Romero Camuesa & Arroyo Seco Retaining Wall Replacements
Closed Solicitation Posted
- Solicitation number
- 12970224R0015
- Agency
-
Forest Service
Department of Agriculture
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Place of performance
- Santa Barbara, California 93105, United States
- Points of contact
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of Agriculture Forest Service is seeking bids for the Romero Camuesa & Arroyo Seco Retaining Wall Replacements project. This project consists of removing and replacing failed retaining walls at two sites on National Forest System Roads in the Los Padres National Forest in California. The required work includes structural excavation, installation of rip-rap with rockfall netting, construction of 975 square feet of new mechanically stabilized earth walls with drainage systems, roadway reconditioning, and installation of delineators. Contractors will also be required to survey and stake the new walls, test imported materials, and implement soil erosion and pollution control measures. Bids will be evaluated based on the acceptability of the offer, the capability of the offeror, and price. A site visit is scheduled for April 15-16, 2024, and bids are due by May 1, 2024.
This solicitation is set aside for small businesses. The project locations are in Santa Barbara and Monterey Counties, California. The period of performance is from June 3, 2024 to August 26, 2024. The magnitude of the project has been added to the SAM.gov posting, and the bid guarantee is 20% of the bid price. Only one award will be made from this solicitation.
Notice text
4 versions
Update #4 · Latest ·
This project consists of the removal and replacement of failed retaining walls at one site on National Forest System Road 19S09 (Arroyo Seco) and one site on National Forest System Road 15N15 (Romero Camuesa), both on the Los Padres National Forest. The site on NFSR 19S09 is located approximately 27 miles (36 minutes) west of the Monterey District Ranger Station in King City, California, near the Arroyo Seco Campground. The site on NFSR 15N15 is located approximately 18 miles (50 minutes) north of Montecito, California, one mile west of the Divide Peak OHV staging area.
The required work includes the removal of a failed block wall on 19S09 and a failed crib wall on 15N15, structural excavation, the installation of Class 4 rip-rap, including rockfall netting, the installation of a combined 975 square feet of new mechanically stabilized earth wall, including geocomposite sheet drainage systems, roadway reconditioning, including an aggregate base surface course, and the installation of carsonite delineators. The contractor will also be required to survey and stake the new retaining walls, test imported materials in accordance with specifications, and institute soil erosion and pollution control measures in accordance with plans, specifications, and the contractor-submitted Soil Erosion Control Plan.
Magnitude of construction: Between $500,000 and $1,000,000.
A site visit will be held April 15, 2024 through April 16, 2024
There will be one site visit which includes both days
Contractors will meet at 1000L at the following locations:
April 15th: San Marcos fire station
5398 E Camino Cielo, Santa Barbara, CA 93105
April 16th: Arroyo Seco campground
47600 Arroyo Seco Rd, Greenfield, CA 93927
RFIs to be submitted to george.staggs@usda.gov by 1700 CDT April 24, 2024
Update #3 ·
This project consists of the removal and replacement of failed retaining walls at one site on National Forest System Road 19S09 (Arroyo Seco) and one site on National Forest System Road 15N15 (Romero Camuesa), both on the Los Padres National Forest. The site on NFSR 19S09 is located approximately 27 miles (36 minutes) west of the Monterey District Ranger Station in King City, California, near the Arroyo Seco Campground. The site on NFSR 15N15 is located approximately 18 miles (50 minutes) north of Montecito, California, one mile west of the Divide Peak OHV staging area.
The required work includes the removal of a failed block wall on 19S09 and a failed crib wall on 15N15, structural excavation, the installation of Class 4 rip-rap, including rockfall netting, the installation of a combined 975 square feet of new mechanically stabilized earth wall, including geocomposite sheet drainage systems, roadway reconditioning, including an aggregate base surface course, and the installation of carsonite delineators. The contractor will also be required to survey and stake the new retaining walls, test imported materials in accordance with specifications, and institute soil erosion and pollution control measures in accordance with plans, specifications, and the contractor-submitted Soil Erosion Control Plan.
Magnitude of construction: Between $500,000 and $1,000,000.
A site visit will be held April 15, 2024 through April 16, 2024
There will be one site visit which includes both days
Contractors will meet at 1000L at the following locations:
April 15th: San Marcos fire station
5398 E Camino Cielo, Santa Barbara, CA 93105
April 16th: Arroyo Seco campground
47600 Arroyo Seco Rd, Greenfield, CA 93927
RFIs to be submitted to george.staggs@usda.gov by 1700 CDT April 17, 2024
Update #2 ·
This project consists of the removal and replacement of failed retaining walls at one site on National Forest System Road 19S09 (Arroyo Seco) and one site on National Forest System Road 15N15 (Romero Camuesa), both on the Los Padres National Forest. The site on NFSR 19S09 is located approximately 27 miles (36 minutes) west of the Monterey District Ranger Station in King City, California, near the Arroyo Seco Campground. The site on NFSR 15N15 is located approximately 18 miles (50 minutes) north of Montecito, California, one mile west of the Divide Peak OHV staging area.
The required work includes the removal of a failed block wall on 19S09 and a failed crib wall on 15N15, structural excavation, the installation of Class 4 rip-rap, including rockfall netting, the installation of a combined 975 square feet of new mechanically stabilized earth wall, including geocomposite sheet drainage systems, roadway reconditioning, including an aggregate base surface course, and the installation of carsonite delineators. The contractor will also be required to survey and stake the new retaining walls, test imported materials in accordance with specifications, and institute soil erosion and pollution control measures in accordance with plans, specifications, and the contractor-submitted Soil Erosion Control Plan.
A site visit will be held April 15, 2024 through April 16, 2024
There will be one site visit which includes both days
Contractors will meet at 1000L at the following locations:
April 15th: San Marcos fire station
5398 E Camino Cielo, Santa Barbara, CA 93105
April 16th: Arroyo Seco campground
47600 Arroyo Seco Rd, Greenfield, CA 93927
RFIs to be submitted to george.staggs@usda.gov by 1700 CDT April 17, 2024
Update #1 ·
This project consists of the removal and replacement of failed retaining walls at one site on National Forest System Road 19S09 (Arroyo Seco) and one site on National Forest System Road 15N15 (Romero Camuesa), both on the Los Padres National Forest. The site on NFSR 19S09 is located approximately 27 miles (36 minutes) west of the Monterey District Ranger Station in King City, California, near the Arroyo Seco Campground. The site on NFSR 15N15 is located approximately 18 miles (50 minutes) north of Montecito, California, one mile west of the Divide Peak OHV staging area.
The required work includes the removal of a failed block wall on 19S09 and a failed crib wall on 15N15, structural excavation, the installation of Class 4 rip-rap, including rockfall netting, the installation of a combined 975 square feet of new mechanically stabilized earth wall, including geocomposite sheet drainage systems, roadway reconditioning, including an aggregate base surface course, and the installation of carsonite delineators. The contractor will also be required to survey and stake the new retaining walls, test imported materials in accordance with specifications, and institute soil erosion and pollution control measures in accordance with plans, specifications, and the contractor-submitted Soil Erosion Control Plan.
A site visit will be held April 15, 2024 through April 16, 2024
There will be one site visit which includes both days
Contractors will meet at 1000L at the following locations:
April 15th: San Marcos fire station
5398 E Camino Cielo, Santa Barbara, CA 93105
April 16th: Arroyo Seco campground
47600 Arroyo Seco Rd, Greenfield, CA 93927
Files
Show all 17
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| GOGA 336173 - Repair Conzelman Road | National Office | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity