This is Amendment 02 to solicitation ISD-358573-RK for interior upgrades to four village houses at Fermi National Accelerator Laboratory. The amendment extends the proposal due date from February 17, 2025 to February 24, 2025 at 3:00 PM CST.

The amendment provides answers to 15 contractor questions, clarifying several technical requirements: contractors must submit certified payroll showing prevailing wage payments, be fit-test trained for respirators, and be EPA Lead-Safe certified due to pre-1978 construction. FFDG will handle asbestos abatement of flooring. The scope includes replacing sinks/faucets, painting cabinet doors, window glazing replacement, electrical work (with confirmation of adequate panel capacity), standardizing to white outlet covers, LED lighting upgrades, bathroom renovations with greenboard drywall and FRP panels, and galvanized pipe replacement at three locations (28 Sauk, 19 Nequa, 12 Shabbona). Workers accessing crawl spaces for pipe replacement must be confined space trained and certified. A price sheet breaking out costs per house has been posted on SAM.gov.

View the file

Other files

File Type Posted
Exhibit P Wage Determinations.pdf PDF
Exhibit Q Proposal Form.pdf PDF
Amendment 01.pdf PDF
Price Sheet.xlsx XLSX spreadsheet
Exhibit C Payment Bond FL 42 (Rev 12.22).pdf PDF
Exhibit B 2025 Construction Insurance Requirements.pdf PDF
Exhibit L 010010_General_Requirements_3_2022.pdf PDF
Exhibit M 013100_ESH_Requirements_3-2022.pdf PDF
Exhibit N 013300_Submittals.pdf PDF
Exhibit P Wage Determinations.pdf PDF
Exhibit Q Proposal Form.pdf PDF
Exhibit R 10-2-153_014100_Quality_Requirements_-_March_2024.pdf PDF
Exhibit S VILLAGE HOMES_GIS MAP.pdf PDF
1.0 Request for Proposal Construction 4 village houses.pdf PDF
Exhibit C Payment Bond FL-42 (Rev 12.22).pdf PDF
Exhibit D FL-41 (Rev 12.22) - Bid Bond.pdf PDF
Exhibit E Performance Bond FL-40 (Rev 12.22).pdf PDF
Exhibit G Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit I Proposal Certifications Form PUR-466 Rev. 1 (10142021).pdf PDF
Exhibit J Subcontractor Annual Representations -Certifications (SARC) Form SARC (Rev. 3) (04082022).pdf PDF
Exhibit K FAR 52-219-9-Small-Business-Subcontracting-Plan-.pdf PDF
Exhibit O Sample Subcontract.pdf PDF
Exhibit A FFDG General Terms and Conditions for Construction (01.2025).pdf PDF
Exhibit F SOW 4 houses upgrade.pdf PDF
Exhibit H Statement and Acknowledgment (Standard Form 1413) (Rev 42013).pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT TO SOLICITATION

AMENDMENT NO.

DATE OF AMENDMENT:

February 17 , 2025

SOLICITATION (REQUEST FOR PROPOSAL) NO.

ISD-358573-RK

DATE RFP ISSUED:

January 05, 2025

PROJECT NO.

N/A

PROPOSAL CLOSE (DUE) DATE :

3:00 PM CT on February 17, 2025 Update : February 24 2025

TITLE OF PROJECT:

Four (4) village houses interior upgrade

Offerors must acknowledge this Amendment prior to the hour and date set forth in the solicitation by the following method:

1. Return the Amendment with a signature on the acknowledgment signature line.

If by virtue of this Amendment you desire to change an offer already submitted, such change may be made by email making reference to the Solicitation and this Amendment and it is received prior to the due date and time set for proposals.

The above referenced Solicitation is amended as follows:

• PROPOSAL DUE DATE

Current: The offeror’s proposal is to be emailed to the Procurement Specialist no later than 3:00 PM CST on February 17, 2025

Update: The offeror’s proposal is to be emailed to the Procurement Specialist no later than 3:00 PM CST on February 24, 2025

• QUESTIONS & ANSWERS

1. Will a new bid form be issued to note bids to be broken out per house remodel instead of a lump sum?

Yes, a price sheet has been issued and posted on Sam.gov

2. If this is a Fermi Lab, Davis Bacon Project, please confirm all contractors on the project will be required to submit certified payroll showing prevailing wage payments?

Yes , certified payroll submission is required.

3. Will Fermi Lab ES&H require all contractors involved in drywall demo & replacement work be fit test trained for respirators due to silica dust hazards & provide training proof with their safety hazard analysis submitted for each home being worked on?

- Yes, contractors will need to be fit test trained and wear silica dust respirators and provide training documentation.

- LEAD PAINT:

“Village housing was built prior to 1978 and falls under the US Environmental Protection Agency’s (EPA) Renovation, Repair, and Painting (RRP) Rule. Contractor shall be a US EPA Lead-Safe Certified Firm and shall conduct all work in accordance with RRP Rule requirements, including paint testing of all surfaces to be affected by the work using an EPA-recognized test kit, or other method. Firm and worker certification and training records shall be provided to

Fermilab prior to commencement of work. All additional records required under the RRP Rule shall be provided to Fermilab at the completion of the project.”

4. Have the kitchen floor sub layers mastic/tile to be removed been tested for asbestos?

- Yes the flooring has been tested for asbestos. FFDG will be responsible for abatement.

5. Are the stainless sinks & faucets in each kitchen also to be replaced with new?

- Yes replace with new stainless steel sinks and faucets.

6. In the kitchens, please confirm if the only the exteriors of the cabinets & both sides of the doors are to be painted.

- Both sides of cabinet doors are to be painted. Along with exterior trim.

7. At the walk thru for 14 Potawatomi, it was noted there was no window seal issues in the dining room and front room windows. Can those be eliminated from the scope of work?

- Please remove 14 Potawatomi windows from scope of work.

8. Regarding the notes for various window replacement, can the glazing be removed & replaced in lieu of changing out the entire window. This has been done in past repairs in village when the seals are broken.

- Yes just replace glazing on windows within scope of work.

9. Has it been confirmed in all four houses that there is enough room for 30A breakers to be added to the old service panels? If not, will Fermi lab be doing a service upgrade to the panel prior to the start of construction?

- 14 Potawatomi – Yes there is enough power on existing service panel.

- 19 Neuqua – Yes there is enough power on the existing service panel.

- 12 Shabbona – yes there is enough power on the existing service panel.

- 28 Sauk – Yes there is enough power on the existing service panel.

Additional electrical scope

- Add electrical circuits at the following locations for electric stoves:

(There is enough power at existing panels.)

o 14 Potawatomi o 19 Nequa o 12 Shabbona

10. Regarding electrical switch & outlet cover plates, the houses do not have the same consistent plates throughout. Will it be required to change them out? If so, what will the required finish be?

- Replace all outlet covers with white outlet covers to match.

- Ensure GFCI outlets are installed in all wet walls per code.

11. Is there a spec on the type of LED lighting that is required throughout the homes in the village?

- Match existing light fixture types with LED. Contractor to select light fixtures.

12. Please clarify if new tub & surround are to be removed & relaced with similar or if a walk-in shower unit will be required to replace the tub. A walk-in shower would then require new full height doors or a shower curtain.

1. Replace with similar per scope of work.

13. In the four bathrooms, please clarify if existing old drywall is to be removed on walls & ceiling and replaced with mold resistant green board as has been done in other home remodels in the Fermi Village recently.

1. Yes, all drywall is to be replaced with Greenboard.

14. In the four bathrooms, please confirm if white FRP panels will be installed on the walls & above the tub/shower surround to match recently remodeled bathrooms in the Fermi Lab Village.

1. Yes, install FRP above tub / shower along with wet walls.

15. At the walk thru, it was commented by a Fermi Lab employee that certain homes may have been already changed from galvanized to copper pipe. Please confirm.

1. – Galvanized pipe replacement will be needed at.

- 28 Sauk.

- 19 Nequa.

- 12 Shabbona.

2. 14 Potawatomi does not need galvanized pipe replacement.

PLEASE NOTE THAT THE CRAWL SPACES THAT WILL NEED TO BE ACCESSED IN ORDER TO

REPLACE GALVINIZED PIPES ARE CONSIDERED NON PERMITTED CONFINED SPACES AND

WORKERS USING THAT SPACE WILL NEED TO BE CONFINED SPACE TRAINED AND CERTIFIED.

All other terms and conditions as referenced under the subject RFP remain unchanged.

Kindly acknowledge receipt by signing and returning one (1) copy of this Amendment.

Company Name

Signature & Date

Name & Title of Individual

Fermi Forward Discovery Group, LLC Kirk Road & Wilson St.

P.O. Box 500, MS 312

Batavia, Illinois 60510-0500 USA

Richard Konan Procurement Specialist III

(630) 840 2835 rkonan@fnal.gov mailto:damico@fnal.gov