About this opportunity
The Department of the Army is soliciting proposals for a Job Order Contract (JOC) to provide construction services for a broad variety of small minor construction projects at Fort Irwin, California. The contract will be structured as a single award, Firm Fixed Price, Indefinite Delivery Indefinite Quantity (IDIQ) arrangement consisting of a 30-day phase-in period and a 60-month ordering period. Contractors must demonstrate specific capabilities including bonding capacity of $20 million for concurrent task orders and $30 million aggregate per year, along with key personnel requirements for a Program Manager, Site Superintendent, Quality Control Manager, and Safety Manager. The evaluation will be conducted using three factors: Technical Acceptability, Past Performance, and Price, with award made to the lowest priced, technically acceptable offeror. The original proposal due date was October 10, 2024, though the solicitation has undergone multiple amendments extending deadlines and updating requirements, with the most recent amendment removing services for paving, demolition, and abatement from the scope of work.
This procurement is designated as a 100% 8(a) competitive set-aside, restricting competition to eligible small disadvantaged businesses. The solicitation indicates that if the incumbent contractor wins the award, the 30-day phase-in period will not be required, though no specific incumbent is named in the documentation. The anticipated contract value ranges between $75 million and $100 million over the five-year performance period. Work will be performed primarily at Fort Irwin, California, which comprises over 763,474 acres and includes approximately 1,648 buildings totaling 8.9 million square feet, with additional locations including the Barstow-Daggett Airport in Daggett, California, and the Barstow Outreach Center in Barstow, California. The contractor will be required to use E4Clicks commercial cost estimating software with RSMeans pricing data and must develop three separate coefficient factors for normal working hours, other than normal working hours, and non-pre-priced items that cannot exceed 10% of the contract value.
Notice text
17 versions
Update #17 · Latest ·
Update as of 5 June 2025: The Source Selection Evaluation Board is still in progress. No response to this notice required at this time. Please continue to monitor Sam.gov for further updates.
************************************************************************************************************************************************
Update as of 1 May 2025: The Source Selection Evaluation Board is still in progress. No response to this notice required at this time. Please continue to monitor Sam.gov for further updates.
************************************************************************************************************************************************
Update as of 3 April 2025: The Source Selection Evaluation Board is still in progress. No response required to this notice at this time. Please continue to monitor Sam.gov for further updates.
************************************************************************************************************************************************
Update as of 21 March 2025: Solicitation Amendment 9 was not issued. Solicitation Amendment 10 was issued on 21 March 2025 to adhere to OSD Class Deviation - Restoring Merit-Based Opportunity in Federal Contracts signed 4 March 2025. Clauses 52.222-21, 52.222-23, 52.222-26 and 52.222-27 have been removed. Clause 52.244-6 (JAN 2025) has been removed and replaced with 52.244-6 Subcontracts for Commercial Products and Commercial Services (MAR 2025) (DEVIATION 2025-O0003). All other items and conditions remain unchanged.
****************************************************************************************************************************************************
Update as of 7 March 2025: The Source Selection Evaluation Board is still in progress. No response required to this notice at this time, please continue to monitor Sam.gov for further updates.
************************************************************************************************************************************************
Update as of 3 February 2025: The Source Selection Evaluation Board is still in progress. Please continue to monitor Sam.gov for further updates.
****************************The purpose of this solicitation amendment is to provide the updated Statement of Work (SOW) dated 26 September 2024. The main updates to the SOW are as follows: 1) SOW 3.0 Scope of Work has been updated to remove services for the sole purpose of Paving, Demolition and Abatement. These services are not authorized for acquisition under this JOC. 2) SOW 9.0 Personnel has been updated to reflect changes to key personnel, personnel qualifications and on-site staff. All other items and conditions remain virtually unchanged.**************************************
Update #16 ·
Update as of 1 May 2025: The Source Selection Evaluation Board is still in progress. No response to this notice required at this time. Please continue to monitor Sam.gov for further updates.
************************************************************************************************************************************************
Update as of 3 April 2025: The Source Selection Evaluation Board is still in progress. No response required to this notice at this time. Please continue to monitor Sam.gov for further updates.
************************************************************************************************************************************************
Update as of 21 March 2025: Solicitation Amendment 9 was not issued. Solicitation Amendment 10 was issued on 21 March 2025 to adhere to OSD Class Deviation - Restoring Merit-Based Opportunity in Federal Contracts signed 4 March 2025. Clauses 52.222-21, 52.222-23, 52.222-26 and 52.222-27 have been removed. Clause 52.244-6 (JAN 2025) has been removed and replaced with 52.244-6 Subcontracts for Commercial Products and Commercial Services (MAR 2025) (DEVIATION 2025-O0003). All other items and conditions remain unchanged.
****************************************************************************************************************************************************
Update as of 7 March 2025: The Source Selection Evaluation Board is still in progress. No response required to this notice at this time, please continue to monitor Sam.gov for further updates.
************************************************************************************************************************************************
Update as of 3 February 2025: The Source Selection Evaluation Board is still in progress. Please continue to monitor Sam.gov for further updates.
****************************The purpose of this solicitation amendment is to provide the updated Statement of Work (SOW) dated 26 September 2024. The main updates to the SOW are as follows: 1) SOW 3.0 Scope of Work has been updated to remove services for the sole purpose of Paving, Demolition and Abatement. These services are not authorized for acquisition under this JOC. 2) SOW 9.0 Personnel has been updated to reflect changes to key personnel, personnel qualifications and on-site staff. All other items and conditions remain virtually unchanged.**************************************
Update #15 ·
Update as of 3 April 2025: The Source Selection Evaluation Board is still in progress. No response required to this notice at this time. Please continue to monitor Sam.gov for further updates.
************************************************************************************************************************************************
Update as of 21 March 2025: Solicitation Amendment 9 was not issued. Solicitation Amendment 10 was issued on 21 March 2025 to adhere to OSD Class Deviation - Restoring Merit-Based Opportunity in Federal Contracts signed 4 March 2025. Clauses 52.222-21, 52.222-23, 52.222-26 and 52.222-27 have been removed. Clause 52.244-6 (JAN 2025) has been removed and replaced with 52.244-6 Subcontracts for Commercial Products and Commercial Services (MAR 2025) (DEVIATION 2025-O0003). All other items and conditions remain unchanged.
****************************************************************************************************************************************************
Update as of 7 March 2025: The Source Selection Evaluation Board is still in progress. No response required to this notice at this time, please continue to monitor Sam.gov for further updates.
************************************************************************************************************************************************
Update as of 3 February 2025: The Source Selection Evaluation Board is still in progress. Please continue to monitor Sam.gov for further updates.
****************************The purpose of this solicitation amendment is to provide the updated Statement of Work (SOW) dated 26 September 2024. The main updates to the SOW are as follows: 1) SOW 3.0 Scope of Work has been updated to remove services for the sole purpose of Paving, Demolition and Abatement. These services are not authorized for acquisition under this JOC. 2) SOW 9.0 Personnel has been updated to reflect changes to key personnel, personnel qualifications and on-site staff. All other items and conditions remain virtually unchanged.**************************************
Update #14 ·
Update as of 21 March 2025: Solicitation Amendment 9 was not issued. Solicitation Amendment 10 was issued on 21 March 2025 to adhere to OSD Class Deviation - Restoring Merit-Based Opportunity in Federal Contracts signed 4 March 2025. Clauses 52.222-21, 52.222-23, 52.222-26 and 52.222-27 have been removed. Clause 52.244-6 (JAN 2025) has been removed and replaced with 52.244-6 Subcontracts for Commercial Products and Commercial Services (MAR 2025) (DEVIATION 2025-O0003). All other items and conditions remain unchanged.
****************************************************************************************************************************************************
Update as of 7 March 2025: The Source Selection Evaluation Board is still in progress. No response required to this notice at this time, please continue to monitor Sam.gov for further updates.
************************************************************************************************************************************************
Update as of 3 February 2025: The Source Selection Evaluation Board is still in progress. Please continue to monitor Sam.gov for further updates.
****************************The purpose of this solicitation amendment is to provide the updated Statement of Work (SOW) dated 26 September 2024. The main updates to the SOW are as follows: 1) SOW 3.0 Scope of Work has been updated to remove services for the sole purpose of Paving, Demolition and Abatement. These services are not authorized for acquisition under this JOC. 2) SOW 9.0 Personnel has been updated to reflect changes to key personnel, personnel qualifications and on-site staff. All other items and conditions remain virtually unchanged.**************************************
Update #13 ·
Update as of 7 March 2025: The Source Selection Evaluation Board is still in progress. No response required to this notice at this time, please continue to monitor Sam.gov for further updates.
************************************************************************************************************************************************
Update as of 3 February 2025: The Source Selection Evaluation Board is still in progress. Please continue to monitor Sam.gov for further updates.
****************************The purpose of this solicitation amendment is to provide the updated Statement of Work (SOW) dated 26 September 2024. The main updates to the SOW are as follows: 1) SOW 3.0 Scope of Work has been updated to remove services for the sole purpose of Paving, Demolition and Abatement. These services are not authorized for acquisition under this JOC. 2) SOW 9.0 Personnel has been updated to reflect changes to key personnel, personnel qualifications and on-site staff. All other items and conditions remain virtually unchanged.**************************************
Update #12 ·
Update as of 3 February 2025: The Source Selection Evaluation Board is still in progress. Please continue to monitor Sam.gov for further updates.
****************************The purpose of this solicitation amendment is to provide the updated Statement of Work (SOW) dated 26 September 2024. The main updates to the SOW are as follows: 1) SOW 3.0 Scope of Work has been updated to remove services for the sole purpose of Paving, Demolition and Abatement. These services are not authorized for acquisition under this JOC. 2) SOW 9.0 Personnel has been updated to reflect changes to key personnel, personnel qualifications and on-site staff. All other items and conditions remain virtually unchanged.**************************************
Update #11 ·
****************************The purpose of this solicitation amendment is to provide the updated Statement of Work (SOW) dated 26 September 2024. The main updates to the SOW are as follows: 1) SOW 3.0 Scope of Work has been updated to remove services for the sole purpose of Paving, Demolition and Abatement. These services are not authorized for acquisition under this JOC. 2) SOW 9.0 Personnel has been updated to reflect changes to key personnel, personnel qualifications and on-site staff. All other items and conditions remain virtually unchanged.**************************************
Update #10 ·
The purpose of this solicitation amendment is to provide the updated Statement of Work (SOW) dated 26 September 2024. The main updates to the SOW are as follows: 1) SOW 3.0 Scope of Work has been updated to remove services for the sole purpose of Paving, Demolition and Abatement. These services are not authorized for acquisition under this JOC. 2) SOW 9.0 Personnel has been updated to reflect changes to key personnel, personnel qualifications and on-site staff. All other items and conditions remain virtually unchanged.
Update #9 ·
****************The purpose of this solicitation amendment is to extend the proposal due date from 26 Sep 2024 to 10 Oct 2024 in preparation for an upcoming change to the Statement of Work. An updated Statement of Work will be released in an upcoming solicitation amendment. All other items and conditions remain unchanged. ***********************************
Update #8 ·
***********The purpose of Solicitation Amendment 0006 is to extend the proposal due date from 19 Sep 2024 to 26 Sep 2024; 2) Include Questions 098-109 on Attachment 13 - Government Responses to Industry Questions_Updated 10 September 2024, update Attachment 1 - Ft. Irwin Job Order Contract (JOC) Statement of Work_11 September 2024, Attachment 14 - SAIDIQ Ordering Guide 20240910 and other administrative actions. All other items and conditions remain unchanged.*****************
************The purpose of solicitation amendment 005 is to: 1) Extend the proposal due date from 12 SEP 2024 to 19 SEP 2024; 2) Included questions 087-097 on Attachment 13-Government Responses to Industry Questions_Updated 26AUG24; 3) Update SOW paragraph 5.1 and 6.1_5September 2024; 4) Include Attachment 14 - SAIDIQ Ordering Guide 20240828; 5) Updated Section 00 21 013 - Instructions to Bidders. All other items and conditions remain unchanged. ****************
*********** The purpose of this solicitation amendment is to: Extend the proposal due date from 05 SEP 2024 to 12 SEP 2024.*******
************The purpose of this solicitation amendment is to: 1) Extend the proposal due date from 23 AUG 2024 to 05 SEP 2024. 2) Respond to questions from industry and complete, update the CLIN structure, SOW, list of attachments, etc., and other administrative actions. All other items and conditions remain unchanged.*************
Background and Purpose: The Directorate of Public Works (DPW) provides support to the Fort Irwin, California (CA) Garrison Command and its major tenant organizations, which together currently utilize approximately 1648 buildings and structures consisting of approximately 8.9 million square feet on the installation.
U.S. Army Garrison Fort Irwin, CA, provides training for Combat Support (CS) and CombatService Support (CSS) units in the Western United States. Fort Irwin comprises more than 763,474 acres of un-encroached mountains. valleys, and plains. There are several major military tenant organizations at Fort Irwin: the Operations Group; the 11th Armored Calvary Regiment: The Joint Improvised Explosive Device (IED) Defeat Organization and the 916th Support Brigade.
The customer for this acquisition is the U.S. Army Installation Management Command (IMCOM) in support of the United States Army Garrison (USAG) Ft. Irwin.
Update #7 ·
************The purpose of solicitation amendment 005 is to: 1) Extend the proposal due date from 12 SEP 2024 to 19 SEP 2024; 2) Included questions 087-097 on Attachment 13-Government Responses to Industry Questions_Updated 26AUG24; 3) Update SOW paragraph 5.1 and 6.1_5September 2024; 4) Include Attachment 14 - SAIDIQ Ordering Guide 20240828; 5) Updated Section 00 21 013 - Instructions to Bidders. All other items and conditions remain unchanged.
*********** The purpose of this solicitation amendment is to: Extend the proposal due date from 05 SEP 2024 to 12 SEP 2024.*******
************The purpose of this solicitation amendment is to: 1) Extend the proposal due date from 23 AUG 2024 to 05 SEP 2024. 2) Respond to questions from industry and complete, update the CLIN structure, SOW, list of attachments, etc., and other administrative actions. All other items and conditions remain unchanged.*************
Background and Purpose: The Directorate of Public Works (DPW) provides support to the Fort Irwin, California (CA) Garrison Command and its major tenant organizations, which together currently utilize approximately 1648 buildings and structures consisting of approximately 8.9 million square feet on the installation.
U.S. Army Garrison Fort Irwin, CA, provides training for Combat Support (CS) and CombatService Support (CSS) units in the Western United States. Fort Irwin comprises more than 763,474 acres of un-encroached mountains. valleys, and plains. There are several major military tenant organizations at Fort Irwin: the Operations Group; the 11th Armored Calvary Regiment: The Joint Improvised Explosive Device (IED) Defeat Organization and the 916th Support Brigade.
The customer for this acquisition is the U.S. Army Installation Management Command (IMCOM) in support of the United States Army Garrison (USAG) Ft. Irwin.
Update #6 ·
*********** The purpose of this solicitation amendment is to: Extend the proposal due date from 05 SEP 2024 to 12 SEP 2024.*******
************The purpose of this solicitation amendment is to: 1) Extend the proposal due date from 23 AUG 2024 to 05 SEP 2024. 2) Respond to questions from industry and complete, update the CLIN structure, SOW, list of attachments, etc., and other administrative actions. All other items and conditions remain unchanged.*************
Background and Purpose: The Directorate of Public Works (DPW) provides support to the Fort Irwin, California (CA) Garrison Command and its major tenant organizations, which together currently utilize approximately 1648 buildings and structures consisting of approximately 8.9 million square feet on the installation.
U.S. Army Garrison Fort Irwin, CA, provides training for Combat Support (CS) and CombatService Support (CSS) units in the Western United States. Fort Irwin comprises more than 763,474 acres of un-encroached mountains. valleys, and plains. There are several major military tenant organizations at Fort Irwin: the Operations Group; the 11th Armored Calvary Regiment: The Joint Improvised Explosive Device (IED) Defeat Organization and the 916th Support Brigade.
The customer for this acquisition is the U.S. Army Installation Management Command (IMCOM) in support of the United States Army Garrison (USAG) Ft. Irwin.
Update #5 ·
************The purpose of this solicitation amendment is to: 1) Extend the proposal due date from 23 AUG 2024 to 05 SEP 2024. 2) Respond to questions from industry and complete, update the CLIN structure, SOW, list of attachments, etc., and other administrative actions. All other items and conditions remain unchanged.*************
Background and Purpose: The Directorate of Public Works (DPW) provides support to the Fort Irwin, California (CA) Garrison Command and its major tenant organizations, which together currently utilize approximately 1648 buildings and structures consisting of approximately 8.9 million square feet on the installation.
U.S. Army Garrison Fort Irwin, CA, provides training for Combat Support (CS) and CombatService Support (CSS) units in the Western United States. Fort Irwin comprises more than 763,474 acres of un-encroached mountains. valleys, and plains. There are several major military tenant organizations at Fort Irwin: the Operations Group; the 11th Armored Calvary Regiment: The Joint Improvised Explosive Device (IED) Defeat Organization and the 916th Support Brigade.
The customer for this acquisition is the U.S. Army Installation Management Command (IMCOM) in support of the United States Army Garrison (USAG) Ft. Irwin.
Update #4 ·
The purpose of this solicitation amendment is to: 1) Extend the proposal due date from 23 AUG 2024 to 05 SEP 2024. 2) Respond to questions from industry and complete, update the CLIN structure, SOW, list of attachments, etc., and other administrative actions. All other items and conditions remain unchanged.
Update #3 ·
*******18 July 2024: The purpose of this solicitation amendment 0002 is to: 1) Include Attachment 12 - In-Person Site Visit PowerPoint Presentation_17JUL24, 2) include the vendor participant sign in roster for the 17 July 2024 in-person site visit, and 3) extend the due date for all questions regarding the solicitation from 22 July 2024 to 25 July 2024. All other items and conditions remain unchanged.*******
*******11 July 2024: The purpose of this solicitation amendment 0001 is to: 1. Update Attachment 11 name in the List of Attachments section from ‘Attachment 11 - Fort Irwin Painted Rock Vendor Parking for In-Person Site Visit_26JUN24’ to ‘Attachment 11 - Fort Irwin Map for the 17 July 2024 In-Person Site Visit.’2. Update Attachment 11 - Fort Irwin Map for the 17 July 2024 In-Person Site Visit map with the latest version dated 10JUL24..3. Update the 17 July 2024 in-person site visit start time from 8:00 a.m. PDT to 9:00. 4.Update the Ship to Address point of contact from Chris Woodruff to Emilio Villegas. All other items and conditions remain unchanged.******
This requirement is for Construction services for a broad variety of small minor construction projects at Fort Irwin, California. Work is to be performed in accordance with (IAW) the Statement of Work (SOW), titled Ft. Irwin Job Order Contract (JOC) Statement of Work (SOW)_30MAY24. This is a 100% 8(a) Competitive set-aside. The contract awarded as a result of this solicitation will be a single award, Firm Fixed Price (FFP), Indefinite Delivery Indefinite Quantity (IDIQ) Job Order Contract (JOC) consisting of a 30-day phase-in period, and an ordering period consisting of 60-months (in the event the incumbent is awarded the contract, a phase-in period will not take place. The time for commencement of work and the calendar days allocated for completion of work will be determined at the task order level.
Update #2 ·
***********Solicitation Amendment Posted 11 July 2024. The purpose of the solicitation amendment is to: 1. Update Attachment 11 name in the List of Attachments section from ?Attachment 11 - Fort Irwin Painted Rock Vendor Parking for In-Person Site Visit_26JUN24? to ?Attachment 11 - Fort Irwin Map for the 17 July 2024 In-Person Site Visit.?2. Update Attachment 11 - Fort Irwin Map for the 17 July 2024 In-Person Site Visit map with the latest version dated 10JUL24..3. Update the 17 July 2024 in-person site visit start time from 8:00 a.m. PDT to 9:00. 4.Update the Ship to Address point of contact from Chris Woodruff to Emilio Villegas. All other items and conditions remain unchanged.**********
This requirement is for Construction services for a broad variety of small minor construction projects at Fort Irwin, California. Work is to be performed in accordance with (IAW) the Statement of Work (SOW), titled Ft. Irwin Job Order Contract (JOC) Statement of Work (SOW)_30MAY24. This is a 100% 8(a) Competitive set-aside. The contract awarded as a result of this solicitation will be a single award, Firm Fixed Price (FFP), Indefinite Delivery Indefinite Quantity (IDIQ) Job Order Contract (JOC) consisting of a 30-day phase-in period, and an ordering period consisting of 60-months (in the event the incumbent is awarded the contract, a phase-in period will not take place. The time for commencement of work and the calendar days allocated for completion of work will be determined at the task order level.
Update #1 ·
This requirement is for Construction services for a broad variety of small minor construction projects at Fort Irwin, California. Work is to be performed in accordance with (IAW) the Statement of Work (SOW), titled Ft. Irwin Job Order Contract (JOC) Statement of Work (SOW)_30MAY24. This is a 100% 8(a) Competitive set-aside. The contract awarded as a result of this solicitation will be a single award, Firm Fixed Price (FFP), Indefinite Delivery Indefinite Quantity (IDIQ) Job Order Contract (JOC) consisting of a 30-day phase-in period, and an ordering period consisting of 60-months (in the event the incumbent is awarded the contract, a phase-in period will not take place. The time for commencement of work and the calendar days allocated for completion of work will be determined at the task order level.
Files
Show all 48
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Solicitation | |
| Fort Irwin Job Order Contract (JOC) | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Fort Benning Job Order Contract | Department of the Army | Woman-Owned Small Business | |
| IDIQ JOC total small-business set-aside for electrical and other wiring installation projects at various government facilities located within the marine corps logistics base barstow, marine CO | Naval Facilities Engineering Command | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity