About this opportunity

This solicitation seeks cooling tower maintenance and repair services for the National Institute of Standards and Technology Center for Neutron Research in Gaithersburg, Maryland. Services include inspecting, cleaning, performing routine maintenance, and completing any necessary repairs on two sets of cooling towers and associated deicing, fire protection, and plume abatement systems over a five-year period. Proposals are due by September 15, 2020 and the contract will be awarded on a firm-fixed price basis to the offeror that provides the best overall value.

The requirement has been set aside for total small businesses. The primary NAICS code is 238210 and PSC code R499, with an estimated period of performance from the date of award through five base years and a potential for an additional six months. The place of performance is the NIST campus located at 20899 Gaithersburg, Maryland. Services are to maintain the infrastructure that cools the secondary water for the facility's heavy water-moderated nuclear research reactor licensed by the Nuclear Regulatory Commission.

Notice text

3 versions

Update #3 · Latest ·

Amendment 2

The purpose of this amendment is to extend the due date for quotations from 10 September by 3:00 PM EDT to 15 September at 3:00 PM EDT.

Amendment 1

The purpose of this amendment is to provide responses to Request for Information (RFI) questions and include attachments as a result of the responses to the RFI.

The NIST Center for Neutron Research (NCNR) owns and operates a heavy water-moderated nuclear test reactor and associated neutron beam research facility. The NCNR’s reactor is licensed with the Nuclear Regulatory Commission (NRC) under the name National Bureau of Standards Reactor (NBSR). The Reactor's secondary cooling water is cooled by a set of cooling towers. The cooling towers are located behind the NCNR (Building 235). The main cooling tower was built in 2002 by Balcke-Dürr. It's constructed on a concrete basin with pressure treated wood and fiberglass siding. Exterior wood surfaces consist of a stairway, railings and plywood decking. It has 3 cooling cells (#1, #2 and #3). The secondary cooling tower is a modular design. It was erected in 2011, is supported on steel pilons and is made of stainless steel. It is a BAC model 3781C tower. It has 2 cooling cells (#4 and #5).

The overall condition of the cooling towers is good. The cooling towers are in need of routine maintenance, repairs, and cleaning. In addition, the right-angle gear drives made by Amarillo in tower cells 1-4 are aged and in need of special attention. The right-angle gear drive for cell #5 was replaced in December 2019. This is to include maintenance, cleaning and repairs.

The objective of this requirement is to inspect, clean, perform routine maintenance, and complete required repairs on both sets of cooling towers. This contract also includes several subsystems that work in tandem with the main cooling tower structures. These systems include a deicing system, a fire protection system and a plume abatement system.

Update #2 ·

Amendment 1

The purpose of this amendment is to provide responses to Request for Information (RFI) questions and include attachments as a result of the responses to the RFI.

The NIST Center for Neutron Research (NCNR) owns and operates a heavy water-moderated nuclear test reactor and associated neutron beam research facility. The NCNR’s reactor is licensed with the Nuclear Regulatory Commission (NRC) under the name National Bureau of Standards Reactor (NBSR). The Reactor's secondary cooling water is cooled by a set of cooling towers. The cooling towers are located behind the NCNR (Building 235). The main cooling tower was built in 2002 by Balcke-Dürr. It's constructed on a concrete basin with pressure treated wood and fiberglass siding. Exterior wood surfaces consist of a stairway, railings and plywood decking. It has 3 cooling cells (#1, #2 and #3). The secondary cooling tower is a modular design. It was erected in 2011, is supported on steel pilons and is made of stainless steel. It is a BAC model 3781C tower. It has 2 cooling cells (#4 and #5).

The overall condition of the cooling towers is good. The cooling towers are in need of routine maintenance, repairs, and cleaning. In addition, the right-angle gear drives made by Amarillo in tower cells 1-4 are aged and in need of special attention. The right-angle gear drive for cell #5 was replaced in December 2019. This is to include maintenance, cleaning and repairs.

The objective of this requirement is to inspect, clean, perform routine maintenance, and complete required repairs on both sets of cooling towers. This contract also includes several subsystems that work in tandem with the main cooling tower structures. These systems include a deicing system, a fire protection system and a plume abatement system.

Update #1 ·

The NIST Center for Neutron Research (NCNR) owns and operates a heavy water-moderated nuclear test reactor and associated neutron beam research facility. The NCNR’s reactor is licensed with the Nuclear Regulatory Commission (NRC) under the name National Bureau of Standards Reactor (NBSR). The Reactor's secondary cooling water is cooled by a set of cooling towers. The cooling towers are located behind the NCNR (Building 235). The main cooling tower was built in 2002 by Balcke-Dürr. It's constructed on a concrete basin with pressure treated wood and fiberglass siding. Exterior wood surfaces consist of a stairway, railings and plywood decking. It has 3 cooling cells (#1, #2 and #3). The secondary cooling tower is a modular design. It was erected in 2011, is supported on steel pilons and is made of stainless steel. It is a BAC model 3781C tower. It has 2 cooling cells (#4 and #5).

The overall condition of the cooling towers is good. The cooling towers are in need of routine maintenance, repairs, and cleaning. In addition, the right-angle gear drives made by Amarillo in tower cells 1-4 are aged and in need of special attention. The right-angle gear drive for cell #5 was replaced in December 2019. This is to include maintenance, cleaning and repairs.

The objective of this requirement is to inspect, clean, perform routine maintenance, and complete required repairs on both sets of cooling towers. This contract also includes several subsystems that work in tandem with the main cooling tower structures. These systems include a deicing system, a fire protection system and a plume abatement system.

Files

Show all 17

Notice history

Notice Type Posted
NIST Center for Neutron Research Cooling Tower Maintenance and Repair Services Award Award Notice
This notice Latest solicitation Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Cooling Tower, Roofing, and Structural Construction District of Columbia 20024, United States · NAICS 236220 Bureau of Engraving and Printing Total Small Business
Turbine, cooling, in repair/modification of NAICS 336413 Naval Supply Systems Command No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors