7_-_GLEN18-1101_AF_66_Form.xls

XLS spreadsheet 136 KB Posted

Attached to
Solicitation_GLEN_18-1101
Solicitation number
FA255019RA010
Issued by

About this file

This document is a submittal schedule for a federal contract solicitation to replace mission essential systems at a Central Utility Plant on an Air Force base. The solicitation seeks proposals to (1) replace transformers and associated equipment in the transformer yard, (2) replace eight roof mounted exhaust fans and wall louvers, and (3) replace obsolete generator synchronizers, load controllers, and the generator operator HMI system. Offerors must submit qualifications, plans, test results, and other documentation according to the schedule's deadlines, with responses required within 30 days of award and some tests required 160-200 days after notice to proceed. The 50th Civil Engineer Squadron at the Department of the Air Force Space Command is the contracting agency.

AF 66

View the file

Other files

Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal 1

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT NAMESOLICITATION /CONTRACT NUMBER
GLEN 18-1101B600 Electrical & Mechanical Systems Repair
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERCERTIFICATE OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYAS-BUILT DRAWINGSREPORTTEST RESULTSREQUIRED SUBMISSION DATE
(CALENDAR DAYS)DATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVALREMARKS
GENERAL
1Project Specific MSDS Sheets1AWARD+30
2Form-3064 Contract Progress Schedule1AWARD+30
3Form-3065 Contract Progress Report1NTP+WEEKLY
4Health, Safety, and Environment Plan(s)1AWARD+10
6Contractor's Quality Control Plan1AWARD+10
7Operation and Storage Areas1AWARD+10
8Utility Outages1AWARD+60
9Submittal Log1AWARD+30
DESIGN
10Shop Drwaings for Transformer Repalcement1AWARD+30
11Shop Drwaings for Generator Synchronizers and Load Controllers1AWARD+30
CIVIL
11Demolition Work plan1AWARD+30
12Current Backflow Preventer Inspection Cart1110days prior to any work
13Joint layout plan10days prior to any work
14Select fill class 6 sieve analysis11AWARD+30
15soil compaction test results11Within 3 days after test results are made available
16concrete mix design per ACI11AWARD+30
17concrete batch tickets, each truck11Following day
18concrete 7 and 28 day ACI compressive strength test results11Within 3 days after test results are made available
19product data -expansion joint sealant11AWARD+30
20concrete aggregate sieve analysis11Pour+30
21concrete curing compounds, admixtures, joint sealants, expansion joints, and asphalt crack sealant materials11AWARD+30
22sampling and testing. Aggregate base-sieve results, field density tests11Within 3 days after test results are made available
ELECTRICAL
23Medium Voltage Cables111AWARD+60
24Medium Voltage Cable Test Reports1AWARD+60
25Cable Splicer, Terminator and Installer Qualifications1AWARD+30
26Low Voltage Cables111AWARD+30
27Connectors111AWARD+30
28Terminals111AWARD+30
29Breakers111AWARD+30
30Conduits11AWARD+30
31Transformers111AWARD+30
32Transformer Checks and Tests Reports11NTP+160
33Transformer Field Test Reports11NTP+160
34Common Generator Grounding Resistor111AWARD+30
35Grounding Resistor Checks and Tests Reports11NTP+180
36Grounding Resisitor Hi-Pot Test Report11NTP+180
37Exhaust Fans111AWARD+30
38Louvers111AWARD+30
39Louver Actuators111AWARD+30
40Thermostat111AWARD+30
41Discoonect switches111AWARD+30
42Electrodes11AWARD+30
43Grounding Conductors11AWARD+30
44Grounding Test Well11AWARD+30
45Medium Voltage Surge Arresters111AWARD+30
46Pulling Wire Plan1AWARD+30
47Medium Cable Hi-Pot Test Reports1NTP+200
48Generator Synchronizers and Load Controllers1111AWARD+30
49Temporary Power Plan for Transformer Repacement1AWARD+30
50Other Associated Hardware111AWARD+30
51Portable Generator and fuel tank11AWARD+30
CLOSEOUT
51O&M Maintainance data, manuals and Manufacturer's Warranties1DUE AT Pre-Final
52Factory and Field Test Certificates, Logs and Test Results11DUE AT FINAL
53Contractor's Warranty Period Begins1DUE AT FINAL
54Selective Coordination Study Results and Protective Devices Settings1DUE AT Re-Final
55As Built Drawings in AutoCAD & PDF electronic formats + 1 set in printed hard copy1DUE AT Pre-Final

&L&9Project Submittal Form AF-66