Natomas Reach D Pumping Plant 4

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W9123821B0002
Agency
ENDIST Sacramento US Army Corps of Engineers, Department of Defense
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Z1NE Maintenance Of Water Supply Facilities
Place of performance
Sacramento CA 95824 USA

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks construction services to relocate Pumping Plant 4 and associated facilities for the Natomas Reach D Pumping Plant project. Work includes raising discharge pipes 10 feet, adding a new vault and outfall structure, removing existing buildings and installing a new trash rack and pumps. The Department of the Army Corps of Engineers Engineering District Sacramento will award a firm-fixed price contract to the responsive, responsible bidder submitting the lowest total bid. Bids were due on January 26, 2021 and were to be submitted electronically through the DoD Secure Access File Exchange system.

There is no set-aside designation. The primary NAICS code is 237110 and PSC code is C211. Five contractors submitted bids ranging from $7,081,758 to $12,100,496 by the deadline. The apparent low bidder was IGE at $7,081,758. The work is to be performed in Sacramento, California and includes relocating Pumping Plant 4 discharge pipes, raising the pump station pad, installing new pumps and fencing to address 200-year flood protection requirements at the Natomas Reach D site.

Notice text

5 versions

Update #5 · Latest ·

*** 12/26/21- Posted Bid Opening Abstract ***

*** Amendment 0002 Posted - Revised Plans and Specs ***

*** Amendment 0001 Posted - Extended Bid due date and changed Bid Opening time*****

*** 12/30/20 -  Site visit sign-in sheet posted ***

The work includes relocating Pumping Plant 4 discharge pipes to be raised 10 feet to be above the 200-year water surface elevation and adding a new vault and outfall structure. Additional work includes removal of existing Pumping Plant 4 building and trash rack and reconfiguring the pump station intake and installing a new trash rack. The pump station pad will be raised and have new pumps installed but will not include a new building. A driveway to the new trash rack will also be located adjacent to the Electrical Building, with power provided from the adjacent PG&E lines. Six-foot high chain-link fencing will enclose the Pumping Plant area, with gates installed as shown on the plans. Access ramps and landside toe roads will be reconfigured to accommodate the new pumping plant layout.   

Update #4 ·

*** Amendment 0002 Posted - Revised Plans and Specs ***

*** Amendment 0001 Posted - Extended Bid due date and changed Bid Opening time*****

*** 12/30/20 -  Site visit sign-in sheet posted ***

The work includes relocating Pumping Plant 4 discharge pipes to be raised 10 feet to be above the 200-year water surface elevation and adding a new vault and outfall structure. Additional work includes removal of existing Pumping Plant 4 building and trash rack and reconfiguring the pump station intake and installing a new trash rack. The pump station pad will be raised and have new pumps installed but will not include a new building. A driveway to the new trash rack will also be located adjacent to the Electrical Building, with power provided from the adjacent PG&E lines. Six-foot high chain-link fencing will enclose the Pumping Plant area, with gates installed as shown on the plans. Access ramps and landside toe roads will be reconfigured to accommodate the new pumping plant layout.   

Update #3 ·

*** Amendment 0001 Posted - Extended Bid due date and changed Bid Opening time*****

*** 12/30/20 -  Site visit sign-in sheet posted ***

The work includes relocating Pumping Plant 4 discharge pipes to be raised 10 feet to be above the 200-year water surface elevation and adding a new vault and outfall structure. Additional work includes removal of existing Pumping Plant 4 building and trash rack and reconfiguring the pump station intake and installing a new trash rack. The pump station pad will be raised and have new pumps installed but will not include a new building. A driveway to the new trash rack will also be located adjacent to the Electrical Building, with power provided from the adjacent PG&E lines. Six-foot high chain-link fencing will enclose the Pumping Plant area, with gates installed as shown on the plans. Access ramps and landside toe roads will be reconfigured to accommodate the new pumping plant layout.   

Update #2 ·

*** 12/30/20 -  Site visit sign-in sheet posted ***

The work includes relocating Pumping Plant 4 discharge pipes to be raised 10 feet to be above the 200-year water surface elevation and adding a new vault and outfall structure. Additional work includes removal of existing Pumping Plant 4 building and trash rack and reconfiguring the pump station intake and installing a new trash rack. The pump station pad will be raised and have new pumps installed but will not include a new building. A driveway to the new trash rack will also be located adjacent to the Electrical Building, with power provided from the adjacent PG&E lines. Six-foot high chain-link fencing will enclose the Pumping Plant area, with gates installed as shown on the plans. Access ramps and landside toe roads will be reconfigured to accommodate the new pumping plant layout.   

Update #1 ·

The work includes relocating Pumping Plant 4 discharge pipes to be raised 10 feet to be above the 200-year water surface elevation and adding a new vault and outfall structure. Additional work includes removal of existing Pumping Plant 4 building and trash rack and reconfiguring the pump station intake and installing a new trash rack. The pump station pad will be raised and have new pumps installed but will not include a new building. A driveway to the new trash rack will also be located adjacent to the Electrical Building, with power provided from the adjacent PG&E lines. Six-foot high chain-link fencing will enclose the Pumping Plant area, with gates installed as shown on the plans. Access ramps and landside toe roads will be reconfigured to accommodate the new pumping plant layout.   

Attachments

Show all 17

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Natomas Reach D Pumping Plant 4 Award Award Notice
Natomas Reach D Pumping Plant 4 This notice · Latest solicitation Solicitation
Pre-Solicitation Notice Natomas Reach D Pumping Plant 4 Original Special Notice

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity