FennFinalRFP.doc

DOC document 591 KB Posted

Attached to
Nez Perce Clearwater NF - Fenn Ranger Station Water and Wastewater Systems Replacement
Solicitation number
AG-02RC-S-13-0042
Issued by

About this file

Solicitation Packet

View the file

Other files

File Type Posted
Amendment2Pgs2_3.docx DOCX document
Amendment2page1.doc DOC document
QuestionsAnswers2.docx DOCX document
Amendment1page1.doc DOC document
Amendment1Pgs2_3.docx DOCX document
FinalQuestionsAnswers.docx DOCX document
Amend1Pg4OxidationDitchTypical.pdf PDF
SiteTourNotes.docx DOCX document
AttendanceList.docx DOCX document
Fenn_Civil__Part3.pdf PDF
Fenn_Civil__Part1.pdf PDF
Fenn_Civil__Part2.pdf PDF
ELECTRIC_DRAWINGS.pdf PDF
Fenn_Civil__Part4.pdf PDF
FENNSpecialProjectSpecifications.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

RFP AG-02RC-S-13-0042

2. TYPE OF SOLICITATION

FORMCHECKBOX

SEALED BID (IFB)

FORMCHECKBOX

NEGOTIATED (RFP)

3. DATE ISSUED

5/1/2013

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

6. PROJECT NO.

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

USDA, Forest Service

Idaho Montana Acquisition Team

Nez Perce Clearwater National Forests

104 Airport Road

Grangeville, ID 83530 USDA, Forest Service

Idaho Montana Acquisition Team

Nez Perce Clearwater National Forests

104 Airport Road

Grangeville, ID 83530

9. FOR INFORMATION

CALL:

a. NAME

KAREN RUKLIC

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(208) 983-5144; kruklic@fs.fed.us

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

Fenn Ranger Station Water and Wastewater Systems Replacement Moose Creek Ranger District; Nez Perce Clearwater National Forest

Idaho County, Idaho

FAXED OFFERS ARE NOT ACCEPTABLE. ORIGINAL BID BONDS ARE REQUIRED. OFFERS MUST BE MAILED OR HAND-CARRIED AND RECEIVED BY MAY 30, 2013 AT 4:00 PM LOCAL TIME.

PRICE RANGE AND FUNDS AVAILABILITY: The Government’s estimate is between $500,000 - $1,000,000 for the base item and all additive alternate items. Funds are not presently available for this contract. The Government’s obligation under this contract is contingent upon receipt of appropriated funds prior to contract award. See FAR 52.232-18 Availability of Funds in Section I.

IMPORTANT: This acquisition has been set-aside for HUBZone Concerns (see FAR 52.219-3, Notice of Total HUBZone Set-Aside, Section I). Offerors must certified HUBZone Concerns with the Small Business Administration. For information regarding the on-line application process, go to the following website at https://eweb1.sba.gov/hubzone/internet/. This process can take 90 days or more to complete.

11. The Contractor shall begin performance within 10 days of receipt of the notice to proceed, and complete project in accordance with deadlines stated in FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) Alternate I. This performance period is FORMCHECKBOX mandatory, FORMCHECKBOX negotiable. (See Section F, Deliveries and Performance.)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12b.)

FORMCHECKBOX

YES

FORMCHECKBOX

NO

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a.

Sealed offers in original and 2 copies of technical proposals (see Section L) to perform the work required are due at the place specified in Item 8 by 4:00 pm local time May 30, 2013. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

b.

An offer guarantee

FORMCHECKBOX

is, FORMCHECKBOX is not required. (See FAR 52.228-1 Bid Guarantee, Section I) c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than 90 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212

1442-101

STANDARD FORM 1442 (REV. 4-85)

Computer Generated

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

Duns No. ______________________________________

TIN: ___________________________________________

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE

FACILITY CODE

17.

The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

PLEASE COMPLETE THIS BLOCK

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.
DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

FORMCHECKBOX

10 U.S.C. 2304(c)( )

FORMCHECKBOX

41 U.S.C. 253(c)( )

26. ADMINISTERED BY

CODE

27. PAYMENT WILL BE MADE BY

USDA – Forest Service

Idaho Montana Acquisition Team

Nez Perce Clearwater National Forests 104 Airport Road

Grangeville, ID 83530

Submit invoice to CO for the work performed. Invoice will be reviewed by the COR and approved or rejected by the CO within 7 days of receipt of the invoice. Rejected invoices must be corrected and resubmitted. CO will submit approved invoices to:

USDA, OCFO, COD, APB

PO Box 60075

New Orleans, LA 70160

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

FORMCHECKBOX

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

FORMCHECKBOX

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

KAREN RUKLIC

30b. SIGNATURE

30c. DATE

31b. UNITED STATES OF AMERICA

BY

31c. DATE

Computer Generated

STANDARD FORM 1442 BACK (REV. 4-85)

TABLE OF CONTENTS

Page(s)

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

1 - 2

SECTION B - SUPPLIES OR SERVICES AND PRICES

7 - 11

B- 1 - Schedule of Items

B- 2 – Schedule of Items; Additive Alternate Items #1-#5

B- 3 – Price Proposal Instructions

B- 4 – Bond Premiums

B- 5 – Award of Additive Alternate Items

B- 6 –Set-aside notice

B- 7 – Idaho Use Tax

SECTION C - DESCRIPTION/SPECIFICATIONS

12 - 15

C- 1 - Scope of Contract

C- 2 - Project Location

C- 3 - Price Range

C- 4 - Government-Furnished Property

C- 5 – Start Work

C- 6 – Period of Performance

C- 5 - Standard Specifications

C- 7 - Special Project Specifications

C- 8 - Drawings

SECTION E - INSPECTION AND ACCEPTANCE

E- 1 - Clauses Incorporated by Reference

SECTION F - DELIVERIES OR PERFORMANCE

F- 1 - Clauses Incorporated by Reference

F- 2 - Commencement, Prosecution, and Completion of Work Alt I

SECTION G – CONTRACT ADMINISTRATION

G- 1 – Post Award Conference

G- 2 – Contracting Officer’s Representative

G- 3 – Government-Furnished Property

SECTION H - SPECIAL CONTRACT REQUIREMENTS

19 - 25

H- 1 - Clauses Incorporated by Reference

H- 2- Utility Services

H- 3 - Physical Data

H- 4 - Key Personnel

H- 5 – Work Camps, Staging and Storage Areas

H- 6 – Fire Control

H- 7 – Local Material Sources

H- 8 - Loss, Damage, or Destruction

H- 9 - Incidental Payment Items

H- 10 - Conformity with Drawings and Specifications

H- 11 - Samples, Tests, Cited Specifications

H-12 - Barricades, Warning Signs, and Other Devices

H-13 - Landscape Preservation

H-14 - Contractor Performance Assessment Reporting System

H-15 - Contractor Workforce Certification

H-16 - State of Idaho’s Notice to Offeror

PART II - CONTRACT CLAUSES

SECTION I - CONTRACT CLAUSES

26 - 42

I- 1 - Clauses Incorporated by Reference

I- 2 - Reporting Executive Compensation and First-Tier Subcontract Awards

I- 3 - Central Contractor Registration Maintenance

I- 4 - Updates of Publicly Available Information Regarding Responsibility Matters

I- 5 - Assurance Regarding Felony Conviction or Tax Delinquent Status for Corporate

Applicants Alternate I

I- 6 - Option for Increased Quantity—Separately Priced Line Item

I- 7 - Post Award Small Business Program Representation

I-8 - Buy American Act - Construction Materials

I-9 - Bid Guarantee

I-10 - Performance and Payment Bonds - Construction

I-11 - Alternative Forms of Security

I-12 - Insurance Coverage Alternate I

I-13- Availability of Funds

I-14 – Archaeological or Historical Sites

I-15 - Providing Accelerated Payment to Small Business Subcontractors

I-16 - Permits and Responsibilities

I-17 - Alterations In Contract

I-18 - Authorized Deviations in Clauses

I-19 - Order of Precedence - Construction

PART III - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

43 - 54

J- 1 – General Wage Decisions

J- 2 – Special ProjectSpecifications

J- 3 – Drawings

J- 4 – State of Idaho Certificate of Verification of Workers’ Compensation Insurance

PART IV - REPRESENTATIONS AND INSTRUCTIONS

SECTION K - REPRESENTATIONS, CERTIFICATIONS, AND OTHER

55 - 61

STATEMENTS OF OFFERORS AND RESPONDENTS

K- 1 - Annual Representations and Certifications

K- 2 - Information Regarding Responsibility Matters

K- 3 - Representation by Corporations Regarding an Unpaid Delinquent Tax Liability or a Felony Conviction Alternate I

SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

62 - 67

AND RESPONDENTS

L- 1 - Solicitation Provisions Incorporated by Reference

L- 2 - Central Contractor Registration

L- 3 - Inquiries

L- 4 - Instructions for the Preparation of Technical and Business Proposals

L- 5 - Amendments to Proposals

L- 6 - Type of Contract

L- 7 - Davis-Bacon Act—Secondary Site of the Work

L- 8 - Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity

For Construction

L- 9 - Notice of Buy American Act Requirements - Construction Materials

L-10 - Service of Protest

L-11 - Site Visit (Construction) Alternate I

L-12 - Preparation of Proposals – Construction

L-13 - Authorized Deviations in Provisions

SECTION M - EVALUATION FACTORS FOR AWARD

68 - 71

M- 1 - Evaluation Criteria

M- 2 - Award Statement

M- 3 - Evaluation of Options Exercised at Time of Contract Award

PAGE LEFT BLANK

PART I - THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICES

Fenn Ranger Station – Water & Wastewater Systems Replacement Nez Perce Clearwater National Forest Moose Creek Ranger District Idaho County, Idaho

B- 1 Schedule of Items: Base Items

ITEM NO.
DESCRIPTION
METHOD *

OF

MEASURE

UNIT
ESTIMATED

QUANTITY

UNIT

PRICE

TOTAL

GENERAL ITEMS

013216.14(A)
Mobilization/ Demobilization
LSQ
LS
1
$
$
022101.0(A)
Construction Surveying and Staking
LSQ
LS
1
$
$
023219.0(A)
Exploratory Excavation
AQ
HRS
40
$
$
312500.1(A)
Soil Erosion and Pollution Control
LSQ
LS
1
$
$
133423.13
Trailer House Relocation
LSQ
LS
1
$
$

DEMOLITION ITEMS

311100.1(A,B)
North Homes Area
LSQ
LS
1
$
$
311100.2(A,B)
Ranger Station Area
LSQ
LS
1
$
$
311100.3(A,B)
Mobile Homes Area
LSQ
LS
1
$
$
311100.4(A,B)
Cedar Flats Area
LSQ
LS
1
$
$
311100.5
Wastewater Treatment Facility
LSQ
LS
1
$
$

WASTEWATER IMPROVEMENTS

333101.1
6" PVC Gravity Sewer Main
AQ
LF
1842
$
$
333101.2
4" PVC Gravity Service
AQ
LF
1929
$
$
333101.3
Mainline Manholes
DQ
EA
2
$
$
333101.4
Connection to Buildings (with cleanouts)
DQ
EA
17
$
$
333101.5
Connections to RV Pad’s
DQ
EA
11
$
$
333219.0
Dosing Manhole Vault & Lift Station Vault
LSQ
LS
5
$
$
333220.0
Dosing MH & Lift Station Vault – Electrical & Pumps
LSQ
LS
5
$
$
ITEM NO.
DESCRIPTION
METHOD OF MEASURE
UNIT
ESTIMATED QUANTITY
UNIT PRICE
TOTAL

WASTEWATER IMPROVEMENTS CONTINUED

333404.1
2 ½” Forcemain PVC Piping
AQ
LF
525
$
$
333404.2
2 ½” Forcemain HDPE Piping
AQ
LF
449
$
$
333404.3
2” Forcemain PVC Piping
AQ
LF
369
$
$
333405.1
Gravellless Drainfields
DQ
LF
2230
$
$
323010.0
Fencing
AQ
LF
320
$
$
321216.1 (A)
AC (Asphalt Concrete) Patching
DQ
SY
482
$
$
333610.4
Septic Tank (1500gal)
AQ
EA
2
$
$
333610.3
Septic Tank (2000 gal)
AQ
EA
2
$
$
333610.2
Septic Tank (2500 gal)
AQ
EA
2
$
$
333610.1
Septic Tank (3000 gal)
AQ
EA
1
$
$
333610.5
Sewer Holding tank (6,000 gal)
AQ
EA
1
$
$

WATER IMPROVEMENTS

312500.1(B)
Soil Erosion and Pollution Control
LSQ
LS
1
$
$
331116.1
4” HDPE Water Main Piping
AQ
LF
2400
$
$
331116.3(A)
2” HDPE Water Main Piping
AQ
LF
1170
$
$
331116.4(A)
1" HDPE Service Pipe with Curb Stops
AQ
LF
1569
$
$
331116.6(A)
Blow-Offs
DQ
EA
5
$
$
331116.7(A)
Connection to Buildings and Main Lines, & Well
DQ
EA
20
$
$
331116.8
Connections at RV Pads (including FFH)
DQ
EA
14
$
$
331116.5(A)
Valves
AQ
EA
6
$
$
331116.12(A)
Frost Free Hydrants
AQ
EA
8
$
$
321216.1(B)
AC=Asphalt Concrete Patching
DQ
LF
1373
$
$
035000.0
Cleaning and Coating Reservior
LSQ
LS
1
$
$
331116.9
Reservior Valve Replacement(2”,3”,6”&8”)
AQ
EA
5
$
$
331116.11
3" Reservior Diffuser Pipe & Float Reset
LSQ
LS
1
$
$
331116.10
Reservior Access Hatch Replacement
DQ
EA
2
$
$

TOTAL PRICE ALL BASE ITEMS $___________________

B- 2 Schedule of Items: Additive Alternate Items #1 - #5

ADDITIVE ALTERNATE ITEM #1: NORTH HOMES WATER IMPROVEMENTS

SUB-ITEM NO.
DESCRIPTION
METHOD OF MEASURE
UNIT
ESTIMATED QUANTITY
UNIT PRICE
TOTAL
311100.1(C)
Demolition
LSQ
LS
1
$
$
312500.1(C)
Soil Erosion and Pollution Control
LSQ
LS
1
$
$
331116.3(B)
2” HDPE Main Piping
AQ
LF
780
$
$
331116.4(B)
1” HDPE Service Pipe with Curb Stops
AQ
LF
45
$
$
331116.6(B)
Blow-Offs
DQ
EA
1
$
$
331116.7(B)
Connection to Buildings Main Lines & Well
DQ
EA
2
$
$
331116.5(B)
Valves
AQ
EA
2
$
$
331116.12(B)
Frost Free Hydrants
AQ
EA
1
$
$
321216.1(C)
AC Patching
DQ
SY
20
$
$
SUBTOTAL ADDITIVE ALTERNATE #1
$

ADDITIVE ALTERNATE ITEM #2: CEDAR FLATS WATER IMPROVEMENTS - SOUTH HOME

311100.4(C)
Demolition
LSQ
LS
1
$
$
312500.1(D)
Soil Erosion and Pollution Control
LSQ
LS
1
$
$
331116.3(C)
2” HDPE Main Piping
AQ
LF
303
$
$
331116.4(C)
1" HDPE Service Pipe with Curb Stops
AQ
LF
127
$
$
31116.7(C)
Connection to Existing Water Main
DQ
EA
1
$
$
331116.6(C)
Blow-Offs
DQ
EA
1
$
$
331116.7(C)
Connection to Buildings Main Lines & Well
DQ
EA
2
$
$
331116.9(B)
Remove 4” Valve
AQ
EA
1
$
$
SUBTOTAL ADDITIVE ALTERNATE ITEM #2
$

ADDITIVE ALTERNATE #3: CEDAR FLATS WATER IMPROVEMENTS – MAINTENANCE SHOP & TREE COOLER

311100.4(D)
Demolition
LSQ
LS
1
$
$
312500.1(E)
Soil Erosion and Pollution Control
LSQ
LS
1
$
$
331116.3(D)
2” HDPE Main Piping
AQ
LF
187
$
$

ADDITIVE ALTERNATE ITEM #3: CEDAR FLATS WATER IMPROVEMENTS – MAINTENANCE SHOP & TREE COOLER (CONTINUED)

SUB-ITEM NO.
DESCRIPTION
METHOD OF MEASURE
UNIT
ESTIMATED QUANTITY
UNIT PRICE
TOTAL
33116.4(D)
1" HDPE Service Pipe with Curb Stops
AQ
LF
23
$
$
331116.6(C)
Blow-Offs
DQ
EA
1
$
$
331116.7(D)
Connection to Buildings Main Lines & Well
DQ
EA
2
$
$
331116.5(D)
Valves
AQ
EA
1
$
$
331116.12(C)
Frost Free Hydrants
AQ
EA
1
$
$
SUBTOTAL ADDITIVE ALTERNATE ITEM #3
$

ADDITIVE ALTERNATE ITEM #4: CEDAR FLATS WATER IMPROVEMENTS – DORM TO WELL CONNECTION

311100.4(E)
Demolition
LSQ
LS
1
$
$
312500.1(F)
Soil Erosion and Pollution Control
LSQ
LS
1
$
$
331116.2
3” HDPE Main Line
DQ
LF
188
$
$
331116.3(E)
2” HDPE Main Line
DQ
LF
130
$
$
331116.7(E)
Connection to Buildings Main Lines & Well
DQ
EA
4
$
$
SUBTOTAL ADDITIVE ALTERNATE ITEM #4
$

ADDITIVE ALTERNATE ITEM #5: GENERAL ITEMS

013216.14(B)
Mobilization/

Demobilization

LSQ
LS
1
$
$
022101.0(B)
Construction Survey and Staking
LSQ
LS
1
$
$
023219.0(B)
Exploratory Excavation
AQ
HRS
40
$
$
SUBTOTAL ADDITIVE ALTERNATE ITEM #5
$
TOTAL PRICE ALL ADDITIVE ALTERNATE ITEMS
$
TOTAL OFFER VALUE FOR BASE AND ALL ADDITIVE ALTERNATE ITEMS
$

* Designated Method of Measurement:

DQ – Designed Quantities; AQ - Actual Quantities, LSQ - Lump Sum Quantities; SQ – Staked Quantities; CQ – Contract Quantities B-3 PRICE PROPOSAL INSTRUCTIONS: Unit prices and total item amounts must be submitted for all Base and Additive Alternate items and sub-items in order to be considered for award. Do not round the extended item amounts and provide prices to the nearest cent.

B- 4 AGAR 452.232-70 Reimbursement for Bond Premiums--Fixed-Price Con. Contracts (NOV 1996) The Contract Price includes the total amount for premiums that the Contractor attributes to the furnishing of performance and payment bonds required by the contract. Reimbursement for bond premiums under the clause at FAR 52.232-5, Payments Under Fixed-Price Construction Contract, shall not cover any amount therefore not included in the contract price.

B-5 AWARD OF ADDITIVE ALTERATE ITEMS: The Government reserves the right to award additive alternate items concurrent with award of the base items. Additive alternate items shall be awarded in the subgroupings identified by number. Award of the additive alternate items is not restricted to an all-or-nothing basis. If award is made of one or more of the Additive Alternate Items #1-4, Additive Alternate #5: General Items shall be awarded as well. Contractors shall price the General Items in such a manner that adequate payment is assured if all four of the additive alternate items are awarded. Award of two or more of the additive alternate items shall be contingent upon funding availability.

B-6 SET-ASIDE NOTICE: This acquisition has been set-aside for HUBZone Concerns (see FAR 52.219-3, Notice of Total HUBZone Set-Aside in Section I). Offerors must certified HUBZone Concerns with the U.S. Small Business Administration. For information regarding the on-line application process, go to the following website at https://eweb1.sba.gov/hubzone/internet/.

B-7 IDAHO USE TAX: Under clause 52.236-7, Permits and Responsibilities, Contractors shall be responsible for complying with any Federal, State, and municipal laws, codes and regulations applicable to the performance of the work. Questions regarding assessment of Idaho Use Tax on Government Furnished Property should be directed to the Idaho State Tax Commission at (208) 799-3491.

PART I - THE SCHEDULE

SECTION C - DESCRIPTION/SPECIFICATIONS

C- 1 Scope of Contract: This project is one of the implementation projects of the Collaborative Forest Landscape Restoration Project (CFLRP). The goal of the CFLRP project is to utilize collaborative, science based ecosystem restoration techniques to improve watershed function while encouraging ecological, economic and social sustainability with an emphasis on providing local employment opportunities.

Contractor shall furnish all labor, materials (except those designated as Government-furnished), equipment, supervision, structures and transportation necessary to complete the construction of the water and wastewater improvements in accordance with the drawings and specifications. The major items include the installation of a sewer system that includes: installation of 4 drain fields (2,230lf), 7 septic tanks (ranging in size from 3000-1500gal), 1,842 linear feet of 6 inch diameter gravity PVC pipe; 1,929 linear feet of 4 inch diameter gravity PVC pipe; 974 linear feet of 2½ inch dia. force main PVC and HDPE (200psi) pipe; 369 linear feet of 2 inch diameter force main PVC (200psi) pipe, 1 lift station, 4 dosing stations and manholes, 29 sewer service connections, installation of 6000 gallon RV holding tank, and other miscellaneous fencing and asphalt patching associated with the sewer system replacement. Work also includes all electrical systems needed for the new sewer system.

Other items include the repair and replacement of water system components including: installation of 3,420 linear feet of 4 inch diameter HDPE pipe, 188 linear feet of 3 inch diameter HDPE pipe, 1470 linear feet of 2 inch diameter HDPE pipe, 2,655 linear feet of 1 inch diameter HDPE pipe, 12 water gate valves, 34 water service connections, reservoir cleaning, coating & replacement of reservoir access lids, fencing, and various asphalt patching, and other repairs of disturbed areas associated with the water system part of the project. There will also be some rough carpentry and installation of electrical trailer hook ups and water and sewer trailer hook ups.

C- 2 Project Location : The project is located at the Fenn Ranger Station/Cedar Flats Work Center, at 831 Selway Road in Kooskia, Idaho on the Nez Perce-Clearwater National Forests. From Orofino travel 57 miles east to Lowell, ID, turn right on to the Selway Road #223, travel 4.7 miles to Fenn Ranger Station. A formal pre-bid tour is scheduled for May 10, 2013. (See FAR 52.236-27 Site Visit (Construction) Alternate I, in Section L for details.)

C- 3 Price Range: The Government Cost Estimate, per FAR 36.204, is between $500,000 and $1,000,000 for this project.

C- 4 Government-Furnished Property: ¾” Minus Crushed Gravel. (See Section G -1 and Section I, FAR 52.245-1 Government Property.)

C-5 Start Work: It is estimated that work will begin approximately July 15, 2012.

C-6 Period of Performance: See Part I, Section F, Clause 52.211-10 Alt I.

C- 7 Special Project Specifications: Special Project Specifications entitled “Water and Wastewater Systems Replacement – Fenn Ranger Station” are incorporated into this solicitation and any resultant contract. The contents are detailed below:

TABLE OF CONTENTS

DIVISION 00 – SPECIAL SECTION

000114 Measurement and Payment 1-3

DIVISION 01 – GENERAL REQUIREMENTS

011113 Work Covered by Contract 1-5

013216.14 Mobilization Payment Procedures 1-2

DIVISION 02 – EXISTING CONDITIONS

022101 Construction Surveying and Staking 1-2

023219 Exploratory Excavation 1-2

DIVISION 03 – CONCRETE

035000 Cementitious Crystalline Waterproof Coating 1-8

DIVISION 13 – SPECIAL CONSTRUCTION

133423.13 Portable and Mobile Buildings 1-1

DIVISION 26 – Electrical

262010 Basic Electrical Requirements 1-5

262028 Codes and Standards

262030 Tests and Demonstration of the Complete Electrical System

262060 Electrical System 1-19

262090 Catalog Sheets 1-13

DIVISION 31 – EARTHWORK

311100 Clearing and Grubbing and Removal of Obstructions 1-5

312316.16 Structure Excavation and Compaction for Minor Structures 1-2

312333 Trenching and Backfilling 1-5

312500 Permanent Erosion Control 1-2

DIVISION 32 – EXTERIOR IMPROVEMENTS

321123 Crushed Aggregates 1-5

321216 Asphalt Patching (Commercial Sources) 1-3

323010 Fencing

DIVISION 33 – UTILITIES

331116 Site Water Utility Distribution Piping 1-12

333101 Gravity Sewers and Appurtenances 1-8

333219 Sewer Lift Station & Dosing Manhole Vault Structure 1-3

333220 Lift Station & Dosing Manhole Effluent Pumping System 1-5

333404 Sewer Pressure Force Main 1-2

333405 Gravelless Drainfield 1-4

333610 Precast Concrete Septic Tanks & Holding Tanks 1-3

The Special Project Specifications are physically located in a separate attachment to the solicitation and are listed in Section J.

C- 8 Drawings: The drawings are entitled “Water and Wastewater Systems Replacement – Fenn Ranger Station” are divided into two (2) major sections: Civil Drawings (60 Sheets) and Electrical Drawings (14 Sheets). The drawings are listed below:

CIVIL DRAWINGS

Title Sheet

Quantities

General Notes & Legend

Control Point Map

Control Point Table

Demolition Site Plan Overview

Wastewater Treatment Facility Demolition Plan

Wastewater Treatment Facility Demolition Photos

North Homes Area Demolition Plan

Ranger Station Area Demolition Plan

Mobile Homes Area Demolition Plan

Cedar Flats Area Demolition Plan

Reservoir Area Demolition Plan

Sewer System Site Plan Overview

North Homes Area Sewer Main “A” – P&P

North Homes Treatment & Drainfield Details

Ranger Station Area Sewer Main “B” – P&P

Ranger Station Area Sewer Main “C” – P&P

Ranger Station Area Sewer Force Main “D” – P&P

Ranger Station Treatment & Drainfield Details

Ranger Station Area Drainfield Details

Mobile Homes Area Sewer Main “E” – P&P

Mobile Homes Area Sewer Main “F” – P&P

Mobile Homes Treatment & Drainfield Details

Mobile Homes Area Drainfield Details

Cedar Flats Area Sewer Main “H” – P&P

Cedar Flats Area Treatment & Sewer Main “H” – P&P

Cedar Flats Area Treatment & Sewer Main “H & I” – P&P

Cedar Flats Area Treatment & Drainfield Details

Cedar Flats Area Drainfield Details

RV Dump Station – Holding Tank

Gravelless Drainfield Details

Gravity Sewer Details

1500 Gallon Double Septic Tank Details

2000 Gallon Septic Tank Details

2000 Gallon Double Septic Tank Details

2500 Gallon Septic Tank Details

2500 Gallon Double Septic Tank Details

3000 Gallon Double Septic Tank Details

6000 Gallon Holding Tank Details

Lift Station / Dosing Details

Water System Site Plan Overview

Mobile Homes Water Main “A” P&P STA 0+00 TO STA 4+40

Mobile Homes Water Main “A” P&P STA 4+40 TO STA 8+80

Mobile Homes Water Main “A” P&P STA 8+80 TO STA 13+20

Mobile Homes Water Main “A” P&P STA 13+20 TO STA 17+60

Ranger Station Water Main “A” P&P STA 17+60 TO 22+00

Ranger Station Water Main “A” P&P STA 22+00 TO 26+40

North Homes Water Main “A” P&P STA 26+40 TO 30+80

North Homes Water Main “A” P&P STA 30+80 TO 34+20

Mobile Homes Water Main “B” P&P STA 200+00 TO 201+05

Ranger Station Water Main “C” P&P STA 400+00 TO 401+20

Cedar Flats Water Main “D” P&P STA 400+00 TO 401+87

Cedar Flats Water Main “E” P&P STA 50+00 TO 54+00

Cedar Flats Water Main “E” P&P STA 54+00 TO 57+08

Cedar Flats Water Main “F” P&P STA 300+00 TO 303+00

Water Details

Water Details

Existing Reservoir Shop Drawing w/ Circulation Piping

New Reservoir Access Lid Details

ELECTRICAL DRAWINGS

E0.0 Electrical Index Sheet

E1.0 North Homes Area Site Electrical

E1.1 North Homes Area Photos

E2.0 Ranger Station Area Site Electrical

E2.1 Ranger Station Area Photos

E3.0 Mobile Homes Area Site Electrical

E3.1 Mobile Homes Area Photos

E4.0 Cedar Flats Area #1 Site Electrical

E4.1 Cedar Flats Area #1 Photos

E5.0 Cedar Flats Area #2 Site Electrical

E5.1 Cedar Flats Area #2 Photos

E6.0 Lift Station Details

E6.1 Lift Station Structure Details

E6.2 Trench Details

The Drawings are incorporated into this solicitation and any resultant contract. Drawings are physically located in a separate attachment to the solicitation and are detailed in Section J.

PART I - THE SCHEDULE

SECTION E - INSPECTION AND ACCEPTANCE

E- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

PART I - THE SCHEDULE

SECTION F - DELIVERIES OR PERFORMANCE

F- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 Suspension of Work (APR 1984) F- 2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) Alternate I (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10-calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use as follows. All items in the base bid shall be completed prior to October 15, 2013, except the following which may be completed as late as July 15, 2014: Item 311100.5 Demolition of Wastewater Treatment Facility and Item 321216.1(A&B) Asphalt Patching. All additive alternate items awarded shall be completed no later than July 15, 2014. The time stated for completion shall include final cleanup of the premises.

The following work restrictions also apply to the prosecution of work:

· Contractor shall restrict on-site work to those hours between 7:00 am to 8:00 pm; however, work may be performed Monday – Sunday with weekend work acceptable. An Operating Schedule that includes the days and hours planned for on-site work shall be submitted to the CO at the prework meeting and updated biweekly.

· Work which would disrupt operations of the RV Dump Station shall occur after Labor Day or prior to Memorial Day.

· Use of water and sewer shall not be disrupted for more than 24 hours for any office, maintenance or work facility. Use of water and sewer shall not be disrupted for more than 8 hours for any individual residence.

· Contractor shall notify the Government 14 days prior to the commencement of Item 311100.5 Demolition of Wastewater Treatment Facility. On-site Government monitoring is required during the performance of this work due to the presence of a historically significant heritage site adjacent to the current wastewater treatment facility.

The October 15, 2013 completion date is based on the assumption that the successful offeror will receive the notice to proceed by July 1, 2013. This completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

PART I - THE SCHEDULE

SECTION G – CONTRACT ADMINISTRATION DATA

G-1 AGAR 452.215-73 Post Award Conference (NOV 1996) A post award conference with the successful offeror is required. It will be scheduled and held within 30 days of the commencement of work. The conference will be held at Nez Perce National Forest Supervisor’s Office, 104 Airport Road, Grangeville, ID 83530.

G-2 - CONTRACTING OFFICER'S REPRESENTATIVE

The Contracting Officer will designate a representative, hereinafter referred to as the Contracting Officer's Representative (COR) or, alternatively, as the Engineer, who will provide on-the-ground administration for the Government. The COR will be designated in writing and a copy of the designation will be furnished to the Contractor before or at the prework conference. The Contractor is cautioned to read the COR designation because certain authority under the contract is reserved solely for the Contracting Officer. The term "Contracting Officer" as used throughout the Specifications, shall be interpreted to include the Contracting Officer's designated representative(s) acting within the limits of their delegation of authority.

G-3 GOVERNMENT-FURNISHED PROPERTY

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the “Government Property” FAR clause contained elsewhere in the contract.

· Type ¾” Minus Crushed Aggregate will be provided by the Government for use on this project. The stockpile is located at O-Hara Pit located at mile post 0.5 of Forest Road 651. Directions to the site are as follows: From Kooskia, Idaho travel east of Highway 12 to Forest Service Road 223 (Selway River Road). Follow Road 223 for 7 miles to the junction of Road 651 turn to the right. Travel 0.5 miles up Forest Service Road 651 the pit is located on the right.

PART I - THE SCHEDULE

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.236-72 Use of Premises (NOV 1996) H-2 Utility Services

Electric power and potable water from the existing system is available for use without metering and without payment of use charges. Methods shall be made to conserve and reduce costs related to this use. Connections and extensions shall be the responsibility of the contractor.

H- 3 FAR 52.236-4 Physical Data (APR 1984) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations performed by Forest Service and Idaho Health Department; these investigations have found the drainfield sites to be acceptable to the state. A backhoe was used to dig test pits; all five pits had acceptable soils and dry bottoms. Additional pits were dug to test the condition of the pipe at various locations. Pipe within the trailer park consisted of many different types (copper, galvanized, steel, etc.) and had many leaks. Pipe within the Cedar Flats home area also had considerable deterioration. Pipe from the Trailer park to the Cedar Flats homes was in good and sound condition. Pipe in the Main Ranger station site was very old.

(b) Weather conditions at Fenn Ranger station can be very wet. Normal spring weather begins in February and is rainy until the middle or end of June. From July to the end of August is usually dry with occasional thunderstorms or light sprinkles. September thru November can be rainy or moist. Snow does not typically occur until late November or December and lasts until February.

(c) Transportation facilities on all roads to the site are paved two-lane roads. The Selway Road, Forest Service Road 223, however is not plowed from snow in the winter.

H- 4 Key Personnel The key personnel specified in the Offeror’s Technical Proposal are considered to be essential to the work being performed hereunder. Prior to diverting any of the specified individuals to other programs, the Contractor shall notify the Contracting Officer reasonably in advance and shall submit justification (including proposed substitutions) in sufficient detail to permit evaluation of the impact on the contract. No diversion shall be made by the Contractor without the written consent of the Contracting Officer: Provided that the Contracting Officer may ratify in writing such diversion and such ratification shall constitute the consent of the Contracting Officer required by this clause. The contract may be amended from time to time during the course of the contract to either add or delete personnel, as appropriate.

H-5 Work Camps, Staging and Storage Areas Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers on site. Overnight camping is commercially available near the project area. Overnight camping on site is prohibited. The contractor must provide toilets and sanitary facilities at each work location for its employees.

H- 6 Fire Control

(a) Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.

(b) Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or the Contractor’s employees, the Contractor when requested by the Contracting Officer shall place the employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.

Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area.

An equitable adjustment in contract time may be made for this period.

(c) Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to the Contractor’s operation under the contract.

(1) Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.

(2) Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:

One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.

One - shovel, round point #0 lady or equal.

One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.

One - water container (at least 1-gallon capacity), not required with stationary equipment.

(3) Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.

(4) Powersaws. For each powersaw used in connection with this contract, the following will be provided:

One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.

One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.

Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.

(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.

(6) Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.

(7) Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.

(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.

(9) Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.

All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.

(10) Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.

(11) Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.

When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:

(i) All high fire risk operations could be terminated at 1300 local time.

(ii) All burning could be stopped, including debris burning fires.

(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.

(12) Pump and Trailer. N/A

(13) Burning. Before starting any open burning, the Contractor shall comply with the following:

(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.

(ii) Obtain a burning permit from the District Ranger.

(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.

(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.

(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.

(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his/her discretion, prohibit all open burning for definite periods within specific areas of the National Forest.

H- 7 Local Material Sources

(a) Designated Sources--Sources of local materials will be designated on the drawings. The Government assumes responsibility for the quality and quantity of material in the source. The Contractor shall determine the equipment and work required to produce the specified product.

The Contractor shall utilize all suitable material in the source. The designation of source will include the rights of the Contractor to use certain area(s) for plant site, stockpiles, and haul roads.

Should the designated source, due to causes beyond the control of the Contractor, contain insufficient suitable material, the Government will provide another source with an equitable adjustment in accordance with the Differing Site Conditions and Changes clauses.

(b) Contractor-Furnished Sources--When the material sources are not designated as provided above or the Contractor elects not to use designated sources, the Contractor shall be responsible for providing the specified product with no adjustment in contract price, unless weight/volume relationship differences between designated source material and Contractor-furnished source material result in financial disadvantage to the Government. Quality testing shall be the responsibility of the Contractor. Test results shall be furnished to the Contracting Officer.

H- 8 Loss, Damage, or Destruction

(a) Equipment furnished with operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.

All claims arising under this clause will be submitted to the Contracting Officer.

H- 9 Incidental Payment Items

The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.

H- 10 Conformity with Drawings and Specifications

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.

H- 11 Samples, Tests, Cited Specifications Reference made in the contract to specifications, standards, or test methods adopted by AASHTO, ASTM, GSA, or other recognized National technical associations, shall mean specifications, standards, or test methods (including interim or tentative issues) which are in effect on the date of the solicitation.

H-12 Barricades, Warning Signs, and Other Devices The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

The contractor is responsible for the safety of the public and Government employees while work is being done adjacent to offices, maintenance/work facilities, residences and recreation facilities. Barricades, suitable and sufficient lights, danger signals, signs, etc. shall be erected to safeguard the public and Government employees from injury within trenches kept open overnight. Acceptable travel routes should be flagged for residences when normal access is disrupted.

H-13 Landscape Preservation

(a) Do not remove, deface, injure, or destroy trees, shrubs, lawn, natural or constructed features not designated for removal by the contract. Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material, which falls outside of these limits, shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste water from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

H-14 Contractor Performance Assessment Reporting System (FEB 2011)

(a) General. This contract is subject to Federal Acquisition Regulations (FAR), Agriculture Acquisition Regulations (AGAR), and…

This is the start of the file's text. The full file is on GovTribe.