PAO Chiller System
Closed Pre-Solicitation Posted
Not the latest version. See the latest solicitation from .
- Solicitation number
- 14816
- Agency
-
Air Force Sustainment Center
Air Force Materiel Command, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 333415 Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment Manufacturing
- Place of performance
- Hill Air Force Base, Utah 84056, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of the Air Force Materiel Command Air Force Sustainment Center is seeking qualified suppliers to provide and install a PAO Chiller System at Hill Air Force Base in Utah. This procurement encompasses the construction of a dedicated, sound-attenuated mechanical room to house PAO chillers and pumps, along with the installation of an overflow basin and support infrastructure. Key contract requirements include constructing walls using 6-inch metal studs with drywall and R-21 insulation, achieving a Sound Transmission Class (STC) rating of 45 for noise attenuation, installing appropriate doors for equipment access and maintenance, and integrating the chiller support and containment systems with existing facility infrastructure. The government is actively conducting market research to determine capabilities and competitiveness, with the primary evaluation criteria focusing on contractor experience with PAO chiller systems, capabilities to meet technical specifications, and commitment to SAM registration and WAWF payment process familiarity. The pre-solicitation response deadline was September 25, 2025, and the formal solicitation is expected by the February 9, 2026 due date.
This procurement has not been designated as a set-aside, though the government is actively seeking small business involvement, including 8(a), Service-Disabled Veteran Owned, Hubzone, and Women-Owned small business concerns. No incumbent contractor or specific award value has been disclosed in the pre-solicitation notice. The opportunity is classified under NAICS code 333415 (Air-Conditioning and Warm Air Heating Equipment Manufacturing) with a small business size standard of 1,250 employees, and falls under PSC category 1660 (Aircraft Air Conditioning, Heating, and Pressurizing Equipment). The scope of work includes modifications to existing raised access flooring and grid ceiling systems, as well as aesthetic integration with the existing laboratory environment. Contractors must demonstrate familiarity with technical construction standards, containment systems, and facility infrastructure modifications to successfully compete for this contract.
Notice text
2 versions
Update #2 · Latest ·
PAO Chiller System. Please see Sources Saught doc and Equipment List attached.
Follow up from initial RFI request (PAO Chiller System (Notice ID: 14816), provide capabilities for the following? The full SOW is also attached for reference.
- Provide and install all material to construct overflow basin for PAO chillers and pumps.
- Mechanical Room to House PAO Chillers
- 5.3.1 The Contractor shall construct a dedicated, sound-attenuated room at the designated
location to house the PAO chillers. The room shall meet the following specifications:
-
- 5.3.2 Walls: Construct walls using 6-inch, 16-gauge metal studs with 5/8-inch drywall on both
sides. Install R-21 insulation within the framing. Extend walls from the true floor to the
underside of the metal deck above, effectively creating a full-height barrier.
-
- 5.3.3 Sound Attenuation: The complete room assembly (walls and doors) must achieve a Sound
Transmission Class (STC) rating of 45.
-
- 5.3.4 Doors: Install doors with a minimum STC rating of 45. Provide at least one door of sufficient
size to facilitate the passage of the PAO chillers during installation and maintenance.
-
- 5.3.5 Finishes: Paint the walls to match the existing laboratory aesthetic.
- 5.3.6 Floor and Ceiling Integration: The Contractor shall modify the existing raised access floor and
grid ceiling as necessary to accommodate the new wall placement and chiller skid, ensuring a
seamless and integrated appearance. This modification shall not be done until the
mechanical room is in place and the Chiller skids arrive.
- Chiller Support and Containment
- 5.4.1 The chiller room shall house the support and isolation stand(s) for the PAO chillers.
- 5.4.2 Each stand shall include a containment pan to meet the contract requirements, unless the
chiller units have integrated containment features.
-
- 5.4.3 The new mechanical room layout must accommodate the Pall Filter unit.
- 5.4.4 The height of the support stands shall match the existing raised access floor height.
- 5.4.5 In-fill the area around the stands with raised access floor panels to maintain a consistent
floor surface.
- Paint/Finish
- 5.6.1 Any damage to paint must be repaired using 1 coat primer and 2 coats paint and shall match
existing paint.
- Plumbing
- 5.8.1 Contractor shall direct the overflow drain line to an overflow drain catch. This overflow drain
catch must be separate from the spill catch system.
-
- 5.8.2 If the allocated space is not sufficiently sized for the PAO chiller system, the Contractor shall
propose an alternate solution before contract is awarded.
Update #1 ·
PAO Chiller System. Please see Sources Saught doc and Equipment List attached.
Files
| File | Type | Posted |
|---|---|---|
| Sources Sought.docx | DOCX document | |
| Draft Equipment List.docx | DOCX document |
Notice history
| Notice | Type | Posted |
|---|---|---|
| 14816 Polyalphaolefin (PAO) Chiller Skid System | Solicitation | |
| 14816 PAO Chiller System Combined Synopsis/Solicitation | Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Chiller | Aviation | No set-aside | |
| Troubleshoot & Repair of Portable Chillers Service Requirement | Air Education and Training Command | Total Small Business | |
| Chiller assy, aircra | Aviation | No set-aside | |
| Chiller | Land and Maritime | No set-aside | |
| SABER V Hill AFB | Air Force Sustainment Center | Competitive 8(a) |