FENNSpecialProjectSpecifications.pdf
PDF 8 MB Posted
- Solicitation number
- AG-02RC-S-13-0042
About this file
Attachment J-2 Special Project Specifications 126 pages
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment2Pgs2_3.docx | DOCX document | |
| Amendment2page1.doc | DOC document | |
| QuestionsAnswers2.docx | DOCX document | |
| Amendment1page1.doc | DOC document | |
| Amendment1Pgs2_3.docx | DOCX document | |
| FinalQuestionsAnswers.docx | DOCX document | |
| Amend1Pg4OxidationDitchTypical.pdf | ||
| SiteTourNotes.docx | DOCX document | |
| AttendanceList.docx | DOCX document | |
| Fenn_Civil__Part3.pdf | ||
| Fenn_Civil__Part1.pdf | ||
| Fenn_Civil__Part2.pdf | ||
| FennFinalRFP.doc | DOC document | |
| ELECTRIC_DRAWINGS.pdf | ||
| Fenn_Civil__Part4.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF CONTENTS
DIVISION 00 – SPECIAL SECTION
000114 Measurement and Payment ................................................................... 1-3
DIVISION 01 – GENERAL REQUIREMENTS
011113 Work Covered by Contract ..................................................................... 1-5
013216.14 Mobilization Payment Procedures ......................................................... 1-2
DIVISION 02 – EXISTING CONDITIONS
022101 Construction Surveying and Staking ...................................................... 1-2 023219 Exploratory Excavation .......................................................................... 1-2
DIVISION 03 – CONCRETE
035000 Cementitious Crystalline Waterproof Coating ........................................ 1-8
DIVISION 13 – SPECIAL CONSTRUCTION
133423.13 Portable and Mobile Buildings ............................................................... 1-1
DIVISION 26 – ELECTRICAL
262010 Basic Electrical Requirements ............................................................... 1-5 262028 Codes and Standards 262030 Tests and Demonstration of the Complete Electrical System 262060 Electrical System ................................................................................. 1-19 262090 Catalog Sheets .................................................................................... 1-13
DIVISION 31 – EARTHWORK
311100 Clearing and Grubbing and Removal of Obstructions ............................ 1-5
312316.16 Structure Excavation and Compaction for Minor Structures .................. 1-2 312333 Trenching and Backfilling ....................................................................... 1-5 312500 Permanent Erosion Control ................................................................... 1-2
DIVISION 32 – EXTERIOR IMPROVEMENTS
321123 Crushed Aggregates .............................................................................. 1-5 321216 Asphalt Patching (Commercial Sources) .............................................. 1-3 323010 Fencing
DIVISION 33 – UTILITIES
331116 Site Water Utility Distribution Piping .................................................... 1-12 333101 Gravity Sewers and Appurtenances ...................................................... 1-8 333219 Sewer Lift Station & Dosing Manhole Vault Structure ............................ 1-3 333220 Lift Station & Dosing Manhole Effluent Pumping System ...................... 1-5 333404 Sewer Pressure Force Main .................................................................. 1-2 333405 Gravelless Drainfield .............................................................................. 1-4 333610 Precast Concrete Septic Tanks & Holding Tanks .................................. 1-3
CIVIL DRAWINGS
1 Title Sheet 2 Quantities 3 General Notes & Legend 4 Control Point Map 5 Control Point Table 6 Demolition Site Plan Overview 7 Wastewater Treatment Facility Demolition Plan 8 Wastewater Treatment Facility Demolition Photos 9 North Homes Area Demolition Plan 10 Ranger Station Area Demolition Plan 11 Mobile Homes Area Demolition Plan 12 Cedar Flats Area Demolition Plan 13 Reservoir Area Demolition Plan 14 Sewer System Site Plan Overview 15 North Homes Area Sewer Main “A” – P&P 16 North Homes Treatment & Drainfield Details 17 Ranger Station Area Sewer Main “B” – P&P 18 Ranger Station Area Sewer Main “C” – P&P 19 Ranger Station Area Sewer Force Main “D” – P&P 20 Ranger Station Treatment & Drainfield Details 21 Ranger Station Area Drainfield Details 22 Mobile Homes Area Sewer Main “E” – P&P 23 Mobile Homes Area Sewer Main “F” – P&P 24 Mobile Homes Treatment & Drainfield Details
25 Mobile Homes Area Drainfield Details 26 Cedar Flats Area Sewer Main “H” – P&P
27 Cedar Flats Area Treatment & Sewer Main “H” – P&P 28 Cedar Flats Area Treatment & Sewer Main “H & I” – P&P
29 Cedar Flats Area Treatment & Drainfield Details 30 Cedar Flats Area Drainfield Details 31 RV Dump Station – Holding Tank 32 Gravelless Drainfield Details 33 Gravity Sewer Details 34 1500 Gallon Double Septic Tank Details 35 2000 Gallon Septic Tank Details 36 2000 Gallon Double Septic Tank Details
37 2500 Gallon Septic Tank Details 38 2500 Gallon Double Septic Tank Details
39 3000 Gallon Double Septic Tank Details 40 6000 Gallon Holding Tank Details 41 Lift Station / Dosing Details 42 Water System Site Plan Overview 43 Mobile Homes Water Main “A” P&P STA 0+00 TO STA 4+40 44 Mobile Homes Water Main “A” P&P STA 4+40 TO STA 8+80 45 Mobile Homes Water Main “A” P&P STA 8+80 TO STA 13+20 46 Mobile Homes Water Main “A” P&P STA 13+20 TO STA 17+60 47 Ranger Station Water Main “A” P&P STA 17+60 TO 22+00 48 Ranger Station Water Main “A” P&P STA 22+00 TO 26+40 49 North Homes Water Main “A” P&P STA 26+40 TO 30+80 50 North Homes Water Main “A” P&P STA 30+80 TO 34+20 51 Mobile Homes Water Main “B” P&P STA 200+00 TO 201+05 52 Ranger Station Water Main “C” P&P STA 400+00 TO 401+20 53 Cedar Flats Water Main “D” P&P STA 400+00 TO 401+87 54 Cedar Flats Water Main “E” P&P STA 50+00 TO 54+00 55 Cedar Flats Water Main “E” P&P STA 54+00 TO 57+08 56 Cedar Flats Water Main “F” P&P STA 300+00 TO 303+00 57 Water Details 58 Water Details
59 Existing Reservoir Shop Drawing w/ Circulation Piping 60 New Reservoir Access Lid Details
ELECTRICAL DRAWINGS
E0.0 Electrical Index Sheet E1.0 North Homes Area Site Electrical E1.1 North Homes Area Photos E2.0 Ranger Station Area Site Electrical E2.1 Ranger Station Area Photos E3.0 Mobile Homes Area Site Electrical E3.1 Mobile Homes Area Photos E4.0 Cedar Flats Area #1 Site Electrical E4.1 Cedar Flats Area #1 Photos E5.0 Cedar Flats Area #2 Site Electrical E5.1 Cedar Flats Area #2 Photos E6.0 Lift Station Details E6.1 Lift Station Structure Details E6.2 Trench Details
Section 000114
MEASUREMENT AND PAYMENT
SECTION 000114
PART 1: GENERAL
1.1 DESCRIPTION
Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered incidental to and included in the payment of the pay items in the Schedule of Items.
When more than one class, size, or thickness is specified in the Schedule of Items for any pay item, alphabetic suffixes will be added to the item number to differentiate between the items to be bid.
1.2 METHOD OF MEASUREMENT
The following methods of measurement are used to determine contract quantities for payment:
For individual construction items, longitudinal and lateral measurements for area computations will be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for seeding, mulching, sprigging, and sodding will be along slope lines.
The average end area method will be used to compute volumes of excavation or embankment. However, if in the judgment of the Contracting Officer (C.O.) the average end area method is impractical, measurement will be made by volume in hauling vehicles or by other three dimensional methods.
Structures will be measured according to neat lines shown on the drawings or as altered by the C.O. in writing to fit field conditions.
For items that are measured by the linear foot, such as pipe culverts, guard-rails, underdrains, etc., measurements will be made parallel to the base or foundation upon which the structures are placed, unless otherwise shown on the drawings.
For aggregates weighed for payment, the tonnage will be adjusted to dry weight. If moisture determination is necessary, the daily average moisture content will be determined from not less than three representative samples of aggregate taken at random intervals each day that aggregate is being weighed.
For bituminous material, volumes will be measured at 60°F or will be corrected to the volume at 60°F by using ASTM D1250 for asphalts or ASTM D633 for tars. Emulsified asphalt will be measured at 60°F, or measured by converting the gallonage at another temperature to gallonage at 60°F by means of the following formula:
Gallons at 60°F = Gallons at A°F 1 + 0.00025 A°F - 60°F
In which A°F is the temperature of the material at the time the gallonage is measured.
For vehicular shipments, net certified scale weights or weights based on certified volumes will be used as a basis of measurement. Measurements will be adjusted when bituminous material has been lost from the vehicle or the distributor, has been wasted, or has otherwise not been incorporated into this work. Determining true weights of hauling vehicles shall be made by weighing the empty vehicles at least once a day at the time the C.O. directs. Each vehicle shall bear a plainly legible identification mark. When bituminous materials are shipped, net certified weights, or volume corrected for loss of foaming, can be used for computing quantities.
For standard manufactured items, such as fence, wire, plates, rolled shapes, pipe conduits, etc., identified by gage, weight, section dimensions, etc., such identification shall be considered the nominal weights or dimensions. Unless by tolerances in cited specifications, manufacturer’s tolerances will be accepted.
1.3 UNITS OF MEASUREMENT
Payment will be by units defined and determined according to US Standard Measure and by the following:
A. Cubic Yard: A measurement computed by one of the following methods:
1. Excavation or Embankment - The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
2. Material in Place or Stockpile - The measurement computed with dimensions of the in-place material. Computations may be made by the average end area method or prismoidal formula for stockpiled material.
3. Material in the Delivery Vehicle - The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
B. Cubic Yard Mile - A combination of linear and volumetric measurement meaning the movement of a cubic yard of material one mile.
C. Each - One complete unit which may consist of one or more parts.
D. M. Gals - One thousand gallons.
E. Station - One hundred linear feet.
F. Station Yard - A combination of linear and volumetric measurement meaning the movement of a cubic yard of material one station.
G. Ton - Short ton consisting of 2,000 pounds.
H. Unit - A single quantity regarded as a whole in calculation; for example, 1000 square feet.
1.4 PAYMENT
One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
A. Designed Quantities (DQ). These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data includes the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units of the originally contemplated work will not be made unless authorized under one or more of the following conditions:
1. As a result of changes authorized by the C.O. in the originally contemplated work. Minor changes to adjust balance points, etc. will not be considered changes in quantities.
2. As a result of the C.O. determining that errors exist in the original design data used to determine designed quantities that cause a pay item to change by 15 percent or more.
3. As a result of the Contractor submitting to the C.O. a written request showing evidence of errors in the original design data used to determine design quantities that cause a pay item total to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
Final payment will be made for the designed quantities at the unit price shown in the Schedule of Items, subject to the Variation in Quantities Provisions.
B. Staked Quantities (SQ) - These quantities are determined from staked measurements prior to construction.
C. Actual Quantities (AQ) - These quantities are determined for measurements of completed work.
D. Design Quantities (DQ) - These quantities are specified on the plans.
E. Lump Sum Quantities (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They will not be measured.
PART 2: PRODUCTS – Not Used
PART 3: EXECUTION – Not Used
PART 4: MEASUREMENT AND PAYMENT – Not Used
END OF SECTION
Section 011113
WORK COVERED BY CONTRACT
SECTION 011113
1.1 LOCATION OF PROJECT
The project is located at the Fenn Ranger Station/Cedar Plats Work Center, at 831 Selway Road in Kooskia, Idaho on the Nez Perce-Clearwater National Forests.
1.2 BIDDING THIS PROJECT
This project will be bid as follows:
Base Bid – All of the wastewater improvements in and connecting the North Homes
Area, Ranger Station Area, Mobile Homes Area and the Cedar Flats Area.
All of the water improvements (Line “A”) Station 0+00 to station 25+90 – All of the water improvements in the Mobile Home Area and Ranger Station Area. In addition waterline “E” (Station 0+50 – Station 57+08) and the improvements indicated at the water storage reservoir and two valves connecting the reservoir to the 6” water main. Plus minor frost free hydrant installations at the North Homes Sites and Cedar Flats Area.
Additive Alternate #1 – North Homes (Line “A” Station 25+90 to 33+20) plus all connections, services, blow offs, valves, AC patching, etc. indicated on the plans. See drawing sheet 11 & 48-50.
Additive Alternate #2 – Cedar Flats (Line “F” Station 300+00 to Station 303+00) plus all connections, services, blow offs, valves, AC patching, frost free hydrant, etc. indicated on the plans and remove 4” valve. See drawing sheets 12 & 56.
Additive Alternate #3 – Cedar Flats (Line “D” Station 400+00 to Station 401+87) plus all connections, services, blow offs, valves, AC patching, frost free hydrant, etc. indicated on the plans. See drawing sheets 12 & 53.
Additive Alternate #4 – Cedar Flats replace the service line from the 6” water main to the dorm (130 lineal feet) and the supply line from the well to the dorm mechanical room and back to the 6” water main (188 lineal feet). See drawing sheets 12 & 53.
1.3 DESCRIPTION OF WORK
A. Furnish all labor, materials, equipment, supervision, structures and transportation necessary to complete the construction of the water and wastewater improvements in accordance with the drawings and specifications.
B. The major items of work include the following:
Water
1. 2,400 linear feet of 4 inch diameter, Class 200psi HDPE pipe
2. 1,170 linear feet of 2 inch diameter, Class 200psi HDPE pipe
3. 1,569 linear feet of 1 inch diameter DR-11 Class 200psi HDPE pipe
4. 6 water gate valves
5. 34 water service connections
6. Reservoir cleaning, coating & replacement of resorvoir access lids
7. 377 square yards asphalt concrete patching
Sewer
8. 1,842 linear feet of 6 inch diameter gravity SCH40 PVC pipe
9. 1,929 linear feet of 4 inch diameter gravity SCH40 PVC pipe
10. 974 linear feet of 2½ inch dia. force main PVC and HDPE (200psi) pipe
11. 369 linear feet of 2 inch diameter force main PVC (200psi) pipe
12. 1 Lift station
13. 4 dosing manholes
14. Septic tanks (2 – 1,500 gallon, 2 – 2,000 gallon, 2 – 2,500 gallon and 1 –
3,000 gallon)
15. 4 drainfields (2,230 linear feet of trenches)
16. 28 sewer service connections
17. 320 linear feet fencing
18. 482 square yards asphalt concrete patching
19. 6,000 gallon concrete RV holding tank
C. The general layout and the details of the required work are shown on the construction drawings.
1.4 START OF WORK
It is anticipated that work will begin approximately Summer 2013.
1.5 CONTRACT TIME
Work shall be completed in accordance with FAR 52.211-10 Commencement, Prosecution, and Completion of Work Alternate I found in Part I, Section F of the solicitation.
1.6 NOTIFICATION
Notify Contracting Officer (C.O.) of intent to begin work at least 5 days in advance.
1.7 USE OF GOVERNMENT FACILITIES
A. The Ranger Station is scheduled to be open to the public during the construction of the improvements.
B. Sanitary Facilities: Sanitary facilities are the contractors responsibility.
C. Electrical Power: Commercial power is available at the site.
D. Potable Water: Potable water is available at the site until it must be turned off due to construction.
E. Information Requests: Submit requests for information in writing to the C.O. and allow seven (7) working days for a response.
1.8 SUBMITTALS
A. It shall be the Contractor's responsibility to submit all items with such promptness as to cause no delay in the work. Approvals must be obtained before starting work which involves the item. The Contractor shall allow 10 business days for processing of submittals by the Government.
B. Manufacturer's Literature: Submit 4 copies to the C.O. for approval on the items required herein. Literature shall be marked or otherwise designated to indicate the exact model, size, etc., the Contractor proposes to use. Information shall be adequate to determine compliance with the specifications without additional research by the C.O.. One copy of approved submittals will be returned to Contractor.
C. Provide manufacturer's literature on the following:
HDPE piping and couplings and fittings PVC piping and coupling and fittings Valves CI valve boxes Dosing manhole structures, controls and mechanical equipment Lift station structure, controls & mechanical equipment Septic tanks & filters CI & aluminum covers
1.9 SCHEDULES
Furnish 1 copy each of the following items after award of contract for review and/or approval pursuant to contract provisions:
A. Proposed progress schedule showing starting and completion dates of various work tasks.
B. List of proposed subcontractors and their intended work. Sub-contractors must have the C.O.'s written approval prior to work on the project.
C. Submit updated schedule to the C.O.with each pay request.
1.10 STAKING
The Contractor will stake all component of work on this project. The C.O. shall approve the locations.
1.11 SAFETY PRECAUTIONS
Provide suitable signs, barricades, temporary fencing, etc. to provide for public safety and prevent access to the project site.
1.12 DISPOSAL SITE
The existing oxidation treatment plant shall be removed from the Cedar Flats Work Center Site in its entirety (drying beds, oxidation ditch, control building and contents, mechanical equipment, inlet trash rack, chlorination equipment, clanfier digestor, chlorament contact tank, etc).
Project waste materials and minor clearing debris shall be removed from the project site and disposed of at an approved sanitary landfill, or other acceptable disposal site by the Contractor. No burning of construction materials or debris will be allowed at the project site.
1.13 CLEANUP
Maintain the project work area in a clean and orderly condition throughout the progress of work under this contract.
1.14 STORAGE OF MATERIALS
The Contractor will be allowed to store materials at the project site. Coordinate the location of the storage area with the C.O. Materials subject to damage from the weather shall be adequately protected by the Contractor. The Contractor shall be solely responsible for the loss of or damage to materials stored at the job site.
1.15 LOCATION OF EXISTING UTILITIES
Locate existing utilities: If any utility is damaged during this project, repair immediately.
1.16 NOXIOUS WEED CONTROL
In order to reduce the potential spread of noxious weeds onto National Forest System lands, the contractor will be required to clean all construction equipment that operates off existing roads prior to the equipment entering the National Forest boundary. The cleaning shall remove all dirt and plant parts that may carry noxious weed seeds inside the National Forest boundary.
The contractor shall notify the C.O. at least one working day in advance of planned equipment delivery to get agreement on the location of where the cleaning will occur, and schedule a time for inspection by the Forest Service.
1.17 FENN RANGER STATION/CEDAR FLATS WORK CENTER
The water and sewer systems shall be kept in service while the improvements to the system are being constructed. The use of temporary by-pass lines, short shut downs, etc. must be coordinated with the C.O.
PART 3: EXECUTION
3.1 MATERIALS TO BE RETURNED TO GOVERNMENT
A. LMI Chorinator
B. Backflow Preventer (watts 009QT)
3.2 GOVERNMENT PROVIDED ITEMS:
A. Crusher Gravel. O’Hara Pit. Location of the O’Hara Pit is mile post 0.5 of Forest Road 651. Directions to the site area as follows: From Kooskia, Idaho travel east on Highway 12 to Forest Service Road 223 (Selway River Road). Follow Road 223 for 7 miles to the junction of Road 651 on the right.
PART 4: MEASUREMENT AND PAYMENT
4.1 No separate payment will be made for work under this section.
Section 013216.14
MOBILIZATION PAYMENT PROCEDURES
SECTION 013216.14
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incidents to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
PART 2: PRODUCTS – NOT USED
PART 3: EXECUTION – NOT USED
4.1 PROGRESS PAYMENTS WILL BE MADE AS FOLLOWS:
A. Bond premiums will be reimbursed after receipt of the evidence of payment
B. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
C. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original not including mobilization and bond premiums.
D. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
E. Progress payments for mobilization and preparatory work shall be subject to retainage.
4.2 BASIS OF PAYMENT
A. Payment will be made under:
PAY ITEM DESCRIPTION PAY UNIT
013216.14(A)&(B) Mobilization Lump Sum
013216.14(A)&(B) Mobilization shall be measured and paid for by the lump sum at the contract unit bid price. Payment shall be considered full compensation for all preparatory work and operations performed by the Contractor, including but not limited
Section 013216.14 to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for the establishment of all offices, buildings, and other facilities necessary for all work on the project; for premium on bonds and insurance for the contract; for other work and operations that must be performed or costs incurred before beginning work on various items of the project; and for all labor, equipment, materials and incidentals necessary to complete the work. Mobilization costs for subcontracted work shall be considered to be included.
Section 022101
CONSTRUCTION SURVEYING AND STAKING
SECTION 022101
A. Furnish all surveys and calculations necessary to layout and control the work to specified lines, grades, and tolerances. Use survey personnel that are trained, experienced and skilled in construction layout and control. Protect all furnished control points. Reset destroyed control points or set new ones.
PART 2: PRODUCTS
2.1 GENERAL REQUIREMENTS
A. Furnish all materials and equipment required to perform this work.
B. Produce manual survey notes in standard filed notebook, written in a clear, orderly and neat manner meeting the requirements and standard surveying practices of the profession. If notes are generated electronically, produce notes in a format meeting these requirements. Submit survey notes, including electronic notes, to the C.O. every ten days and upon completion of each survey function. The C.O. will review the field notes for acceptance. The finished notes become the property of the Government.
3.1 GENERAL
A. The Government will furnish control points and benchmarks throughout the project and as shown on the plans.
B. Verify all Government set control points before any layout staking is performed.
Preserve and protect Government furnished control points and replace any that may be damaged, displaced or removed.
C. Set all stakes necessary to control all work under the contract. This includes, but is not limited to: centerline stations, clearing limits, slope stakes, drainage structures, surfacing courses, pavement, sewer, water, buildings and any other items of work included in the contract.
D. Survey tolerances shall be as follows:
Centerline 0.2’ Horizontal N/A Vertical Slope Stake 0.3’ Horizontal 0.2’ Vertical Water 0.3’ Horizontal 0.2’ Vertical Sewer 0.3’ Horizontal 0.1’ Vertical Structures 0.1’ Horizontal 0.1’ Vertical Subgrade 0.2’ Horizontal 0.1’ Vertical Aggregate 0.2’ Horizontal 0.1’ Vertical
Section 022101
E. Inspection may be conducted by random checks of any portion of the layout and control work. The C.O. may order work not performed with sufficient accuracy to be corrected. No compensation will allowed for corrective work. The contractor is responsible for securing proper dimensions, lines, grades and elevations for all parts of the work and owner’s inspection will not relieve the contractor of this responsibility.
4.1 Payment will be made under:
Pay Item Description Pay Unit
022101.0(A)&(B) Construction Surveying and Staking Lump Sum
022101.0(A)&(B): Measurement will be made on a lump sum quantity. Payment will be full compensation for providing all materials, labor, tools and equipment necessary to complete the construction surveying and staking as required on the plans and specifications.
Section 023219
EXPLORATORY EXCAVATION
SECTION 023219
A. Exploratory excavation for determining utility locations, groundwater depths, soil conditions, etc.
1.2 RELATED SECTIONS
A. Section 312316 – Structure Excavation and Compaction for Minor Structures
B. Section 312333 – Trenching and Backfill
2.1 GENERAL REQUIREMENTS
A. Construction materials and equipment used for the work shall meet all requirements of the Contract Documents.
B. Use, handle and store material in such a manner as to preserve quality and fitness for the work.
C. Immediately remove materials from the site of work that do not conform to the requirements of the Contract Documents as determined by the C.O.
A. As requested by the C.O., provide the fueled and operated backhoe at least 60 horsepower (45kw) as rated by the manufacturer, laborer, and trench shoring to perform the exploratory excavation.
B. Provide for dewatering of the exploratory excavation and disposal of the pumped water at an approved discharge point.
C. Perform exploratory excavation to the utility or item requiring location at which time the C.O. will obtain field measurements. If necessary, conduct rock removal per Section 312333 – Trenching and Backfill.
D. Excavate, backfill, and restore surfacing to pre-construction conditions.
E. No exploratory excavation payment will be made without the C.O. authorizing the work.
Section 023219
023219.0(A)&(B) Exploratory Excavation Hours
023219.0(A)&(B) Measurement will be made by the C.O. for the exploratory excavation time to the nearest ½ hour. Payment for actual time on the job site, and as directed by the C.O., will be full compensation for providing all materials, labor, tools and equipment necessary to complete the exploratory excavation, backfilling and final clean-up of an area. Any damage done while working on the Bid Item will be paid for by the contractor.
Section 035000
CEMENTITIOUS CRYSTALLINE WATERPROOF COATING
SECTION 035000
PART 1: GENERAL
1.1 SUMMARY
A. Furnishing of all labor, materials, services and equipment necessary for the supply and installation of cementitious crystalline waterproofing to concrete substrates, above-grade or below-grade, on either dry or wet side of substrates, (in the 60,000 gallon reservoir) as indicated on drawings and as specified herein. Disinfection of the reservoir is also included.
1.2 REFERENCES
A. Applicable Standards: The following standards are referenced herein.
1. American Society for Testing and Materials (ASTM)
2. Army Corps of Engineers (CRD)
3. NSF International (NSF)
1.3 SYSTEM DESCRIPTION
A. Cementitious Crystalline Waterproofing: Blend of portland cement, fine treated silica sand and active proprietary chemicals. When mixed with water and applied as a cementitious coating, the active chemicals cause a catalytic reaction which generates a non-soluble crystalline formation of dendritic fibers within the pores and capillary tracts of concrete. This process causes concrete to become permanently sealed against the penetration of liquids from any direction.
1.4 SUBMITTALS
A. Product Data: Submit product data, including manufacturer's specifications, installation instructions, and general recommendations for waterproofing applications. Also include manufacturer's certification or other data substantiating that products comply with requirements of Contract Documents.
B. Manufacturer's Certification: Provide certificates signed by manufacturer or manufacturer's representative certifying that the materials to be installed comply in all respects with the requirements of this specification, and that the applicator is qualified and approved to install the materials in accordance with manufacturer's product data.
1.5 QUALITY ASSURANCE
A. Manufacturer Qualifications: Manufacturer shall be ISO 9001 registered, and shall have no less than 10 years’ experience in manufacturing the cementitious crystalline waterproofing materials for the required work. Manufacturers that cannot provide the performance test data specified herein will not be considered for the project.
B. Applicator: Waterproofing applicator shall be experienced in the installation of cementitious crystalline waterproofing materials as demonstrated by previous successful installations, and shall be approved by the manufacturer in writing.
C. Technical Consultation: The waterproofing manufacturer's representative shall provide technical consultation on waterproofing application.
1.7 DELIVERY, STORAGE AND HANDLING
A. Delivery: Deliver packaged waterproofing materials to project site in original undamaged containers, with manufacturer's labels and seals intact.
1.8 PROJECT CONDITIONS
A. Compliance: Comply with manufacturer's product data regarding condition of substrate to receive waterproofing, weather conditions before and during installation, and protection of the installed waterproofing system.
1.9 WARRANTY
A. Manufacturer's Warranty: Manufacturer shall provide standard product warranty executed by authorized company official. Term of warranty shall be (specify term) years from Date of Substantial Completion.
B. Applicator's Warranty: Applicator shall warrant the waterproofing installation against defects caused by faulty workmanship or materials for a period of (specify term) years from Date of Substantial Completion. The warranty will cover the surfaces treated and will bind the applicator to repair, at his expense, any and all leaks through the treated surfaces which are not due to structural weaknesses or other causes beyond applicator's control such as fire, earthquake, tornado and hurricane.
The warranty shall read as follows:
1. Warranty: The applicator warrants that, upon completion of the work, surfaces treated with cementitious crystalline waterproofing will be and will remain free from water leakage resulting from defective workmanship or materials for a period of five (5) years from Date of Substantial Completion. In the event that water leakage occurs within the warranty period from such causes, the applicator shall, at his sole expense, repair, replace or otherwise correct such defective workmanship or materials. Applicator shall not be liable for consequential damages and applicator's liability shall be limited to repair, replacement or correcting of defective workmanship or materials. Applicator shall have no responsibility with respect to water leakage or other defects caused by structural failure or movement of the structure, or any other causes beyond Applicator's control.
PART 2: PRODUCTS
2.1 MATERIALS
A . The waterproofing product must be “Made in America”.
B . Acceptable Manufacturer:
Euclid Chemical Company
19218 Redwood Road Cleveland, OH 44110
C. Products: The Crystalline waterproofing materials shall meet the manufacturer standard of Vandex BB75 or approved equal.
D. Substitutions: Please bid the product specified. An “as-equal” product may be submitted after award. If approved by the C.O. it may be used.
E. Source Quality: Obtain proprietary crystalline waterproofing products from a single manufacturer.
2.2 MIXES
A. General: Mix waterproofing material by volume with clean water which is free from salt and deleterious materials. Mix waterproofing material in quantities that can be applied within 20 to 30 minutes from time of mixing. As mixture thickens, stir frequently, but do not add additional water. Do not mix bonding agents or admixtures with crystalline waterproofing materials.
B. Brush Application Mix: Measure dry powder and place in mixing container.
Measure water and mix into the dry powder with a paddle on a slow speed electric drill (250 RPM) or other type mixer which is acceptable to manufacturer.
Mixing proportions shall be as recommended by manufacturer.
C. Spray Application Mix: Mixing shall be same as specified for brush application except that mixture shall be thinner. Follow the manufacturer’s proportions as a guide. Adjust proportions to match type of spray equipment and pressures used.
3.1 EXAMINATION
A. Site Visit: Prior to waterproofing installation, arrange visit to project site with waterproofing manufacturer's representative. Representative shall inspect and certify that concrete surfaces are in acceptable condition to receive waterproofing treatment.
B. Verification of Substrates: Verify that concrete surfaces are sound and clean, and that form release agents and materials used to cure the concrete are compatible with waterproofing treatment.
C. Examination for Defects: Examine surfaces to be waterproofed for form tie holes and structural defects such as honeycombing, rock pockets, faulty construction joints and cracks. Such defects to be repaired in accordance to manufacturer's product data and 3.2 below.
3.2 PREPARATION
A. Concrete Finish: Concrete surfaces to receive waterproofing treatment shall have an open capillary system to provide tooth and suction, and shall be free from scale, excess form oil, laitance, curing compounds and foreign matter.
Horizontal surfaces shall have a rough wood float or broom finish. Where a smooth trowel finish is required on horizontal surface, crystalline waterproofing material shall be applied by dry shake method at time of concrete finishing in accordance with manufacturer's product data.
B. Surface Preparation: Smooth surfaces (e.g. where steel forms are used) or surfaces covered with excess form oil or other contaminants shall be washed, lightly sand-blasted, water-blasted, or acid etched with muriatic acid as necessary to provide a clean absorbent surface. Surfaces to be acid-etched shall be saturated with water prior to application of acid.
C. Repair of Defects: Surface defects shall be repaired in accordance with manufacturer's instructions as follows:
1. Form Tie Holes, Construction Joints, Cracks: Chip out defective areas in a “U” shaped slot one inch wide and a minimum of one inch deep. Clean slot of debris and dust. Soak area with water and remove excess surface water. Apply a slurry coat at the rate of 1.5 1b./sq. yd. to the slot. Allow slurry to reach an initial set, then fill cavity with Dry-Pac. Compress tightly into cavity using pneumatic packer or block and hammer
2. Rock Pockets, Honeycombing or Other Detective Concrete: Rout out detective areas to sound concrete. Remove loose materials and saturate with water. Remove excess surface water and apply a slurry coat to area.
After slurry has set, but while still “green”, fill cavity to surface level with non-shrink grout.
D. Wetting Concrete: Prior to application of waterproofing treatment, thoroughly saturate concrete surfaces with clean water as required to ensure migration of crystalline chemicals into voids and capillary tracts of the concrete. Remove free surface water before application.
3.3 APPLICATION
A. Construction Joints: Apply water proofing in slurry form at a rate of 2.0 lb./sq. yd.
to joint surfaces between concrete pours. Moisten surfaces prior to slurry application. Where joint surfaces are not accessible prior to pouring new concrete, consult manufacturer for application procedure.
B. Surface Application: After repairs, surface preparation, treatment of construction joints and sealing strip placement have been completed in accordance with manufacturer's product data and as specified herein, waterproofing uniformly to concrete surfaces with semi-stiff bristle brush or broom, or suitable spray equipment. Application rates and locations shall be as indicated in the drawings and in accordance with manufacturer's product data.
When brushing, work slurry well into surface of the concrete, filling surface pores and hairline cracks. When spraying, hold nozzle close enough to ensure that slurry is forced into pores and hairline cracks.
1. First Coat (of two coat application): Apply slurry coat to locations indicated on drawings in accordance with manufacturer's product data.
2. Second Coat: Where indicated on drawings or as required by manufacturer's product data, slurry coat while first coat of waterproofing is still “green" but after it has reached an initial set. Use light prewatering between coats when rapid drying conditions exist.
3.4 CURING
A. General Begin curing as soon as coating has hardened sufficiently so as not to be damaged by a fine spray. Cure with a mist fog spray of clean water three times a day for 2 to 3 days, or cover treated surfaces with damp burlap for the prescribed period. In warm climates, more than three sprayings per day may be necessary to prevent excessive drying of coating.
B. Air Circulation: Do not lay plastic sheeting directly on the waterproofing coating as air contact is required for proper curing. If poor circulation exists in treated areas, it may be necessary to provide fans or blown air to aid in curing of waterproofing treatment.
C. Holding Structures: For concrete reservoirs, cure for three days and then allow treatment to set (air cure) for 12 days before filling structure with liquid.
D. Protection: During the curing period, protect treated surfaces from damage by wind, sun, rain and temperatures below 36°F. If plastic sheeting is used for protection, it must be raised off of waterproofing coating to allow sufficient air circulation.
E. Curing Agent: If moist curing is not possible, use a chemical curing agent that is specifically designed for or compatible with the approved crystalline waterproofing treatment. Curing agent shall have at least two years of successful field use and shall be approved by waterproofing manufacturer in writing.
3.5 FIELD QUALITY CONTROL
A. Observation: Do not conceal installed waterproofing system before it has been observed by C.O.
3.6 CLEANING AND PROTECTION
A. Cleaning: Clean spillage and soiling from adjacent surfaces using appropriate cleaning agents and procedures approved by the manufacturer.
B. Protection: Take measures to protect completed Waterproofing coat from damage after application. Do not permit traffic on unprotected coating areas.
3.7 DISINFECTION OF THE RESERVOIR (AWWA C652-92)
A. Disinfecting – It is recommended that Method 2 per AWWA C652-92. This method is recommended because it does not require disposal or neutralization of large amounts heavily chlorinated water which can be hazardous to the environment.
B. Chlorination, AWWA Method 2:
A Solution of 200 mg/L available chlorine shall be applied directly to the surfaces of all parts of the storage facility which would be in contact with water when the storage facility is full to the overflow elevation.
Method of application: The Chlorine solution may be applied with suitable brushes or spray equipment. The solution shall thoroughly coat all surfaces to be treated, including the inlet and outlet piping, and shall be applied to any separate drain piping such that it will have available chlorine of not less than 10 mg/L when filled with water. Overflow piping need not be disinfected.
Retention: The surfaces disinfected shall remain in contact with the strong chlorine solution for at least 30 minutes after which potable water shall be admitted, the drain piping shall be purged of the 10 mg/L chlorinated water, and the storage facility shall be filled to its overflow level. Then, subject to satisfactory bacteriological testing, acceptable aesthetic quality, such water may be served to the distribution system.
C. Disposal of chlorinated water – Use a “reducing” agent as defined in AWWA
C652-92.
3.8 LEAK TESTING THE RESERVOIR
A. Testing (Reservoir) – Testing of the reservoir consists of filling the reservoir to check for water tightness. This “leak” test can be completed during the initial filling after the reservoir is disinfected. The testing of the water can be done from this initial filling and if there are no obvious problems with the reservoir, it can be put on line without emptying and refilling.
To test the reservoir, fill to 100% full, close all valves and let set for 24 hours.
Note the height of the water. Check the water height after 3 consecutive 24 hour periods. Allowing for evaporation, the water level shouldn’t drop more than 1 tenth of one percent in any 24 hour period.
B. Testing (Water) – This testing consists of taking samples of the water to certified lab for bacteria testing prior to placing the reservoir in service. Special attention must be given to ensure that the water source has been tested and is clear of bacteria and contaminants.
035000.0 Cleaning, Coating, Testing and Disinfection of Reservoir Lump Sum
035000.0 Measurement of this item shall be based on a lump sum basis. Payment shall include draining the reservoir; cleaning the walls, floor and roof to the recommendations of the cementitious coating supplier; temporarily providing a pressure tank and piping, fitting, etc. so that the existing well can be directly connected to the water distribution system during the reservoir cleaning and coating operation; materials, labor and equipment to complete this item as indicated in the contract documents and on the construction drawings. Payment will be made when the cleaning, coating, testing and disinfection operation is completed, inspected, and accepted by the C.O.
Section 133423.13
PORTABLE AND MOBILE BUILDINGS
SECTION 133423.13
PORTABLE AND MOBILE BUILDINGS
1.1 GENERAL
A. This section covers the relocation of the trailer house #1321 and sheds #2672 &
#2674 to the lot location approximately 220 feet north of trailer house #1321.
PART 2: PRODUCTS – NOT USED
A. Prepare Lot #2674 to receive the trailer house, roof structure and the shed. This would include trail house pads/footings and underground utility hook-up.
B. Relocate the existing trailer house to its new location at Lot 2674.
C. Relocate the existing trailer house roof structure, the carport wall and roof, decks and steps to Lot #2674.
D. Relocate the shed (Building #2672) next to the relocated trailer house. Set the shed as directed by the C.O.
E. Cleanup Lot #1321 (i.e. concrete pads/footings, fill miscellaneous holes, etc.).
4.1 PAYMENT WILL BE MADE UNDER:
PAY ITEM DESCRIPTION PAY UNIT
133423.13 Relocate Trailer House #1321 to Lot #2674 Lump Sum
133423.13 Measurement for the relocation of trailer house #1321, shed #2672 and shed #2674 will be measured on a lump sum basis. Payment will be made under this pay item for all required work and materials needed to complete this item. Payment under this item will include: construction of trailer house footing/pads, underground utility hook-ups, relocation of the trailer house and two sheds, removal and disposal of Lot #1321 concrete slab, decks, steps, relocation of the trailer house roof structure, relocate the carport wall and roof structure, cleanup Lot #1321 and any other items required to relocate the trailer house and reconnect it backup.
Section 262010
BASIC ELECTRICAL REQUIREMENTS
SECTION 262010
PART 1: GENERAL INFORMATION
1.1 PROJECT LOCATION
A. The project is located at Fenn Ranger Station as indicated on the civil engineering drawings.
1.2 WHAT THE CONTRACTOR PROVIDES
A. The contractor provides all labor and materials necessary to accomplish the project as generally described in the specifications and on the drawings.
1.3 GENERAL SCOPE OF THE WORK
A. The contractor furnishes and installs sewage lift stations and septic tank alarm boxes in a number of locations which require a variety of branch circuit supplies.
1.4 GENERAL REQUIREMENTS
A. GROUNDING
A ground wire shall be installed in all new circuits.
B. NEUTRAL SIZE
All circuits shall have a full sized insulated neutral. In no case shall a neutral conductor be used in common with any other circuit.
C. CONDUCTOR TYPE
The conductor type is THWN copper conductors in EMT conduit above grade and Schedule 80 PVC below grade, unless otherwise indicated.
D. RECEPTACLES
All receptacles shall be NEMA 5-20R, Specification Grade unless otherwise indicated.
E. BOXES
All outlet, switching, and junction boxes shall be metal regardless of wiring method.
1.5 MATERIAL PACKAGE
A. COMPLETE PACKAGE
The electrical contractor shall obtain the complete package of materials including the civil engineering drawings and specifications. Anything else is an incomplete package and the electrical contractor will be missing important information regarding what is required to complete the job correctly.
PART 2: SCOPE OF WORK
2.1 SEWAGE LIFT STATIONS
A. The contractor furnishes and installs sewage lift stations in 5 locations.
2.2 ALARM BOXES
A. The contractor furnishes alarm boxes in 5 locations.
2.3 BRANCH CIRCUITS
A. The contractor furnishes and installs new branch circuits to the new lift stations from a variety of sources. This includes panels, fusible switches, feeders, and other existing electrical system modifications and additions as indicated on the drawings.
PART 3: GENERAL REQUIREMENTS
3.1 SUMMARY
A. This section specifies the basic requirements for electrical installations and includes requirements common to more than one section of Division 26.
3.2 ROUGH-IN
A. Verify final locations for rough-ins with field measurements and with the requirements of the actual equipment to be connected.
3.3 ELECTRICAL INSTALLATIONS
A. Coordinate electrical equipment and materials installation with other building and site components and installations including coordination with site trenching for joint use trenching.
B. Verify all dimensions by field measurements.
C. Sequence, coordinate, and integrate installations of electrical materials and equipment for efficient flow of the Work.
D. Coordinate the cutting and patching of building components to accommodate the installation of electrical equipment and materials.
E. Install electrical equipment to facilitate maintenance and repair or replacement of equipment components. As much as practical, connect equipment for ease of disconnecting, with minimum of interference with other installations.
F. Coordinate connection of electrical systems with exterior underground utilities and services. Comply with requirements of governing regulations, franchised service companies, and controlling agencies. Provide connection for each service.
3.4 CUTTING AND PATCHING
A. This Article specifies the cutting and patching of electrical equipment, components, and materials and includes removal and legal disposal of selected materials, components, and equipment.
B. Do not endanger or damage installed Work through procedures and processes of cutting and patching.
C. Arrange for repairs required to restore other work, because of damage caused as a result of electrical installations.
D. No additional compensation will be authorized for cutting and patching work that is necessitated by ill-timed, defective, or non conforming installations.
E. Cut, remove and legally dispose of selected electrical equipment, components, and materials as indicated, including, but not limited to, removal of electrical items indicated to be removed and items made obsolete by the new work.
F. Protect the structure, furnishings, finishes, and adjacent materials not indicated or scheduled to be removed.
3.5 NAMEPLATE DATA
A. Provide permanent operational data nameplate on each item of power operated equipment, indicating manufacturer, product name, model number, serial number, capacity, operating and power characteristics, labels of tested compliances, and similar essential data.
B. Locate nameplates in an accessible location.
3.6 DELIVERY, STORAGE, AND HANDLING
A. Deliver products to project properly identified with names, model numbers, types, grades, compliance labels, and similar information needed for distinct identifications; adequately packaged and protected to prevent damage during shipment, storage and handling.
B. Store equipment and materials at the site, unless off-site storage is authorized in writing.
C. Protect stored equipment and materials from damage.
D. Coordinate deliveries of electrical materials and equipment to minimize construction site congestion.
E. Limit each shipment of materials and equipment to the items and quantities needed for the smooth and efficient flow of installations.
3.7 RECORD DOCUMENTS
A. Mark Drawings to indicate revisions to conduit size and location both exterior and interior; actual equipment locations, dimensioned for column lines; concealed equipment, dimensioned to column lines; distribution and branch electrical circuitry; fuse and circuit breaker…