About this opportunity

The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9 is soliciting a Request for Quote (RFQ) for Life Safety Statement of Conditions Inspection Services under NAICS code 541350 (Building Inspection Services). The contractor must conduct a comprehensive 100% survey of fire and smoke barrier walls above accessible ceilings at two Lexington VA Health Care System campuses, identify deviations from NFPA 101 and NFPA 99 standards, and deliver detailed documentation including redlined drawings and deviation lists. Key qualifications require the contractor to have completed at least ten Life Safety Assessments at medical facilities with a minimum of two at other VA facilities, with the team lead holding a Bachelor of Science in Engineering and Professional Fire Protection Engineer certification. The contractor must provide all deliverables in both electronic format on CD and six hard-copy binders organized by campus and functional use, along with 12 hours of post-delivery consultation support. The questions deadline was February 4, 2026, with quotes due by February 9, 2026, at 12:00 PM EST, and Amendment 0002 issued on February 4, 2026, clarified that work must be completed up to 90 days after the contract award date, with site visits occurring at least 60 days from award.

This solicitation is designated as a 100% set-aside for Service-Disabled Veteran-Owned Small Business (SDVOSB) and Veteran-Owned Small Business (VOSB) concerns verified in the SBA certification database. The contract is valued at $11.5 million as a firm-fixed-price award with FOB Destination terms and Net 15 payment discounts, requiring full payment upon completion and acceptance with no partial payments permitted. The scope covers two campuses approximately five miles apart: Troy Bowling Campus (527,186 square feet, including Buildings 1 and 1a with a new Mental Health Suite under construction) and Franklin R. Sousley Campus (465,575 square feet, encompassing 15 buildings) for a combined total of 992,761 square feet. The contract period runs from March 1, 2026, through June 30, 2026, with performance location at both Lexington, Kentucky VA medical center campuses. All contractor personnel must complete VA security orientation and obtain picture badges prior to site work, and work shall not occur on federal holidays unless directed by the contracting office.

Notice text

3 versions

Update #3 · Latest ·

Questions & Answers

Can we have more detail and respectfully request clarification regarding the project schedule, as multiple sections appear to contain differing completion requirements. Section B.2.A.4 (pg. 5) states completion by March 30, 2026, or within 30 days of the site visit, whichever comes first. Site visits shall occur at least 60 days from Award Date and the Final Product shall be completed 90 days after Award Date.

Section F (pg. 8) states completion within 12 weeks of contract issuance or June 30, 2026, whichever comes first. See response from Question 1

Section B.3 (pg. 10) repeats the 12 weeks of contract issuance or June 30, 2026, whichever comes first requirement. See response from Question 1

Amendment Section F (pg. 6) also states within 12 weeks of contract issuance or June 30, 2026, whichever comes first. See response from Question 1

Can you please clarify which schedule requirement governs? Additionally, please confirm whether the use of whichever comes first is intentional, as a late contract award could result in an extremely compressed or impractical performance period. Prefer to schedule a site visit within 2 months (60 days) from Award Date, and have the final product about a month out from that (90 days).

In Amendment 0001 Section A. General Information #4 Performance Period states "The contractor shall complete the work required under this SOW by March 30, 2026, or within 30 days of completion of site survey, whichever comes first. Work at the government site shall not take place on Federal holidays unless directed by the Contracting Office." However, the original solicitation states that the PoP is 03/01/2026-06/30/2026. Please confirm what the PoP is for this effort. Period of Performance (PoP) date is subject to change, pending award date. The requirement shall be completed up to 90 days after the Award Date.

Do any of the buildings have identified deviations without a current corrective action that the contractor will be required to take over before arriving on site? No, any deviations or deficiencies that are found should be documented, but corrective actions will be addressed by VA staff and/or a separate contract if appropriate.

Is the contractor permitted to split the effort into several site visits? Or should the contractor perform the inspection consecutively? Consecutive would be ideal, but we would allow for splitting up the work if needed depending on time constraints.

Please confirm the requirement for 10 references of similar projects. See Amendment 0001 SOW changes Section J.

Is the contract able to be modified for partial payments based upon an agreed payment schedule? This contract shall NOT provide partial payments. This contract will provide payment upon completion and acceptance of Service.

END OF AMENDMENT

Update #2 ·

5

STATEMENT OF WORK

GENERAL INFORMATION

1. Title of Project: Life Safety Statement of Conditions and Above Ceiling Life Safety Assessment

2. Scope of Work: The Lexington VA Health Care System (LVAHCS) requires a complete Life Safety Statement of Conditions (SOC) Assessment for its Troy Bowling Campus (Cooper) and Franklin R. Sousley (Leestown) Campus. The contractor will conduct and document the SOC assessment and recommend any subsequent recommendations for improvements (formerly called PFI) of the SOC. Conduct a complete (100%) survey of fire and smoke barrier walls above the accessible ceilings. (As an infection control precaution, do not survey above ceilings in patient-occupied rooms). On redlined drawings, denote wall deficiencies noted for future repair. All deliverables and bid items will be for the following complete buildings:

Troy Bowling Campus (527,186 ft2)

1101 Veterans Drive

Lexington, Kentucky 40502

Buildings: 1 and 1a (Tower and Main Buildings)

Tower Existing 329,531 Ft2

Main Building Existing 197,655 Ft2

Buildings Currently Under Construction: First floor of Tower Building for New Mental Health Suite (approx. 12,500 Ft2 occupancy will change from Ambulatory Health Care to Mixed, which will include a locked down mental health suite)

Franklin R. Sousley Campus (465,575 ft2)

2250 Leestown Road

Lexington, Kentucky 40511

Buildings: 1, 2, 3, 4, 16, 17, 25, 27, 28, 29, 201, 202, 204, 205, and 206

Bldg 1 Existing 58,929 Ft2

Bldg 2 Existing 25,398 Ft2

Bldg 3 Existing 45,665 Ft2

Bldg 4 Existing 8,989 Ft2

Bldg 16 Existing 43,872 Ft2

Bldg 17 Existing 40,013 Ft2

Bldg 25 Existing 50,347 Ft2

Bldg 27 Existing 47,228 Ft2

Bldg. 28 Existing 33,239 ft2

Bldg. 29 Existing 50,857 Ft2

Bldg. 201 Existing 11,124 ft2

Bldg. 202 Existing 11,154 ft2

Bldg. 206 Fisher House Existing 13,260 ft2

Bldg 204 Existing 12,500 ft2

Bldg 205 Existing 13,000 ft2

The Campuses are approximately five (5) miles apart.

3. Background: VA Directive 7701 COMPREHENSIVE OCCUPATIONAL SAFETY AND HEALTH PROGRAM states that the requirements of The Joint Commission (TJC) will be integrated into VHA health care facilities. VISN 9 also directs that Network Medical Centers will ensure and support the requirements and standards of the Joint Commission and the Long Term Care Institute, Inc. (LTCI).

The Joint Commission Statement of Conditions (SOC) is a proactive electronic document developed by the Joint Commission to help an organization complete a critical self-assessment of its current level of compliance and describe how to resolve any Life Safety Code (LSC) deficiencies. The Statement of Conditions is a living , ongoing management tool that should be used in a management process that continually identifies, assesses, and resolves LSC deficiencies.

The contractor will conduct a thorough Life Safety Assessment of each building requiring an SOC. Failure to completely identify all LSC deficiency could result in a deficiency. The SOC process encourages the owner to make known all LSC deficiencies. The SOC is part of the accreditation process for the LVAHCS. The last SOC was completed and entered the database in 2023. The facility was accredited following their June 2025 survey.

The Community Living Center (Buildings 27, 201, 202, 204, and 205) on the Sousley Campus is also inspected for Life Safety compliance by the Long Term Care Institute, Inc. (LTCI) who provides third party accreditation focusing on long term care quality and performance improvement, compliance program development, and review in long term care, hospice and other residential care settings. The LVAHCS had a recently active construction project for a new Community Living Center, Buildings 204 and 205, with activation in September 2025. The new/currently under construction Community Living Center is not in the scope of this contract, but assistance in complying with the LTCI life safety requirements is within scope.

4. Performance Period: The contractor shall complete the work required under this SOW by March 30, 2026, or within 30 days of completion of site survey, whichever comes first. Work at the government site shall not take place on Federal holidays unless directed by the Contracting Officer.

5. Type of Contract: Firm fixed price.

B. CONTRACT AWARD MEETING

The contractor meeting will occur immediately upon arrival at site. The contractor will plan for and coordinate human and equipment access needs with the Contract Officer Repersentive (COR) and Chief Engineering/Designated Representative. Meeting will identify what equipment, facilities, and manufacturer documentation is required.

C. GENERAL REQUIREMENTS

1. Contractor will coordinate visit(s) with COR to schedule physical visits and obtain necessary accesses to complete assessment.

2. Contractor will plan to walk approximately 465,575 ft2 at Sousley Campus and 527,186 ft2 at Bowling Campus. Existing square footage broken down per building from the VA Capital Asset Inventory is found in the A. GENERAL INFORMATION section.

3. Contractor will coordinate to attend contractor safety & security orientation on a Monday or Tuesday morning at 8:30 AM to obtain a picture badge to work on the property. Two forms of government issued ID is required for badging. The contractor will provide a list of employees working on the contract one week in advance to the COR. Orientation packet will need to be completed in advance. Contractor must wear a VA issued picture badge when working at the LVAHCS.

4. Contractor will identify what documentation is required prior to arrival, throughout the visit and if any documentation will leave the property. All information will be communicated to the COR help facilitate the requirements of the contract.

5. Contractor will provide computer hardware and software, assessment tools and references. Contractor will also provide any necessary personal protective equipment (i.e. hard hat, safety glasses, etc.)

6. Contractor will be working in an operating 24/7 medical environment and must continually consider access, privacy, and staff care missions while conducting physical assessment.

7. Contractor will coordinate any afterhours physical assessment work 48 hours prior to the start of that work.

8. Contractor staff must wear a picture badge when working on LVAHCS property. The badge must be turned in to the COR at the conclusion of the project.

9. Contractor will have access to historical drawings and specifications of all buildings, as available. These drawings and specifications can be copied for reference during the physical assessment. The Contractor will identify what drawings or specifications are required initially and as the project progresses.

10. Life Safety SOC Assessment will utilize the most current editions of NFPA 101, Life Safety Code and NFPA 99 Healthcare (per TJC and VA Mandate).

11. Above Ceiling 100% Fire and Smoke Barrier Wall Inspection with no above ceiling inspections occurring in COVID-19 rooms.

D. SPECIFIC MANDATORY TASKS AND ASSOCIATED DELIVERABLES

Description of Tasks and Associated Deliverables:

Task (A): Deviations from NFPA Life Safety Code.

Deliverable (1): Deviations will be identified and documented to initiate work orders and related Plan for Improvement entries on the e-SOC.

Deliverable (2): Deviations will provide redlined floor plans of deficiencies and, walls and cross corridors to be decommissioned to assist in location/identification for corrective action.

Deliverable (3): Provide two desk copies (3-ring binder) of both deviation list and redlined floor plans.

Task (B): Minor deficiency list.

Deliverable (4): Provide separate document identifying minor deficiencies that need corrected.

Task (C): Consultation support.

Deliverable (5): Provide consultation support to COR/Engineering staff in correctly responding to deficiencies. Follow-up technical support by telephone/electronic mail to LVAHCS staff on the current Statement of Condition or other fire related issues leading up to the next Joint Commission survey for a total of 12 hours anticipating an average of one hour per month.

Deliverable (6): Review existing e-SOC and assist in update and recommend data input, as required.

Deliverable (7): Provide recommendations on how to correct any non-compliant items that are not correctable by simple, straight forward methods.

Deliverable (8): Provide an exit conference after all surveys are completed with LVAHCS, Engineering Service (Safety, Projects, and Operations) to discuss findings and trends for a maximum of two hours.

Task (D): Final Document

Deliverable (9): Provide an electronic copy (in a CD format, the LVAHCS does not allow the use of thumb drives) of the final documents and annotated drawings in both PDF and Automated Computer-aided Design files. The floor plan drawings will show the current room layout, fire walls, fire doors, smoke barrier walls, smoke compartment names or designations and occupancy classification for each floor. Identify suites, hazardous rooms and note any special life safety features.

Deliverable (10): Provide six hard copies in a 3-ring binder (two binders will contain both Bowling and Sousley Campuses, two binders will contain only Bowling Campus and two binders will contain only Sousley Campus). The six copies shall be labeled as follows:

Master Copy - Bowling and Franklin R. Sousley Campuses

Projects Copy - Bowling and Franklin R. Sousley Campuses

Bowling M&R Shop Copy Bowling Campus

Bowling M&R General Foremen Copy Bowling Campus

Sousley M&R Shop Copy Sousley Campus

Sousley M&R General Foremen Copy Sousley Campus

Task (E): Fire and Smoke Barrier Wall Inspection

Deliverable (11): Small scale floor plan drawings showing the current room layout, fire walls, fire doors, smoke barrier walls, smoke compartment names or designations and classification for each floor. Identify any location where penetrations are not sealed correctly with intumescent fire stop. On the drawings the non-compliant penetrations shall be designated by utility type (electrical, plumbing, HVAC duct, data cabling, etc.).

Deliverable (12): Provide a narrative description and photographs of the of the non-compliant penetrations. The narrative description should break down the scope of the non-compliance by building and penetration type. The narrative will assist in the development of a bid document for a penetrations repair project.

SCHEDULE FOR DELIVERABLES

Contractor will provide deliverables to COR within 12 weeks of contract issue date or June 30, 2026, whichever comes first.

G. PROPOSAL REQUIRMENTS

1. Project Schedule

2. Draft Documentation Submittal including inspection methodology

3. Lead Surveyor Qualifications and Team Member Qualifications including education, licenses/certifications and work experience.

4. Contractor shall provide past performance references to validate satisfactory performance in similar requirements as outlined in the scope of work.

H. CHANGES TO STATEMENT OF WORK

Any changes to this SOW shall be authorized and approved only through written correspondence from the Contracting Officer. A copy of each change will be kept in a project folder along with all other products of the project. Costs incurred by the contractor through the actions of parties other than the Contracting Officer shall be borne by the contractor.

I. GOVERNMENT RESPONSIBILITIES

1. COR will coordinate to provide a CD containing the most current electronic drawing files (in AutoCAD) and current fire and smoke barrier wall arrangements for review and re-plotting prior to site survey.

2. COR will coordinate key access for the team to areas identified by the Contractor.

3. COR will coordinate a work area for the Contractor while they are on site. Contractor will notify COR one week prior to arrival of the number of chairs, tables, etc required.

4. COR will coordinate for ladder(s) based on Contractor s requests.

5. COR will coordinate final comment response within three-weeks of draft documentation receipt from contractor.

J. CONTRACTOR EXPERIENCE REQUIREMENTS

Contractor s assessment team will have experience completing ten or more Life Safety Assessments at medical facilities of which 2 must be from VA Medical Facilities. The team will have the following minimum qualifications:

1.Team Lead Qualification:

Bachelor of Science Degree in Engineering who is a Registered Fire Protection Engineer or Bachelor of Science in Fire Protection Engineering

2. Strong knowledge of the requirements of the Life Safety Code especially NFPA 99, NFPA 101 and LTCI.

3. Strong knowledge of building structure as it relates to healthcare facilities. Contractor shall provide past performance references to validate satisfactory performance in similar requirements as outlined in the scope of work.

4. Experience in construction / remodeling projects to understand impacts to existing structures.

5. Experience working with TJC requirements and TJC e-SOC database.

6. Working understanding of variances, equivalencies, and exceptions to make appropriate recommendations.

K. CONFIDENTIALITY AND NONDISCLOSURE

It is agreed that:

1. The preliminary and final deliverables and all associated working papers, application source code, and other material deemed relevant by VA which the contractor generated in the performance of this task order are the exclusive property of the U.S. Government and shall be submitted to the Contracting Officer at the conclusion of the task order.

2. The Contracting Officer will be the sole authorized official to release verbally or in writing, any data, the draft deliverables, the final deliverables, or any other written or printed materials pertaining to this task order. No information shall be released by the contractor. Any request for information relating to this task order presented to the contractor shall be submitted to the Contracting Officer for response.

3. Press releases, marketing material or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the Contracting Officer.

L. CONTRACTOR PERSONNEL SECURITY REQUIREMENTS

No contractor access to VA computer systems required.

Security clause is not indicated based upon Appendix A of VA Handbook 6500.6

Update #1 ·

END OF SOLICITATION

Files

File Type Posted
36C24926Q0091 0002.docx DOCX document
36C24926Q0091 0001.docx DOCX document
36C24926Q0091_1.docx DOCX document

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
H342--RFQ Life Safety Statement of Conditions Inspection Services Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Life Safety Drawings San Diego, California 92161, United States · NAICS 541340 Veterans Integrated Service Network 22 Service-Disabled Veteran-Owned Small Business
CTX Life Safety Assessment and Fire Damper Inspection Temple, Texas 76504, United States · NAICS 561621 Veterans Integrated Service Network 17 Service-Disabled Veteran-Owned Small Business
H112--Annual/Sem-i annual fire smoke inspections and auto door services l EKH Kansas 66048, United States · NAICS 541350 Veterans Integrated Service Network 15 Total Small Business
NTX Elevator Inspection Bonham, Texas 75418, United States · NAICS 541350 Veterans Integrated Service Network 17 Service-Disabled Veteran-Owned Small Business
H361--LEX Triannual Energy Study and ARC Flash Testing Department of Veterans Affairs Lexington, KY Bowling & Sousley Divisions, Lexington, Kentucky 40511, United States · NAICS 238210 Veterans Integrated Service Network 9 Service-Disabled Veteran-Owned Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors