AMENDMENT NO. 0005 FUEL SYSTEM MAINTENANCE HANGAR
W912BV-08-R-2014 VANCE AFB, OK
AMENDMENT OF SOLICITATION
1. CONTRACTOR ID CODE
NOT APPLICABLE (NA) PAGE 1 OF
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If Applicable)
0005 1 Aug 08 NA NA
6. ISSUED BY
CODE
7. ADMINISTERED BY (If other than Item 6)
CODE
DISTRICT ENGINEER
TULSA DISTRICT, CORPS OF ENGINEERS
1645 SOUTH 101ST EAST AVENUE
TULSA, OK 74128-4609
NA
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (%) 9A. AMENDMENT OF SOLICITATION NO.
W912BV-08-R-2014
% 9B. DATED (SEE ITEM 11)
26 Jun 08
10A. MODIFICATION OF CONTRACT/ORDER NO.
NA
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE NA
11. THIS ITEM APPLIES ONLY TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, X is not extended.
THE PROPOSAL DUE DATE IS 11 AUG 08 AS PREVIOUSLY ANNOUNCED.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
NA
NA 13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14
(%) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b)
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not; is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Section 00010 Proposal Schedule: Delete the existing Proposal Schedule; replace with the attached revised Proposal Schedule.
NOTE: IN THIS AMENDMENT “SOLICITATION NO.”, “OFFER”, AND “OFFEROR” MEAN “INVITATION NO.”, “BID”, AND “BIDDER”, RESPECTIVELY Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as hertofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
NA
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
NA NA
(Signature of person authorized to sign) (Signature of person authorized to sign)
NSN 7540-01-162-8070 30-105-02 STANDARD FORM 30 (REV. 10-8)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
Fuel System Maintenance Hangar Vance AFB, OK
00010-3 Revised by Amendment 0005
PROPOSAL SCHEDULE
Item No.
Description
Quantity
Unit
Unit Price
Amount
BASE PROPOSAL
1. Design Phase (Part 1)
Preliminary Design
a. Design Costs Sum Job xxx $_________
b. Non-Design Costs Sum Job xxx $_________
Sub-Total Design Phase Part 1 $__________
2. Design Phase (Part 2)
Final Design
Sub-Total Design Phase Part 2 $__________
3.
Build Phase
Construction Costs
Sum Job xxx $_________
SUBTOTAL BASE PROPOSAL $_________
OPTIONAL PROPOSAL ITEMS
4. Option 1 – Convert Bldg 188 to Aircraft Wash Rack.
Refer to Section 01 01 40 STATEMENT OF WORK for description of optional proposal item.
c. Construction Costs Sum Job Xxx $_________
Sub-Total Option 1 $_________
5. Option 2 – Provide Fabric Hangar Doors in Bldg 188.
Refer to Section 01 01 40 STATEMENT OF WORK for description of optional proposal item.
c. Construction Costs Sum Job xxx $_________
Sub-Total Option 2 $_________
00010-4
6. Option 3 – Demolition of Building 260. Refer to Section 01 01 40 STATEMENT OF WORK for description of optional proposal item.
All Work Sum Job xxx $_________
7. Option 4 – LEED CERTIFICATION. Provide LEED certification to the required level.
See Section 01 01 40, paragraph 4.4d.
All Work Sum Job Xxx $_________
Sub-Total Optional Proposal Items $_________
TOTAL BASE PROPOSAL & OPTIONAL ITEMS
PROPOSAL SCHEDULE NOTES
1. Offerors shall propose on all items.
2. Only one contract for the entire schedule will be awarded under this solicitation.
3. DESIGN COSTS DEFINITION
Design costs shall consist of preparation of designs, plans, drawings, and specifications.
4. NON-DESIGN COSTS DEFINITION
Non-design costs shall include the following: initial site visits, field, topographic, property, boundary and utility surveys, economic studies and other investigations, preparation or verifications of as-built drawings; preparation of general and development criteria;
services of consultants where not specifically applied to the preparation of working drawings or specifications; preparation of Environmental impact assessments, statements and supporting data;
engineering services during construction; renderings or photographs of completed designs; reproduction of designs for review purposes; and travel and per diem allowances in connection with the above excludable services.
5. COST LIMITATION
The established design cost limitation for the Design Costs of Design Phase Part 1 and Part 2 is 6 percent of the total cost for the Build Phase. Offerors whose cost proposal exceeds the design cost limitation for the design costs portion of the project may be rejected.
6. CONSTRUCTION COST LIMITATION (CCL)
The Construction Cost Limitation is defined as the maximum total contract sum which includes all categories of cost (i.e., design, non-design, and construction). See Section 00110 PROPOSAL PREPARATION, EVALUATION, AND CONTRACT AWARD.
7. OPTIONAL PROPOSAL ITEM DISCRIPTIONS
Optional Proposal Items shall be as described in the RFP documents.
7. EVALUATION OF OPTIONS
00010-5
The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the Base Proposal.
(Total Base Proposal and Optional Proposal Items.) Evaluation of options will not obligate the Government to exercise the options.
8. AWARD OF OPTIONAL PROPOSAL ITEMS
Optional proposal items as stated above, may, at the option of the Government, may be awarded at any time from the date of contract award or may be exercised at any time from the date of contract award until 90 days after issue of the Notice to Proceed.
All options or any combination thereof may be exercised by the Government.
File details come from the government source that posted it. Updated .