About this opportunity

The Smithsonian Institution is soliciting for a Construction Management at Risk (CMc) contract for the construction of the Bezos Learning Center (BLC) at the Smithsonian National Air and Space Museum in Washington, DC. The selected contractor will provide pre-construction and construction phase services through a guaranteed maximum price agreement, with a total period of performance estimated at 36 months from the notice to proceed in September 2024. The scope of work includes critical elements such as site work, utilities, foundations, structural systems, architectural finishes, MEP systems, elevators, roofing, curtain wall, food service equipment, and theater specialties. Firms will be evaluated using a two-step procurement process, with the most qualified firms advancing to the technical and pricing evaluation. Questions are due by February 14, 2024 and proposals are due by March 4, 2024, with a contract award anticipated in August 2024.

This is an unrestricted solicitation open to all responsible sources, with no set-aside designations. The estimated construction cost range is between $72-76 million, and the place of performance is in Washington, DC. The North American Industry Classification System (NAICS) code is 236220 - Commercial and Institutional Building Construction, with a size standard of $45 million in average annual receipts. The solicitation also requires a minimum 40% small business subcontracting goal with specific allocation targets to various socioeconomic categories.

Notice text

11 versions

Update #11 · Latest ·

Amendment 0010 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

35% Documents Provided

Request for Best and Final Cost Proposal

---------------------------------------------

Amendment 0009 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 109 to 168 (Step 2)

-----------------------------------------------

Amendment 0008 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Bid Due Date Extended

-----------------------------------------------

Amendment 0007 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 107 to 108 (Step 2)

-----------------------------------------------

Amendment 0006 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 97 to 106 (Step 2)

-----------------------------------------------

Amendment 0005 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 19 to 96 (Step 2)

Preliminary Draft 35% DD

-----------------------------------------------

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1 to 18 (Step 2)

-----------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to announce the firms selected to advance to Step 2.

-----------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 11-21

------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Contract Revision

Responses to RFI’s for Questions 1-10

-------------------------------------------

The Smithsonian Institution is soliciting for a Construction Management at Risk Contract (CMc) for the construction of the Bezos Learning Center (BLC) at the Smithsonian National Air and Space Museum (NASM), located in Washington, DC. The proposed contract listed here is UNRESTRICTED. All responsible sources are encouraged to submit a proposal, which will be considered by the Smithsonian. The new Bezos Learning Center (BLC) will be a pan-Institutional resource that will be overseen by the NASM Director and the Associate Director for Education and Visitor Experience. A primary focus of its programs shall reach underserved communities in Washington, DC and across the nation, both at the site of the new facility and virtually through remote capabilities, as the Center will employ the latest technological resources and developments available. Other ancillary programming will take place within and surrounding the facility, such as a 600- to 700-seat quick-service (fast casual) restaurant accessible from the Museum's main level as well as an Astronomy Park and Observatory on the East Terrace. The permanent installation of the currently temporary Phoebe Waterman Haas Public Observatory shall be addressed as an integral part of the overall BLC project efforts. The Smithsonian anticipates awarding a contract for pre-construction services by August 2024 and commencing of site preparation activity in early 2025. The Smithsonian expects contractor turnover of the building for the installation of exhibits starting in mid-2027 and the new BLC will open to the public in late 2027 to coincide with NASM 50th Anniversary.

The selected CMc shall provide Pre-construction Phase Services and Construction Phase Services through a guaranteed maximum price (GMP) agreement. Total period of performance including Pre-construction and Construction is estimated to be from notice to proceed in September 2024 to substantial completion in May 2027. The estimated construction cost is between $72,000,000 and $76,000,000. Critical elements of the work include, but are not limited to; pre-construction services, site work, utility work, excavation, foundations, dewatering, concrete and steel super-structure, landscape and hardscape, high level architectural finishes (both interior and exterior), MEP systems, elevators, roofing, exterior curtain wall with unique façade treatment, food service equipment, and theater specialties. Additional requirements for performance include procedures and documentation to ensure compliance with the established LEED building criteria; practices, procedures and documentation related to integrated building commissioning; and experience with the procedures for the use of Building Information Modeling (BIM).

Firm evaluation and selection will be conducted in accordance with FAR Part 15, Best Value Procurement, utilizing a two-step procurement model. Step One of the RFP will consist of a list of prequalifying criteria to assist the agency in identifying those CMc contractors that have demonstrated past specialized experience in comparable and non-comparable CMc projects and other relevant qualifying factors. It is the Smithsonian's intent to advance the most highly qualified companies for further consideration under Step Two, technical and pricing evaluation of the RFP. Companies which are advanced to Step Two of the RFP will be evaluated in accordance with the technical criteria as set forth in the RFP.

The North American Industry Classification Code (NAICS) for this procurement is 236220 and the size standard under this code is $45 million average annual receipts over the last three years. This announcement is open to all businesses regardless of size. If the selected firm is a large business, a subcontracting plan consistent with PL 95-507, PL 99-661 and PL 100-656 will be required with the final fee proposal. A minimum goal of 40% of the total planned subcontracting dollars shall be placed with small business concerns. At least 10% of total planned subcontracting dollars shall be placed with Small disadvantaged businesses (SDB), including Historically Black Colleges and Universities or Minority Institutions; 10% with Women-owned small businesses (WOSB); 7% shall be placed with Hub-zone Small Businesses (HubZone), 7% with Veteran-owned small businesses (VOSB); and 7% with Service Disabled Veteran-owned small businesses (SDV). The subcontracting plan is required with this submittal. Any prime or joint venture found to be officially notified of non-compliance on past contracts and the non-compliance is outstanding will not be considered for this project. Failure to adequately explain reasons for not meeting previous contract goals may result in a lower overall rating and ultimate non-selection. An approved small business-subcontracting plan will be required prior to award.

Prospective contractors must be registered in the Systems for Award Management (SAM) prior to award of a contract. Information on registration and annual confirmation requirements may be obtained via the Internet at http://www.sam.gov. Lack of registration in the SAM database will make an offeror ineligible for award.

Davis Bacon Wage Determination DC20240002 (Building) and DC20240001 (Heavy) shall apply.

Total period of performance for Preconstruction and Construction Services is 36 months from the date of Notice to Proceed.

QUESTIONS/CLARIFICATIONS

It is desired that all questions/clarifications be sent in, sequentially numbered for example first questions 1,2,3, second set of questions 4, 5, 6, etc. in word format to ChanVC@si.edu. It is requested that all questions be sent in no later than 3 PM Eastern Time on February 14, 2024.

SUBMISSION REQUIREMENTS

Proposals are to be sent as an electronic copy and is required to be submitted to DropBox.com using the link:

https://www.dropbox.com/request/JJQjFNSBrebXJkmi2LuC

Statements of Qualifications (SOQ) must be received no later than 3PM Eastern Time on March 4, 2024, to be considered. Please see the attached solicitation for more details regarding submission requirements.

THE STATEMENT OF QUALIFICATIONS DUE DATE IS MARCH 4, 2024, AT 3:00PM EST.

Update #10 ·

Amendment 0009 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 109 to 168 (Step 2)

-----------------------------------------------

Amendment 0008 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Bid Due Date Extended

-----------------------------------------------

Amendment 0007 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 107 to 108 (Step 2)

-----------------------------------------------

Amendment 0006 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 97 to 106 (Step 2)

-----------------------------------------------

Amendment 0005 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 19 to 96 (Step 2)

Preliminary Draft 35% DD

-----------------------------------------------

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1 to 18 (Step 2)

-----------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to announce the firms selected to advance to Step 2.

-----------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 11-21

------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Contract Revision

Responses to RFI’s for Questions 1-10

-------------------------------------------

The Smithsonian Institution is soliciting for a Construction Management at Risk Contract (CMc) for the construction of the Bezos Learning Center (BLC) at the Smithsonian National Air and Space Museum (NASM), located in Washington, DC. The proposed contract listed here is UNRESTRICTED. All responsible sources are encouraged to submit a proposal, which will be considered by the Smithsonian. The new Bezos Learning Center (BLC) will be a pan-Institutional resource that will be overseen by the NASM Director and the Associate Director for Education and Visitor Experience. A primary focus of its programs shall reach underserved communities in Washington, DC and across the nation, both at the site of the new facility and virtually through remote capabilities, as the Center will employ the latest technological resources and developments available. Other ancillary programming will take place within and surrounding the facility, such as a 600- to 700-seat quick-service (fast casual) restaurant accessible from the Museum's main level as well as an Astronomy Park and Observatory on the East Terrace. The permanent installation of the currently temporary Phoebe Waterman Haas Public Observatory shall be addressed as an integral part of the overall BLC project efforts. The Smithsonian anticipates awarding a contract for pre-construction services by August 2024 and commencing of site preparation activity in early 2025. The Smithsonian expects contractor turnover of the building for the installation of exhibits starting in mid-2027 and the new BLC will open to the public in late 2027 to coincide with NASM 50th Anniversary.

The selected CMc shall provide Pre-construction Phase Services and Construction Phase Services through a guaranteed maximum price (GMP) agreement. Total period of performance including Pre-construction and Construction is estimated to be from notice to proceed in September 2024 to substantial completion in May 2027. The estimated construction cost is between $72,000,000 and $76,000,000. Critical elements of the work include, but are not limited to; pre-construction services, site work, utility work, excavation, foundations, dewatering, concrete and steel super-structure, landscape and hardscape, high level architectural finishes (both interior and exterior), MEP systems, elevators, roofing, exterior curtain wall with unique façade treatment, food service equipment, and theater specialties. Additional requirements for performance include procedures and documentation to ensure compliance with the established LEED building criteria; practices, procedures and documentation related to integrated building commissioning; and experience with the procedures for the use of Building Information Modeling (BIM).

Firm evaluation and selection will be conducted in accordance with FAR Part 15, Best Value Procurement, utilizing a two-step procurement model. Step One of the RFP will consist of a list of prequalifying criteria to assist the agency in identifying those CMc contractors that have demonstrated past specialized experience in comparable and non-comparable CMc projects and other relevant qualifying factors. It is the Smithsonian's intent to advance the most highly qualified companies for further consideration under Step Two, technical and pricing evaluation of the RFP. Companies which are advanced to Step Two of the RFP will be evaluated in accordance with the technical criteria as set forth in the RFP.

The North American Industry Classification Code (NAICS) for this procurement is 236220 and the size standard under this code is $45 million average annual receipts over the last three years. This announcement is open to all businesses regardless of size. If the selected firm is a large business, a subcontracting plan consistent with PL 95-507, PL 99-661 and PL 100-656 will be required with the final fee proposal. A minimum goal of 40% of the total planned subcontracting dollars shall be placed with small business concerns. At least 10% of total planned subcontracting dollars shall be placed with Small disadvantaged businesses (SDB), including Historically Black Colleges and Universities or Minority Institutions; 10% with Women-owned small businesses (WOSB); 7% shall be placed with Hub-zone Small Businesses (HubZone), 7% with Veteran-owned small businesses (VOSB); and 7% with Service Disabled Veteran-owned small businesses (SDV). The subcontracting plan is required with this submittal. Any prime or joint venture found to be officially notified of non-compliance on past contracts and the non-compliance is outstanding will not be considered for this project. Failure to adequately explain reasons for not meeting previous contract goals may result in a lower overall rating and ultimate non-selection. An approved small business-subcontracting plan will be required prior to award.

Prospective contractors must be registered in the Systems for Award Management (SAM) prior to award of a contract. Information on registration and annual confirmation requirements may be obtained via the Internet at http://www.sam.gov. Lack of registration in the SAM database will make an offeror ineligible for award.

Davis Bacon Wage Determination DC20240002 (Building) and DC20240001 (Heavy) shall apply.

Total period of performance for Preconstruction and Construction Services is 36 months from the date of Notice to Proceed.

QUESTIONS/CLARIFICATIONS

It is desired that all questions/clarifications be sent in, sequentially numbered for example first questions 1,2,3, second set of questions 4, 5, 6, etc. in word format to ChanVC@si.edu. It is requested that all questions be sent in no later than 3 PM Eastern Time on February 14, 2024.

SUBMISSION REQUIREMENTS

Proposals are to be sent as an electronic copy and is required to be submitted to DropBox.com using the link:

https://www.dropbox.com/request/JJQjFNSBrebXJkmi2LuC

Statements of Qualifications (SOQ) must be received no later than 3PM Eastern Time on March 4, 2024, to be considered. Please see the attached solicitation for more details regarding submission requirements.

THE STATEMENT OF QUALIFICATIONS DUE DATE IS MARCH 4, 2024, AT 3:00PM EST.

Update #9 ·

Amendment 0008 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Bid Due Date Extended

-----------------------------------------------

Amendment 0007 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 107 to 108 (Step 2)

-----------------------------------------------

Amendment 0006 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 97 to 106 (Step 2)

-----------------------------------------------

Amendment 0005 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 19 to 96 (Step 2)

Preliminary Draft 35% DD

-----------------------------------------------

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1 to 18 (Step 2)

-----------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to announce the firms selected to advance to Step 2.

-----------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 11-21

------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Contract Revision

Responses to RFI’s for Questions 1-10

-------------------------------------------

The Smithsonian Institution is soliciting for a Construction Management at Risk Contract (CMc) for the construction of the Bezos Learning Center (BLC) at the Smithsonian National Air and Space Museum (NASM), located in Washington, DC. The proposed contract listed here is UNRESTRICTED. All responsible sources are encouraged to submit a proposal, which will be considered by the Smithsonian. The new Bezos Learning Center (BLC) will be a pan-Institutional resource that will be overseen by the NASM Director and the Associate Director for Education and Visitor Experience. A primary focus of its programs shall reach underserved communities in Washington, DC and across the nation, both at the site of the new facility and virtually through remote capabilities, as the Center will employ the latest technological resources and developments available. Other ancillary programming will take place within and surrounding the facility, such as a 600- to 700-seat quick-service (fast casual) restaurant accessible from the Museum's main level as well as an Astronomy Park and Observatory on the East Terrace. The permanent installation of the currently temporary Phoebe Waterman Haas Public Observatory shall be addressed as an integral part of the overall BLC project efforts. The Smithsonian anticipates awarding a contract for pre-construction services by August 2024 and commencing of site preparation activity in early 2025. The Smithsonian expects contractor turnover of the building for the installation of exhibits starting in mid-2027 and the new BLC will open to the public in late 2027 to coincide with NASM 50th Anniversary.

The selected CMc shall provide Pre-construction Phase Services and Construction Phase Services through a guaranteed maximum price (GMP) agreement. Total period of performance including Pre-construction and Construction is estimated to be from notice to proceed in September 2024 to substantial completion in May 2027. The estimated construction cost is between $72,000,000 and $76,000,000. Critical elements of the work include, but are not limited to; pre-construction services, site work, utility work, excavation, foundations, dewatering, concrete and steel super-structure, landscape and hardscape, high level architectural finishes (both interior and exterior), MEP systems, elevators, roofing, exterior curtain wall with unique façade treatment, food service equipment, and theater specialties. Additional requirements for performance include procedures and documentation to ensure compliance with the established LEED building criteria; practices, procedures and documentation related to integrated building commissioning; and experience with the procedures for the use of Building Information Modeling (BIM).

Firm evaluation and selection will be conducted in accordance with FAR Part 15, Best Value Procurement, utilizing a two-step procurement model. Step One of the RFP will consist of a list of prequalifying criteria to assist the agency in identifying those CMc contractors that have demonstrated past specialized experience in comparable and non-comparable CMc projects and other relevant qualifying factors. It is the Smithsonian's intent to advance the most highly qualified companies for further consideration under Step Two, technical and pricing evaluation of the RFP. Companies which are advanced to Step Two of the RFP will be evaluated in accordance with the technical criteria as set forth in the RFP.

The North American Industry Classification Code (NAICS) for this procurement is 236220 and the size standard under this code is $45 million average annual receipts over the last three years. This announcement is open to all businesses regardless of size. If the selected firm is a large business, a subcontracting plan consistent with PL 95-507, PL 99-661 and PL 100-656 will be required with the final fee proposal. A minimum goal of 40% of the total planned subcontracting dollars shall be placed with small business concerns. At least 10% of total planned subcontracting dollars shall be placed with Small disadvantaged businesses (SDB), including Historically Black Colleges and Universities or Minority Institutions; 10% with Women-owned small businesses (WOSB); 7% shall be placed with Hub-zone Small Businesses (HubZone), 7% with Veteran-owned small businesses (VOSB); and 7% with Service Disabled Veteran-owned small businesses (SDV). The subcontracting plan is required with this submittal. Any prime or joint venture found to be officially notified of non-compliance on past contracts and the non-compliance is outstanding will not be considered for this project. Failure to adequately explain reasons for not meeting previous contract goals may result in a lower overall rating and ultimate non-selection. An approved small business-subcontracting plan will be required prior to award.

Prospective contractors must be registered in the Systems for Award Management (SAM) prior to award of a contract. Information on registration and annual confirmation requirements may be obtained via the Internet at http://www.sam.gov. Lack of registration in the SAM database will make an offeror ineligible for award.

Davis Bacon Wage Determination DC20240002 (Building) and DC20240001 (Heavy) shall apply.

Total period of performance for Preconstruction and Construction Services is 36 months from the date of Notice to Proceed.

QUESTIONS/CLARIFICATIONS

It is desired that all questions/clarifications be sent in, sequentially numbered for example first questions 1,2,3, second set of questions 4, 5, 6, etc. in word format to ChanVC@si.edu. It is requested that all questions be sent in no later than 3 PM Eastern Time on February 14, 2024.

SUBMISSION REQUIREMENTS

Proposals are to be sent as an electronic copy and is required to be submitted to DropBox.com using the link:

https://www.dropbox.com/request/JJQjFNSBrebXJkmi2LuC

Statements of Qualifications (SOQ) must be received no later than 3PM Eastern Time on March 4, 2024, to be considered. Please see the attached solicitation for more details regarding submission requirements.

THE STATEMENT OF QUALIFICATIONS DUE DATE IS MARCH 4, 2024, AT 3:00PM EST.

Update #8 ·

Amendment 0007 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 107 to 108 (Step 2)

-----------------------------------------------

Amendment 0006 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 97 to 106 (Step 2)

-----------------------------------------------

Amendment 0005 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 19 to 96 (Step 2)

Preliminary Draft 35% DD

-----------------------------------------------

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1 to 18 (Step 2)

-----------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to announce the firms selected to advance to Step 2.

-----------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 11-21

------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Contract Revision

Responses to RFI’s for Questions 1-10

-------------------------------------------

The Smithsonian Institution is soliciting for a Construction Management at Risk Contract (CMc) for the construction of the Bezos Learning Center (BLC) at the Smithsonian National Air and Space Museum (NASM), located in Washington, DC. The proposed contract listed here is UNRESTRICTED. All responsible sources are encouraged to submit a proposal, which will be considered by the Smithsonian. The new Bezos Learning Center (BLC) will be a pan-Institutional resource that will be overseen by the NASM Director and the Associate Director for Education and Visitor Experience. A primary focus of its programs shall reach underserved communities in Washington, DC and across the nation, both at the site of the new facility and virtually through remote capabilities, as the Center will employ the latest technological resources and developments available. Other ancillary programming will take place within and surrounding the facility, such as a 600- to 700-seat quick-service (fast casual) restaurant accessible from the Museum's main level as well as an Astronomy Park and Observatory on the East Terrace. The permanent installation of the currently temporary Phoebe Waterman Haas Public Observatory shall be addressed as an integral part of the overall BLC project efforts. The Smithsonian anticipates awarding a contract for pre-construction services by August 2024 and commencing of site preparation activity in early 2025. The Smithsonian expects contractor turnover of the building for the installation of exhibits starting in mid-2027 and the new BLC will open to the public in late 2027 to coincide with NASM 50th Anniversary.

The selected CMc shall provide Pre-construction Phase Services and Construction Phase Services through a guaranteed maximum price (GMP) agreement. Total period of performance including Pre-construction and Construction is estimated to be from notice to proceed in September 2024 to substantial completion in May 2027. The estimated construction cost is between $72,000,000 and $76,000,000. Critical elements of the work include, but are not limited to; pre-construction services, site work, utility work, excavation, foundations, dewatering, concrete and steel super-structure, landscape and hardscape, high level architectural finishes (both interior and exterior), MEP systems, elevators, roofing, exterior curtain wall with unique façade treatment, food service equipment, and theater specialties. Additional requirements for performance include procedures and documentation to ensure compliance with the established LEED building criteria; practices, procedures and documentation related to integrated building commissioning; and experience with the procedures for the use of Building Information Modeling (BIM).

Firm evaluation and selection will be conducted in accordance with FAR Part 15, Best Value Procurement, utilizing a two-step procurement model. Step One of the RFP will consist of a list of prequalifying criteria to assist the agency in identifying those CMc contractors that have demonstrated past specialized experience in comparable and non-comparable CMc projects and other relevant qualifying factors. It is the Smithsonian's intent to advance the most highly qualified companies for further consideration under Step Two, technical and pricing evaluation of the RFP. Companies which are advanced to Step Two of the RFP will be evaluated in accordance with the technical criteria as set forth in the RFP.

The North American Industry Classification Code (NAICS) for this procurement is 236220 and the size standard under this code is $45 million average annual receipts over the last three years. This announcement is open to all businesses regardless of size. If the selected firm is a large business, a subcontracting plan consistent with PL 95-507, PL 99-661 and PL 100-656 will be required with the final fee proposal. A minimum goal of 40% of the total planned subcontracting dollars shall be placed with small business concerns. At least 10% of total planned subcontracting dollars shall be placed with Small disadvantaged businesses (SDB), including Historically Black Colleges and Universities or Minority Institutions; 10% with Women-owned small businesses (WOSB); 7% shall be placed with Hub-zone Small Businesses (HubZone), 7% with Veteran-owned small businesses (VOSB); and 7% with Service Disabled Veteran-owned small businesses (SDV). The subcontracting plan is required with this submittal. Any prime or joint venture found to be officially notified of non-compliance on past contracts and the non-compliance is outstanding will not be considered for this project. Failure to adequately explain reasons for not meeting previous contract goals may result in a lower overall rating and ultimate non-selection. An approved small business-subcontracting plan will be required prior to award.

Prospective contractors must be registered in the Systems for Award Management (SAM) prior to award of a contract. Information on registration and annual confirmation requirements may be obtained via the Internet at http://www.sam.gov. Lack of registration in the SAM database will make an offeror ineligible for award.

Davis Bacon Wage Determination DC20240002 (Building) and DC20240001 (Heavy) shall apply.

Total period of performance for Preconstruction and Construction Services is 36 months from the date of Notice to Proceed.

QUESTIONS/CLARIFICATIONS

It is desired that all questions/clarifications be sent in, sequentially numbered for example first questions 1,2,3, second set of questions 4, 5, 6, etc. in word format to ChanVC@si.edu. It is requested that all questions be sent in no later than 3 PM Eastern Time on February 14, 2024.

SUBMISSION REQUIREMENTS

Proposals are to be sent as an electronic copy and is required to be submitted to DropBox.com using the link:

https://www.dropbox.com/request/JJQjFNSBrebXJkmi2LuC

Statements of Qualifications (SOQ) must be received no later than 3PM Eastern Time on March 4, 2024, to be considered. Please see the attached solicitation for more details regarding submission requirements.

THE STATEMENT OF QUALIFICATIONS DUE DATE IS MARCH 4, 2024, AT 3:00PM EST.

Update #7 ·

Amendment 0006 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 97 to 106 (Step 2)

-----------------------------------------------

Amendment 0005 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 19 to 96 (Step 2)

Preliminary Draft 35% DD

-----------------------------------------------

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1 to 18 (Step 2)

-----------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to announce the firms selected to advance to Step 2.

-----------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 11-21

------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Contract Revision

Responses to RFI’s for Questions 1-10

-------------------------------------------

The Smithsonian Institution is soliciting for a Construction Management at Risk Contract (CMc) for the construction of the Bezos Learning Center (BLC) at the Smithsonian National Air and Space Museum (NASM), located in Washington, DC. The proposed contract listed here is UNRESTRICTED. All responsible sources are encouraged to submit a proposal, which will be considered by the Smithsonian. The new Bezos Learning Center (BLC) will be a pan-Institutional resource that will be overseen by the NASM Director and the Associate Director for Education and Visitor Experience. A primary focus of its programs shall reach underserved communities in Washington, DC and across the nation, both at the site of the new facility and virtually through remote capabilities, as the Center will employ the latest technological resources and developments available. Other ancillary programming will take place within and surrounding the facility, such as a 600- to 700-seat quick-service (fast casual) restaurant accessible from the Museum's main level as well as an Astronomy Park and Observatory on the East Terrace. The permanent installation of the currently temporary Phoebe Waterman Haas Public Observatory shall be addressed as an integral part of the overall BLC project efforts. The Smithsonian anticipates awarding a contract for pre-construction services by August 2024 and commencing of site preparation activity in early 2025. The Smithsonian expects contractor turnover of the building for the installation of exhibits starting in mid-2027 and the new BLC will open to the public in late 2027 to coincide with NASM 50th Anniversary.

The selected CMc shall provide Pre-construction Phase Services and Construction Phase Services through a guaranteed maximum price (GMP) agreement. Total period of performance including Pre-construction and Construction is estimated to be from notice to proceed in September 2024 to substantial completion in May 2027. The estimated construction cost is between $72,000,000 and $76,000,000. Critical elements of the work include, but are not limited to; pre-construction services, site work, utility work, excavation, foundations, dewatering, concrete and steel super-structure, landscape and hardscape, high level architectural finishes (both interior and exterior), MEP systems, elevators, roofing, exterior curtain wall with unique façade treatment, food service equipment, and theater specialties. Additional requirements for performance include procedures and documentation to ensure compliance with the established LEED building criteria; practices, procedures and documentation related to integrated building commissioning; and experience with the procedures for the use of Building Information Modeling (BIM).

Firm evaluation and selection will be conducted in accordance with FAR Part 15, Best Value Procurement, utilizing a two-step procurement model. Step One of the RFP will consist of a list of prequalifying criteria to assist the agency in identifying those CMc contractors that have demonstrated past specialized experience in comparable and non-comparable CMc projects and other relevant qualifying factors. It is the Smithsonian's intent to advance the most highly qualified companies for further consideration under Step Two, technical and pricing evaluation of the RFP. Companies which are advanced to Step Two of the RFP will be evaluated in accordance with the technical criteria as set forth in the RFP.

The North American Industry Classification Code (NAICS) for this procurement is 236220 and the size standard under this code is $45 million average annual receipts over the last three years. This announcement is open to all businesses regardless of size. If the selected firm is a large business, a subcontracting plan consistent with PL 95-507, PL 99-661 and PL 100-656 will be required with the final fee proposal. A minimum goal of 40% of the total planned subcontracting dollars shall be placed with small business concerns. At least 10% of total planned subcontracting dollars shall be placed with Small disadvantaged businesses (SDB), including Historically Black Colleges and Universities or Minority Institutions; 10% with Women-owned small businesses (WOSB); 7% shall be placed with Hub-zone Small Businesses (HubZone), 7% with Veteran-owned small businesses (VOSB); and 7% with Service Disabled Veteran-owned small businesses (SDV). The subcontracting plan is required with this submittal. Any prime or joint venture found to be officially notified of non-compliance on past contracts and the non-compliance is outstanding will not be considered for this project. Failure to adequately explain reasons for not meeting previous contract goals may result in a lower overall rating and ultimate non-selection. An approved small business-subcontracting plan will be required prior to award.

Prospective contractors must be registered in the Systems for Award Management (SAM) prior to award of a contract. Information on registration and annual confirmation requirements may be obtained via the Internet at http://www.sam.gov. Lack of registration in the SAM database will make an offeror ineligible for award.

Davis Bacon Wage Determination DC20240002 (Building) and DC20240001 (Heavy) shall apply.

Total period of performance for Preconstruction and Construction Services is 36 months from the date of Notice to Proceed.

QUESTIONS/CLARIFICATIONS

It is desired that all questions/clarifications be sent in, sequentially numbered for example first questions 1,2,3, second set of questions 4, 5, 6, etc. in word format to ChanVC@si.edu. It is requested that all questions be sent in no later than 3 PM Eastern Time on February 14, 2024.

SUBMISSION REQUIREMENTS

Proposals are to be sent as an electronic copy and is required to be submitted to DropBox.com using the link:

https://www.dropbox.com/request/JJQjFNSBrebXJkmi2LuC

Statements of Qualifications (SOQ) must be received no later than 3PM Eastern Time on March 4, 2024, to be considered. Please see the attached solicitation for more details regarding submission requirements.

THE STATEMENT OF QUALIFICATIONS DUE DATE IS MARCH 4, 2024, AT 3:00PM EST.

Update #6 ·

Amendment 0005 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 19 to 96 (Step 2)

Preliminary Draft 35% DD

-----------------------------------------------

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1 to 18 (Step 2)

-----------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to announce the firms selected to advance to Step 2.

-----------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 11-21

------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Contract Revision

Responses to RFI’s for Questions 1-10

-------------------------------------------

The Smithsonian Institution is soliciting for a Construction Management at Risk Contract (CMc) for the construction of the Bezos Learning Center (BLC) at the Smithsonian National Air and Space Museum (NASM), located in Washington, DC. The proposed contract listed here is UNRESTRICTED. All responsible sources are encouraged to submit a proposal, which will be considered by the Smithsonian. The new Bezos Learning Center (BLC) will be a pan-Institutional resource that will be overseen by the NASM Director and the Associate Director for Education and Visitor Experience. A primary focus of its programs shall reach underserved communities in Washington, DC and across the nation, both at the site of the new facility and virtually through remote capabilities, as the Center will employ the latest technological resources and developments available. Other ancillary programming will take place within and surrounding the facility, such as a 600- to 700-seat quick-service (fast casual) restaurant accessible from the Museum's main level as well as an Astronomy Park and Observatory on the East Terrace. The permanent installation of the currently temporary Phoebe Waterman Haas Public Observatory shall be addressed as an integral part of the overall BLC project efforts. The Smithsonian anticipates awarding a contract for pre-construction services by August 2024 and commencing of site preparation activity in early 2025. The Smithsonian expects contractor turnover of the building for the installation of exhibits starting in mid-2027 and the new BLC will open to the public in late 2027 to coincide with NASM 50th Anniversary.

The selected CMc shall provide Pre-construction Phase Services and Construction Phase Services through a guaranteed maximum price (GMP) agreement. Total period of performance including Pre-construction and Construction is estimated to be from notice to proceed in September 2024 to substantial completion in May 2027. The estimated construction cost is between $72,000,000 and $76,000,000. Critical elements of the work include, but are not limited to; pre-construction services, site work, utility work, excavation, foundations, dewatering, concrete and steel super-structure, landscape and hardscape, high level architectural finishes (both interior and exterior), MEP systems, elevators, roofing, exterior curtain wall with unique façade treatment, food service equipment, and theater specialties. Additional requirements for performance include procedures and documentation to ensure compliance with the established LEED building criteria; practices, procedures and documentation related to integrated building commissioning; and experience with the procedures for the use of Building Information Modeling (BIM).

Firm evaluation and selection will be conducted in accordance with FAR Part 15, Best Value Procurement, utilizing a two-step procurement model. Step One of the RFP will consist of a list of prequalifying criteria to assist the agency in identifying those CMc contractors that have demonstrated past specialized experience in comparable and non-comparable CMc projects and other relevant qualifying factors. It is the Smithsonian's intent to advance the most highly qualified companies for further consideration under Step Two, technical and pricing evaluation of the RFP. Companies which are advanced to Step Two of the RFP will be evaluated in accordance with the technical criteria as set forth in the RFP.

The North American Industry Classification Code (NAICS) for this procurement is 236220 and the size standard under this code is $45 million average annual receipts over the last three years. This announcement is open to all businesses regardless of size. If the selected firm is a large business, a subcontracting plan consistent with PL 95-507, PL 99-661 and PL 100-656 will be required with the final fee proposal. A minimum goal of 40% of the total planned subcontracting dollars shall be placed with small business concerns. At least 10% of total planned subcontracting dollars shall be placed with Small disadvantaged businesses (SDB), including Historically Black Colleges and Universities or Minority Institutions; 10% with Women-owned small businesses (WOSB); 7% shall be placed with Hub-zone Small Businesses (HubZone), 7% with Veteran-owned small businesses (VOSB); and 7% with Service Disabled Veteran-owned small businesses (SDV). The subcontracting plan is required with this submittal. Any prime or joint venture found to be officially notified of non-compliance on past contracts and the non-compliance is outstanding will not be considered for this project. Failure to adequately explain reasons for not meeting previous contract goals may result in a lower overall rating and ultimate non-selection. An approved small business-subcontracting plan will be required prior to award.

Prospective contractors must be registered in the Systems for Award Management (SAM) prior to award of a contract. Information on registration and annual confirmation requirements may be obtained via the Internet at http://www.sam.gov. Lack of registration in the SAM database will make an offeror ineligible for award.

Davis Bacon Wage Determination DC20240002 (Building) and DC20240001 (Heavy) shall apply.

Total period of performance for Preconstruction and Construction Services is 36 months from the date of Notice to Proceed.

QUESTIONS/CLARIFICATIONS

It is desired that all questions/clarifications be sent in, sequentially numbered for example first questions 1,2,3, second set of questions 4, 5, 6, etc. in word format to ChanVC@si.edu. It is requested that all questions be sent in no later than 3 PM Eastern Time on February 14, 2024.

SUBMISSION REQUIREMENTS

Proposals are to be sent as an electronic copy and is required to be submitted to DropBox.com using the link:

https://www.dropbox.com/request/JJQjFNSBrebXJkmi2LuC

Statements of Qualifications (SOQ) must be received no later than 3PM Eastern Time on March 4, 2024, to be considered. Please see the attached solicitation for more details regarding submission requirements.

THE STATEMENT OF QUALIFICATIONS DUE DATE IS MARCH 4, 2024, AT 3:00PM EST.

Update #5 ·

Amendment 0004 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 1 to 18 (Step 2)

-----------------------------------------------

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to announce the firms selected to advance to Step 2.

-----------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 11-21

------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Contract Revision

Responses to RFI’s for Questions 1-10

-------------------------------------------

The Smithsonian Institution is soliciting for a Construction Management at Risk Contract (CMc) for the construction of the Bezos Learning Center (BLC) at the Smithsonian National Air and Space Museum (NASM), located in Washington, DC. The proposed contract listed here is UNRESTRICTED. All responsible sources are encouraged to submit a proposal, which will be considered by the Smithsonian. The new Bezos Learning Center (BLC) will be a pan-Institutional resource that will be overseen by the NASM Director and the Associate Director for Education and Visitor Experience. A primary focus of its programs shall reach underserved communities in Washington, DC and across the nation, both at the site of the new facility and virtually through remote capabilities, as the Center will employ the latest technological resources and developments available. Other ancillary programming will take place within and surrounding the facility, such as a 600- to 700-seat quick-service (fast casual) restaurant accessible from the Museum's main level as well as an Astronomy Park and Observatory on the East Terrace. The permanent installation of the currently temporary Phoebe Waterman Haas Public Observatory shall be addressed as an integral part of the overall BLC project efforts. The Smithsonian anticipates awarding a contract for pre-construction services by August 2024 and commencing of site preparation activity in early 2025. The Smithsonian expects contractor turnover of the building for the installation of exhibits starting in mid-2027 and the new BLC will open to the public in late 2027 to coincide with NASM 50th Anniversary.

The selected CMc shall provide Pre-construction Phase Services and Construction Phase Services through a guaranteed maximum price (GMP) agreement. Total period of performance including Pre-construction and Construction is estimated to be from notice to proceed in September 2024 to substantial completion in May 2027. The estimated construction cost is between $72,000,000 and $76,000,000. Critical elements of the work include, but are not limited to; pre-construction services, site work, utility work, excavation, foundations, dewatering, concrete and steel super-structure, landscape and hardscape, high level architectural finishes (both interior and exterior), MEP systems, elevators, roofing, exterior curtain wall with unique façade treatment, food service equipment, and theater specialties. Additional requirements for performance include procedures and documentation to ensure compliance with the established LEED building criteria; practices, procedures and documentation related to integrated building commissioning; and experience with the procedures for the use of Building Information Modeling (BIM).

Firm evaluation and selection will be conducted in accordance with FAR Part 15, Best Value Procurement, utilizing a two-step procurement model. Step One of the RFP will consist of a list of prequalifying criteria to assist the agency in identifying those CMc contractors that have demonstrated past specialized experience in comparable and non-comparable CMc projects and other relevant qualifying factors. It is the Smithsonian's intent to advance the most highly qualified companies for further consideration under Step Two, technical and pricing evaluation of the RFP. Companies which are advanced to Step Two of the RFP will be evaluated in accordance with the technical criteria as set forth in the RFP.

The North American Industry Classification Code (NAICS) for this procurement is 236220 and the size standard under this code is $45 million average annual receipts over the last three years. This announcement is open to all businesses regardless of size. If the selected firm is a large business, a subcontracting plan consistent with PL 95-507, PL 99-661 and PL 100-656 will be required with the final fee proposal. A minimum goal of 40% of the total planned subcontracting dollars shall be placed with small business concerns. At least 10% of total planned subcontracting dollars shall be placed with Small disadvantaged businesses (SDB), including Historically Black Colleges and Universities or Minority Institutions; 10% with Women-owned small businesses (WOSB); 7% shall be placed with Hub-zone Small Businesses (HubZone), 7% with Veteran-owned small businesses (VOSB); and 7% with Service Disabled Veteran-owned small businesses (SDV). The subcontracting plan is required with this submittal. Any prime or joint venture found to be officially notified of non-compliance on past contracts and the non-compliance is outstanding will not be considered for this project. Failure to adequately explain reasons for not meeting previous contract goals may result in a lower overall rating and ultimate non-selection. An approved small business-subcontracting plan will be required prior to award.

Prospective contractors must be registered in the Systems for Award Management (SAM) prior to award of a contract. Information on registration and annual confirmation requirements may be obtained via the Internet at http://www.sam.gov. Lack of registration in the SAM database will make an offeror ineligible for award.

Davis Bacon Wage Determination DC20240002 (Building) and DC20240001 (Heavy) shall apply.

Total period of performance for Preconstruction and Construction Services is 36 months from the date of Notice to Proceed.

QUESTIONS/CLARIFICATIONS

It is desired that all questions/clarifications be sent in, sequentially numbered for example first questions 1,2,3, second set of questions 4, 5, 6, etc. in word format to ChanVC@si.edu. It is requested that all questions be sent in no later than 3 PM Eastern Time on February 14, 2024.

SUBMISSION REQUIREMENTS

Proposals are to be sent as an electronic copy and is required to be submitted to DropBox.com using the link:

https://www.dropbox.com/request/JJQjFNSBrebXJkmi2LuC

Statements of Qualifications (SOQ) must be received no later than 3PM Eastern Time on March 4, 2024, to be considered. Please see the attached solicitation for more details regarding submission requirements.

THE STATEMENT OF QUALIFICATIONS DUE DATE IS MARCH 4, 2024, AT 3:00PM EST.

Update #4 ·

Amendment 0003 to the RFP is hereby issued and attached for download. The purpose of the amendment is to announce the firms selected to advance to Step 2.

-----------------------------------------------

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 11-21

------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Contract Revision

Responses to RFI’s for Questions 1-10

-------------------------------------------

The Smithsonian Institution is soliciting for a Construction Management at Risk Contract (CMc) for the construction of the Bezos Learning Center (BLC) at the Smithsonian National Air and Space Museum (NASM), located in Washington, DC. The proposed contract listed here is UNRESTRICTED. All responsible sources are encouraged to submit a proposal, which will be considered by the Smithsonian. The new Bezos Learning Center (BLC) will be a pan-Institutional resource that will be overseen by the NASM Director and the Associate Director for Education and Visitor Experience. A primary focus of its programs shall reach underserved communities in Washington, DC and across the nation, both at the site of the new facility and virtually through remote capabilities, as the Center will employ the latest technological resources and developments available. Other ancillary programming will take place within and surrounding the facility, such as a 600- to 700-seat quick-service (fast casual) restaurant accessible from the Museum's main level as well as an Astronomy Park and Observatory on the East Terrace. The permanent installation of the currently temporary Phoebe Waterman Haas Public Observatory shall be addressed as an integral part of the overall BLC project efforts. The Smithsonian anticipates awarding a contract for pre-construction services by August 2024 and commencing of site preparation activity in early 2025. The Smithsonian expects contractor turnover of the building for the installation of exhibits starting in mid-2027 and the new BLC will open to the public in late 2027 to coincide with NASM 50th Anniversary.

The selected CMc shall provide Pre-construction Phase Services and Construction Phase Services through a guaranteed maximum price (GMP) agreement. Total period of performance including Pre-construction and Construction is estimated to be from notice to proceed in September 2024 to substantial completion in May 2027. The estimated construction cost is between $72,000,000 and $76,000,000. Critical elements of the work include, but are not limited to; pre-construction services, site work, utility work, excavation, foundations, dewatering, concrete and steel super-structure, landscape and hardscape, high level architectural finishes (both interior and exterior), MEP systems, elevators, roofing, exterior curtain wall with unique façade treatment, food service equipment, and theater specialties. Additional requirements for performance include procedures and documentation to ensure compliance with the established LEED building criteria; practices, procedures and documentation related to integrated building commissioning; and experience with the procedures for the use of Building Information Modeling (BIM).

Firm evaluation and selection will be conducted in accordance with FAR Part 15, Best Value Procurement, utilizing a two-step procurement model. Step One of the RFP will consist of a list of prequalifying criteria to assist the agency in identifying those CMc contractors that have demonstrated past specialized experience in comparable and non-comparable CMc projects and other relevant qualifying factors. It is the Smithsonian's intent to advance the most highly qualified companies for further consideration under Step Two, technical and pricing evaluation of the RFP. Companies which are advanced to Step Two of the RFP will be evaluated in accordance with the technical criteria as set forth in the RFP.

The North American Industry Classification Code (NAICS) for this procurement is 236220 and the size standard under this code is $45 million average annual receipts over the last three years. This announcement is open to all businesses regardless of size. If the selected firm is a large business, a subcontracting plan consistent with PL 95-507, PL 99-661 and PL 100-656 will be required with the final fee proposal. A minimum goal of 40% of the total planned subcontracting dollars shall be placed with small business concerns. At least 10% of total planned subcontracting dollars shall be placed with Small disadvantaged businesses (SDB), including Historically Black Colleges and Universities or Minority Institutions; 10% with Women-owned small businesses (WOSB); 7% shall be placed with Hub-zone Small Businesses (HubZone), 7% with Veteran-owned small businesses (VOSB); and 7% with Service Disabled Veteran-owned small businesses (SDV). The subcontracting plan is required with this submittal. Any prime or joint venture found to be officially notified of non-compliance on past contracts and the non-compliance is outstanding will not be considered for this project. Failure to adequately explain reasons for not meeting previous contract goals may result in a lower overall rating and ultimate non-selection. An approved small business-subcontracting plan will be required prior to award.

Prospective contractors must be registered in the Systems for Award Management (SAM) prior to award of a contract. Information on registration and annual confirmation requirements may be obtained via the Internet at http://www.sam.gov. Lack of registration in the SAM database will make an offeror ineligible for award.

Davis Bacon Wage Determination DC20240002 (Building) and DC20240001 (Heavy) shall apply.

Total period of performance for Preconstruction and Construction Services is 36 months from the date of Notice to Proceed.

QUESTIONS/CLARIFICATIONS

It is desired that all questions/clarifications be sent in, sequentially numbered for example first questions 1,2,3, second set of questions 4, 5, 6, etc. in word format to ChanVC@si.edu. It is requested that all questions be sent in no later than 3 PM Eastern Time on February 14, 2024.

SUBMISSION REQUIREMENTS

Proposals are to be sent as an electronic copy and is required to be submitted to DropBox.com using the link:

https://www.dropbox.com/request/JJQjFNSBrebXJkmi2LuC

Statements of Qualifications (SOQ) must be received no later than 3PM Eastern Time on March 4, 2024, to be considered. Please see the attached solicitation for more details regarding submission requirements.

THE STATEMENT OF QUALIFICATIONS DUE DATE IS MARCH 4, 2024, AT 3:00PM EST.

Update #3 ·

Amendment 0002 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Responses to RFI’s for Questions 11-21

------------------------------------------------

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Contract Revision

Responses to RFI’s for Questions 1-10

-------------------------------------------

The Smithsonian Institution is soliciting for a Construction Management at Risk Contract (CMc) for the construction of the Bezos Learning Center (BLC) at the Smithsonian National Air and Space Museum (NASM), located in Washington, DC. The proposed contract listed here is UNRESTRICTED. All responsible sources are encouraged to submit a proposal, which will be considered by the Smithsonian. The new Bezos Learning Center (BLC) will be a pan-Institutional resource that will be overseen by the NASM Director and the Associate Director for Education and Visitor Experience. A primary focus of its programs shall reach underserved communities in Washington, DC and across the nation, both at the site of the new facility and virtually through remote capabilities, as the Center will employ the latest technological resources and developments available. Other ancillary programming will take place within and surrounding the facility, such as a 600- to 700-seat quick-service (fast casual) restaurant accessible from the Museum's main level as well as an Astronomy Park and Observatory on the East Terrace. The permanent installation of the currently temporary Phoebe Waterman Haas Public Observatory shall be addressed as an integral part of the overall BLC project efforts. The Smithsonian anticipates awarding a contract for pre-construction services by August 2024 and commencing of site preparation activity in early 2025. The Smithsonian expects contractor turnover of the building for the installation of exhibits starting in mid-2027 and the new BLC will open to the public in late 2027 to coincide with NASM 50th Anniversary.

The selected CMc shall provide Pre-construction Phase Services and Construction Phase Services through a guaranteed maximum price (GMP) agreement. Total period of performance including Pre-construction and Construction is estimated to be from notice to proceed in September 2024 to substantial completion in May 2027. The estimated construction cost is between $72,000,000 and $76,000,000. Critical elements of the work include, but are not limited to; pre-construction services, site work, utility work, excavation, foundations, dewatering, concrete and steel super-structure, landscape and hardscape, high level architectural finishes (both interior and exterior), MEP systems, elevators, roofing, exterior curtain wall with unique façade treatment, food service equipment, and theater specialties. Additional requirements for performance include procedures and documentation to ensure compliance with the established LEED building criteria; practices, procedures and documentation related to integrated building commissioning; and experience with the procedures for the use of Building Information Modeling (BIM).

Firm evaluation and selection will be conducted in accordance with FAR Part 15, Best Value Procurement, utilizing a two-step procurement model. Step One of the RFP will consist of a list of prequalifying criteria to assist the agency in identifying those CMc contractors that have demonstrated past specialized experience in comparable and non-comparable CMc projects and other relevant qualifying factors. It is the Smithsonian's intent to advance the most highly qualified companies for further consideration under Step Two, technical and pricing evaluation of the RFP. Companies which are advanced to Step Two of the RFP will be evaluated in accordance with the technical criteria as set forth in the RFP.

The North American Industry Classification Code (NAICS) for this procurement is 236220 and the size standard under this code is $45 million average annual receipts over the last three years. This announcement is open to all businesses regardless of size. If the selected firm is a large business, a subcontracting plan consistent with PL 95-507, PL 99-661 and PL 100-656 will be required with the final fee proposal. A minimum goal of 40% of the total planned subcontracting dollars shall be placed with small business concerns. At least 10% of total planned subcontracting dollars shall be placed with Small disadvantaged businesses (SDB), including Historically Black Colleges and Universities or Minority Institutions; 10% with Women-owned small businesses (WOSB); 7% shall be placed with Hub-zone Small Businesses (HubZone), 7% with Veteran-owned small businesses (VOSB); and 7% with Service Disabled Veteran-owned small businesses (SDV). The subcontracting plan is required with this submittal. Any prime or joint venture found to be officially notified of non-compliance on past contracts and the non-compliance is outstanding will not be considered for this project. Failure to adequately explain reasons for not meeting previous contract goals may result in a lower overall rating and ultimate non-selection. An approved small business-subcontracting plan will be required prior to award.

Prospective contractors must be registered in the Systems for Award Management (SAM) prior to award of a contract. Information on registration and annual confirmation requirements may be obtained via the Internet at http://www.sam.gov. Lack of registration in the SAM database will make an offeror ineligible for award.

Davis Bacon Wage Determination DC20240002 (Building) and DC20240001 (Heavy) shall apply.

Total period of performance for Preconstruction and Construction Services is 36 months from the date of Notice to Proceed.

QUESTIONS/CLARIFICATIONS

It is desired that all questions/clarifications be sent in, sequentially numbered for example first questions 1,2,3, second set of questions 4, 5, 6, etc. in word format to ChanVC@si.edu. It is requested that all questions be sent in no later than 3 PM Eastern Time on February 14, 2024.

SUBMISSION REQUIREMENTS

Proposals are to be sent as an electronic copy and is required to be submitted to DropBox.com using the link:

https://www.dropbox.com/request/JJQjFNSBrebXJkmi2LuC

Statements of Qualifications (SOQ) must be received no later than 3PM Eastern Time on March 4, 2024, to be considered. Please see the attached solicitation for more details regarding submission requirements.

THE STATEMENT OF QUALIFICATIONS DUE DATE IS MARCH 4, 2024, AT 3:00PM EST.

Update #2 ·

Amendment 0001 to the RFP is hereby issued and attached for download. The purpose of the amendment is to make the following changes to the Solicitation:

Contract Revision

Responses to RFI’s for Questions 1-10

-------------------------------------------

The Smithsonian Institution is soliciting for a Construction Management at Risk Contract (CMc) for the construction of the Bezos Learning Center (BLC) at the Smithsonian National Air and Space Museum (NASM), located in Washington, DC. The proposed contract listed here is UNRESTRICTED. All responsible sources are encouraged to submit a proposal, which will be considered by the Smithsonian. The new Bezos Learning Center (BLC) will be a pan-Institutional resource that will be overseen by the NASM Director and the Associate Director for Education and Visitor Experience. A primary focus of its programs shall reach underserved communities in Washington, DC and across the nation, both at the site of the new facility and virtually through remote capabilities, as the Center will employ the latest technological resources and developments available. Other ancillary programming will take place within and surrounding the facility, such as a 600- to 700-seat quick-service (fast casual) restaurant accessible from the Museum's main level as well as an Astronomy Park and Observatory on the East Terrace. The permanent installation of the currently temporary Phoebe Waterman Haas Public Observatory shall be addressed as an integral part of the overall BLC project efforts. The Smithsonian anticipates awarding a contract for pre-construction services by August 2024 and commencing of site preparation activity in early 2025. The Smithsonian expects contractor turnover of the building for the installation of exhibits starting in mid-2027 and the new BLC will open to the public in late 2027 to coincide with NASM 50th Anniversary.

The selected CMc shall provide Pre-construction Phase Services and Construction Phase Services through a guaranteed maximum price (GMP) agreement. Total period of performance including Pre-construction and Construction is estimated to be from notice to proceed in September 2024 to substantial completion in May 2027. The estimated construction cost is between $72,000,000 and $76,000,000. Critical elements of the work include, but are not limited to; pre-construction services, site work, utility work, excavation, foundations, dewatering, concrete and steel super-structure, landscape and hardscape, high level architectural finishes (both interior and exterior), MEP systems, elevators, roofing, exterior curtain wall with unique façade treatment, food service equipment, and theater specialties. Additional requirements for performance include procedures and documentation to ensure compliance with the established LEED building criteria; practices, procedures and documentation related to integrated building commissioning; and experience with the procedures for the use of Building Information Modeling (BIM).

Firm evaluation and selection will be conducted in accordance with FAR Part 15, Best Value Procurement, utilizing a two-step procurement model. Step One of the RFP will consist of a list of prequalifying criteria to assist the agency in identifying those CMc contractors that have demonstrated past specialized experience in comparable and non-comparable CMc projects and other relevant qualifying factors. It is the Smithsonian's intent to advance the most highly qualified companies for further consideration under Step Two, technical and pricing evaluation of the RFP. Companies which are advanced to Step Two of the RFP will be evaluated in accordance with the technical criteria as set forth in the RFP.

The North American Industry Classification Code (NAICS) for this procurement is 236220 and the size standard under this code is $45 million average annual receipts over the last three years. This announcement is open to all businesses regardless of size. If the selected firm is a large business, a subcontracting plan consistent with PL 95-507, PL 99-661 and PL 100-656 will be required with the final fee proposal. A minimum goal of 40% of the total planned subcontracting dollars shall be placed with small business concerns. At least 10% of total planned subcontracting dollars shall be placed with Small disadvantaged businesses (SDB), including Historically Black Colleges and Universities or Minority Institutions; 10% with Women-owned small businesses (WOSB); 7% shall be placed with Hub-zone Small Businesses (HubZone), 7% with Veteran-owned small businesses (VOSB); and 7% with Service Disabled Veteran-owned small businesses (SDV). The subcontracting plan is required with this submittal. Any prime or joint venture found to be officially notified of non-compliance on past contracts and the non-compliance is outstanding will not be considered for this project. Failure to adequately explain reasons for not meeting previous contract goals may result in a lower overall rating and ultimate non-selection. An approved small business-subcontracting plan will be required prior to award.

Prospective contractors must be registered in the Systems for Award Management (SAM) prior to award of a contract. Information on registration and annual confirmation requirements may be obtained via the Internet at http://www.sam.gov. Lack of registration in the SAM database will make an offeror ineligible for award.

Davis Bacon Wage Determination DC20240002 (Building) and DC20240001 (Heavy) shall apply.

Total period of performance for Preconstruction and Construction Services is 36 months from the date of Notice to Proceed.

QUESTIONS/CLARIFICATIONS

It is desired that all questions/clarifications be sent in, sequentially numbered for example first questions 1,2,3, second set of questions 4, 5, 6, etc. in word format to ChanVC@si.edu. It is requested that all questions be sent in no later than 3 PM Eastern Time on February 14, 2024.

SUBMISSION REQUIREMENTS

Proposals are to be sent as an electronic copy and is required to be submitted to DropBox.com using the link:

https://www.dropbox.com/request/JJQjFNSBrebXJkmi2LuC

Statements of Qualifications (SOQ) must be received no later than 3PM Eastern Time on March 4, 2024, to be considered. Please see the attached solicitation for more details regarding submission requirements.

THE STATEMENT OF QUALIFICATIONS DUE DATE IS MARCH 4, 2024, AT 3:00PM EST.

Update #1 ·

The Smithsonian Institution is soliciting for a Construction Management at Risk Contract (CMc) for the construction of the Bezos Learning Center (BLC) at the Smithsonian National Air and Space Museum (NASM), located in Washington, DC. The proposed contract listed here is UNRESTRICTED. All responsible sources are encouraged to submit a proposal, which will be considered by the Smithsonian. The new Bezos Learning Center (BLC) will be a pan-Institutional resource that will be overseen by the NASM Director and the Associate Director for Education and Visitor Experience. A primary focus of its programs shall reach underserved communities in Washington, DC and across the nation, both at the site of the new facility and virtually through remote capabilities, as the Center will employ the latest technological resources and developments available. Other ancillary programming will take place within and surrounding the facility, such as a 600- to 700-seat quick-service (fast casual) restaurant accessible from the Museum's main level as well as an Astronomy Park and Observatory on the East Terrace. The permanent installation of the currently temporary Phoebe Waterman Haas Public Observatory shall be addressed as an integral part of the overall BLC project efforts. The Smithsonian anticipates awarding a contract for pre-construction services by August 2024 and commencing of site preparation activity in early 2025. The Smithsonian expects contractor turnover of the building for the installation of exhibits starting in mid-2027 and the new BLC will open to the public in late 2027 to coincide with NASM 50th Anniversary.

The selected CMc shall provide Pre-construction Phase Services and Construction Phase Services through a guaranteed maximum price (GMP) agreement. Total period of performance including Pre-construction and Construction is estimated to be from notice to proceed in September 2024 to substantial completion in May 2027. The estimated construction cost is between $72,000,000 and $76,000,000. Critical elements of the work include, but are not limited to; pre-construction services, site work, utility work, excavation, foundations, dewatering, concrete and steel super-structure, landscape and hardscape, high level architectural finishes (both interior and exterior), MEP systems, elevators, roofing, exterior curtain wall with unique façade treatment, food service equipment, and theater specialties. Additional requirements for performance include procedures and documentation to ensure compliance with the established LEED building criteria; practices, procedures and documentation related to integrated building commissioning; and experience with the procedures for the use of Building Information Modeling (BIM).

Firm evaluation and selection will be conducted in accordance with FAR Part 15, Best Value Procurement, utilizing a two-step procurement model. Step One of the RFP will consist of a list of prequalifying criteria to assist the agency in identifying those CMc contractors that have demonstrated past specialized experience in comparable and non-comparable CMc projects and other relevant qualifying factors. It is the Smithsonian's intent to advance the most highly qualified companies for further consideration under Step Two, technical and pricing evaluation of the RFP. Companies which are advanced to Step Two of the RFP will be evaluated in accordance with the technical criteria as set forth in the RFP.

The North American Industry Classification Code (NAICS) for this procurement is 236220 and the size standard under this code is $45 million average annual receipts over the last three years. This announcement is open to all businesses regardless of size. If the selected firm is a large business, a subcontracting plan consistent with PL 95-507, PL 99-661 and PL 100-656 will be required with the final fee proposal. A minimum goal of 40% of the total planned subcontracting dollars shall be placed with small business concerns. At least 10% of total planned subcontracting dollars shall be placed with Small disadvantaged businesses (SDB), including Historically Black Colleges and Universities or Minority Institutions; 10% with Women-owned small businesses (WOSB); 7% shall be placed with Hub-zone Small Businesses (HubZone), 7% with Veteran-owned small businesses (VOSB); and 7% with Service Disabled Veteran-owned small businesses (SDV). The subcontracting plan is required with this submittal. Any prime or joint venture found to be officially notified of non-compliance on past contracts and the non-compliance is outstanding will not be considered for this project. Failure to adequately explain reasons for not meeting previous contract goals may result in a lower overall rating and ultimate non-selection. An approved small business-subcontracting plan will be required prior to award.

Prospective contractors must be registered in the Systems for Award Management (SAM) prior to award of a contract. Information on registration and annual confirmation requirements may be obtained via the Internet at http://www.sam.gov. Lack of registration in the SAM database will make an offeror ineligible for award.

Davis Bacon Wage Determination DC20240002 (Building) and DC20240001 (Heavy) shall apply.

Total period of performance for Preconstruction and Construction Services is 36 months from the date of Notice to Proceed.

QUESTIONS/CLARIFICATIONS

It is desired that all questions/clarifications be sent in, sequentially numbered for example first questions 1,2,3, second set of questions 4, 5, 6, etc. in word format to ChanVC@si.edu. It is requested that all questions be sent in no later than 3 PM Eastern Time on February 14, 2024.

SUBMISSION REQUIREMENTS

Proposals are to be sent as an electronic copy and is required to be submitted to DropBox.com using the link:

https://www.dropbox.com/request/JJQjFNSBrebXJkmi2LuC

Statements of Qualifications (SOQ) must be received no later than 3PM Eastern Time on March 4, 2024, to be considered. Please see the attached solicitation for more details regarding submission requirements.

THE STATEMENT OF QUALIFICATIONS DUE DATE IS MARCH 4, 2024, AT 3:00PM EST.

Files

Show all 11

Notice history

Notice Type Posted
Solicitation construction bezos learning center (BLC) Award Award Notice
This notice Latest solicitation Solicitation
Presolicitation notice construction bezos learning center (BLC) Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
PRESOLICITATION Small Business Construction IDIQ Washington, DC Metropolitan Region Washington, District of Columbia, United States · NAICS 236220 Smithsonian Institution Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity