Fermi National Accelerator Laboratory (Fermilab) is seeking a qualified subcontractor to perform comprehensive interior upgrades for four village houses located in Batavia, Illinois. The Department of Energy's solicitation, issued by Fermi Forward Discovery Group, LLC, requires a residential remodeling contractor to complete extensive renovations including bathroom demolition and remodeling, kitchen cabinet painting, countertop replacement, pipe replacement, flooring installation, interior painting, light fixture replacement, and window upgrades. This is a Lowest Price Technically Acceptable (LPTA) procurement, with proposals due on February 17, 2025, at 3:00 PM CST, and a mandatory pre-proposal site visit scheduled for January 23, 2025. Offerors must submit both technical and business/management proposals, with a 90-day minimum proposal acceptance period. Evaluation will focus on technical compliance, pricing, and meeting the specified performance requirements outlined in the detailed Statement of Work.

The solicitation is designated as a small business set-aside under NAICS code 236118 (Residential Remodelers) with a size standard of $45 million. The project covers four specific village houses: Potawatomi 14, Shabbona 12, Neuqua 19, and Sauk 28, with work to be performed at the Fermi National Accelerator Laboratory campus. Contractors must comply with Davis-Bacon Act wage requirements and Buy American Act regulations for construction materials. The project includes specific bonding requirements, including a bid guarantee of 20% of the proposal price, and 100% payment and performance bonds for contracts exceeding certain monetary thresholds. While no specific total contract value is explicitly stated, the comprehensive scope of work suggests a significant renovation project with multiple detailed specifications for each house. The work will be managed by a Task Manager/Construction Coordinator, with Fermi Research Alliance providing oversight and project support.

Notice text

INTRODUCTION

This project intends to obtain a qualified Subcontractor to perform interior repairs including bathroom demolition, bathroom reinstall, replacement of galvanized pipe, painting of kitchen cabinets, replacement of countertops, interior painting, installation of light fixtures, and replacement of flooring at Village House Potawatomi 14 at Fermi National Accelerator Laboratory (Fermilab) located in Batavia, Illinois. Fermilab is operated by the Fermi Research Alliance (FRA).  FRA will provide a Task Manager / Construction Coordinator (TM/CC) to provide oversight of the project.

The purpose of this statement of work (SOW) is to obtain the supervision, expertise, labor, materials, and equipment in relation to the work indicated below.

SCOPE OF WORK

The Subcontractor shall perform the following:

Bathroom Demolition

  1. Mobilize to Potawatomi 14 in the Fermilab Village.
  2. Cover door openings with plastic sheeting (or similar) to prevent the spread of dust to other areas.
  3. Ensure that water to the bathroom is secured, as necessary.
  4. Remove all currently installed fixtures, flooring, wall tile, and cabinets from the bathroom.
  5. Remove all existing galvanized pipe.
  6. Dispose of removed items and debris in dumpster provided by FRA.
  7. Perform close out of job site.
    1. Ensure all tools, equipment, and waste are removed.
    2. Perform turnover / closeout of job with TM/CC.

Bathroom Remodel

  1. Mobilize to Potawatomi 14 in the Fermilab Village.
  2. Replace all existing galvanized pipe in the bathroom with copper pipe.
  3. Adapt and renovate any plumbing positions as necessary for installation of new fixtures.
  4. Determine if any changes are required for electrical outlets or fixtures.
  5. Perform Lock Out / Tag Out (LOTO) of any electrical outlets or fixtures as needed.
  6. Install new light fixture, fan, and outlets equivalent to what is currently installed in the bathroom.
  7. Install new vinyl wall and floor tile equivalent to that currently installed.
  8. Install new single sink bathroom vanity (grey cabinet with white vanity sink) and verify leak tight.
  9. Install new standard acrylic white bath tub / shower surround and verify leak tight.
  10. Install new standard white, round toilet and verify leak tight.
  11. Install standard satin nickel finish towel bar, paper holder, and shower curtain bar.
  12. Dispose of any garbage / debris in dumpster provided by FRA.
  13. Perform close out of job site.
    1. Ensure all tools, equipment, and waste are removed.
    2. Perform turnover / closeout of job with TM/CC.

Kitchen Countertop Demolition

  1. Mobilize to Potawatomi 14 in the Fermilab Village.
  2. Ensure that water to the kitchen is secured, as necessary.
  3. Disconnect sink drains and water lines from faucet and ensure there is no connection to countertop.
  4. Remove kitchen countertop taking care to preserve kitchen cabinets.
  5. Clean any remaining adhesive from cabinets.
  6. Dispose of old countertop in FRA provided dumpster.

Paint Kitchen Cabinets

  1. Mobilize to Potawatomi 14 in the Fermilab Village.
  2. Remove all hardware and doors from kitchen cabinets.
  3. Prep and clean cabinets for painting by using a degreaser and lightly sanding, as required.
  4. Prime cabinets to ensure paint adheres to the surface.
  5. Paint the cabinets using a minimum of two coats Benjamin Moore EcoSpec in color #1600 Timber Wolf.
  6. Reinstall doors and hardware.
  7. Perform close out of job site.
    1. Ensure all tools, equipment, and waste are removed.
    2. Perform turnover / closeout of job with TM/CC.

Install Kitchen Countertop

  1. Mobilize to Potawatomi 14 in the Fermilab Village.
  2. Measure the installation area for the countertop to ensure proper fit.
  3. Cabinets should be laminate in Wilsonart White Carrara 4924-38 or equivalent.
  4. Dry fit the countertop and scribe to fit any irregularities in the wall or cabinets.
  5. Cut or sand along scribe line, as necessary, to ensure proper fit.
  6. Fasten countertops to cabinets.
  7. Caulk any seams or gaps.
  8. Reinstall sink and caulk any seams or gaps.
  9. Reattach sink drains and faucet.
  10. Perform close out of job site.
    1. Ensure all tools, equipment, and waste are removed.
    2. Perform turnover / closeout of job with TM/CC.

Carpet Removal and Installation

  1. Mobilize to Potawatomi 14 in the Fermilab Village.
  2. Remove existing carpet and pad in all currently carpeted rooms.
  3. Dispose of carpet and pad in FRA supplied dumpster.
  4. Prep floors as necessary to ready them for carpet installation (staple removal, adhesive removal, cleaning, etc.).
  5. Install new carpet and pad (Dream Weaver, Rock Solid III, Dark Platinum).
  6. Perform close out of job site.
    1. Ensure all tools, equipment, and waste are removed.
    2. Perform turnover / closeout of job with TM/CC.

Laminate Flooring Removal and Installation

  1. Mobilize to Potawatomi 14 in the Fermilab Village.
  2. Remove existing non-carpet flooring and underlayment (as applicable) in all rooms (except bathroom).
  3. Dispose of old flooring in FRA supplied dumpster.
  4. Prep floors as necessary to ready them for laminate floor installation (staple removal, adhesive removal, cleaning, etc.).
  5. Install new laminate flooring and underlayment (Aladdin Commercial AH080 in color 910 Drumhill).
  6. Perform close out of job site.
    1. Ensure all tools, equipment, and waste are removed.
    2. Perform turnover / closeout of job with TM/CC.

Galvanized Pipe Replacement

  1. Mobilize to Potawatomi 14 in the Fermilab Village.
  2. Ensure that water is isolated to the building.
  3. Remove all existing galvanized pipe in the building.
  4. Dispose of removed pipe in the dumpster provided by FRA.
  5. Install copper pipe of the same diameter to replace the existing galvanized pipe.
  6. Restore water flow to the building and validate that all newly installed pipe is leak tight.
  7. Perform close out of job site.
    1. Ensure all tools, equipment, and waste are removed.
    2. Perform turnover / closeout of job with TM/CC.

Interior Paining

  1. Mobilize to Potawatomi 14 in the Fermilab Village.
  2. Tarp, mask, and prepare building for interior paint.
  3. Scrape peeling paint and dispose as required.
  4. Patch all holes, cracks, and imperfections prior to painting.
  5. Paint all walls with a minimum of two coats satin paint in color to be determined.
  6. Paint all ceilings with a minimum of two coats Benjamin Moore Eco Spec Interior Latex eggshell paint in color to be determined.
  7. Paint all trim and interior doors with a minimum of two coats Benjamin Moore Eco Spec Interior Latex semi gloss paint (color to be provided).
  8. Paint exterior front and back doors with a minimum of two coats Benjamin Moore Eco Spec Interior Latex semi gloss paint.
  9. Perform close out of job site.
    1. Ensure all tools, equipment, and waste are removed.
    2. Perform turnover / closeout of job with TM/CC.

Light Replacement

  1. Mobilize to Potawatomi 14 in the Fermilab Village.
  2. Perform Lock Out / Tag Out (LOTO) of lights as required for installation.
  3. Remove all non-functional light fixtures from the building.
  4. Replace non-functional light fixtures with new fixtures. 
  5. Remove LOTO and validate that fixtures are functional.
  6. Dispose of removed lights per FRA guidelines.
    1. Dumpster will be provided by FRA for disposal of waste.
  7. Perform close out of job site.
    1. Ensure all tools, equipment, and waste are removed.
    2. Perform turnover / closeout of job with TM/CC.

Window Replacement

  1. Mobilize to Potawatomi 14 in the Fermilab Village.
  2. Remove existing windows and trim from the dining room and front of the house. 
  3. Dispose of old window and trim in FRA supplied dumpster.
  4. Prepare opening for installation of new window.
  5. Install new windows of the same style as currently installed and ensure that it properly sealed.
  6. Reinstall trim and patch paint where required.
  7. Perform close out of job site.
    1. Ensure all tools, equipment, and waste are removed.
    2. Perform turnover / closeout of job with TM/CC.

Add 220 V Power Supply

  1. Mobilize to the laundry closet of Potawatomi 14 in the Fermilab Village.
  2. Perform LOTO as required to prevent electrical shock.
  3. Select a breaker that can support 220 V outlet (i.e. 30 amp, double pole).
  4. Drill / cut holes to set electrical box and cables.
  5. Install electrical box.
  6. Feed electrical wire (10 gauge) from breaker box to the electrical box previously installed.
  7. Attach wires to outlet and ensure that the outlet is grounded.
  8. Remove LOTO and ensure that there is power to the outlet.
  9. Perform close out of job site.
    1. Ensure all tools, equipment, and waste are removed.
    2. Perform turnover / closeout of job with TM/CC.

Files

File Type Posted
Amendment 02.pdf PDF
Price Sheet.xlsx XLSX spreadsheet
Exhibit C Payment Bond FL 42 (Rev 12.22).pdf PDF
Exhibit Q Proposal Form.pdf PDF
Exhibit P Wage Determinations.pdf PDF
Amendment 01.pdf PDF
Exhibit A FFDG General Terms and Conditions for Construction (01.2025).pdf PDF
Exhibit F SOW 4 houses upgrade.pdf PDF
Exhibit H Statement and Acknowledgment (Standard Form 1413) (Rev 42013).pdf PDF
1.0 Request for Proposal Construction 4 village houses.pdf PDF
Exhibit C Payment Bond FL-42 (Rev 12.22).pdf PDF
Exhibit D FL-41 (Rev 12.22) - Bid Bond.pdf PDF
Exhibit E Performance Bond FL-40 (Rev 12.22).pdf PDF
Exhibit B 2025 Construction Insurance Requirements.pdf PDF
Exhibit L 010010_General_Requirements_3_2022.pdf PDF
Exhibit M 013100_ESH_Requirements_3-2022.pdf PDF
Exhibit N 013300_Submittals.pdf PDF
Exhibit P Wage Determinations.pdf PDF
Exhibit Q Proposal Form.pdf PDF
Exhibit R 10-2-153_014100_Quality_Requirements_-_March_2024.pdf PDF
Exhibit S VILLAGE HOMES_GIS MAP.pdf PDF
Exhibit G Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit I Proposal Certifications Form PUR-466 Rev. 1 (10142021).pdf PDF
Exhibit J Subcontractor Annual Representations -Certifications (SARC) Form SARC (Rev. 3) (04082022).pdf PDF
Exhibit K FAR 52-219-9-Small-Business-Subcontracting-Plan-.pdf PDF
Exhibit O Sample Subcontract.pdf PDF
Show all 26

Similar open opportunities

Opportunity Agency Set-aside Responses due
Central Utility Building Addition and Renovation Construction, UIP Subproject 1-CUB Batavia, Illinois 60510, United States · NAICS 236210 Fermi National Accelerator Laboratory No set-aside
Wilson Hall Floor 16 Electric and Elevator Machine Rooms Fire Rating and Mechanical Upgrade Illinois 60510, United States · NAICS 236220 Fermi National Accelerator Laboratory Total Small Business
PIP-II F-37 building LWC pump room piping system installation Batavia, Illinois 60510, United States · NAICS 23822 Fermi National Accelerator Laboratory No set-aside
RFP 7-B164-P-00002-00 (RR GC BPA FY27) Lemont, Illinois 60439, United States · NAICS 236220 Office of Science No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors