--fuel maintenance hangar, vance AFB, OK
Awarded Award Notice Posted
- Solicitation number
- W912BV-08-R-2014
- Agency
- ENDIST Tulsa US Army Corps of Engineers, Department of Defense
- Awarded
- to Mason & Hanger, Inc.
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W912BV-08-C-2010 Federal contract award
- NAICS code
- Not on record
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
6 versions
Update #6 · Latest ·
Added: Jun 03, 2008 3:58 pm
Modified: Sep 26, 2008 1:03 pmTrack Changes
AWARD NOTICE FOR SOLICITATION W912BV-08-R-2014, CONTRACT NO. W912BV-08-C-2010. Contractor address information incorrect on Award Notice.
Should Read:
Mason & Hanger, Inc.
7270 W. 162nd Street
Overland Park, KS 66085
All other Award Information is correct.
Update #5 ·
Added: Jun 03, 2008 3:58 pm
Modified: Aug 01, 2008 1:13 pmTrack Changes
The proposal due date is 11 Aug 08 as previously annouced.
Section 00010 Proposal Schedule: Delete the existing proposal schedule; Replace with the Revised Proposal Schedule.
Update #4 ·
Added: Jun 03, 2008 3:58 pm Modified: Jul 30, 2008 10:48 amTrack Changes THE PROPOSAL DUE DATE IS 11 AUGUST 2008 AS PREVIOUSLY ANNOUCED.
Update #3 ·
Added: Jun 03, 2008 3:58 pm Modified: Jun 23, 2008 11:36 amTrack Changes The Project Description is Changed to read, DESIGN AND CONSTRUCT A Fuel System Maintenance Hangar ...
Update #2 ·
Added: Jun 03, 2008 3:58 pm
Modified: Jun 04, 2008 11:01 amTrack Changes
Project Description: Construct a fuel system maintenance hangar, which will provide four adequately sized bays to accommodate T-1A Jayhawk aircraft assigned to Vance AFB, with administration area, supporting storage area and restrooms. This facility will also support the T-38 and T-6A aircraft assigned to Vance AFB. The facility shall be of non-combustible construction with insulated metal exterior wall and roof systems on a reinforced concrete floor slab and foundation. Relocate all exterior utilities that are incident to the new construction. This project will provide all required materials, equipment, and necessary support for the construction of a state-of-art aircraft fuel system maintenance hangar. Renovation of the existing fuel system hangar to wash rack and demolition of supply facility 260 is included within this project. This work will include relocating existing wash rack equipment from a current location to the existing fuel maintenance hanger. All technical and engineering data related to this solicitation will be distributed using the Federal Business Opportunities website.
Ms. Susan Killgore, Contract Specialist, (918)669-7136.
Issue date on/or about 26 Jun 2008.
Update #1 ·
Added: Jun 03, 2008 3:58 pm
Project Description: Construct a fuel system maintenance hangar, which will provide four adequately sized bays to accommodate T-1A Jayhawk aircraft assigned to Vance AFB, with administration area, supporting storage area and restrooms. This facility will also support the T-38 and T-6A aircraft assigned to Vance AFB. The facility shall be of non-combustible construction with insulated metal exterior wall and roof systems on a reinforced concrete floor slab and foundation. Relocate all exterior utilities that are incident to the new construction. This project will provide all required materials, equipment, and necessary support for the construction of a state-of-art aircraft fuel system maintenance hangar. Renovation of the existing fuel system hangar to wash rack and demolition of supply facility 260 is included within this project. This work will include relocating existing wash rack equipment from a current location to the existing fuel maintenance hanger. All technical and engineering data related to this solicitation will be distributed using the Federal Business Opportunities website.
Ms. Susan Killgore, Contract Specialist, (918)669-7136.