American River Common Features (ARCF) Spec No. 2122 Riverside Canal Relocation and Natomas Basin - Reach B Addendum No. 1
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 73 05
SUPPLEMENTARY CONDITION REQUIREMENTS FOR PROJECTS: RIVERSIDE CANAL RELOCATION
AND REACH B
01/10
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.2.1 Preconstruction Submittals
1.3 SUPPLEMENTARY CONDITIONS REQUIREMENTS
1.3.1 SCR-1 Location of Work
1.3.2 SCR-2 Scope of Work
1.3.3 SCR-3 Allowable Time, Schedule Constraints and Time of
Completion
1.3.4 SCR-4 Site Conditions
1.3.5 SCR-5 Lands and Right-of-Way
1.3.6 SCR-6 Access by Government, and Other Jurisdictional Public
Agencies
1.3.7 SCR-7 Borrow Source
1.3.8 SCR-8 Contractor's Tools and Equipment
1.3.9 SCR-9 Locking Gates
1.3.10 SCR-10 Water Source for Construction Operations
1.3.11 SCR-11 Cleaning Up
1.3.12 SCR-12 Protection of Existing Improvements
1.3.13 SCR-13 Record Drawings
1.3.14 SCR-14 Flood Emergency
1.3.15 SCR-15 Permits and Approvals
1.3.16 SCR-16 Dust Control
1.3.17 SCR-17 Fire Control
1.3.18 SCR-18 Air Pollution Control
1.3.19 SCR-19 Noise Control
1.3.20 SCR-20 Allowable Work Hours
1.3.21 SCR-21 Cultural Resources
1.3.22 SCR-22 Protection of Existing Trees
1.3.23 SCR-23 Biological Resources
1.3.24 SCR-24 Raptor and Migratory Birds
1.3.25 SCR-25 Wetlands and Sensitive Habitats
1.3.26 SCR-26 U.S. Fish and Wildlife Service
1.3.27 SCR-27 Speed Limit
1.3.28 SCR-28 Reclamation District 1000 (RD1000) Coordination
1.3.29 SCR-29 Natomas Mutual Water Company (NMWC) Coordination
1.3.30 SCR-30 Provision Regarding Maintaining Minimum Flood
Protection During Construction
1.3.31 SCR-31 Coordination with the Contracting Officer and Utilities
Relocation
1.3.32 SCR-32 Haul Routes
1.3.33 SCR-33 Resource Coordination
1.3.34 SCR-34 Flood Contingency Plan
1.3.35 SCR-35 Utility Provider Response Plan
DOCUMENT 00 73 05 Page 1
1.3.36 SCR-36 Stop Work Authority
1.3.37 SCR-37 Floodway Construction Schedule
1.3.38 SCR-38 High Visibility Fencing, Habitat Preservation and
Buffers
1.3.39 SCR-39 General Safety Requirements
1.3.40 SCR-40 Storm Water Pollution Prevention Plan
1.3.41 SCR-41 Grading (Encroachment) Permit
1.3.42 SCR-42 Staging Area
1.3.43 SCR-43 Recreation/Community Mitigation - Riverside Canal
Relocation and Reach B
1.3.44 SCR-44 City Streets - Riverside Canal Relocation and Reach B
1.3.45 SCR-45 Storage Area - Riverside Canal Relocation and Reach B
1.3.46 SCR-46 Project Signage
1.3.47 SCR-47 Traffic Control Plan
1.3.48 SCR-48 Garden Highway
1.3.49 SCR-49 Mailbox Removal and Replacement on Garden Highway
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
DOCUMENT 00 73 05 Page 2
SECTION 00 73 05
SUPPLEMENTARY CONDITION REQUIREMENTS FOR PROJECTS: RIVERSIDE CANAL RELOCATION
AND REACH B
01/10
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
CONSOLIDATED EM 385-1-1 (2014) Safety and Health Requirements Manual
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation. The following shall be in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals; G
Permits and Approvals; G
Construction emission/dust control plan; G
Permit, waiver or other documentation with the mapped haul routes from local jurisdictions to repair or compensate for damage; G
Flood Contingency Plan; G
Utility Provider Response Plan; G
Grading (Encroachment) Permit; G
Certification of Insurance
Security Bonds
List of Proposed Subcontractors
Construction Progress Schedule
Network Analysis Schedule
Submittal Register
Schedule of Prices
Health & Safety Plan
DOCUMENT 00 73 05 Page 3
Work Plan
QC Plan
Erosion Protection Plan
1.2.1 Preconstruction Submittals
Submit the following prior to commencment of construction:
Certification of Insurance
Security Bonds
List of Proposed Subcontractors
Construction Progress Schedule
Network Analysis Schedule
Submittal Register
Schedule of Prices
Health & Safety Plan
Work Plan
QC Plan
Erosion Protection Plan
1.3 SUPPLEMENTARY CONDITIONS REQUIREMENTS
1.3.1 SCR-1 Location of Work
The Natomas Basin is approximately 53,000 acres (82 square miles) and is situated northwest of downtown Sacramento. Reach B, which is located along the Garden Highway along the Sacramento River (east of Power Line Road to Farm Road), is approximately 2.3 miles in length (STA 650+00 to STA 773+00).
1.3.2 SCR-2 Scope of Work
The work in this Contract includes relocating the existing Riverside Canal, levee remediations including adjacent levee with seepage berms, Pumping Plant 3 modifications, utility relocations, and incidental related work.
Refer to Section 01 11 00 for additional detail.
Access to the construction site will involve temporary partial and full lane closures on Garden Highway.
1.3.3 SCR-3 Allowable Time, Schedule Constraints and Time of Completion
The time of completion for this contract, which shall include all segments of work to be completed in their entirety and in accordance with the project plans and these specifications, shall be as outlined below and incorporated into the Contractor's schedule
DOCUMENT 00 73 05 Page 4
Contractor shall not perform any work within the existing floodway (waterside of the levee) along Garden Highway between November 1 and April 15.
TIME OF COMPLETION FOR REACH B
Description of Work Date of Completion
A. Contracting Officer and Resident Engineer's Office Facility
Installed and ready for occupancy not later than five (5) calendar days prior to start of construction.
B. Traffic Control Plan Traffic Control Plan shall be approved and traffic control measures installed prior to the start of construction activities
C. Copies of Permits Contractor to provide to Contracting Officer within 10 days of receipt
D. Flood contingency plan including Flood Evacuation Plan for the waterside staging area
Submit to Contracting officer 30 days prior to commencement of construction activities
E. Complete adjacent levee (design top of levee final grade), seepage berms, and Pumping Plant 3 work
October 31
F. Complete erosion control seeding of all areas
November 30
G. Complete demobilization and site clean-up of all areas
November 30
H. Record Drawings Submit to Contracting Officer within 10 days after Government approval of working drawings
Ground disturbance work along Garden Highway shall not begin before April 15.
1.3.4 SCR-4 Site Conditions
The Contractor shall satisfy himself or herself concerning the nature and location of the work; the general and local conditions, particularly those affecting transportation, disposal, handling and storage facilities;
availability of labor, water, power, communications, roads, climatic conditions and seasons; physical conditions at the job sites and Project areas as a whole; job-site topography and ground conditions; permits, equipment, and facilities needed preliminary to, and during, work prosecution; and all other matters which can in any way affect the work, including cost thereof. Failure of the Contractor to become acquainted with all available information regarding any applicable conditions will not relieve the Contractor from the responsibility for properly estimating either the difficulties or the costs of successfully performing the work.
1.3.5 SCR-5 Lands and Right-of-Way
The right-of-way for the construction work, as shown on the Plans, will be provided by the Government. The Contractor is responsible for obtaining land rights and easements for areas to be used for the Contractor's own
DOCUMENT 00 73 05 Page 5 convenience outside the right of way shown and footprint limits on the Plans and shall absorb complete liability for the use, and/or associated activities related to the use of such land. The Contractor is responsible for all work and costs associated with obtaining land rights and easements.
If the contractor receives land rights and easements outside of the construction limits, these rights shall be received in writing and shall be forwarded to the Government for their records. Contractor shall also receive release of liability of the Government for any damage to these addition areas in writing.
Compliance with environmental and cultural laws shall be followed by the contractor if using lands other than those identified by the Government.
1.3.6 SCR-6 Access by Government, and Other Jurisdictional Public Agencies
The Contractor shall allow the following Agencies and Jurisdictional public agencies unrestricted access to the project site at all times:
United States Army Corps of Engineers
California Department of Water Resources
Reclamation District 1000
Sacramento Area Flood Control Agency
County of Sacramento
City of Sacramento
Sacramento Area Sewer District
Central Valley Flood Protection Board
California State Department of Fish and Wildlife
United States Fish and Wild Life Service
National Marine Fishery Service
All Visitors shall comply with the safety requirement in the EM 385-1-1 and contractor safety plans. All Visitors shall coordinate with the onsite Government representative prior to visiting the job site.
1.3.7 SCR-7 Borrow Source
Contractor shall use Bollinger borrow source for Riverside Canal Relocation and Huffstutlerthe Johnson Ranch and WhitterWitter Ranch borrow sourcesites for the Riverside Canal Relocation and Reach B levee improvements, to the depth and limits indicated and sequenced as described on the Plans. The borrow sources are along and adjacent to the project limits. The Contractor shall comply with protocols in Section 31 23 00 BORROW SITE EXCAVATION of Volume 2 and paragraph 1.3.19 of Section 00 73 05, of these specifications.
1.3.8 SCR-8 Contractor's Tools and Equipment
The Contractor shall furnish all equipment, materials, tools, supplies, and
DOCUMENT 00 73 05 Page 6 manufactured articles required for the completion of the work in accordance with the Contract. The Contractor shall take the necessary precautions to secure tools and equipment from theft while on-site. The Government assumes no responsibility for lost, vandalized, or stolen equipment belonging to the Contractor, its subcontractors, or its employees.
1.3.9 SCR-9 Locking Gates
The Contractor shall take care to protect and operate any existing gates that control access to the Project right-of-way, in conformance with the Government, RD1000, and the County of Sacramento requirements. These requirements include preventing passage through the gates of unauthorized persons and equipment during periods of Contractor use of the gates and locking the gates during non-construction periods, if so directed by the Contracting Officer.
1.3.10 SCR-10 Water Source for Construction Operations
Contractor is responsible for identifying, securing, and obtaining all water needed for the project for both potable uses and for construction purposes. Water shall not be pumped from the Sacramento River.
Construction water should be reused onsite to the extent practical and disposed of in a manner consistent with the quality of the water after use. Excess water shall not be disposed of into any wetland, stream, river, or storm drainage without all applicable local and regulatory permitting.
Contractor shall be responsible for disposal of all construction water.
1.3.11 SCR-11 Cleaning Up
The Contractor shall dispose of all trash items in closed containers, which shall be removed at least once per day. Vegetative wastes shall be chipped and delivered to waste energy facilities, mulched, composted, or used for firewood and removed at least once per week.
1.3.12 SCR-12 Protection of Existing Improvements
Except as specified herein or as shown on the Plans, existing structures and utility lines shall not be disturbed, damaged, or undermined by the Contractor, except where in the opinion of the Contracting Officer it is essential to relocate such improvements. If relocation of any facility is required, the Contractor shall relocate the improvements to be at least equal in condition to the original. The Contractor shall take all necessary precautions to prevent any damage to existing facilities. Should damage or injury occur as a result of the Contractor's operations, the Contractor shall repair or replace such damaged facilities to the Contracting Officer's satisfaction at the Contractor's expense.
The Contractor shall repair any damage to public and private streets resulting from the Contractor's operations, as directed by the Contracting Officer. Repair shall be made per industry standards and conform to local jurisdictional requirements. Repairs shall be made at no additional cost to the Government.
1.3.13 SCR-13 Record Drawings
The Contractor shall maintain a neat and accurate marked set of working record drawings in accordance with the Specifications. The record drawings
DOCUMENT 00 73 05 Page 7 shall be subject to the inspection of the Contracting Officer at all times and shall be kept current weekly with all work instructions, change orders, and construction adjustments shown thereon and initiated by inspection.
The Contracting Officer reserves the right to withhold progress payments, or portions thereof, if record drawings are not maintained as stated above.
1.3.14 SCR-14 Flood Emergency
In the event of a flood emergency requiring action by the jurisdictional flood control agencies prior to completion of the work, the Contracting Officer shall have the right to suspend the work. Such suspension includes the right of the Contracting Officer to take over the Project to conduct flood protection activities in accordance with the flood contingency plan.
1.3.15 SCR-15 Permits and Approvals
The Contracting Officer has obtained various permits, agreements, and rights for performance of the work. These permits may be described more fully in other SCRs and these specifications. The Contractor will be required to obtain additional permits or be a signatory on the Contracting Officer obtained permits as noted throughout the specifications. The Contractor shall be responsible for complying with all conditions of the permits and agreements. Any delays to the Project resulting from the Contractor's failure to follow permit requirements will not be the responsibility of the Contracting Officer and the Contractor will not be granted any extension of time for such delays.
The Contractor is responsible for obtaining all environmental permits or use permits (including CALTRANS Encroachment Permit) and SAFCA Right of Entry required for easements to land being used for the Contractor's own convenience and for work within the State Right of Way. Any delays to the Project resulting from the lack of these additional permits or the Contractor's failure to follow permit requirements will not be the responsibility of the Contracting Officer and the Contractor will not be granted any extension of time or additional compensation for such delays.
Copies of all permits obtained by the Contractor shall be given to the Contracting Officer within 10 days of receipt of permit. The contractor is responsible for paying all permit fees.
1.3.16 SCR-16 Dust Control
The Contractor shall comply with the provisions of Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS of the Specifications. The Contractor shall prepare and submit a construction emission/dust control plan to the Contracting Officer and Sacramento Metropolitan Air Quality Management District (SMAQMD) and shall receive approval of the plan before groundbreaking. During the performance of the work, the Contractor shall assume all responsibility for dust control and shall furnish all labor, equipment, and means required, and shall carry out proper and efficient measures wherever and as often as necessary to prevent the construction operations from producing dust in amounts harmful to persons, damaging to property, or causing a nuisance to persons living nearby or occupying buildings in the vicinity of the work, or as directed by the Contracting Officer. Dust control will be strictly enforced with particular emphasis on work areas adjacent to residential and agricultural properties. The curtailment of the construction activities as a result of inadequate dust control measures will not be considered an unavoidable delay. The Contractor shall suspend all grading operations when fugitive dust levels exceed levels specified by SMAQMD regulations or deemed unacceptable by the
DOCUMENT 00 73 05 Page 8
Contracting Officer. The Contractor is responsible for paying any fees assessed by SMAQMD.
1.3.17 SCR-17 Fire Control
No burning shall be allowed for any activities associated with this project.
Delivering removed vegetative material to compost or waste-to-energy facilities, or repurposing is encouraged. Land filling of material shall be minimized.
Smoking shall not be permitted in areas near flammable materials such as dry grass or in restricted areas as identified by the Contracting Officer.
Cigarette butts shall be placed in appropriate receptacles.
1.3.18 SCR-18 Air Pollution Control
The Contractor shall comply with the air pollution control protocols specified in Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS of the Specifications. To the extent available, the Contractor shall use existing power sources for the Contractor provided trailers rather than temporary power generators. If existing power sources are unavailable, clean fuel, low-emission on-site stationary generator equipment shall be used.
Low-sulfur fuel shall be used for stationary construction equipment. The Contractor shall be responsible for arranging appropriate consultation with the Air Resources Board and the SMAQMD, to determine registration and permitting requirements before operating portable engines or portable engine-driven equipment at the project site.
1.3.19 SCR-19 Noise Control
The Contractor shall comply with Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS of the Specifications to avoid and minimize noise impacts from the construction activities.
Before construction activity begins within 500 feet of one or more residences, the Contractor shall provide written notification to the potentially affected residents, identifying the type, duration, and frequency of activities. Notification materials shall also identify a mechanism for residents to register complaints with the appropriate jurisdiction if demolition noise levels are overly intrusive.
Before haul truck trips are initiated on roads within 600 feet of one or more residences, the Contractor shall provide written notification at least one day before to the potentially affected residents, identifying the hours and frequency of haul truck trips. Notification materials shall also identify a mechanism for residents to register complaints with the appropriate jurisdiction if haul truck noise levels are overly intrusive or outside exempt daytime hours.
1.3.20 SCR-20 Allowable Work Hours
The Contractor shall limit construction activities to between the following hours on the following days for Riverside Canal Relocation Project and Reach B:
Construction shall be performed Monday through Saturday 7 AM to 6 PM and Sunday 9 AM to 6 PM.
DOCUMENT 00 73 05 Page 9
Heavy machinery activity off of the levee is restricted to the staging area for one hour prior to 7:00 AM and for one hour after sunset (as posted in the newspaper or online) or 10:00 PM whichever occurs sooner. No other construction work will be allowed outside the above mentioned hours. Any extended work hours must be reflected in the Contractor's initially approved schedule for the Project.
During flood contingency plan operations, work hour restrictions are not applicable.
1.3.21 SCR-21 Cultural Resources
The Contractor shall comply with protocols in Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, of the Specifications.
Contractor shall conduct Construction Personnel Training for all on-site employees. If cultural resources are discovered during construction activities, Contractor shall cease work within 100 feet of the vicinity of the find and immediately contact the archaeologist, through the Contracting Officer, and cooperate with all pertinent mitigation procedures.
Construction personnel shall participate in a cultural awareness program, which will be provided by the USACE Archeologist at the start of construction. As needed, the Contractor shall provide a translator to allow the training to be conducted in Spanish for Spanish language speakers and other languages as needed or necessary.
1.3.22 SCR-22 Protection of Existing Trees
All trees of any kind inside the work limits and designated in the drawings as protect in place are to be protected. Contractor shall place protective barrier fencing where possible at the drip line around trees designated as protect in place in the drawings. All trees outside the work limits, of any kind, are not to be disturbed. Contractor shall place protective barrier fencing around trees adjacent to construction areas as directed by the Contracting Officer. If damaged by the Contractor, damaged trees and landscaping shall be replaced by Contractor or otherwise mitigated as directed by Contracting Officer at the Contractor's expense.
1.3.23 SCR-23 Biological Resources
The Contractor shall comply with the Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, of the Specifications to avoid and minimize effect upon endangered or sensitive species in the Project area. The Contractor shall schedule activities to comply with the provisions and provide required notice for surveys to be conducted by the Government's Environmental Representative. Construction personnel shall participate in an environmental awareness program, which will be provided by the USACE Biologist at the start of construction. As needed, the Contractor shall provide a translator to allow the training to be conducted in Spanish for Spanish language speakers and other languages as needed or necessary.
1.3.24 SCR-24 Raptor and Migratory Birds
The Contractor shall comply with the provisions of the Construction Contractor Protocols for Avoiding and Minimizing Impacts to Raptors, Special Status, and Other Nesting Birds, which are included in Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, of the Specifications. If an injured bird is found on the Project site, the Contracting Officer shall be notified immediately so the animal can be relocated to a either a wildlife
DOCUMENT 00 73 05 Page 10 care facility or a raptor recovery facility.
1.3.25 SCR-25 Wetlands and Sensitive Habitats
The Contractor shall not impact Wetlands and Sensitive Habitats.
1.3.26 SCR-26 U.S. Fish and Wildlife Service
A Biological Opinion has been issued by the U.S. Fish and Wildlife Service.
The Contract Documents contain all of the terms and conditions from the Biological Opinion, and the Contractor is responsible for implementing all requirements and obligations sited in the Contract Documents.
1.3.27 SCR-27 Speed Limit
The speed limit in all Project work areas and along levees shall be 15 m.p.h., except on county roads, city streets and highways. The Contracting Officer may also require that speed limits on project site be reduced further to ensure vibration limits, dust protocols or other criteria are not violated. The Contractor shall post, at a minimum, two speed limit signs at each end of the work zone.
1.3.28 SCR-28 Reclamation District 1000 (RD1000) Coordination
RD1000 manages the existing levees and owns and operates drainage facilities along the existing levees throughout the project area. The Contractor shall coordinate their work with RD1000 through the Contracting Officer, allowing RD1000 access to its facilities at all times. The Contractor shall maintain access for RD1000 through the Contracting Officer at all times.
The Contractor shall conduct the work so that RD1000 personnel and equipment are not prevented from access to and passage along the existing levees at all times for normal and emergency purposes.
The Contractor shall coordinate installation of the temporary bridges or culverts in any drainage ditches with RD1000. Culverts for temporary drainage canal crossings shall be removed prior to start of the flood season on November 1. Where temporary crossings must remain during the flood season, November 1 to April 15th, bridging should be used where practical, or culverts should be appropriately shall be sized for peak flows.
1.3.29 SCR-29 Natomas Mutual Water Company (NMWC) Coordination
The Natomas Mutual Water Company (NMWC) owns and operates untreated surface water irrigation facilities throughout the project area. The Contractor shall coordinate the work with NMWC through the Contracting Officer, allowing NMWC access to its facilities at all times. If NMWC facilities are required to be taken out of service, the Contractor shall coordinate with NMWC and provide temporary facilities of equal capacity to NMWC facilities. NMWC owns and operates the Riverside Irrigation Canal which parallels the SREL south of Power Line Road. Laterals to the Riverside Irrigation Canal (also owned and operated by NMWC) include the Radio Road Irrigation Ditch, J-Ditch, Lateral 13, Parker Road Ditch, and Tree Road Ditch. NMWC owns and operates the Riverside Pumping Plant which provides supply from the river for the Riverside Irrigation Canal. A recirculation pump at RD1000 Plant 3 is owned and operated by NMWC and provides
DOCUMENT 00 73 05 Page 11 recirculated water supply to the Riverside Irrigation Canal.
Surface water rights for all canals and ditches within the Natomas Basin, including the RD1000 drainage canals, are controlled by NMWC. A permit is required from NMWC to withdraw water for construction uses from ditches and canals within the construction area.
Haul road crossings over irrigation canals must be permitted as an encroachment through NMWC facilities. Bridging is the preferred method for temporary crossings. Where culverts are proposed, temporary pipes should be sized for maximum flow rate and velocities less than two feet per second, accounting for limited submergence. In some instances, culvert crossings may not be permitted without other system upgrades due to inherent system capacity limitations and other operational limitations.
Unless otherwise approved by NMWC, all temporary culverts shall be removed after construction. Contractor shall be responsible for obtaining required permits from NMWC and scheduling the installations with NMWC. Where temporary ramps and bridges are constructed for irrigation canal crossings, access around crossings must be provided for operators, including NMWC, The Natomas Basin Conservancy, RD1000, and other agricultural operations.
Contractor shall provide specific details in advance, which will address continuity of flows during construction, anticipated maximum outage duration (if allowed), anticipated duration of use, details of erosion protection, plans for providing access for operators, and other information as requested by the Contracting Officer and NMWC. Areas disturbed by temporary facilities shall be restored to pre-construction condition to the satisfaction of the NMWC and the Contracting Officer.
The Riverside Irrigation Canal system (including associated laterals) is generally operated between April 1st and September 15th. Portions of this system are also operated intermittently year-round to maintain permanent plantings. The Contractor shall coordinate all system outages with NMWC.
System outages require significant pre-construction planning, communication with irrigation users, and preparation by NMWC operators. Temporary facilities may be required elsewhere in the system to allow for rerouting of flows and Contractor shall work with NMWC to facilitate. The Contractor shall develop specific plans for any planned system outages and obtain Contracting Officer and NMWC approval in advance of outages.
Unless specifically identified on the Plans or otherwise approved by NMWC, the Contractor shall not be permitted temporary access along the top of canal embankments, including equipment and material storage, parking, and staging. All temporary access shall be along the toe of embankments at field level. Where work encroaches upon canal embankments, the top of existing canal embankments shall be restored and re-leveled as required to provide the required freeboard above operating levels to the satisfaction of NMWC and the Contracting Officer.
Riverside Irrigation Canal
The Riverside Irrigation Canal is an existing irrigation main irrigation canal that parallels the SREL at the toe of the levee from downstream of Power Line Road to approximately I-80. The canal will be relocated landward to accommodate future levee construction activities. The canal is supplied with water from the Sacramento River at NMWC's Riverside Pumping Plant, just north of Radio Road, and re-circulated agricultural tailwater from a NMWC recirculation pump at RD1000's Pumping Plant No. 3. In addition to providing irrigation water to adjacent fields, the canal supplies lateral irrigation canals which serve properties to the east. To
DOCUMENT 00 73 05 Page 12 the extent practical, outages should be planned to occur outside of primary irrigation season. The work may be performed during peak irrigation season provided tie-ins are staged to avoid interruption of irrigation service.
Temporary piping and/or piping will be required to maintain service during tie-ins or for other outages. The Contractor shall provide temporary facilities (pumps, piping, etc.), make temporary connections, and operate the system to maintain irrigation flows. The plan for maintaining continuity of the irrigation flows during construction shall be developed by the Contractor in advance and is subject to approval by NMWC.
Irrigation Water Delivery Requirements
Contractor shall furnish, operate, and maintain temporary pumping and piping facilities as required to maintain minimum system flows as described in the following table. This table shows flows in major facilities; flow requirements for smaller lateral canals shall be a minimum of 5 cfs.
Tie-ins of temporary facilities that require short duration outages will require substantial pre-construction planning, and may require improvements and/or temporary facilities at other points in the system for rerouting flows. The table below lists the minimum flows required at the pumping plant.
Riverside Canal Minimum Required Flows from South of Plant 3 to Radio Road
Time Period Minimum flow (cfs)
April 1 - October 15 20
October 16 - March 31 0
Dates are approximate.
Riverside Canal Minimum Required Flows from South of Radio Road to Farm Road
Time Period Minimum flow (cfs)
April 1 - October 15 50
October 16 - March 31 0
Dates are approximate.
Riverside Canal Minimum Required Flows from South of Farm Road
Time Period Minimum flow (cfs)
April 1 - October 15 20
October 16 - March 31 0**
Dates are approximate.
Pumping Plant 3 Irrigation Recirculation Outage
The NCMWC owns and operates recirculation pumps located in the RD1000 Pumping Plant 3 sump. A common forebay serves the RD1000 and NCMWC pumps within the sump and is fed by the RD1000 Pumping Plant 3 Intake Channel.
Outages that require dewatering of the intake channel and sump will interrupt the NCMWC water supply. During such outages, the Contractor shall
DOCUMENT 00 73 05 Page 13 furnish, operate and maintain temporary pumping facilities as required to continue deliveries of water to the NCMWC Riverside Canal that comply with the Irrigation Water Delivery requirements described above. The temporary pumps shall discharge into the Riverside Canal on the south side of Pumping Plant 3 Intake Channel, within the concrete lined section upstream of the first control structure. The rate of flow shall be adjustable. Facilities located within Pumping Plant 3 intake channel shall be subject to the approval of its owner RD1000 (in addition to NCMWC) and shall include provisions to prevent erosion or conditions detrimental to the long term maintenance of the channel.
1.3.30 SCR-30 Provision Regarding Maintaining Minimum Flood Protection During Construction
Do not begin activities that reduce the level of flood protection, as determined by the Contracting Officer, pior to April 15 of any year.
Contractor must have all levee and pipeline improvements completed by October 31 or any year unless otherwise approved by the Contracting Officer. Do not disturb the existing levee system after October 31.
Disturbances include but is not limited to the crown access roads, ramps, pipes and/or utilities crossings, stability berms, or excavations within the limits of construction. Stockpiling suitable construction materials, tree removal, reservoir work, clearing, grubbing, and stripping operations along the landside of the levee, removal and installation of services and utilities along the landside are acceptable provided no materials are stored on the levee, on the wwaterside or within 100 feet of the existing landside levee toe.
1.3.31 SCR-31 Coordination with the Contracting Officer and Utilities Relocation
Contractor shall coordinate and cooperate with the Contracting Officer and all utility providers on relocation of any overhead and underground electrical, sewer, water and storm utilities within the limits of construction that may hinder the performance of Contractor's construction activities. Contractor shall assist in coordination and work with the Contracting Officer such that the utilities are relocated in time not to delay and to allow for completion of improvements in accordance with the Time of Completion schedule. Unless the relocation is called for on the drawings, the cost of any relocations is the responsibility of the Contractor.
1.3.32 SCR-32 Haul Routes
All haul and access routes shall be existing public roads and maintenance roads, except for restrictions noted in this section. Contractor to utilize San Juan Road and El Centro Road for all hauling activities.
Contractor to avoid Garden Highway for hauling traffic. Stockpiling of construction materials, including portable equipment, vehicles, and supplies, shall be restricted to designated construction staging areas and work sites. Movement of heavy equipment to and from the Project site shall be restricted to load limit approved roadways in this paragraph. Paved areas at construction access points shall be swept each day, or more frequently, as required by the Contracting Officer to control dust and clean up material tracked or spilled on said paved areas or roadways. The Contractor shall conform to all governing codes, laws, and ordinances.
Contractor shall obtain a permit, waiver or other documentation with the mapped haul routes from local jurisdictions to repair or compensate for
DOCUMENT 00 73 05 Page 14 damage to local roads used in hauling to or from the project site. The permit, waiver or other documentation provided by the local jurisdiction may specify the conditions for repairs to be performed or appropriate compensation to account for the road damage. Contractor shall provide a copy of the permit, waiver or other documentation from local jurisdictions with the mapped haul routes to the Contracting Officer and resident engineer prior to commencement of haul operations. All cost associated with permits, haul road repairs, fees shall be the responsibility of the Contractor and shall not be paid separately from unit prices or lump-sum prices contained in the Bidding Schedule.
1.3.33 SCR-33 Resource Coordination
All contact and coordination with the resource agencies shall occur through the Contracting Officer in coordination with the Government's environmental representative.
1.3.34 SCR-34 Flood Contingency Plan
In the event the water surface elevation of the adjacent river is forecasted by the State-Federal Flood Forecast Center to increase significantly for any reason, the Contracting Officer reserves the right to require the Contractor to stop excavation and to begin continuous operations to complete all partially completed section(s) of the levee embankment. At least 15 days prior to any Levee Excavation, the Contractor shall submit a contingency plan outlining the contingency operations in the event that river elevations rise above the flood stage (as defined by the USACE) are forecasted. The contingency plan shall include the proposed measure to protect the landside areas which have a reduced level of protection due to construction activities. The plan shall include river stage monitoring, river stage at which the plan will be activated, material and equipment to be used in performance of the contingency plan, and location, type and quantity of the stockpiled emergency material. The plan shall also include the length of levee, where stockpiled material will be stored, and the method for monitoring river elevations. The Contractor shall keep any levee degrade material on the project site for the duration of the construction period, protected from inclement weather, for use as emergency backfill as necessary. The Flood Contingency Plan shall be submitted to the Contracting Officer for review.
1.3.35 SCR-35 Utility Provider Response Plan
Contractor shall prepare and submit a Utility Provider Response Plan to the Contracting Officer, Sacramento Area Sewer District (SASD), Sacramento Municipal Utility District (SMUD), Comcast, and the City of Sacramento.
Plan shall detail how utility locations are verified, provide protocol for coordination with Utility Providers, detail process on conducting required worker training for all on-site employees with respect to accidental utility damage, and provide utility provider emergency contact information. Contractor is responsible for coordinating any temporary utility services needs during construction, and shall assume all temporary utility services cost.
1.3.36 SCR-36 Stop Work Authority
The Contracting Officer and Administrative Contracting Officer shall have the authority to immediately stop any activity that is not in compliance with the permits, and/or order any reasonable measure to avoid the unauthorized take of an individual of the Covered Species (e.g., giant
DOCUMENT 00 73 05 Page 15 garter snake, Swainson's hawk, valley elderberry longhorn beetle, Federally- and State-listed fish).
1.3.37 SCR-37 Floodway Construction Schedule
Contractor shall not perform any work within the existing floodway including all staging area activities (i.e., waterside or within the Sacramento River floodplain) per the date restrictions in Time of Completion requirement herein and shall not begin any construction until evaluation of upstream conditions indicate that inundation of these areas is unlikely to occur.
1.3.38 SCR-38 High Visibility Fencing, Habitat Preservation and Buffers
Contractor shall provide high visibility fencing that shall be placed to prevent encroachment of construction personnel and equipment into areas outside of or adjacent to the project footprint that contain sensitive habitats, including at least 20 feet from the dripline of elderberry shrubs and up to 200 feet from the edge of aquatic features that are suitable giant garter snake habitat. K-Rails, if used, shall be used in areas noted on the drawings. The fencing shall be inspected by the Contractor before the start of each work day and shall be maintained until completion of the Project. The Contractor shall not remove the fencing until construction of the Project is completed. No insecticides, herbicides, or other chemicals that might harm the valley elderberry longhorn beetle or its host plant shall be used within 20 feet of the elderberry shrubs.
1.3.39 SCR-39 General Safety Requirements
The Contractor shall conform to all applicable occupational safety and health standards, rules, regulations, and orders established by the State of California or Federal Government. The Contractor shall, upon request, submit to the Contracting Officer a copy of their Injury Illness Prevention Program (IIPP) (including Site Safety Plan and Code of Safe Work Practices) for review. The Contractor is required to fulfill the requirements of these programs during the prosecution of the Work, and comply with conditions set forth in the Specifications. The Contractor shall comply with all regulations set forth in CONSOLIDATED EM 385-1-1.
1.3.40 SCR-40 Storm Water Pollution Prevention Plan
Contractor shall develop a Storm Water Pollution Prevent Plan (SWPPP) and submit in accordance with Section 01 57 23.
1.3.41 SCR-41 Grading (Encroachment) Permit
Contractor shall obtain an Encroachment Permit from City of Sacramento prior to initializing work. Copy of work permit shall be submitted to the Contracting Officer prior to disturbing ground.
1.3.42 SCR-42 Staging Area
Staging areas available to the Contractor are between the construction limits shown on the Plans. Approval of staging areas shall be coordinated with Contracting Officer. If additional areas are available for use, they will be the responsibility of the Contractor to obtain.
Below is a list of expected activities that will occur inside of the staging area.
DOCUMENT 00 73 05 Page 16
A. General Activities
1. The contractor will place temporary facilities (trailers) as well as daily parking for USACE construction manager, contractor staff and project visitors;
2. The temporary storage of miscellaneous items such as project fencing and salvaged guard rails may occur within the staging area.
B. Utility Relocation
1. Overhead utility relocation work performed by others will include the use of utility line trucks and require the temporary storage of conductor wire and utility poles;
2. Electrical transformer storage will not be allowed within the staging area;
3. Underground utility relocation work will require the temporary storage of earthwork spoils and the removed utility lines;
C. Tree Removal Equipment and Materials
1. Equipment for removal of tree stumps along the crown and landside slope and toe of the Garden Highway levee may be temporarily stored within the staging area;
2. Debris from downed trees may be temporarily stored within the staging area.
D. Earthwork Material and Equipment
1. The contractor may store road paving equipment within the staging area as well as aggregate base material for roadway placement;
2. The contractor will temporarily place earthwork spoils that include topsoil and levee embankment material from slope flatting activities.
E. Road Work Material and Equipment
1. The storage of asphalt-concrete paving removed for levee improvements will not be allowed within the staging area;
2. The contractor may store road paving equipment within the staging area as well as aggregate base material for roadway placement.
Suitable impervious liner or tarping materials shall be placed under paving equipment to catch and allow removal of oils.
1.3.43 SCR-43 Recreation/Community Mitigation - Riverside Canal Relocation and Reach B
A minimum of two weeks prior to start of work Contractor shall provide written notification to the City of Sacramento DPW Representatives, City of Sacramento Department of Transportation, City of Sacramento Bike/Pedestrian Coordinator, City Public Information Officers, and Sacramento Regional Transit, as well as outreach to the immediate project neighbors advising of the work, duration, the days of the week work is to take place, and the hours to be worked for each day. USACE and Contractor to provide, via posted signage, a USACE project manager name, contact number and e-mail address as well as a Contractor project manager name, contact number and e-mail address, for residents in the vicinity of the Premises should any concern from the immediate project neighbors arise with regard to noise, traffic, or other such disturbance which directly results from USACE's and/or Contractor's work. The purpose of USACE and Contractor posting their respective contact information is to avoid Construction Inspection and Survey staff having to field telephone calls and other inquiries related to USACE's and Contractor's work.
DOCUMENT 00 73 05 Page 17
1.3.44 SCR-44 City Streets - Riverside Canal Relocation and Reach B
The Contractor shall ensure that its construction equipment and hauling operations do not damage City or County streets. Prior to start of construction, Contractor shall video and photograph all city and country streets within the construction area and along all haul routes before construction operations begin. Photographs shall be submitted to the Contracting Officer and the City Department of Public Works Representative, Jon Liffring, Supervising Construction Inspector, (the "DPW Representative"), (916) 808-7124, and will be used to compare before and after project conditions at the project's end. Any damage to the City or County streets caused by Contractor's operations must be repaired at Contractor's cost and to City's or County's satisfaction.
The Contractor shall notify and submit truck routes for review to the Contracting Officer and the DPW Representative prior to starting work.
Furthermore, the Contractor shall provide the City Representative with a location for a wash out area to wash and clean Contractor's trucks, equipment and tires before they exit the construction area.
1.3.45 SCR-45 Storage Area - Riverside Canal Relocation and Reach B
Contractor shall erect chain link fencing a minimum of eight (8) feet tall around the perimeter of its storage area. The fencing shall post signage no smaller than 3' x 3' in size providing the Contractor's company name as well as a name and telephone number for Contractor who may be contacted by the public in general in the event that any issues arise out of the use of the Premises. All material remnants need to be removed from the storage site. Otherwise, a protective barrier shall be placed between the ground surface and stockpiled materials. Upon conclusion of the work, or prior to the time period that the use of the staging area shall cease, whichever occurs first, Contractor shall return the site to a condition equal to or better than the condition it was in at the time the of the Contractor's entry into the site.
1.3.46 SCR-46 Project Signage
The Contractor shall provide all signage for the project. Sign wording, sizes and other parameters shall be coordinated with the Contracting Officer and/or his/her representative.
1.3.47 SCR-47 Traffic Control Plan
In lieu of the traffic plan provided for Reach B as a part of these contract documents, the contractor may opt to submit an alternative Traffic Control Plan to USACE (SPK), Sacramento County Department of Transportation, and City of Sacramento Traffic Division for review and approval prior to commencing construction activities.
1.3.48 SCR-48 Garden Highway
The Contractor shall provide a Traffic Control Plan meeting the following requirements:
(1) Access to properties and/or driveways adjacent to Garden Highway within the project limit must be provided and maintained at all times during construction.
(2) Complete road closure must be approved by the Contracting Officer prior to implementing traffic control measures.
DOCUMENT 00 73 05 Page 18
(3) Short term duration of one-lane, flagger controlled, traffic operation is acceptable with approval from the Contracting Officer.
(4) Contractor shall provide and maintain access along Garden Highway to one of two ramps (STA 660+71 and 664+77) at all times during construction.
1.3.49 SCR-49 Mailbox Removal and Replacement on Garden Highway
Contractor shall remove existing mailboxes and structures, and construct new roadside mailboxes that service homes fronting on Garden Highway in accordance with the following:
1. Mailboxes to be removed and replaced with new mailboxes shall be as specified by the Government and includes the following mailbox numbers as shown on the plans:.
4171 Garden Highway 3973 Garden Highway 4161 Garden Highway 3963 Garden Highway 4160 Garden Highway 3959 Garden Highway 4153 Garden Highway 3957 Garden Highway 4145 Garden Highway 3955 Garden Highway 4141 Garden Highway 3949 Garden Highway 4140 Garden Highway 3947 Garden Highway 4120 Garden Highway 3941 Garden Highway 4111 Garden Highway 3853 Garden Highway 4101 Garden Highway 3843 Garden Highway 4075 Garden Highway 3831 Garden Highway 4061 Garden Highway 3815 Garden Highway 4027 Garden Highway 3800 Garden Highway 4007 Garden Highway 3791 Garden Highway 4001 Garden Highway 3777 Garden Highway 3997 Garden Highway 3771 Garden Highway 3981 Garden Highway 3721 Garden Highway 3651 Garden Highway 3101 Garden Highway 3575 Garden Highway 3099 Garden Highway 3563 Garden Highway 3077 Garden Highway 3551 Garden Highway 3071 Garden Highway 3540 Garden Highway 3067 Garden Highway 3505 Garden Highway 3061 Garden Highway 3445 Garden Highway 3045 Garden Highway 3333 Garden Highway 3039 Garden Highway 3201 Garden Highway 3031 Garden Highway 3197 Garden Highway 3025 Garden Highway 3131 Garden Highway 3017 Garden Highway 3121 Garden Highway 2945 Garden Highway 3111 Garden Highway 2931 Garden Highway 3107 Garden Highway
2. Contractor shall remove and dispose of in a legal manner the existing mailboxes at the properties listed above including all associated mailbox structures and foundations. At the request of the property owner, components of the existing mailboxes shall be salvaged by the Contractor and delivered to the owner. Contractor shall coordinate with the Contracting Officer prior to removal of any existing mailbox.
3. Contractor shall generally construct new roadside mailboxes on the waterside hinge of Garden Highway. The exact location of the new mailbox will be as directed by the Contracting Officer.
DOCUMENT 00 73 05 Page 19
4. Contractor shall meet the following requirements in construction and placement of the new roadside mailboxes:
a. All new mailboxes shall be constructed in accordance with Postal Service Regulation 39 CFR Part 111, "Standards Governing the Design of Curbside Mailboxes." Mailboxes must match the sample Heavy Duty Mailbox as provided by the Contracting Officer.
Contractor must request sample Heavy Duty Mailbox 30 days before scheduling removal of existing…