This document summarizes a federal solicitation for renovations to the Iargo Springs Interpretive Site. The project consists of replacing existing vault toilets and an information kiosk with new interpretive signage. It also involves removing and replacing an existing wood stair, observation decking, and sections of a boardwalk. New elevated boardwalk loops will be constructed across Cooke Dam Pond. All clearing and tree removal must be completed by March 29, 2024 and the overall period of performance extends through September 27, 2024. The solicitation was issued by the US Department of Agriculture Forest Service for site improvements located in Iosco County, Michigan.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12445524R0003 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
540B
OSCODA MI 48750-1595
5761 N SKEEL
HURON SHORES RANGER STATION
USDA FOREST SERVICE
ATLANTA GA 30309-2449
STE 876S
1720 PEACHTREE ST NW
USDA-FS CSA EAST 13
03/01/20240003
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
01/12/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
This amendment incorporates Questions and Answers as of 2/29/2024. The solicitation is not extended an is still due 3/7/2024 at 1400 Eastern.
Period of Performance: 11/01/2024 to 08/01/2025
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
DEBRA K. BRINN
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
P a g e | 2
12445524R0003 Historic Iargo Springs Stair and Boardwalk Renovation
Questions and Answers February 29, 2024
1. Question:
Would the US Forest Service accept FRP (Fiber Reinforced Polymer) as an alternative in the Iargo Springs design and supply?
Answer: No. The Forest Service wants the materials as specified in the contract documents.
2. Question:
Is there any planned access for the bottom portion of the work? What was the previous access that was used to build the existing stairs and boardwalk system, and if there are any access requirements for this current project.
Answer: The Contractor can decide the best access alternative for the construction. The Forest Service has no pre-determined plan. Access from the river is an option. We have found documentation that a tramway was used to move material down the slope during the original construction. It was comprised of two steel rails with a cable driven by an electric motor. It was located on the old slide that is between the two main springs.
3. Question:
There is wood cribbing on top of helical foundations that would then support the stair structure, there would be potential cost savings to go full steel in lieu of the wood frame.
Answer: The Forest Service wants the wood posts in the locations as shown on the plan. Otherwise, use the boardwalk pier details.
4. Question:
We also noticed that there is a lot of debris in the water where the proposed new section of the boardwalk goes. Would this have to be removed by the contractor or will it be removed prior to the start of the contract?
Answer: It is presumed that the debris observed during the site visit occurred naturally. It is the Contractor's responsibility to clear the site as required to perform the work.
5. Question:
There is a section of the boardwalk that was broken by a falling tree. Would that be fixed prior to our work or is that something that would be added?
Answer: The recent damage to the boardwalk caused by a fallen tree will be repaired by the Forest Service. The previously identified damaged section in the solicitation documents is the only portion included in the Contract.
6. Question:
Will this project be awarded quick enough to be able to get the clearing completed by March 29?
P a g e | 3
Answer: The Forest Service intends to award the project as soon as possible. However, that may not be before March 29. The restriction in the specifications is due to the fungus associated with Oak Wilt. No oak trees may be cut between April 1 and July 15. The Forest Service is willing to work with the Contractor on a case-by-case basis regarding other clearing needs. Due to the demolition required and the location of the trees needing to be cleared, the Forest Service feels there is minimal impact, if any, to the ability to perform the contract around the cutting restrictions.
7. Question:
The completion date is listed as September 27th, is that firm or is there some flexibility on the completion date?
Answer: There is some flexibility on the completion date.
8. Question:
I'm going through the soil borings and can't find where they were taken on the plans. Do you have a map showing where they took those?
Answer: Unfortunately, no, we do not have a map showing the bore locations. The location of each boring is described in the individual boring logs.
9. Question:
The 19% moisture content can only be achieved on the 2x material, anything larger would cause it to split prematurely and be rejected.
Answer: If the material meets the industry standard and preservation guidelines, the Forest Service will accept it.
10. Question:
The treatment method involving Naphthenate and Light Oil is not done in the state of Michigan, MCA .23 would be the substitute. Is this acceptable?
Answer: No. The Forest does not want MCA .23.
11. Question:
Please clarify the Nominal vs Rough Sawn on the items that indicate both. Is it acceptable to use the material per the Michigan DOT specifications?
Answer: Nominal dimensions are acceptable.
12. Question:
The Plan notes indicate HDG fasteners and hardware. However, some of the details indicate Stainless Steel hardware. The deck screws also indicate two different sizes and two different coatings, S.S. or Coated. Could you provide clarification on which is required?
Answer: The notes generally specify galvanized hardware. However, stainless steel hardware should be used where specifically called for in the details such as on page 29, Railing Detail. Note, all Details specify “S.S. CLIP CONNECTION W/ S.S. FASTENERS, TYP.” The deck screws should be the size and coating indicated on the details for each application. If the plans indicate different deck screw sizes for the same application, please indicate the locations so we may resolve the conflict.
P a g e | 4
13. Question:
We visited the site yesterday and noticed that access is just the staircase, and no way to come down the slope. Using the staircase would severely limit the machine size that would install the helical piers for the project as well. I don't know of anything that can do 11' spans and be able to traverse the stairway, what we have that might work would mean reducing the span to roughly 6' instead of the 11' proposed.
Answer: The helical pile foundation was designed by a registered professional engineer based on information as determined from the geotechnical engineer’s recommendations. If the span length is to be altered based on the Contractor's preferred construction methods, then a new design by a registered professional engineer must be submitted to the Forest Service approval. Any additional design or material quantity costs for the convenience of the Contractor are not the responsibility of the Government.
14. Question:
Will there be an additional depth pay item for depths over the proposed 15'. The additional depth pay item would be for any potential overage above the anticipated 2,625' lineal feet of piling. The boring information is very light and it's tough to get a good idea of what depth it would take to achieve the desired load.
Answer: No. There will not be an additional pay item on the Schedule of Items for additional lineal feet of Helical Piling Installation. Please refer to Note 2 in Section B - Schedule of Items. The estimated quantity is a contract quantity subject to Subsection 109.02(b) and FAR Clause 52.211-18 Variation of Estimated Quantity. The FAR clause should address your concerns. It allows for an equitable adjustment in the contract price if the actual quantity varies by more than 15 percent above or below the estimated quantity.
15. Question:
Does the 4/30 deadline for all ground disturbance activities have any wiggle room? I'm thinking about the potential safety issues we could face trying to navigate the slope in a more traditional Michigan winter. We could start in October and work but once the weather starts to turn we would ideally have a winter shutdown until the weather permits and the slope is safer to work on. If we have to work through the winter it could be a lot slower and unsafe potentially.
Answer: Ground disturbing activities must be started when the Notice-to-Proceed is issued and progress as much as possible prior to a winter shutdown. Work on previously disturbed areas may continue through project completion after April 30.
1. Clarification:
On Drawing Sheet 10 of 30, replace the section “STAIRWAY/BOARDWALK TIMBER” with the following:
STAIRWAY/BOARDWALK TIMBER
1. SOLID SAWN TIMBER MEMBERS SHALL CONFORM TO THE REQUIREMENTS OF THE GRADING
RULES AGENCY FOR THE SPECIES, TYPE, AND GRADE SPECIFIED BELOW.
a. DECK PLANKS – SOUTHERN PINE OR DOUGLAS-FIR #1. ROUGH SAWN.
b. POSTS AND RAILS – SOUTHERN PINE #1. SURFACED S4S.
c. BEAMS AND HEADERS - SOUTHERN PINE OR DOUGLAS-FIR #1. ROUGH SAWN.
P a g e | 5
d. STAIR STRINGERS - SOUTHERN PINE OR DOUGLAS-FIR SELECT STRUCTURAL. ROUGH
SAWN.
2. MOISTURE CONTENT 19% MAXIMUM. (Delete requirement)
3. PRESERVATIVE TREATMENT SHALL BE IN ACCORDANCE WITH THE CURRENT AMERICAN WOOD
PROTECTION ASSOCITATION (AWPA) SPECIFICATION.
a. POSTS AND RAILS – AWPA USE CATEGORY SYSTEM U1 FOR USE CATEGORY UC4A.
PRESERVATIVE TREATMENT TO BE MCA.
b. DECK PLANKS, BEAMS, HEADERS, AND STAIR STRINGERS - AWPA USE CATEGORY
SYSTEM U1 FOR USE CATEGORY UC4B. PRESERVATIVE TREATMENT TO BE COPPER
NAPTHENATE IN HEAVY OIL.
4. COPPER NAPTHENATE (2% SOLUTION) SHALL BE FURNISHED FOR FIELD TREATING OF WOOD.
ALL ABRASIONS AND FIELD CUTS SHALL BE CAREFULLY TRIMMED AND GIVEN THREE BRUSH
COATS OFR FIELD TREATMENT SOLUTION. WHERE APPROVED FIELD DRILLING OF BOLT OR NAIL HOLES IS REQUIRED, THE HOLES SHALL BE FILLED WITH PRESERVATIVE PRIOR TO INSERTING THE
FASTENERS.
5. HARDWARE SHALL BE GALVANIZED AND MEET THE REQUIREMENTS OF AASHTO M 270, GRADE
36, WITH NUTS AND BOLTS CONFORMING TO ASTM A307, GRADE A. USE MALLEABLE IRON
WASHERS AGAINST WOOD UNLESS OTHERWISE NOTED ON THE PLANS.