Nez Perce Clearwater NF - Fenn Ranger Station Water and Wastewater Systems Replacement

Award Notice Posted

Solicitation number
AG-02RC-S-13-0042
Agency
Awarded
to Curt J Pieratt
Set-aside
HUBZone

Opportunity facts

Contract number
AG-02RC-C-13-0030 Federal contract award
PSC
Not on record
Place of performance
Fenn Ranger Station 831 Selway Road Kooskia, Idaho 83539, United States

Notice details come from SAM.gov. Updated .

Notice text

5 versions

Update #5 · Latest ·

Contract Award made on 6/20/13.

Update #4 ·


This project is one of the implementation projects of the Collaborative Forest Landscape Restoration Project (CFLRP). The goal of the CFLRP project is to utilize collaborative, science based ecosystem restoration techniques to improve watershed function while encouraging ecological, economic and social sustainability with an emphasis on providing local employment opportunities.

The intent of this contract is to replace the water and wastewater systems at the Fenn Ranger Station. Contractor shall furnish all labor, materials, equipment, supervision, structures and transportation necessary to complete the construction of the water and wastewater improvements in accordance with the drawings and specifications. The major items include the installation of a sewer system that includes: installation of 4 drain fields (2330 lf); 7 septic tanks (ranging in size from 3000-1500 gal); 1,842 linear feet of 6 inch diameter gravity PVC pipe; 1,923 linear feet of 4 inch diameter gravity PVC pipe; 974 linear feet of 2 ½ inch diameter force main PVC and HDPE (200 psi) pipe; 371 linear feet of 2 inch diameter force main PVC (200 psi) pipe; 1 lift station, 4 dosing stations and manholes; 29 sewer service connections, installation of a 6000 gallon RV holding tank; and other miscellaneous fencing and asphalt patching associated with the sewer system replacement and electrical systems needed for the new sewer system. There will also be some rough carpentry, electrical trailer hook ups, and trailer hook ups as well as electrical work associated with the sewer system.

Other items include the repair and replacement of water system components including: installation of 3,420 linear feet of 4 inch diameter HDPE pipe; 188 linear feet of 3 inch diameter HDPE pipe; 1470 linear feet of 2 inch diameter HDPE pipe; 2,655 linear feet of 1 inch diameter HDPE pipe; 12 water gate valves; 34 water service connections; reservoir cleaning; coating and replacement of reservoir access lids; and various asphalt patching and other repairs of disturbed areas associated with the water system part of the project.


The project is located at the Fenn Ranger Station/Cedar Flats Work Center; address: 831 Selway Road, Kooskia, ID on the Moose Creek Ranger District of the Nez Perce Clearwater National Forests. To reach the site from Orofino, ID, travel 57 miles east to Lowell, ID, turn right on to the Selway Raod #223, travel 4.7 miles to Fenn Ranger Station. 

The performance period for this project is approximately July 1, 2013 through July 15, 2014; however, the majority of the base bid must be completed prior to October 15, 2013.   The estimated price range for the project if the base item and all additive alternate items were awarded is between $500,000 -$1,000,000. All of the wastewater system and the majority of the water system is included in the base item. A small portion of work to replace/reconstruct the water system that serves on-site Government housing and the Cedar Flats Maintenance Shop and tree cooler is included as additive alternate items.


This acquisition has been set-aside for HUBZone Concerns. Offerors must be certified HUBZone Concerns with the U.S. Small Business Administration. For information regarding the on-line application process, go to the following website at https://eweb1sp.sba.gov/hubzone/internet/index.cfm. This process can take 90 days or more to complete.

Solicitation was issued May 1, 2013.  Organized pre-bid tour was held May 10, 2013.  An Attendance List was posted to FBO 5/13/13 and Site Tour Notes were posted on 5/17/13.  A summary of Contractor questions and Government answers was posted on 5/21/13 along with Solicitation Amendment 1 (4 total pages).  A second set of Contractor questions and government answers was posted on 5/24/13.  The solicitation was amended a second time on 5/29/13 to correct the quantity and unit of measure for item 321216.1(B).  B-1 Schedule of Items: Base Items was replaced in its entirety.  Offers must be accompanied by original bid bonds and offers must acknowledge both amendments as directed on the SF-30 Amendment Form.  Response deadline was extended to Tuesday 6/4/13 at 4:00 PM local time.

Update #3 ·


This project is one of the implementation projects of the Collaborative Forest Landscape Restoration Project (CFLRP). The goal of the CFLRP project is to utilize collaborative, science based ecosystem restoration techniques to improve watershed function while encouraging ecological, economic and social sustainability with an emphasis on providing local employment opportunities.

The intent of this contract is to replace the water and wastewater systems at the Fenn Ranger Station. Contractor shall furnish all labor, materials, equipment, supervision, structures and transportation necessary to complete the construction of the water and wastewater improvements in accordance with the drawings and specifications. The major items include the installation of a sewer system that includes: installation of 4 drain fields (2330 lf); 7 septic tanks (ranging in size from 3000-1500 gal); 1,842 linear feet of 6 inch diameter gravity PVC pipe; 1,923 linear feet of 4 inch diameter gravity PVC pipe; 974 linear feet of 2 ½ inch diameter force main PVC and HDPE (200 psi) pipe; 371 linear feet of 2 inch diameter force main PVC (200 psi) pipe; 1 lift station, 4 dosing stations and manholes; 29 sewer service connections, installation of a 6000 gallon RV holding tank; and other miscellaneous fencing and asphalt patching associated with the sewer system replacement and electrical systems needed for the new sewer system. There will also be some rough carpentry, electrical trailer hook ups, and trailer hook ups as well as electrical work associated with the sewer system.

Other items include the repair and replacement of water system components including: installation of 3,420 linear feet of 4 inch diameter HDPE pipe; 188 linear feet of 3 inch diameter HDPE pipe; 1470 linear feet of 2 inch diameter HDPE pipe; 2,655 linear feet of 1 inch diameter HDPE pipe; 12 water gate valves; 34 water service connections; reservoir cleaning; coating and replacement of reservoir access lids; and various asphalt patching and other repairs of disturbed areas associated with the water system part of the project.


The project is located at the Fenn Ranger Station/Cedar Flats Work Center; address: 831 Selway Road, Kooskia, ID on the Moose Creek Ranger District of the Nez Perce Clearwater National Forests. To reach the site from Orofino, ID, travel 57 miles east to Lowell, ID, turn right on to the Selway Raod #223, travel 4.7 miles to Fenn Ranger Station. 

The performance period for this project is approximately July 1, 2013 through July 15, 2014; however, the majority of the base bid must be completed prior to October 15, 2013.   The estimated price range for the project if the base item and all additive alternate items were awarded is between $500,000 -$1,000,000. All of the wastewater system and the majority of the water system is included in the base item. A small portion of work to replace/reconstruct the water system that serves on-site Government housing and the Cedar Flats Maintenance Shop and tree cooler is included as additive alternate items.


This acquisition has been set-aside for HUBZone Concerns. Offerors must be certified HUBZone Concerns with the U.S. Small Business Administration. For information regarding the on-line application process, go to the following website at https://eweb1sp.sba.gov/hubzone/internet/index.cfm. This process can take 90 days or more to complete.

Solicitation was issued May 1, 2013.  Organized pre-bid tour was held May 10, 2013.  An Attendance List was posted to FBO 5/13/13 and Site Tour Notes were posted on 5/17/13.  A summary of Contractor questions and Government answers was posted on 5/21/13 along with Solicitation Amendment 1 (4 total pages).  Offers must be accompanied by original bid bonds and offers must acknowledge this amendment as directed on the SF-30 Amendment Form.  Response deadline was not extended.

Update #2 ·


This project is one of the implementation projects of the Collaborative Forest Landscape Restoration Project (CFLRP). The goal of the CFLRP project is to utilize collaborative, science based ecosystem restoration techniques to improve watershed function while encouraging ecological, economic and social sustainability with an emphasis on providing local employment opportunities.

The intent of this contract is to replace the water and wastewater systems at the Fenn Ranger Station. Contractor shall furnish all labor, materials, equipment, supervision, structures and transportation necessary to complete the construction of the water and wastewater improvements in accordance with the drawings and specifications. The major items include the installation of a sewer system that includes: installation of 4 drain fields (2330 lf); 7 septic tanks (ranging in size from 3000-1500 gal); 1,842 linear feet of 6 inch diameter gravity PVC pipe; 1,923 linear feet of 4 inch diameter gravity PVC pipe; 974 linear feet of 2 ½ inch diameter force main PVC and HDPE (200 psi) pipe; 371 linear feet of 2 inch diameter force main PVC (200 psi) pipe; 1 lift station, 4 dosing stations and manholes; 29 sewer service connections, installation of a 6000 gallon RV holding tank; and other miscellaneous fencing and asphalt patching associated with the sewer system replacement and electrical systems needed for the new sewer system. There will also be some rough carpentry, electrical trailer hook ups, and trailer hook ups as well as electrical work associated with the sewer system.

Other items include the repair and replacement of water system components including: installation of 3,420 linear feet of 4 inch diameter HDPE pipe; 188 linear feet of 3 inch diameter HDPE pipe; 1470 linear feet of 2 inch diameter HDPE pipe; 2,655 linear feet of 1 inch diameter HDPE pipe; 12 water gate valves; 34 water service connections; reservoir cleaning; coating and replacement of reservoir access lids; and various asphalt patching and other repairs of disturbed areas associated with the water system part of the project.


The project is located at the Fenn Ranger Station/Cedar Flats Work Center; address: 831 Selway Road, Kooskia, ID on the Moose Creek Ranger District of the Nez Perce Clearwater National Forests. To reach the site from Orofino, ID, travel 57 miles east to Lowell, ID, turn right on to the Selway Raod #223, travel 4.7 miles to Fenn Ranger Station. 

The performance period for this project is approximately July 1, 2013 through July 15, 2014; however, the majority of the base bid must be completed prior to October 15, 2013.   The estimated price range for the project if the base item and all additive alternate items were awarded is between $500,000 -$1,000,000. All of the wastewater system and the majority of the water system is included in the base item. A small portion of work to replace/reconstruct the water system that serves on-site Government housing and the Cedar Flats Maintenance Shop and tree cooler is included as additive alternate items.


This acquisition has been set-aside for HUBZone Concerns. Offerors must be certified HUBZone Concerns with the U.S. Small Business Administration. For information regarding the on-line application process, go to the following website at https://eweb1sp.sba.gov/hubzone/internet/index.cfm. This process can take 90 days or more to complete.

Solicitation was issued May 1, 2013.  Organized pre-bid tour has been scheduled for May 10, 2013, see Section L of solicitation for details.  Offers must be accompanied by original bid bonds.

Update #1 ·

The intent of this contract is to replace the water and wastewater systems at the Fenn Ranger Station. Contractor shall furnish all labor, materials, equipment, supervision, structures and transportation necessary to complete the construction of the water and wastewater improvements in accordance with the drawings and specifications. The major items include the installation of a sewer system that includes: installation of 4 drain fields (2330 lf); 7 septic tanks (ranging in size from 3000-1500 gal); 1,842 linear feet of 6 inch diameter gravity PVC pipe; 1,923 linear feet of 4 inch diameter gravity PVC pipe; 974 linear feet of 2 ½ inch diameter force main PVC and HDPE (200 psi) pipe; 371 linear feet of 2 inch diameter force main PVC (200 psi) pipe; 1 lift station, 4 dosing stations and manholes; 29 sewer service connections, installation of a 6000 gallon RV holding tank; and other miscellaneous fencing and asphalt patching associated with the sewer system replacement and electrical systems needed for the new sewer system. There will also be some rough carpentry, electrical trailer hook ups, and trailer hook ups as well as electrical work associated with the sewer system.

Other items include the repair and replacement of water system components including: installation of 3,420 linear feet of 4 inch diameter HDPE pipe; 188 linear feet of 3 inch diameter HDPE pipe; 1470 linear feet of 2 inch diameter HDPE pipe; 2,655 linear feet of 1 inch diameter HDPE pipe; 12 water gate valves; 34 water service connections; reservoir cleaning; coating and replacement of reservoir access lids; and various asphalt patching and other repairs of disturbed areas associated with the water system part of the project.


The project is located at the Fenn Ranger Station/Cedar Flats Work Center; address: 831 Selway Road, Kooskia, ID on the Moose Creek Ranger District of the Nez Perce Clearwater National Forests. To reach the site from Orofino, ID, travel 57 miles east to Lowell, ID, turn right on to the Selway Raod #223, travel 4.7 miles to Fenn Ranger Station. A formal pre-bid tour shall be scheduled; date and time will be provided in the solicitation.


It is anticipated that the solicitation shall be issued approximately May 1, 2013. The performance period for this project is approximately July 1, 2013 through November 1, 2013. The estimated price range for the project if the base item and all optional items were awarded is between $500,000 -$1,000,000. All of the wastewater system and the majority of the water system shall be included in the base item. A small portion of work to replace/reconstruct the water system that serves on-site Government housing and the Cedar Flats Maintenance Shop and tree cooler shall be included as optional items.


This acquisition has been set-aside for HUBZone Concerns. Offerors must be certified HUBZone Concerns with the U.S. Small Business Administration. For information regarding the on-line application process, go to the following website at https://eweb1sp.sba.gov/hubzone/internet/index.cfm. This process can take 90 days or more to complete.

Files

File Type Posted
Amendment2Pgs2_3.docx DOCX document
Amendment2page1.doc DOC document
QuestionsAnswers2.docx DOCX document
Amendment1page1.doc DOC document
Amendment1Pgs2_3.docx DOCX document
FinalQuestionsAnswers.docx DOCX document
Amend1Pg4OxidationDitchTypical.pdf PDF
SiteTourNotes.docx DOCX document
AttendanceList.docx DOCX document
FennFinalRFP.doc DOC document
Fenn_Civil__Part4.pdf PDF
Fenn_Civil__Part1.pdf PDF
Fenn_Civil__Part2.pdf PDF
ELECTRIC_DRAWINGS.pdf PDF
FENNSpecialProjectSpecifications.pdf PDF
Fenn_Civil__Part3.pdf PDF
Show all 16

Notice history

Notice Type Posted
This notice Latest Award Notice
Fenn Ranger Station Water and Wastewater Systems Replacement Original Award Notice

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors