This solicitation seeks proposals to replace three mission essential systems at a central utility plant on an Air Force base. Offerors are requested to replace transformers and associated equipment in the plant's transformer yard, replace eight exhaust fans and related ventilation components, and replace obsolete generator control systems including synchronizers, load controllers, and human-machine interface equipment. Proposals are due by September 27, 2019. The award will be made to the lowest priced technically acceptable offeror in accordance with FAR part 15. The work must be completed within 365 days of notice to proceed. The Air Force plans to award a firm-fixed-price contract for the work.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NO. 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect calls)
8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NO.
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
RFQ IFB RFP
SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
29. AWARD OF CONTRACT: REF. OFFER
DATED . . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA - FAR (48 CFR) 53.212
10. THIS ACQUISITION IS UNRESTRICTED OR
NAICS:
SIZE STANDARD:
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
SET ASIDE: % FOR:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
8 (A)
EDWOSB
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
FA255019RA010
Solicitation/Contract Form
Supplies or Services and Prices/Cost
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price Amount
0001 Replace the existing transformers, CT-1, CT-4, CT-7, CT-2, CT-5, & CT-8, common generator grounding resistor, interconnecting lines, and grounding system in the transformer yard.
Firm Fixed Price
1.0 Lot
0002 Replace eight roof mounted exhaust fans connected to seven wall louvers controlled by thermostats located in the power generation system area.
Firm Fixed Price
1.0 Lot
0003 Replace the existing obsolete models Woodward synchronizers, load controllers, custom PLC based generator controller, and the generator operator Human Machine Interface (HMI) computer and programming.
Firm Fixed Price
1.0 Lot
Description/Specifications/Statement of Work
Requirements This is a new requirement to replace three mission essential systems in building 600, Central Utility Plant (CUP). (1) Replace the existing transformers, CT-1, CT-4, CT-7, CT-2, CT-5, and CT-8, common generator grounding resistor, interconnecting lines, and grounding system in the transformer yard. (2) Replace eight roof mounted exhaust fans connected to seven wall louvers controlled by thermostats located in the power generation system area. (3) Replace the existing obsolete models Woodward synchronizers, load controllers, custom PLC based generator controller, and the generator operator Human Machine Interface (HMI) computer and programming.
GLEN 18-1011 B600 Electrical and HVAC Upgrade I. Project Title: B600 Electrical and HVAC Upgrade II. Set Aside: HUBZone III. Magnitude: Between $1,000,000 and $5,000,000 IAW FAR 36.204 IV. Period of Performance: 365 days after issuance of NTP V. NAICS Code: 238210 Electrical Contractors and Other Wiring Installation VI. Statement of Work: See Attached VII. Notice to Offeror: Funds ARE NOT currently available for this effort.
VIII. Attachments: See Attachment Section for the attachment list
Offers providing less than ___60___ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
Important Dates:
29 Aug 19: RFP Release 9 Sep 19: Site Visit starting 0830 at Schriever AFB Visitor’s Center 13 Sep 19: All RFI’s due by 2pm 18 Sep 19: RFI responses posted to FBO.GOV by 2pm 27 Sep 19: Proposals due at 2pm
Packaging and Marking
Inspection and Acceptance
0001 Inspection and Acceptance Location
Both Destination Instructions: Inspection will be performed at Schriever AFB.
DoDAAC: F3R3D0 Cage:
DunsNumber:
Duns4Number:
CountryCode: USA
F3R3D0 50 CES
500 OMALLEY AVE STE 19
AF NO MILSBILLS PROC CP 7195676975
SCHRIEVER AFB, CO 80912 3005
United States
OfficeCode:
Michael Mattson Telephone: 719-567-4687 Email:
0002 Inspection and Acceptance Location
Both Destination Instructions: Inspection will be performed at Schriever AFB.
DoDAAC: F3R3D0 Cage:
DunsNumber:
Duns4Number:
CountryCode: USA
F3R3D0 50 CES
500 OMALLEY AVE STE 19
AF NO MILSBILLS PROC CP 7195676975
SCHRIEVER AFB, CO 80912 3005
United States
OfficeCode:
Michael Mattson Telephone: 719-567-4687 Email:
0003 Inspection and Acceptance Location
Both Destination Instructions: Inspection will be performed at Schriever AFB.
DoDAAC: F3R3D0 Cage:
DunsNumber:
Duns4Number:
CountryCode: USA
F3R3D0 50 CES
500 OMALLEY AVE STE 19
AF NO MILSBILLS PROC CP 7195676975
SCHRIEVER AFB, CO 80912 3005
United States
OfficeCode:
Michael Mattson Telephone: 719-567-4687 Email:
Deliveries or Performance
0001 Delivery Schedule Ship To Address
Delivery Schedule From date of lead time event to completion of performance 365 Calendar Days Date of Notice to Proceed Receipt
Place of Performance
DoDAAC: F3R3D0 Cage:
DunsNumber:
Duns4Number:
CountryCode: USA
F3R3D0 50 CES
500 OMALLEY AVE STE 19
AF NO MILSBILLS PROC CP 7195676975
SCHRIEVER AFB, CO 80912 3005
United States
OfficeCode:
Michael Mattson Telephone: 719-567-4687
0002 Delivery Schedule Ship To Address performance 365 Calendar Days Date of Notice to Proceed Receipt
Place of Performance
DoDAAC: F3R3D0 Cage:
DunsNumber:
Duns4Number:
CountryCode: USA
F3R3D0 50 CES
500 OMALLEY AVE STE 19
AF NO MILSBILLS PROC CP 7195676975
SCHRIEVER AFB, CO 80912 3005
United States
OfficeCode:
Michael Mattson Telephone: 719-567-4687
0003 Delivery Schedule Ship To Address performance 365 Calendar Days Date of Notice to Proceed Receipt
Place of Performance
DoDAAC: F3R3D0 Cage:
DunsNumber:
Duns4Number:
CountryCode: USA
F3R3D0 50 CES
500 OMALLEY AVE STE 19
AF NO MILSBILLS PROC CP 7195676975
SCHRIEVER AFB, CO 80912 3005
United States
OfficeCode:
Michael Mattson Telephone: 719-567-4687
Contract Administration Data
Special Contract Requirements
Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
Number Title Effective Date 52.202-1 Definitions Nov 2013 52.203-3 Gratuities Apr 1984 52.203-5 Covenant Against Contigent Fees May 2014 52.203-6 Restrictions on Subcontractor Sales to the Government Sep 2006 52.203-7 Anti-Kickback Procedures May 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity May 2014 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity May 2014 52.203-12 Limitation on Payments to Influence Certain Federal Transactions Oct 2010 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights Apr 52.204-4 Printed or Copies Double-Sided on Postconsumer Fiber Content Paper May 2011 52.204-7 System for Award Management Oct 2016 52.204-9 Personal Identity Verification of Contractor Personnel Jan 2011 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards Oct 2016 52.204-13 System for Award Management Maintenance Oct 2016 52.204-16 Commercial and Government Entity Code Reporting Jul 2016 52.204-18 Commercial and Government Entity Code Maintenance Jul 2016 52.204-19 Incorporation by Reference of Representations and Certifications Dec 2014 52.204-22 Alternative Line Item Proposal Jan 2017 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities Jul 2018 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment Aug 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment Aug 52.209-6 Protecting the Governments's Interst When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment Oct 2015 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters Oct 2018 52.209-10 Prohibition on Contracting With Inverted Demestic Corporations Nov 2015 52.211-10 Commencement, Prosecution, and Completion of Work Apr 1984 52.214-34 Submission of Offers in the English Language Apr 1991 52.214-35 Submission of Offers in U.S. Currency Apr 1991 52.215-1 Alt I Instructions to Offerors--Competitive Acquisition Jan 2017 52.215-2 Audit and Records--Negotiation Nov 2011 52.215-8 Order of Precedence - Uniform Contract Format Oct 1997 52.219-3 Notice of HUBZone Set-Aside or Sole Source Award 52.219-6 Deviation 2019-O0003 Notice of Total Small Business Set-Aside Dec 2018 52.219-8 Utilization of Small Business Concerns Nov 2016 52.219-13 Notice of Set-Aside of Orders Nov 2011 52.219-14 Deviation 2019-O0003 Limitations of Subcontracting Dec 2018 52.222-3 Convict Labor Jun 2003 52.222-4 Contract Work Hours and Safety Standards - Overtime Compensation May 2014 52.222-6 Construction Wage Rate Requirement May 2014 52.222-7 Withholding of Funds May 2014 52.222-8 Payrolls and Basic Records May 2014 52.222-9 Apprentices and Trainees Jul 2005 52.222-10 Compliance With Copeland Act Requirements Feb 1988 52.222-11 Subcontracts (Labor Standards) May 2014 52.222-12 Contract Termination-Debarment May 2014 52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations May 2014 52.222-14 Disputes Concerning Labor Standards Feb 1988 52.222-15 Certification of Eligibility May 2014 52.222-21 Prohibition of Segregated Facilities Apr 2015 52.222-23 Notice of Tequirements for Affirmative Action to Ensure Equal Employment Opportunity for Construction Feb 1999 52.222-26 Equal Opportunity Sep 2016 52.222-27 Affirmative Action Compliance Requirements for Construction Apr 2015 52.222-35 Equal Opportunity for Veterans Oct 2015 52.222-36 Equal Opportunity for Workers with Disabilities Jul 2014
52.222-37 Employment Reports on Veterans Feb 2016 52.222-40 Notification of Employee Rights Under the National Labor Relations Act Dec 2010 52.222-50 Combating Trafficking in Persons Mar 2015 52.222-54 Employment Eligibility Verification Oct 2015 52.222-55 Minimum Wages Under Executive Order 13658 Dec 2015 52.222-62 Paid Sick Leave Under Executive Order 13706 Jan 2017 52.223-5 Pollution Prevention and Right-To-Know Information May 2011 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts May 2008 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving Aug 2011 52.225-13 Restrictions on Certain Foreign Purchases Jun 2008 52.227-1 Authorization and Consent Dec 2007 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement Dec 2007 52.227-4 Patent Indemnity-Construction Contracts Dec 2007 52.228-2 Additional Bond Security Oct 1997 52.228-5 Insurance - Work on a Government Installation Jan 1997 52.228-11 Pledges of Assets Jan 2012 52.228-12 Prospective Subcontractor Requests for Bonds May 2014 52.228-14 Irrevocable Letter of Credit Nov 2014 52.228-15 Performance and Payment Bonds--Construction Oct 2010 52.229-3 Federal, State and Local Taxes Feb 2013 52.232-5 Payments Under Fixed-Price Construction Contracts May 2014 52.232-8 Discounts for Prompt Payment Feb 2002 52.232-13 Notice of Progress Payments Apr 1984 52.232-16 Progress Payments Apr 2012 52.232-17 Interest May 2014 52.232-23 Assignment of Claims May 2014 52.232-27 Prompt Payment for Construction Contracts Jan 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award Management Jul 2013 52.232-39 Unenforceability of Unauthorized Obligations Jun 2013 52.232-40 Providing Accelerated Payments to Small business Subcontractors Dec 2013 52.233-1 Disputes May 2014 52.233-3 Protest After Award Aug 1996 52.233-4 Applicable Law for Breach of Contract Claim Oct 2004 52.236-2 Differing Site Conditions Apr 1984 52.236-5 Material and Workmanship Apr 1984 52.236-6 Superintendence by the Contractor Apr 1984 52.236-7 Permits and Responsibilities Nov 1991 52.236-8 Other Contracts Apr 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements Apr 1984 52.236-10 Operations and Storage Areas Apr 1984 52.236-11 Use and Possession Prior to Completion Apr 1984 52.236-12 Cleaning Up Apr 1984 52.236-13 Accidend Prevention Nov 1991 52.236-15 Schedules for Construction Contracts Apr 1984 52.236-21 Specifications and Drawings for Construction Feb 1997 52.236-26 Preconstruction Conference Feb 1995 52.236-28 Preparation of Proposals - Construction Oct 1991 52.242-13 Bankruptcy Jul 1995 52.242-14 Suspension of Work Apr 1984 52.242-15 Stop-Work Order Aug 1989 52.243-1 Alt II Changes - Fixed Price Aug 1987 52.243-4 Changes Jun 2007 52.244-6 Subcontracts for Commercial Items Nov 2017 52.246-12 Inspection of Construction Aug 1996 52.246-21 Warranty of Construction Mar 1994 52.247-34 F.o.b. Destination Nov 1991 52.248-3 Value Engineering-Construction Oct 2015 52.249-2 Termination for Convenience of the Government (Fixed-Price) Apr 2012 52.249-2 Alt I Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - Alternate I Sep 1996 52.249-10 Default (Fixed-Price Construction) Apr 1984 52.252-3 Alterations in Solicitation Apr 1984 52.252-4 Alterations in Contract Apr 1984 52.253-1 Computer Generated Forms Jan 1991 252.201-7000 Contracting Officer's Representative Dec 1991
252.203-7000 Requirements Relating to Compensation of Former DoD Officials Sep 2011 252.203-7001 Prohibition on Persons Convicted of Fraud or Other Defense-Contract-Related Felonies Dec 2008 252.203-7002 Requirement to Inform Employees of Whistleblower Rights Sep 2013 252.203-7003 Agency Office of the Inspector General Dec 2012 252.203-7005 Representation Relating to Compensation of Former DoD Officials Nov 2011 252.204-7003 Control of Government Personnel Work Product Apr 1992 252.204-7004 Level I Antiterrorism Awareness Training for Contractors Feb 2019 252.204-7006 Billing Instructions Oct 2005 252.204-7008 Compliance With Safeguarding Covered Defense Information Controls Oct 2016 252.204-7012 Safeguarding Covered Defense Information for Litigation Support Oct 2016 252.204-7015 Notice of Authorized Disclosure of Informationfor Litigation Support May 2016 252.205-7000 Provision of Information to Cooperative Agreement Holders Dec 1991 252.209-7004 Subcontracting With Firms that are Owned or Controlled by the Government of a Country that is a State Sponsor of Terrorism Oct 2015 252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors Jan 2018 252.222-7006 Restrictions on the Use of Mandatory Arbitration Agreements Dec 2010 252.223-7001 Gazard Warning Labels Dec 1991 252.223-7004 Drug-Free Work Force Sep 1988 252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials Sep 2014 252.223-7008 Prohibition of Hexavalent Chromium Jun 2013 252.225-7001 Buy American and Balance of Payments Program Dec 2017 252.225-7002 Qualifying Country Sources as Subcontractors Dec 2017 252.225-7012 Preference for Certain Demestic Commodities Dec 2017 252.225-7048 Export-Controlled Items Jun 2013 252.226-7001 Utilization of Indian Organizations, Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns Apr 2019 252.227-7000 Non-estoppel Oct 1966 252.227-7033 Rights in Shop Drawings Apr 1966 252.232-7003 Electronic submission of Payment Requests and Receiving Reports Jun 2012 252.232-7004 DoD Progress Payment Rates Oct 2014 252.232-7003 Electronic Submission of Payment Requstes and Receiving Reports Dec 2018 252.232-7010 Levies on Contract Payments Dec 2006 252.236-7000 Modification Proposals-Price Breakdown Dec 1991 252.242-7006 Accounting System Administration Feb 2012 252.243-7001 Pricing of Contract Modification Dec 1991 252.243-7002 Requests for Equitable Adjustment Dec 2012 252.247-7023 Transportation of Supplies by Sea Apr 2014 5352.223-9000 Elimination of Use of Class 1 Ozone Depleting Substances Nov 2012 5352.242-9000 Contractor Access to Air Force Installations Nov 2012
CLAUSES INCORPORATED BY FULL TEXT
52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-- Representation (Jan 2017)
(a) Definition. As used in this provision-- "Internal confidentiality agreement or statement", "subcontract", and "subcontractor", are defined in the clause at 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.
(b) In accordance with section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions), Government agencies are not permitted to use funds appropriated (or otherwise made available) for contracts with an entity that requires employees or subcontractors of such entity seeking to report waste, fraud, or abuse to sign internal confidentiality agreements or statements prohibiting or otherwise restricting such employees or subcontractors from lawfully reporting such waste, fraud, or abuse to a designated investigative or law enforcement representative of a Federal department or agency authorized to receive such information.
(c) The prohibition in paragraph (b) of this provision does not contravene requirements applicable to Standard Form 312, (Classified Information Nondisclosure Agreement), Form 4414 (Sensitive Compartmented Information Nondisclosure Agreement), or any other form issued by a Federal department or agency governing the nondisclosure of classified information.
(d) Representation. By submission of its offer, the Offeror represents that it will not require its employees or subcontractors to sign or comply with internal confidentiality agreements or statements prohibiting or otherwise restricting such employees or subcontractors from lawfully reporting waste, fraud, or abuse related to the performance of a Government contract to a designated investigative or law enforcement representative of a Federal department or agency authorized to receive such information (e.g., agency Office of the Inspector General).
(End of provision)
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017)
(a) Definitions. As used in this clause-- "Internal confidentiality agreement or statement" means a confidentiality agreement or any other written statement that the contractor requires any of its employees or subcontractors to sign regarding nondisclosure of contractor information, except that it does not include confidentiality agreements arising out of civil litigation or confidentiality agreements that contractor employees or subcontractors sign at the behest of a Federal agency.
"Subcontract" means any contract as defined in subpart 2.1 entered into by a subcontractor to furnish supplies or services for performance of a prime contract or a subcontract. It includes but is not limited to purchase orders, and changes and modifications to purchase orders.
"Subcontractor" means any supplier, distributor, vendor, or firm (including a consultant) that furnishes supplies or services to or for a prime contractor or another subcontractor.
(b) The Contractor shall not require its employees or subcontractors to sign or comply with internal confidentiality agreements or statements prohibiting or otherwise restricting such employees or subcontractors from lawfully reporting waste, fraud, or abuse related to the performance of a Government contract to a designated investigative or law enforcement representative of a Federal department or agency authorized to receive such information (e.g., agency Office of the Inspector General).
(c) The Contractor shall notify current employees and subcontractors that prohibitions and restrictions of any preexisting internal confidentiality agreements or statements covered by this clause, to the extent that such prohibitions and restrictions are inconsistent with the prohibitions of this clause, are no longer in effect.
(d) The prohibition in paragraph (b) of this clause does not contravene requirements applicable to Standard Form 312 (Classified Information Nondisclosure Agreement), Form 4414 (Sensitive Compartmented Information Nondisclosure Agreement), or any other form issued by a Federal department or agency governing the nondisclosure of classified information.
(e) In accordance with section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015, (Pub. L. 113-235), and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions) use of funds appropriated (or otherwise made available) is prohibited, if the Government determines that the Contractor is not in compliance with the provisions of this clause.
(f) The Contractor shall include the substance of this clause, including this paragraph (f), in subcontracts under such contracts.
(End of clause)
52.204-8 Annual Representations and Certifications (Oct 2018) (a)
(1) The North American Industry classification System (NAICS) code for this acquisition is 238210.
(2) The small business size standard is $15M.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)
(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[_] (i) Paragraph (d) applies.
[_] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)
(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless--
(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;
(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or
(C) The solicitation is for utility services for which rates are set by law or regulation.
(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.
(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements--Representation. This provision applies to all solicitations.
(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.
(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that--
(A) Are not set aside for small business concerns;
(B) Exceed the simplified acquisition threshold; and
(C) Are for contracts that will be performed in the United States or its outlying areas.
(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations--Representation.
(vii) 52.209-5; Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.
(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.
(ix) 52.214-14, Place of Performance--Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.
(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.
(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.
(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.
(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.
(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.
(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.
(xiv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.
(xv) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.
(xvi) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(xvii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.
(xviii) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals--Representation. This provision applies to solicitations that include the clause at 52.204-7.
(xix) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.
(xx) 52.225-4, Buy American--Free Trade Agreements--Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225- 3.
(A) If the acquisition value is less than $25,000, the basic provision applies.
(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.
(C) If the acquisition value is $50,000 or more but is less than $80,317, the provision with its Alternate II applies.
(D) If the acquisition value is $80,317 or more but is less than $100,000, the provision with its Alternate III applies.
(xxi) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.
(xxii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan--Certification. This provision applies to all solicitations.
(xxiii) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certification. This provision applies to all solicitations.
(xxiv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.
(2) The following representations or certifications are applicable as indicated by the Contracting Officer:
[Contracting Officer check as appropriate.] ___ (i) 52.204-17, Ownership or Control of Offeror.
___ (ii) 52.204-20, Predecessor of Offeror.
___ (iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.
___ (iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Certification.
___ (v) 52.222-52 Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-- Certification.
___ (vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA-Designated Products (Alternate I only).
___ (vii) 52.227-6, Royalty Information.
___ (A) Basic.
___ (B) Alternate I.
___ (viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.
(d) The Offeror has completed the annual representations and certifications electronically in SAM accessed through https:// www.sam.gov. After reviewing the SAM information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
FAR Clause Title Date Change
Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.
(End of Provision)
52.209-7 Information Regarding Responsibility Matters (Oct 2018)
(a) Definitions. As used in this provision-- "Administrative proceeding" means a non-judicial process that is adjudicatory in nature in order to make a determination of fault or liability (e.g., Securities and Exchange Commission Administrative Proceedings, Civilian Board of Contract Appeals Proceedings, and Armed Services Board of Contract Appeals Proceedings). This includes administrative proceeding at the Federal and State level but only in connection with performance of a Federal contract or grant. It does not include agency actions such as contract audits, site visits, corrective plans, or inspection of deliverables.
"Federal contracts and grants with total value greater than $10,000,000" means--
(1) The total value of all current, active contracts and grants, including all priced options; and
(2) The total value of all current, active orders including all priced options under indefinite-delivery, indefinite-quantity, 8(a), or requirements contracts (including task and delivery and multiple-award Schedules).
"Principal" means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).
(b) The offeror [_] has [_] does not have current active Federal contracts and grants with total value greater than $10,000,000.
(c) If the offeror checked "has" in paragraph (b) of this provision, the offeror represents, by submission of this offer, that the information it has entered in the Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete as of the date of submission of this offer with regard to the following information:
(1) Whether the offeror, and/or any of its principals, has or has not, within the last five years, in connection with the award to or performance by the offeror of a Federal contract or grant, been the subject of a proceeding, at the Federal or State level that resulted in any of the following dispositions:
(i) In a criminal proceeding, a conviction.
(ii) In a civil proceeding, a finding of fault and liability that results in the payment of a monetary fine, penalty, reimbursement, restitution, or damages of $5,000 or more.
(iii) In an administrative proceeding, a finding of fault and liability that results in--
(A) The payment of a monetary fine or penalty of $5,000 or more; or
(B) The payment of a reimbursement, restitution, or damages in excess of $100,000.
(iv) In a criminal, civil, or administrative proceeding, a disposition of the matter by consent or compromise with an acknowledgment of fault by the Contractor if the proceeding could have led to any of the outcomes specified in paragraphs (c)(1)(i), (c)(1)(ii), or (c)(1)(iii) of this provision.
(2) If the offeror has been involved in the last five years in any of the occurrences listed in (c)(1) of this provision, whether the offeror has provided the requested information with regard to each occurrence.
(d) The offeror shall post the information in paragraphs (c)(1)(i) through (c)(1)(iv) of this provision in FAPIIS as required through maintaining an active registration in the System for Award Management which can be accessed via https:// www.sam.gov (see 52.204-7).
(End of provision)
52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) The Contractor shall be required to
(a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than 365 calendar days after the receipt of the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
52.215-5 Facsimile Proposals (Oct 1997)
(a) Definition.
Facsimile proposal, as used in this provision, means a proposal, revision or modification of a proposal, or withdrawal of a proposal that is transmitted to and received by the Government via facsimile machine.
(b) Offerors may submit facsimile proposals as responses to this solicitation. Facsimile proposals are subject to the same rules as paper proposals.
(c) The telephone number of receiving facsimile equipment is: 719-567-3438.
(d) If any portion of a facsimile proposal received by the Contracting Officer is unreadable to the degree that conformance to the essential requirements of the solicitation cannot be ascertained from the document --
(1) The Contracting Officer immediately shall notify the offeror and permit the offeror to resubmit the proposal;
(2) The method and time for resubmission shall be prescribed by the Contracting Officer after consultation with the offeror;
and
(3) The resubmission shall be considered as if it were received at the date and time of the original unreadable submission for the purpose of determining timeliness, provided the offeror complies with the time and format requirements for resubmission prescribed by the Contracting Officer.
(e) The Government reserves the right to make award solely on the facsimile proposal. However, if requested to do so by the Contracting Officer, the apparently successful offeror promptly shall submit the complete original signed proposal.
(End of Provision)
52.216-1 Type of Contract (Apr 1984) The Government contemplates award of a Firm Fixed-Price contract resulting from this solicitation.
(End of Provision)
52.219-28 Post-Award Small Business Program Rerepresentation (Jul 2013)
(a) Definitions. As used in this clause-- Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is "not dominant in its field of operation" when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts--
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/ table-small-business-size-standards .
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
The Contractor represents that it [ ] is, [ ] is not a small business concern under NAICS Code 238210 assigned to contract number ______________.[Contractor to sign and date and insert authorized signer's name and title].
(End of clause)
52.222-5 Construction Wage Rate Requirements--Secondary Site of the Work (May 2014) (a)
(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)
(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
52.225-9 Buy American-Construction Materials (May 2014)
(a) Definitions. As used in this clause-- "Commercially available off-the-shelf (COTS) item"--
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Component" means an article, material, or supply incorporated directly into a construction material.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
"Cost of components" means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
"Domestic construction material" means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
"Foreign construction material" means a construction material other than a domestic construction material.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements the 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: ______ [Contracting Officer to list applicable excepted materials or indicate "none"]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars) * Item 1 Foreign construction material Domestic construction material Item 2 Foreign construction material Domestic construction material [List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] [*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).] (End of Clause)
52.225-10 Notice of Buy American Requirement--Construction Materials (May 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American--Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic…