. The Contractor will remain in compliance with federal statutes during the performance of the contract, including but not limited to the Clean Air Act (CAA), Clean Water Act (CWA), Endangered Species Act, Resource Conservation and Recovery Act (RCRA), and other applicable laws, regulations, and requirements.
7.1.2. Schriever AFB (SAFB) must comply with all Environmental Laws and Regulations as set forth by Federal, State, Department of Defense, Air Force and any other mandated requirements for Federal installations. As such, all SAFB personnel must track all chemicals (hazardous materials), air emissions, storm water, construction and demolition (C&D) debris, and waste/byproducts/excess materials transported, managed, used and disposed from any part of this installation. This requirement is for all installation organizations, workplaces, work centers, shops and for all Contractors doing any work on the installation. Contractors shall investigate, comprehend, and comply with all environmental rules, regulations, and permits applicable to their chosen method of accomplishment of the work under this contract. The Contractor is responsible for any fees for the work that needs to be accomplished and also fees that may be required due to permit violations.
7.1.3. The Contractor will be responsible for, insure and hold the Government harmless for all spills, releases, emission, and discharges of any toxic or hazardous substance, any pollutant, or any waste, whether sudden or gradual, caused by or arising under the performance of this contract. This applies to any substance, material, equipment, or facility utilized by the Contractor. For the purposes of any environmental statute or regulation, the Contractor will be considered the "operator" for any facility used in the performance of the contract, and will indemnify and hold the Government harmless for the failure to adhere to any applicable law or regulation established to protect the human or physical environment. The Contractor will be responsible in the same manner as above regardless of whether activities leading to or causing a spill, release, emission or discharge are performed by the Contractor, its agent or designee, an offender, visitor, or any third party.
7.2. HAZARDOUS MATERIAL/ WASTE MANAGEMENT
The following is a breakdown of all required information that deals with the transport, use and disposal of any hazardous chemicals and waste materials on or from the installation. The Contractor will be further briefed on the SAFB Hazardous Waste Management Plan at the pre-performance conference.
7.2.1. HAZARDOUS MATERIALS
15 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
Contractors using any type of hazardous materials (HM) on SAFB must comply with the review and approval process and shall provide the Contracting Officer (CO) with a list of proposed materials that it plans to use on the installation during the performance of the contract.
7.2.2. At least 30 days prior to the contract start date, the Contractor shall provide to the CO a copy of the 3952 Form, SAFB Hazardous Material Tracking Form - Material and Approval Submittal, listing all materials that will be utilized during the contract period as well as the current Safety Data Sheet (SDS). The 50 Civil Engineering Squadron Environmental Management Element (50 CES/CEIE) will determine if any of the proposed materials are classified as hazardous and are covered under Emergency Planning and Community Right-to-Know Act (EPCRA) (42 U.S.C. 11001-11050). If they fall into this category 50 CES/CEIE will issue an authorized use list to the CO for this Contractor.
7.2.3. Once on site the Contractor will report through the CO to the 50 Logistics Readiness Flight (LRF) HM pharmacy located at building 613 to get approved barcode tracking labels for all HM. The Contractor must maintain a file of all SDSs during the performance of this contract. Any HMs not utilized by the Contractor must be taken off SAFB as soon as the project ends.
7.2.4. If additional HM is required during the course of the contract or if there is a change to existing HM, the Contractor shall update the 3952 Form and provide a SDS for each HM through the CO to 50 CES/CEIE. The Contractor shall submit the new authorization request no later than (NLT) 15 days prior to delivery of the HM onto SAFB.
7.2.5. For each Contractor-identified chemical that 50 CES/CEIE determines does not meet the definition of a HM, EPCRA requirements do not apply. 50 CES/CEIE will notify the CO that the Contractor has authorization to bring and use that material on the installation without reporting usage use unless required under Green Procurement Program or specifications requiring data submittals.
7.2.6. The main Contractor is responsible for reporting all sub-contractors HM usage from the date of hire throughout the duration of their contract through the CO to 50 CES/CEIE. No HM, lubricants, oils, liquids or related materials shall be deposited in the refuse containers on the installation.
7.2.7. The Contractor shall not use products that are, or contain Diisocyanates, Dioxins and Dioxin-like Compounds, Extremely Hazardous Substances, Ozone Depleting Substances (ODS), CFCs or Persistent Bio-accumulative and Toxic chemicals. Any HM containing any of these banned substances will not be allowed on the installation.
7.2.8. If the HM request is for a Class I ODS, 50 CES/CEIE will ensure there is an applicable and current Air Force Senior Acquisition Official (SAO) approval for contract Class I ODS requirements before approving the HM authorization and made available to the Contractor. The CO will also maintain a copy of the SAO approval in the contract file as required by AFI 32-7086.
7.2.9. Reporting Requirements: The Contractor shall submit all information needed by the base to comply with the following:
a. Emergency planning reporting requirements of Section 302 of EPCRA.
b. Emergency notice requirements of Section 304 of EPCRA
c. List of Safety Data Sheets required by Section 311 of EPCRA
d. Emergency and hazardous chemical inventory forms of Section 312 of EPCRA
e. Toxic chemical release inventory of Section 313 of EPCRA, which includes the reduction and recycling information required by Section 6607 of PPA
f. Toxic chemical reduction goals requirements of Section 3-302 of Executive Order 12856
g. Pollution Prevention and Right-to-Know Information as per the FAR 52.223-5 (Apr 1998)
h. Executive Order 13148 Greening the Government through Leadership in Environmental Management
16 | P a g e
“Masters of Space, Home of the 50th Space Wing!”
i. Executive Order 13423, Strengthening Federal Environmental, Energy and Transportation Management
Note: No hazardous or potentially hazardous material may be brought onto the installation without full compliance with all authorization, approval, and reporting requirements specified in the Federal, DOD and Air Force regulations or local supplements.
7.2.10. DISPOSAL OF WASTES (NON-HAZARDOUS, SPECIAL, AND HAZARDOUS)
GENERATED
a. The Integrated Solid Waste Management Plan (ISWMP) is a comprehensive approach to managing non-hazardous solid waste. It encompasses waste prevention, recycling, composting, and disposal programs. Through the ISWMP, Air Force installations or facilities seek to determine the most cost effective, energy-efficient, least-polluting ways to deal with their waste streams in order to protect human health and the environment. As applicable, the ISWMP will be briefed to the Contractor.
b. Non-Hazardous Wastes: Non-hazardous solid waste is regulated under 42 U.S. Code Chapter 82 – Solid Waste Disposal - Resource Conservation and Recovery Act (RCRA) Subtitle D, 40 CFR Part 239-259 and set minimum federal criteria for the operation of municipal waste and industrial waste landfills, including design criteria, location restrictions, financial assurance, corrective action (cleanup), and closure requirement. States play a lead role in implementing these regulations and may set more stringent requirements. In absence of an approved state program, the federal requirements must be met by waste facilities.
c. The Contractor shall transport and dispose of all non-hazardous wastes to a permitted facility or other disposal facility permitted by the state in which the disposal facility is located.
d. Special Wastes: Special…
This is the start of the file's text. The full file is on GovTribe.