GAOA HMF Historic Iargo Springs Stair and Boardwalk Renovation

Cancelled Solicitation Posted

Solicitation number
12445524R0003
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Notice details come from SAM.gov. Updated .

About this opportunity

This federal solicitation is seeking fixed-price construction services for renovations at the Iargo Springs Interpretive Site located in Iosco County, Michigan. The work includes removing and replacing existing vault toilet buildings, an information kiosk, an upper observation deck, an existing wood stair, and select areas of a lower boardwalk. New elevated boardwalk loops and at-grade pathways will also be constructed. The solicitation is issued by the USDA Forest Service, and offerors must submit technical and price proposals by February 13, 2024 addressing factors such as past performance, experience, technical approach, key personnel, and schedule.

The solicitation is set aside for small businesses. The period of performance is through September 27, 2024, with all clearing and tree removal required to be completed by March 29, 2024. The project location is in Iosco County, Michigan near Cooke Dam Pond. The solicitation number is 12445524R0003, and the budget range is not provided.

Notice text

5 versions

Update #5 · Latest ·

AMENDMENT 0003 incorporates Questions and Answers as of 2/29/2024. No extension.

AMENDMENT 0002 extended due date. Now closes 3/7/2024 by 2 pm Eastern also changed performance period and adds groud work restrictions

Q&A posted as of 2/15/2024

AMENDMENT 0001 extended due date. Now closes 2/22/2024 by 2 pm Eastern

This project consists of site improvements to the Iargo Springs Interpretive Site. The existing vault toilet buildings will be removed and replaced. The existing information kiosk will be removed and replaced with new interpretive signage panels. The existing wood stair, from the upper parking area to the lower boardwalk, will be removed and replaced. The upper observation overlook decking will be removed and replaced. Select areas of the lower boardwalk will also be removed and replaced with at grade pathways, and new elevated boardwalk loops will be constructed across Cooke Dam Pond.

The period of performance of this project is through September 27, 2024.

UPDATED via Amendment 0001: All clearing and associated tree removal items must be completed before March 29, 2024.or after July 15, 2024

Project is located in Iosco County, Michigan.

Driving directions are as follows: From the Huron Shores Ranger Station, travel southeast on south Cedar Street for a few hundred feet. Turn left onto F41 and continue northwest for 3.1 miles. Turn left onto Rea Road, and then turn right after 3.1 miles, where Rea Road turns into Bissonette Road to continue on Rea Road for another 1.8 miles. Turn right onto East River Road, and continue west for 12.2 miles to reach the parking lot for Iargo Springs, on the north side of River Road, adjacent to Cooke Dam Pond.

GPS 44.44218755762312, -83.67407977781525

Update #4 ·

AMENDMENT 0002 extended due date. Now closes 3/7/2024 by 2 pm Eastern also changed performance period and adds groud work restrictions

Q&A posted as of 2/15/2024

AMENDMENT 0001 extended due date. Now closes 2/22/2024 by 2 pm Eastern

This project consists of site improvements to the Iargo Springs Interpretive Site. The existing vault toilet buildings will be removed and replaced. The existing information kiosk will be removed and replaced with new interpretive signage panels. The existing wood stair, from the upper parking area to the lower boardwalk, will be removed and replaced. The upper observation overlook decking will be removed and replaced. Select areas of the lower boardwalk will also be removed and replaced with at grade pathways, and new elevated boardwalk loops will be constructed across Cooke Dam Pond.

The period of performance of this project is through September 27, 2024.

UPDATED via Amendment 0001: All clearing and associated tree removal items must be completed before March 29, 2024.or after July 15, 2024

Project is located in Iosco County, Michigan.

Driving directions are as follows: From the Huron Shores Ranger Station, travel southeast on south Cedar Street for a few hundred feet. Turn left onto F41 and continue northwest for 3.1 miles. Turn left onto Rea Road, and then turn right after 3.1 miles, where Rea Road turns into Bissonette Road to continue on Rea Road for another 1.8 miles. Turn right onto East River Road, and continue west for 12.2 miles to reach the parking lot for Iargo Springs, on the north side of River Road, adjacent to Cooke Dam Pond.

GPS 44.44218755762312, -83.67407977781525

Update #3 ·

Q&A posted as of 2/15/2024

AMENDMENT 0001 extended due date. Now closes 2/22/2024 by 2 pm Eastern

This project consists of site improvements to the Iargo Springs Interpretive Site. The existing vault toilet buildings will be removed and replaced. The existing information kiosk will be removed and replaced with new interpretive signage panels. The existing wood stair, from the upper parking area to the lower boardwalk, will be removed and replaced. The upper observation overlook decking will be removed and replaced. Select areas of the lower boardwalk will also be removed and replaced with at grade pathways, and new elevated boardwalk loops will be constructed across Cooke Dam Pond.

The period of performance of this project is through September 27, 2024.

UPDATED via Amendment 0001: All clearing and associated tree removal items must be completed before March 29, 2024.or after July 15, 2024

Project is located in Iosco County, Michigan.

Driving directions are as follows: From the Huron Shores Ranger Station, travel southeast on south Cedar Street for a few hundred feet. Turn left onto F41 and continue northwest for 3.1 miles. Turn left onto Rea Road, and then turn right after 3.1 miles, where Rea Road turns into Bissonette Road to continue on Rea Road for another 1.8 miles. Turn right onto East River Road, and continue west for 12.2 miles to reach the parking lot for Iargo Springs, on the north side of River Road, adjacent to Cooke Dam Pond.

GPS 44.44218755762312, -83.67407977781525

Update #2 ·

AMENDMENT 0001 extended due date. Now closes 2/22/2024 by 2 pm Eastern

This project consists of site improvements to the Iargo Springs Interpretive Site. The existing vault toilet buildings will be removed and replaced. The existing information kiosk will be removed and replaced with new interpretive signage panels. The existing wood stair, from the upper parking area to the lower boardwalk, will be removed and replaced. The upper observation overlook decking will be removed and replaced. Select areas of the lower boardwalk will also be removed and replaced with at grade pathways, and new elevated boardwalk loops will be constructed across Cooke Dam Pond.

The period of performance of this project is through September 27, 2024.

UPDATED via Amendment 0001: All clearing and associated tree removal items must be completed before March 29, 2024.or after July 15, 2024

Project is located in Iosco County, Michigan.

Driving directions are as follows: From the Huron Shores Ranger Station, travel southeast on south Cedar Street for a few hundred feet. Turn left onto F41 and continue northwest for 3.1 miles. Turn left onto Rea Road, and then turn right after 3.1 miles, where Rea Road turns into Bissonette Road to continue on Rea Road for another 1.8 miles. Turn right onto East River Road, and continue west for 12.2 miles to reach the parking lot for Iargo Springs, on the north side of River Road, adjacent to Cooke Dam Pond.

GPS 44.44218755762312, -83.67407977781525

Update #1 ·

This project consists of site improvements to the Iargo Springs Interpretive Site. The existing vault toilet buildings will be removed and replaced. The existing information kiosk will be removed and replaced with new interpretive signage panels. The existing wood stair, from the upper parking area to the lower boardwalk, will be removed and replaced. The upper observation overlook decking will be removed and replaced. Select areas of the lower boardwalk will also be removed and replaced with at grade pathways, and new elevated boardwalk loops will be constructed across Cooke Dam Pond.

The period of performance of this project is through September 27, 2024.

All clearing and associated tree removal items must be completed by March 29, 2024.

Project is located in Iosco County, Michigan.

Driving directions are as follows: From the Huron Shores Ranger Station, travel southeast on south Cedar Street for a few hundred feet. Turn left onto F41 and continue northwest for 3.1 miles. Turn left onto Rea Road, and then turn right after 3.1 miles, where Rea Road turns into Bissonette Road to continue on Rea Road for another 1.8 miles. Turn right onto East River Road, and continue west for 12.2 miles to reach the parking lot for Iargo Springs, on the north side of River Road, adjacent to Cooke Dam Pond.

GPS 44.44218755762312, -83.67407977781525

Files

Show all 14

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
GAOA HMF Historic Iargo Springs Stair and Boardwalk Renovation Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Request for Proposal Effigy Mounds National Monument - EFMO 224159/318539 NAICS 236220 — No set-aside
GAOA Pine Creek Vault Toilet HTNF Sparks, Nevada 89431, United States · NAICS 237990 Forest Service Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors