About this opportunity

This solicitation seeks design and construction services for the relocation and reconfiguration of an existing mezzanine structure at Joint Base McGuire-Dix-Lakehurst in New Jersey. The Department of the Army Corps of Engineers Engineering Support Center Huntsville is procuring a contractor to disassemble a mezzanine in Johnstown, Pennsylvania, transport it to Building 3351 at the New Jersey base, and reassemble it with 1,257 square feet of open space on the second level and 429 square feet of enclosed office and storage space on the first level. Offerors must complete the project within 180 calendar days of receiving the notice to proceed, and proposals will be evaluated based on technical approach, past performance, and price factors. The deadline for proposals is September 4, 2020.

This opportunity is set aside for small businesses only. The work involves design and construction services covered under NAICS codes 237910 and 237990, with an anticipated award value between $250,000 and $500,000 to be completed within 180 calendar days of the notice to proceed at Joint Base McGuire-Dix-Lakehurst in New Jersey. The solicitation was issued by the Department of the Army Corps of Engineers Engineering Support Center Huntsville.

Notice text

5 versions

Update #5 · Latest ·

SOLICITATION AMENDMENT 04: Extends the RFP due date to NLT 9 September 2020 at 10a.m.; Incoporates a summary of answers to bidder inquiries through Projnet, and Changes the disclosure of magnitude to $250K to $500K.

SOLICITATION AMENDMENT 03: Incorporating a revised Statement of Work dated 17 August 2020 and revised/updated Appendix 8 (As-Builts); revising CLIN titles and description, extending the RFP due date to NLT 4 September 2020 at 1200 (CST), reopening Projnet for Bidder Inquiries until 26 August 2020 at 1600 (CST).

SOLICITATION AMENDMENT 02: Incorporating a revised Statement of Work dated 20 May 2020 and revised/updated Appendix 8 (As-Builts).

SOLICITATION AMENDMENT 01: Incorporating a revised Statement of Work dated 15 May 2020, Appendix 8 (As-Builts), and Projnet Question and Answers.

The objective for this Statement of Work (SOW) is to provide plant, material, labor and equipment necessary for the disassembly, relocation and reassembly of first and second floor components of the existing mezzanine structure. Contractor shall relocate the mezzanine from the existing location Johnstown, PA to new location at ECS 99 (Building 3351 Lexington Ave) located at Joint Base McGuire-Dix-Lakehurst (JBMDL), NJ. This effort includes all the necessary required architectural, structural, mechanical, electrical, and telecommunications components necessary for meeting the mission of the 99th Readiness Division (RD). The mezzanine has approximately 1,257.75 of open sf on the first level and has approx. 429 sf of enclosed space on the second level; the Second level includes office and supply/storage area. The mezzanine will be reconfigured with the 1257.75 open sf on the second level, and the 429 sf of enclosed space (including the office and supply/storage area) shall be on the first level.

Update #4 ·

SOLICITATION AMENDMENT 03: Incorporating a revised Statement of Work dated 17 August 2020 and revised/updated Appendix 8 (As-Builts); revising CLIN titles and description, extending the RFP due date to NLT 4 September 2020 at 1200 (CST), reopening Projnet for Bidder Inquiries until 26 August 2020 at 1600 (CST).

SOLICITATION AMENDMENT 02: Incorporating a revised Statement of Work dated 20 May 2020 and revised/updated Appendix 8 (As-Builts).

SOLICITATION AMENDMENT 01: Incorporating a revised Statement of Work dated 15 May 2020, Appendix 8 (As-Builts), and Projnet Question and Answers.

The objective for this Statement of Work (SOW) is to provide plant, material, labor and equipment necessary for the disassembly, relocation and reassembly of first and second floor components of the existing mezzanine structure. Contractor shall relocate the mezzanine from the existing location Johnstown, PA to new location at ECS 99 (Building 3351 Lexington Ave) located at Joint Base McGuire-Dix-Lakehurst (JBMDL), NJ. This effort includes all the necessary required architectural, structural, mechanical, electrical, and telecommunications components necessary for meeting the mission of the 99th Readiness Division (RD). The mezzanine has approximately 1,257.75 of open sf on the first level and has approx. 429 sf of enclosed space on the second level; the Second level includes office and supply/storage area. The mezzanine will be reconfigured with the 1257.75 open sf on the second level, and the 429 sf of enclosed space (including the office and supply/storage area) shall be on the first level.

Update #3 ·

SOLICITATION AMENDMENT 02: Incorporating a revised Statement of Work dated 20 May 2020 and revised/updated Appendix 8 (As-Builts).

SOLICITATION AMENDMENT 01: Incorporating a revised Statement of Work dated 15 May 2020, Appendix 8 (As-Builts), and Projnet Question and Answers.

The objective for this Statement of Work (SOW) is to provide plant, material, labor and equipment necessary for the disassembly, relocation and reassembly of first and second floor components of the existing mezzanine structure. Contractor shall relocate the mezzanine from the existing location Johnstown, PA to new location at ECS 99 (Building 3351 Lexington Ave) located at Joint Base McGuire-Dix-Lakehurst (JBMDL), NJ. This effort includes all the necessary required architectural, structural, mechanical, electrical, and telecommunications components necessary for meeting the mission of the 99th Readiness Division (RD). The mezzanine has approximately 1,257.75 of open sf on the first level and has approx. 429 sf of enclosed space on the second level; the Second level includes office and supply/storage area. The mezzanine will be reconfigured with the 1257.75 open sf on the second level, and the 429 sf of enclosed space (including the office and supply/storage area) shall be on the first level.

Update #2 ·

SOLICITATION AMENDMENT 01: Incorporating a revised Statement of Work dated 15 May 2020, Appendix 8 (As-Builts), and Projnet Question and Answers.

The objective for this Statement of Work (SOW) is to provide plant, material, labor and equipment necessary for the disassembly, relocation and reassembly of first and second floor components of the existing mezzanine structure. Contractor shall relocate the mezzanine from the existing location Johnstown, PA to new location at ECS 99 (Building 3351 Lexington Ave) located at Joint Base McGuire-Dix-Lakehurst (JBMDL), NJ. This effort includes all the necessary required architectural, structural, mechanical, electrical, and telecommunications components necessary for meeting the mission of the 99th Readiness Division (RD). The mezzanine has approximately 1,257.75 of open sf on the first level and has approx. 429 sf of enclosed space on the second level; the Second level includes office and supply/storage area. The mezzanine will be reconfigured with the 1257.75 open sf on the second level, and the 429 sf of enclosed space (including the office and supply/storage area) shall be on the first level.

Update #1 ·

The objective for this Statement of Work (SOW) is to provide plant, material, labor and equipment necessary for the disassembly, relocation and reassembly of first and second floor components of the existing mezzanine structure. Contractor shall relocate the mezzanine from the existing location Johnstown, PA to new location at ECS 99 (Building 3351 Lexington Ave) located at Joint Base McGuire-Dix-Lakehurst (JBMDL), NJ. This effort includes all the necessary required architectural, structural, mechanical, electrical, and telecommunications components necessary for meeting the mission of the 99th Readiness Division (RD). The mezzanine has approximately 1,257.75 of open sf on the first level and has approx. 429 sf of enclosed space on the second level; the Second level includes office and supply/storage area. The mezzanine will be reconfigured with the 1257.75 open sf on the second level, and the 429 sf of enclosed space (including the office and supply/storage area) shall be on the first level.

Files

Similar open opportunities

Opportunity Agency Set-aside Responses due
Design/Build Maintenance and Repair Army Reserve (MRAR), Area Maintenance Support Activity (AMSA) 21, JBMDL, NJ Joint Base MDL, New Jersey, United States · NAICS 236220 ENDIST Louisville Total Small Business
Joint Base Lewis McChord (JBLM) Multi Domain Task Force (MDTF) Buildings (BLDGs) 3223 and 3224 Joint Base Lewis McChord, Washington, United States · NAICS 236220 ENDIST Seattle Total Small Business
Design-Build Maintenance and Repair Army Reserve (MRAR) of Equipment Concentration Site (ECS), B-56767, at North Fort Hood, TX Bldg. 56767 Equipment Concentration Site (ECS) #6428th St. and Park Ave.North Fort Hood, TX Gatesville, Texas 76528, United States · NAICS 236220 ENDIST Louisville Total Small Business
Joint Base Lewis McChord (JBLM) Multi Domain Task Force (MDTF) Buildings (BLDGs) 3221 and 3222 Joint Base Lewis McChord, Washington, United States · NAICS 236220 ENDIST Seattle Total Small Business
Instrument Landing Structure (ILS) Fort Polk, Louisiana, United States · NAICS 238910 ENDIST Fort Worth Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors