Reach B Levee Improvement Construction Project
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W9123819B0020
- Agency
- ENDIST Sacramento US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Place of performance
- Reach B begins just south of the intersection of Garden Highway and Power Line Road (Approximate STA 650+50) and extends downstream to just south of Farm Road (Approximate STA 772+50). Sacramento, California 95814, United States
Notice details come from SAM.gov. Updated .
Notice text
10 versions
Update #10 · Latest ·
The Bid Abstract is hereby posted. Before a contract can be awarded, however, the Contracting Officer must ensure the apparent low-bidder's bid is responsive to the invitation for bid; and the apparent low bidder is responsibile per FAR 9.104-1 and 9.104-2.
Update #9 ·
The Bid Abstract is hereby posted. Before a contract can be awarded, however, the Contracting Officer must ensure the apparent low-bidder's bid is responsive to the invitation for bid; and the apparent low bidder is responsibile per FAR 9.104-1 and 9.104-2.
Update #8 ·
11 September 2019:
Amendment No.: 01 is hereby issued. It incorporates multiple specification and drawing revisions stemming from Government responses to Bidder Inquiries. Note the bid due date extension. Also note that the revisions will be conformed into their respective specification or drawings volume before the contract is awarded. Thus the contract table of contents will not materially change. Any marginal page number or date changes will be reflected in FAR 52.252-4 Alterations in Contract at the time of award.
10 September 2019:
The Natomas Borrow GDR is posted.
6 September 2019:
The Geotechnical Data Reports referenced in Specification Section 02 02 00 Para 3.1.1 are posted.
23 August 2019:
The Site Visit Attendance Roster dated 22 August 2019 is posted.
21 August 2019:
Due to file size limitations, attachments 03, 04, 05 and 06 (See Table of Contents at Section 00 01 10) cannot be uploaded at this time. However, as of 21 August 2019 a web-link has been provided in lieu of an attachment to this post; and Attachments 03 through 06 can be downloaded from this link.
Please stay posted to this notice for further updates.
Update #7 ·
10 September 2019
The Natomas Borrow GDR is posted.
6 September 2019
The Geotechnical Data Reports referenced in Specification Section 02 02 00 Para 3.1.1 are posted.
23 August 2019 -
The Site Visit Attendance Roster dated 22 August 2019 is posted.
21 August 2019
Due to file size limitations, attachments 03, 04, 05 and 06 (See Table of Contents at Section 00 01 10) cannot be uploaded at this time. However, as of 21 August 2019 a web-link has been provided in lieu of an attachment to this post; and Attachments 03 through 06 can be downloaded from this link.
Please stay posted to this notice for further updates.
Update #6 ·
6 September 2019
The Geotechnical Data Reports referenced in Specification Section 02 02 00 Para 3.1.1 are posted.
23 August 2019 -
The Site Visit Attendance Roster dated 22 August 2019 is posted.
21 August 2019
Due to file size limitations, attachments 03, 04, 05 and 06 (See Table of Contents at Section 00 01 10) cannot be uploaded at this time. However, as of 21 August 2019 a web-link has been provided in lieu of an attachment to this post; and Attachments 03 through 06 can be downloaded from this link.
Please stay posted to this notice for further updates.
Update #5 ·
23 August 2019 -
The Site Visit Attendance Roster dated 22 August 2019 is posted.
Update #4 ·
21 August 2019
Due to file size limitations, attachments 03, 04, 05 and 06 (See Table of Contents at Section 00 01 10) cannot be uploaded at this time. However, as of 21 August 2019 a web-link has been provided in lieu of an attachment to this post; and Attachments 03 through 06 can be downloaded from this link.
Please stay posted to this notice for further updates.
Update #3 ·
19 August 2019:
Due to file size limitations, attachments 03, 04, 05 and 06 (See Table of Contents at Section 00 01 10) cannot be uploaded at this time.
Until FBO.gov can provide a viable solution, to request attachments 03, 04, 05 and 06, interested bidders are to email both myself and the contracting officer using the following email addresses:
Greg.L.Treible@usace.army.mil, and
Leah.M.Caldwell@usace.army.mil.
In the email subject line please state: 19B0020 Reach B Attachment Request.
The Government will use a newer file transfer program called DOD-SAFE. It works similarly to the now defunct AMRDEC-Safe.
Please see the solicitation for site visit information and be sure to request these attachments as soon as possible if you'd like to review them before the site visit.
Please stay posted to this notice for further updates.
Update #2 ·
Solicitation No.: W9123819B0020 is hereby issued as of 16 August 2019.
Due to file size limitations, attachments 03, 04, 05 and 06 (See Table of Contents at Section 00 01 10) cannot be uploaded at this time.
Attachments 03, 04, 05 and 06 will be divided into file sizes that FBO.gov is capable of accepting; and the Government will upload these attachments by the end of the day on 19 August 2019.
Please stay posted to this notice for further updates.
Update #1 ·
See attached pre-solicitation notice.
Attachments
Show all 22
Notice history
| Notice | Type | Posted |
|---|---|---|
| Reach B Levee Improvement Construction Project | Award Notice | |
| Reach B Levee Improvement Construction Project | Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity