Pre-Solicitation Notice Natomas Reach D Pumping Plant 4
Closed Special Notice Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- W9123821B0002
- Agency
-
ENDIST Sacramento
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Place of performance
- Sacramento CA 95824 USA
Notice details come from SAM.gov. Updated .
About this opportunity
This Special Notice from the Department of the Army Corps of Engineers Engineering District Sacramento provides advance information regarding a forthcoming solicitation for the Natomas Reach D Pumping Plant 4 project. The notice indicates the Government's intent to issue an Information for Bid seeking a firm-fixed price construction contract with an estimated value between $10 million and $25 million.
The Special Notice outlines plans to relocate the Pumping Plant 4 discharge pipes and raise them above the 200-year water surface elevation. It also details additional work including removing existing structures and equipment, reconfiguring intake and installing new trash racks. Contractors can expect the solicitation to be issued on or around December 10, 2020 via beta.SAM.gov with bids due January 13, 2021. Eligible contractors must self-identify as interested vendors by monitoring the site. The prospective contract action will utilize NAICS code 237990 and product service code Z1NE, with an estimated size standard of $39.5 million. Contractors are advised to regularly check beta.SAM.gov for any updates to the notice or interested vendors list.
Notice text
5 versions
Update #5 · Latest ·
*** UPDATE**
12/16/20 -- scheduled site visit has been postponed and moved to 30 December at 10am PST. The solicitation is forthcoming and will be posted this week.
*** Site visit is CANCELLED for 17 December 2020 at 10:00am PST.
See directions below:
From the Sacramento Downtown area:
Take the CA-16WI-5 N/CA-99N ramp toward Redding Yuba City Merge onto the I-5 N/CA-16 WCA99 N Merge onto CA-99 N via EXIT 525B toward Marysville/Yuba City Take Riego Road exit 311 Turn Left onto Riego Rd. Turn Right onto Garden Highway Turn Right onto Sankey Road About 500 feet Turn left off of Sankey Road and follow the toe road along the levee
*************************************************************************************************************************
Reach D Pumping Plant 4
The Government anticipates issuing an Information for Bid (IFB) with the intent of awarding a Firm-Fixed Price construction contract for W91238-21-B-0002/ Reach D Pumping Plant 4.
Project Description: The work includes relocating Pumping Plant 4 discharge pipes to be raised 10 feet to be above the 200-year water surface elevation and adding a new vault and outfall structure. Additional work includes removal of existing Pumping Plant 4 building and trash rack and reconfiguring the pump station intake and installing a new trash rack. The pump station pad will be raised and have new pumps installed but will not include a new building. A driveway to the new trash rack will also be located adjacent to the Electrical Building, with power provided from the adjacent PG&E lines. Six-foot high chain-link fencing will enclose the Pumping Plant area, with gates installed as shown on the plans. Access ramps and landside toe roads will be reconfigured to accommodate the new pumping plant layout.
In accordance with DFARS 236.204(i) the estimated magnitude of construction is expected to be between $10M and $25M.This prospective contract action will be conducted using NAICS Code is 237990 (Other Heavy and Civil Engineering Construction). The size standard $39,500,000.00. Product Service Code is Z1NE (Maintenance of Water Supply Facilities).
The solicitation will proceed as unrestrictedand is estimated to be issued on or about 10 December 2020 with bids due tentatively on 13 January 2021. The IFB will be issued on the Government Point of Entry known as beta.sam.gov and will establish a firm bid due date/time.
If applicable, the site visit date, time and location will be identified in the solicitation.
BE ADVISED THAT THIS PROJECT MAY BE DELAYED, CANCELLED OR REVISED AT ANY TIME DURING THE PRE-SOLICITATION, SOLICITATION, SELECTION, EVALUATION, NEGOTIATION AND/OR FINAL AWARD PROCESS.
The only INTERESTED VENDORS LISTS (plan-holder's/bidder's list) is available via beta.SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check beta.sam.gov frequently for any changes to the interested vendors list and notice.
Update #4 ·
*** UPDATE**
*** Site visit is scheduled for 17 December 2020 at 10:00am PST. See directions below:
From the Sacramento Downtown area:
Take the CA-16WI-5 N/CA-99N ramp toward Redding Yuba City Merge onto the I-5 N/CA-16 WCA99 N Merge onto CA-99 N via EXIT 525B toward Marysville/Yuba City Take Riego Road exit 311 Turn Left onto Riego Rd. Turn Right onto Garden Highway Turn Right onto Sankey Road About 500 feet Turn left off of Sankey Road and follow the toe road along the levee
**************************************************************************************************************************** Solicitation will be forthcoming. Posted sometime next week.**
Reach D Pumping Plant 4
The Government anticipates issuing an Information for Bid (IFB) with the intent of awarding a Firm-Fixed Price construction contract for W91238-21-B-0002/ Reach D Pumping Plant 4.
Project Description: The work includes relocating Pumping Plant 4 discharge pipes to be raised 10 feet to be above the 200-year water surface elevation and adding a new vault and outfall structure. Additional work includes removal of existing Pumping Plant 4 building and trash rack and reconfiguring the pump station intake and installing a new trash rack. The pump station pad will be raised and have new pumps installed but will not include a new building. A driveway to the new trash rack will also be located adjacent to the Electrical Building, with power provided from the adjacent PG&E lines. Six-foot high chain-link fencing will enclose the Pumping Plant area, with gates installed as shown on the plans. Access ramps and landside toe roads will be reconfigured to accommodate the new pumping plant layout.
In accordance with DFARS 236.204(i) the estimated magnitude of construction is expected to be between $10M and $25M.This prospective contract action will be conducted using NAICS Code is 237990 (Other Heavy and Civil Engineering Construction). The size standard $39,500,000.00. Product Service Code is Z1NE (Maintenance of Water Supply Facilities).
The solicitation will proceed as unrestrictedand is estimated to be issued on or about 10 December 2020 with bids due tentatively on 13 January 2021. The IFB will be issued on the Government Point of Entry known as beta.sam.gov and will establish a firm bid due date/time.
If applicable, the site visit date, time and location will be identified in the solicitation.
BE ADVISED THAT THIS PROJECT MAY BE DELAYED, CANCELLED OR REVISED AT ANY TIME DURING THE PRE-SOLICITATION, SOLICITATION, SELECTION, EVALUATION, NEGOTIATION AND/OR FINAL AWARD PROCESS.
The only INTERESTED VENDORS LISTS (plan-holder's/bidder's list) is available via beta.SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check beta.sam.gov frequently for any changes to the interested vendors list and notice.
Update #3 ·
*** UPDATE**
*** Site visit is scheduled for 17 December 2020. See directions below:
From the Sacramento Downtown area:
Take the CA-16WI-5 N/CA-99N ramp toward Redding Yuba City Merge onto the I-5 N/CA-16 WCA99 N Merge onto CA-99 N via EXIT 525B toward Marysville/Yuba City Take Riego Road exit 311 Turn Left onto Riego Rd. Turn Right onto Garden Highway Turn Right onto Sankey Road About 500 feet Turn left off of Sankey Road and follow the toe road along the levee
**************************************************************************************************************************** Solicitation will be forthcoming. Posted sometime next week.**
Reach D Pumping Plant 4
The Government anticipates issuing an Information for Bid (IFB) with the intent of awarding a Firm-Fixed Price construction contract for W91238-21-B-0002/ Reach D Pumping Plant 4.
Project Description: The work includes relocating Pumping Plant 4 discharge pipes to be raised 10 feet to be above the 200-year water surface elevation and adding a new vault and outfall structure. Additional work includes removal of existing Pumping Plant 4 building and trash rack and reconfiguring the pump station intake and installing a new trash rack. The pump station pad will be raised and have new pumps installed but will not include a new building. A driveway to the new trash rack will also be located adjacent to the Electrical Building, with power provided from the adjacent PG&E lines. Six-foot high chain-link fencing will enclose the Pumping Plant area, with gates installed as shown on the plans. Access ramps and landside toe roads will be reconfigured to accommodate the new pumping plant layout.
In accordance with DFARS 236.204(i) the estimated magnitude of construction is expected to be between $10M and $25M.This prospective contract action will be conducted using NAICS Code is 237990 (Other Heavy and Civil Engineering Construction). The size standard $39,500,000.00. Product Service Code is Z1NE (Maintenance of Water Supply Facilities).
The solicitation will proceed as unrestrictedand is estimated to be issued on or about 10 December 2020 with bids due tentatively on 13 January 2021. The IFB will be issued on the Government Point of Entry known as beta.sam.gov and will establish a firm bid due date/time.
If applicable, the site visit date, time and location will be identified in the solicitation.
BE ADVISED THAT THIS PROJECT MAY BE DELAYED, CANCELLED OR REVISED AT ANY TIME DURING THE PRE-SOLICITATION, SOLICITATION, SELECTION, EVALUATION, NEGOTIATION AND/OR FINAL AWARD PROCESS.
The only INTERESTED VENDORS LISTS (plan-holder's/bidder's list) is available via beta.SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check beta.sam.gov frequently for any changes to the interested vendors list and notice.
Update #2 ·
*** UPDATE**
** Solicitation will be forthcoming. Posted sometime next week.**
** Site visit is scheduled for 17 December 2020. Details will be provided in solicitation**
Reach D Pumping Plant 4
The Government anticipates issuing an Information for Bid (IFB) with the intent of awarding a Firm-Fixed Price construction contract for W91238-21-B-0002/ Reach D Pumping Plant 4.
Project Description: The work includes relocating Pumping Plant 4 discharge pipes to be raised 10 feet to be above the 200-year water surface elevation and adding a new vault and outfall structure. Additional work includes removal of existing Pumping Plant 4 building and trash rack and reconfiguring the pump station intake and installing a new trash rack. The pump station pad will be raised and have new pumps installed but will not include a new building. A driveway to the new trash rack will also be located adjacent to the Electrical Building, with power provided from the adjacent PG&E lines. Six-foot high chain-link fencing will enclose the Pumping Plant area, with gates installed as shown on the plans. Access ramps and landside toe roads will be reconfigured to accommodate the new pumping plant layout.
In accordance with DFARS 236.204(i) the estimated magnitude of construction is expected to be between $10M and $25M.This prospective contract action will be conducted using NAICS Code is 237990 (Other Heavy and Civil Engineering Construction). The size standard $39,500,000.00. Product Service Code is Z1NE (Maintenance of Water Supply Facilities).
The solicitation will proceed as unrestrictedand is estimated to be issued on or about 10 December 2020 with bids due tentatively on 13 January 2021. The IFB will be issued on the Government Point of Entry known as beta.sam.gov and will establish a firm bid due date/time.
If applicable, the site visit date, time and location will be identified in the solicitation.
BE ADVISED THAT THIS PROJECT MAY BE DELAYED, CANCELLED OR REVISED AT ANY TIME DURING THE PRE-SOLICITATION, SOLICITATION, SELECTION, EVALUATION, NEGOTIATION AND/OR FINAL AWARD PROCESS.
The only INTERESTED VENDORS LISTS (plan-holder's/bidder's list) is available via beta.SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check beta.sam.gov frequently for any changes to the interested vendors list and notice.
Update #1 ·
Reach D Pumping Plant 4
The Government anticipates issuing an Information for Bid (IFB) with the intent of awarding a Firm-Fixed Price construction contract for W91238-21-B-0002/ Reach D Pumping Plant 4.
Project Description: The work includes relocating Pumping Plant 4 discharge pipes to be raised 10 feet to be above the 200-year water surface elevation and adding a new vault and outfall structure. Additional work includes removal of existing Pumping Plant 4 building and trash rack and reconfiguring the pump station intake and installing a new trash rack. The pump station pad will be raised and have new pumps installed but will not include a new building. A driveway to the new trash rack will also be located adjacent to the Electrical Building, with power provided from the adjacent PG&E lines. Six-foot high chain-link fencing will enclose the Pumping Plant area, with gates installed as shown on the plans. Access ramps and landside toe roads will be reconfigured to accommodate the new pumping plant layout.
In accordance with DFARS 236.204(i) the estimated magnitude of construction is expected to be between $10M and $25M.This prospective contract action will be conducted using NAICS Code is 237990 (Other Heavy and Civil Engineering Construction). The size standard $39,500,000.00. Product Service Code is Z1NE (Maintenance of Water Supply Facilities).
The solicitation will proceed as unrestrictedand is estimated to be issued on or about 10 December 2020 with bids due tentatively on 13 January 2021. The IFB will be issued on the Government Point of Entry known as beta.sam.gov and will establish a firm bid due date/time.
If applicable, the site visit date, time and location will be identified in the solicitation.
BE ADVISED THAT THIS PROJECT MAY BE DELAYED, CANCELLED OR REVISED AT ANY TIME DURING THE PRE-SOLICITATION, SOLICITATION, SELECTION, EVALUATION, NEGOTIATION AND/OR FINAL AWARD PROCESS.
The only INTERESTED VENDORS LISTS (plan-holder's/bidder's list) is available via beta.SAM.gov. Contractors are responsible for self-identifying as interested vendors and viewing other interested vendors. Contractors should check beta.sam.gov frequently for any changes to the interested vendors list and notice.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Natomas Reach D Pumping Plant 4 | Award Notice | |
| Natomas Reach D Pumping Plant 4 | Solicitation | |
| This notice | Special Notice |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| USACE SPK DB Construction - Natomas NPP Named Pumping Plants - Sacramento, CA | ENDIST Sacramento | No set-aside | |
| $465M SPK small business MATOC for DBB/DB construction | ENDIST Sacramento | Total Small Business | |
| Mississippi River, New Orleans Harbor Cutterhead Dredge No. 2-2025 | ENDIST New Orleans | No set-aside | |
| Mississippi River, New Orleans Harbor Cutterhead Dredge No. 1-2025 | ENDIST New Orleans | No set-aside | |
| New Orleans Harbor and Various Bar Channels Cutterhead Dredge 3-2025 | ENDIST New Orleans | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity