MNA Intake Deck Concrete Beam Rehab
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912EF21B0015
- Agency
- ENDIST Walla Walla US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 238110 Poured Concrete Foundation and Structure Contractors
- PSC
- Z2KA Repair Or Alteration Of Dams
- Place of performance
- Umatilla OR 97882, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks proposals to rehabilitate approximately 48 concrete support beams underneath the intake deck at McNary Lock and Dam located on the Columbia River near Umatilla, Oregon. The U.S. Army Corps of Engineers Walla Walla District is procuring the design and construction of enlarged beam sections utilizing formwork and pumped concrete maintained under positive pressure during curing. Offerors must demonstrate experience on similar projects and the ability to complete all onsite work between June 15 and November 30, 2021. Evaluation will be based on price, technical approach, and past performance. The response deadline is May 7, 2021.
There is no set-aside designation for this procurement. The primary NAICS code is 237990 and PSC code is W912. Eight contractors submitted bids ranging from $2.8 million to $4.8 million in response to solicitation number W912EF21B0015. The apparent low bid of $2.9 million was from Stellar J Corporation to perform the work at McNary Lock and Dam located in both Oregon and Washington, with all onsite activities to be concluded by November 30, 2021 and closeout materials due within 30 days thereafter.
Notice text
7 versions
Update #7 · Latest ·
5/10/2021: Bid opening results from 5/7/2021 Bid opening announement.
5/4/2021: Solicitation Amendment W912EF21B0015-0004 attached with associated updated technical specifications. Please see attached amendment 0004 package for further details.
__________________________________________
4/30/2021: Solicitation Amendment W912EF21B0015-0003 attached with associated updated technical specifications. Please see attached amendment 0003 package for further details.
___________________________________________
4/27/21: solicitation Amendment W912EF21B0015-0002 attached wtih associated revised technical specification and plans. See attached amendment 0002 package for further details.
________________________________________________
4/14/2021: Site visit attendee list from scheduled site visit held on 4/13/2021.
See attached site visit attendee list for further details.
_______________________________________________________________
4/9/2021: Solicitation Amendment W912EF21B0015 attached to clarify date details for scheduling site visit attendance.
See attached amendment for further details.
___________________________________________________________
Solicitation attached W912EF21B0015 with associated technical specifications and drawings.
Scope of Work:
McNary Lock and Dam is located on the Columbia River, near the town of Umatilla, Oregon. The concrete beams are important to the infrastructure of the intake deck as they support the embedded rail system on which the 140-ton Gantry Crane trolleys.
The intake deck is located on the upstream side of the dam, spanning north and south direction. The Washington and Oregon State boundary runs east and west down the center of the dam. The north side of the dam is in Washington; the south side of the dam is in Oregon. The upstream rail is support by concrete support beams located underneath the intake deck.
The scope will include determining the exact amount of concrete and rebar needed to increase the capacity of each support (48 in total) and construct the enlarged beam section using a form and pump methodology where positive pressure is applied and maintained throughout the curing process.
Futher details can be found in the attached solicitaiton package to this notice.
Update #6 ·
5/4/2021: Solicitation Amendment W912EF21B0015-0004 attached with associated updated technical specifications. Please see attached amendment 0004 package for further details.
__________________________________________
4/30/2021: Solicitation Amendment W912EF21B0015-0003 attached with associated updated technical specifications. Please see attached amendment 0003 package for further details.
___________________________________________
4/27/21: solicitation Amendment W912EF21B0015-0002 attached wtih associated revised technical specification and plans. See attached amendment 0002 package for further details.
________________________________________________
4/14/2021: Site visit attendee list from scheduled site visit held on 4/13/2021.
See attached site visit attendee list for further details.
_______________________________________________________________
4/9/2021: Solicitation Amendment W912EF21B0015 attached to clarify date details for scheduling site visit attendance.
See attached amendment for further details.
___________________________________________________________
Solicitation attached W912EF21B0015 with associated technical specifications and drawings.
Scope of Work:
McNary Lock and Dam is located on the Columbia River, near the town of Umatilla, Oregon. The concrete beams are important to the infrastructure of the intake deck as they support the embedded rail system on which the 140-ton Gantry Crane trolleys.
The intake deck is located on the upstream side of the dam, spanning north and south direction. The Washington and Oregon State boundary runs east and west down the center of the dam. The north side of the dam is in Washington; the south side of the dam is in Oregon. The upstream rail is support by concrete support beams located underneath the intake deck.
The scope will include determining the exact amount of concrete and rebar needed to increase the capacity of each support (48 in total) and construct the enlarged beam section using a form and pump methodology where positive pressure is applied and maintained throughout the curing process.
Futher details can be found in the attached solicitaiton package to this notice.
Update #5 ·
4/30/2021: Solicitation Amendment W912EF21B0015-0003 attached with associated updated technical specifications. Please see attached amendment 0003 package for further details.
___________________________________________
4/27/21: solicitation Amendment W912EF21B0015-0002 attached wtih associated revised technical specification and plans. See attached amendment 0002 package for further details.
________________________________________________
4/14/2021: Site visit attendee list from scheduled site visit held on 4/13/2021.
See attached site visit attendee list for further details.
_______________________________________________________________
4/9/2021: Solicitation Amendment W912EF21B0015 attached to clarify date details for scheduling site visit attendance.
See attached amendment for further details.
_________________________________________________________________________________________
Solicitation attached W912EF21B0015 with associated technical specifications and drawings.
Scope of Work:
McNary Lock and Dam is located on the Columbia River, near the town of Umatilla, Oregon. The concrete beams are important to the infrastructure of the intake deck as they support the embedded rail system on which the 140-ton Gantry Crane trolleys.
The intake deck is located on the upstream side of the dam, spanning north and south direction. The Washington and Oregon State boundary runs east and west down the center of the dam. The north side of the dam is in Washington; the south side of the dam is in Oregon. The upstream rail is support by concrete support beams located underneath the intake deck.
The scope will include determining the exact amount of concrete and rebar needed to increase the capacity of each support (48 in total) and construct the enlarged beam section using a form and pump methodology where positive pressure is applied and maintained throughout the curing process.
Futher details can be found in the attached solicitaiton package to this notice.
Update #4 ·
4/27/21: solicitation Amendment W912EF21B0015-0002 attached wtih associated revised technical specification and plans. See attached amendment 0002 package for further details.
________________________________________________
4/14/2021: Site visit attendee list from scheduled site visit held on 4/13/2021.
See attached site visit attendee list for further details.
_______________________________________________________________
4/9/2021: Solicitation Amendment W912EF21B0015 attached to clarify date details for scheduling site visit attendance.
See attached amendment for further details.
_________________________________________________________________________________________
Solicitation attached W912EF21B0015 with associated technical specifications and drawings.
Scope of Work:
McNary Lock and Dam is located on the Columbia River, near the town of Umatilla, Oregon. The concrete beams are important to the infrastructure of the intake deck as they support the embedded rail system on which the 140-ton Gantry Crane trolleys.
The intake deck is located on the upstream side of the dam, spanning north and south direction. The Washington and Oregon State boundary runs east and west down the center of the dam. The north side of the dam is in Washington; the south side of the dam is in Oregon. The upstream rail is support by concrete support beams located underneath the intake deck.
The scope will include determining the exact amount of concrete and rebar needed to increase the capacity of each support (48 in total) and construct the enlarged beam section using a form and pump methodology where positive pressure is applied and maintained throughout the curing process.
Futher details can be found in the attached solicitaiton package to this notice.
Update #3 ·
4/14/2021: Site visit attendee list from scheduled site visit held on 4/13/2021.
See attached site visit attendee list for further details.
_______________________________________________________________
4/9/2021: Solicitation Amendment W912EF21B0015 attached to clarify date details for scheduling site visit attendance.
See attached amendment for further details.
_________________________________________________________________________________________
Solicitation attached W912EF21B0015 with associated technical specifications and drawings.
Scope of Work:
McNary Lock and Dam is located on the Columbia River, near the town of Umatilla, Oregon. The concrete beams are important to the infrastructure of the intake deck as they support the embedded rail system on which the 140-ton Gantry Crane trolleys.
The intake deck is located on the upstream side of the dam, spanning north and south direction. The Washington and Oregon State boundary runs east and west down the center of the dam. The north side of the dam is in Washington; the south side of the dam is in Oregon. The upstream rail is support by concrete support beams located underneath the intake deck.
The scope will include determining the exact amount of concrete and rebar needed to increase the capacity of each support (48 in total) and construct the enlarged beam section using a form and pump methodology where positive pressure is applied and maintained throughout the curing process.
Futher details can be found in the attached solicitaiton package to this notice.
Update #2 ·
4/9/2021: Solicitation Amendment W912EF21B0015 attached to clarify date details for scheduling site visit attendance.
See attached amendment for further details.
_________________________________________________________________________________________
Solicitation attached W912EF21B0015 with associated technical specifications and drawings.
Scope of Work:
McNary Lock and Dam is located on the Columbia River, near the town of Umatilla, Oregon. The concrete beams are important to the infrastructure of the intake deck as they support the embedded rail system on which the 140-ton Gantry Crane trolleys.
The intake deck is located on the upstream side of the dam, spanning north and south direction. The Washington and Oregon State boundary runs east and west down the center of the dam. The north side of the dam is in Washington; the south side of the dam is in Oregon. The upstream rail is support by concrete support beams located underneath the intake deck.
The scope will include determining the exact amount of concrete and rebar needed to increase the capacity of each support (48 in total) and construct the enlarged beam section using a form and pump methodology where positive pressure is applied and maintained throughout the curing process.
Futher details can be found in the attached solicitaiton package to this notice.
Update #1 ·
Solicitation attached W912EF21B0015 with associated technical specifications and drawings.
Scope of Work:
McNary Lock and Dam is located on the Columbia River, near the town of Umatilla, Oregon. The concrete beams are important to the infrastructure of the intake deck as they support the embedded rail system on which the 140-ton Gantry Crane trolleys.
The intake deck is located on the upstream side of the dam, spanning north and south direction. The Washington and Oregon State boundary runs east and west down the center of the dam. The north side of the dam is in Washington; the south side of the dam is in Oregon. The upstream rail is support by concrete support beams located underneath the intake deck.
The scope will include determining the exact amount of concrete and rebar needed to increase the capacity of each support (48 in total) and construct the enlarged beam section using a form and pump methodology where positive pressure is applied and maintained throughout the curing process.
Futher details can be found in the attached solicitaiton package to this notice.
Attachments
| File | Type | Posted |
|---|---|---|
| W912EF21B0015 Bid opening Results 572021.pdf | ||
| W912EF21B0015-0004.pdf | ||
| TechSpec_21B0015_Amend-0004.pdf | ||
| W912EF21B0015-0003 MNA Intake Deck Beam.pdf | ||
| TechSpec_21B0015_Amend-0003.pdf | ||
| W912EF21B0015-0002 -42721.pdf | ||
| TechSpec_21B0015_Amend-0002_27Apr21.pdf | ||
| 21B0015_AMDT00002_Plans.pdf | ||
| MNA-Intake Deck Beam 21B0015 Attendee list.pdf | ||
| W912EF21B0015-0001.pdf | ||
| TechSpec_21B0015_Solicitation Final.pdf | ||
| 21B0015_Plans.pdf | ||
| W912EF21B0015 MNA Intake Deck concrete Beam Rehab .pdf |
Show all 13
Notice history
| Notice | Type | Posted |
|---|---|---|
| MNA Intake Deck Concrete Beam Rehab | Award Notice | |
| MNA Intake Deck Concrete Beam Rehab | Solicitation | |
| MNA Intake Deck Concrete Beam Rehab | Pre-Solicitation | |
| MNA Intake Deck Concrete Beam Rehab | Pre-Solicitation |