Transfer_to_emergency_(with_load)_in_Manual_Mode_B600_2019.pdf

PDF 111 KB Posted

Attached to
Solicitation_GLEN_18-1101
Solicitation number
FA255019RA010
Issued by

About this file

This solicitation seeks proposals to replace three mission essential systems in a Central Utility Plant building on an Air Force base. The contractor will be required to replace six transformers, a common generator grounding resistor, and interconnecting lines in the transformer yard. Additionally, the contractor must replace eight roof mounted exhaust fans and associated wall louvers and thermostats in the power generation area. Finally, the contractor will replace obsolete Woodward synchronizers, load controllers, a custom PLC based generator controller, and the generator operator HMI computer and programming. The solicitation is issued by the 50th Civil Engineer Squadron of the Department of the Air Force Space Command to replace aging infrastructure supporting critical energy systems.

Manual Mode B600

View the file

Other files

Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

START/TRANSFER LOAD TO GENERATORS IN

MANUAL MODE

CENTRAL UTILITY PLANT (B600)

STEP 1: PLACE THE "PLC" MASTER CONTROL SWITCH IN MANUAL

All switches should be in manual / local position

STEP 2: PLACE all Generator SYNCHRONIZED LOAD SELECTOR switches to ISOC

STEP 3: PLACE all ENGINE CONTROL switches to TEST

***NOTE: Wait for generators to start up

STEP 4: CLOSE “B” Feeder Breaker CB-GSB and “M” or “N” Feeder Breaker

CB-GSA/CB-GSA1

STEP 5: PLACE Priority Gen ENGINE CONTROL SWITCH to TEST ON-LINE.

***NOTE: Wait for Generator Breaker Control Switch to close

STEP 6: PLACE remaining ENGINE CONTROL SWITCHES to TEST ON-LINE.

***NOTE: Wait for all Generator Breakers to close on remaining generators

On the MAIN BRKR FROM SUBSTATION SWITCHGEAR

STEP 7: LOWER MASTER IMPORT CONTROL switch until Amperage Meter reads as close to ZERO without going below then OPEN BREAKER CONTROL switch

52-U2M1/52-U1M1.

STEP 8: OPEN “B” FEEDER BREAKER SWITCHGEAR B on U2SB

STEP 9: OPEN “M” or “N” FEEDER BREAKER SWITCHGEAR A on U2SA/U2SA1

NOTIFY ATCC THAT THE BASE IS NOW ON GENERATOR POWER

21 August 2019