About this opportunity

This solicitation seeks bank stabilization services along approximately 2,500 linear feet of shoreline on Lake Francis Case in Lyman and Charles Mix Counties, South Dakota. The U.S. Army Corps of Engineers, Omaha District, is requesting bids to implement bank stabilization measures through activities such as slope grading, geotextile installation, and placement of approximately 2,700 tons of riprap stone. Bids are due by September 9, 2022 and will be evaluated based on price to select the lowest priced, responsible offeror meeting the solicitation's requirements.

This requirement has a total small business set-aside designation. The primary NAICS code is 237990 for other heavy and civil engineering construction, with a size standard of $39.5 million for small businesses. The estimated value of this contract is between $500,000 to $1,000,000, and all work must be completed within 365 calendar days of the notice to proceed. The place of performance will be along approximately 20 miles northwest of Pickstown, South Dakota and 5 miles southwest of Oacoma, South Dakota.

Notice text

5 versions

Update #5 · Latest ·

ABSTRACT OF OFFERS - Uploaded 09/12/2022

Uploaded - Agenda and Q&As from Pre-Bid Meeting

Uploaded - Sign-In Pre-bid Meeting W9128F22B0011 FR Bank Stablization 

SOLICITATION for Fort Randall Bank Stabilizaiton - RM 886 and East Dude Ranch

Project Description: 

This project is for the implementation of bank stabilization measures in Lyman and Charles Mix Counties SD adjacent to Lake Francis Case / Ft. Randall Dam Project                                                                                                                                                 

The work will consist of bank and slope protection of approximately 2,500 linear feet of Lake Francis Case on the site herein referred to as “FY22 Lake Francis Case RM 886 and 963, Lyman and Charles Mix County SD”. The work will consist of cutting, regrading, and compacting the existing bank to provide the proper slope for the placement geotextile fabric and rip rap stone. The contractor will be limited to the designated areas for operations.

The work is located on Lake Francis Case approximately 20 miles northwest of Pickstown SD and approximately 5 miles southwest of Oacoma SD.  The exact location of the work will be provided by the Contracting Officer's Representative

All work and transport of materials associated with this project must comply with all federal, state, and local regulations.

Estimated Construction Costs (only include if applicable):

The estimated construction cost of this project is between $500,000 and $1,000,000. 

NAICS Code:  The Primary North American Industry Classification System (NAICS) code anticipated for solicitation is 237990: Other Heavy and Civil Engineering Construction, with a size standard for Small Business of $39.5M.

-This solicitation is restricted to Small Businesses-    

Update #4 ·

Uploaded - Agenda and Q&As from Pre-Bid Meeting

Uploaded - Sign-In Pre-bid Meeting W9128F22B0011 FR Bank Stablization 

SOLICITATION for Fort Randall Bank Stabilizaiton - RM 886 and East Dude Ranch

Project Description: 

This project is for the implementation of bank stabilization measures in Lyman and Charles Mix Counties SD adjacent to Lake Francis Case / Ft. Randall Dam Project                                                                                                                                                 

The work will consist of bank and slope protection of approximately 2,500 linear feet of Lake Francis Case on the site herein referred to as “FY22 Lake Francis Case RM 886 and 963, Lyman and Charles Mix County SD”. The work will consist of cutting, regrading, and compacting the existing bank to provide the proper slope for the placement geotextile fabric and rip rap stone. The contractor will be limited to the designated areas for operations.

The work is located on Lake Francis Case approximately 20 miles northwest of Pickstown SD and approximately 5 miles southwest of Oacoma SD.  The exact location of the work will be provided by the Contracting Officer's Representative

All work and transport of materials associated with this project must comply with all federal, state, and local regulations.

Estimated Construction Costs (only include if applicable):

The estimated construction cost of this project is between $500,000 and $1,000,000. 

NAICS Code:  The Primary North American Industry Classification System (NAICS) code anticipated for solicitation is 237990: Other Heavy and Civil Engineering Construction, with a size standard for Small Business of $39.5M.

-This solicitation is restricted to Small Businesses-    

Update #3 ·

Uploaded - Q&As from Pre-Bid Meeting

Uploaded - Sign-In Pre-bid Meeting W9128F22B0011 FR Bank Stablization 

SOLICITATION for Fort Randall Bank Stabilizaiton - RM 886 and East Dude Ranch

Project Description: 

This project is for the implementation of bank stabilization measures in Lyman and Charles Mix Counties SD adjacent to Lake Francis Case / Ft. Randall Dam Project                                                                                                                                                 

The work will consist of bank and slope protection of approximately 2,500 linear feet of Lake Francis Case on the site herein referred to as “FY22 Lake Francis Case RM 886 and 963, Lyman and Charles Mix County SD”. The work will consist of cutting, regrading, and compacting the existing bank to provide the proper slope for the placement geotextile fabric and rip rap stone. The contractor will be limited to the designated areas for operations.

The work is located on Lake Francis Case approximately 20 miles northwest of Pickstown SD and approximately 5 miles southwest of Oacoma SD.  The exact location of the work will be provided by the Contracting Officer's Representative

All work and transport of materials associated with this project must comply with all federal, state, and local regulations.

Estimated Construction Costs (only include if applicable):

The estimated construction cost of this project is between $500,000 and $1,000,000. 

NAICS Code:  The Primary North American Industry Classification System (NAICS) code anticipated for solicitation is 237990: Other Heavy and Civil Engineering Construction, with a size standard for Small Business of $39.5M.

-This solicitation is restricted to Small Businesses-    

Update #2 ·

Uploaded - Sign-In Pre-bid Meeting W9128F22B0011 FR Bank Stablization 

SOLICITATION for Fort Randall Bank Stabilizaiton - RM 886 and East Dude Ranch

Project Description: 

This project is for the implementation of bank stabilization measures in Lyman and Charles Mix Counties SD adjacent to Lake Francis Case / Ft. Randall Dam Project                                                                                                                                                 

The work will consist of bank and slope protection of approximately 2,500 linear feet of Lake Francis Case on the site herein referred to as “FY22 Lake Francis Case RM 886 and 963, Lyman and Charles Mix County SD”. The work will consist of cutting, regrading, and compacting the existing bank to provide the proper slope for the placement geotextile fabric and rip rap stone. The contractor will be limited to the designated areas for operations.

The work is located on Lake Francis Case approximately 20 miles northwest of Pickstown SD and approximately 5 miles southwest of Oacoma SD.  The exact location of the work will be provided by the Contracting Officer's Representative

All work and transport of materials associated with this project must comply with all federal, state, and local regulations.

Estimated Construction Costs (only include if applicable):

The estimated construction cost of this project is between $500,000 and $1,000,000. 

NAICS Code:  The Primary North American Industry Classification System (NAICS) code anticipated for solicitation is 237990: Other Heavy and Civil Engineering Construction, with a size standard for Small Business of $39.5M.

-This solicitation is restricted to Small Businesses-    

Update #1 ·

SOLICITATION for Fort Randall Bank Stabilizaiton - RM 886 and East Dude Ranch

Project Description: 

This project is for the implementation of bank stabilization measures in Lyman and Charles Mix Counties SD adjacent to Lake Francis Case / Ft. Randall Dam Project                                                                                                                                                 

The work will consist of bank and slope protection of approximately 2,500 linear feet of Lake Francis Case on the site herein referred to as “FY22 Lake Francis Case RM 886 and 963, Lyman and Charles Mix County SD”. The work will consist of cutting, regrading, and compacting the existing bank to provide the proper slope for the placement geotextile fabric and rip rap stone. The contractor will be limited to the designated areas for operations.

The work is located on Lake Francis Case approximately 20 miles northwest of Pickstown SD and approximately 5 miles southwest of Oacoma SD.  The exact location of the work will be provided by the Contracting Officer's Representative

All work and transport of materials associated with this project must comply with all federal, state, and local regulations.

Estimated Construction Costs (only include if applicable):

The estimated construction cost of this project is between $500,000 and $1,000,000. 

NAICS Code:  The Primary North American Industry Classification System (NAICS) code anticipated for solicitation is 237990: Other Heavy and Civil Engineering Construction, with a size standard for Small Business of $39.5M.

-This solicitation is restricted to Small Businesses-    

Files

Notice history

Notice Type Posted
Fort Randall Bank Stabilization - RM 886 and East Dude Ranch Award Award Notice
This notice Latest solicitation Solicitation
Fort Randall Bank Stabilization - RM 886 and East Dude Ranch Special Notice
Fort Randall Bank Stabilization - RM 886 and East Dude Ranch Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Lower brule north shoreline stabilization and ecosystem restoration, element 2 Big Bend, Lower Brule, South Dakota 57548 · NAICS 237990 ENDIST Omaha Total Small Business
Mill Creek Section 205 Flood Risk Management Improvements Mill Creek Flood Control ChannelWalla Walla, WA 99362Walla Walla County 99362 · NAICS 237990 ENDIST Walla Walla No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors