The Defense Logistics Agency is seeking qualified contractors to construct Dry Swale 3, a stormwater management facility at Defense Supply Center Richmond in Virginia. The procurement involves installation of silt fence, erosion and sediment control measures, a 12-inch thick concrete weir wall (either cast-in-place or precast), a 6-inch PVC underdrain system, and a new chain-link fence, with all work to be completed within 60 days of notice to proceed. Contractors must demonstrate a minimum of five years of relevant experience in stormwater management facility construction, possess valid insurance coverage, obtain base access clearance, and ensure all personnel are OSHA certified and federally trained in environmental compliance. Award will be made to the Lowest Priced Technically Acceptable offeror based on a firm-fixed price evaluation. Critical deadlines include April 6, 2026 for submission of questions and April 24, 2026 for quote submission via email to contracting officer Robert Moragues, with a mandatory site visit scheduled for April 2, 2026 at 10:00 AM that requires security vetting within 5 business days.

This acquisition is set-aside for 100 percent small business under NAICS code 238910 (Site Preparation Contractors), with a small business size standard of $19 million. No incumbent contractor is identified in the solicitation materials. The estimated award value ranges from $125,000 to $175,000, and the contract will have a 60-day period of performance beginning from issuance of notice to proceed. Performance location is Richmond, Virginia (Chesterfield County), with contractors required to maintain a place of business within 125 miles of the site. Prevailing wage rates established by the Department of Labor apply based on Chesterfield County location, and contractors must comply with Virginia Department of Environmental Quality standards, EPA Phase II Watershed Implementation Plan requirements, and all federal environmental and safety regulations, with payment not to exceed 80 percent of the contract value until final inspection acceptance and one-year warranty coverage required after project completion.

Notice text

3 versions

Update #3 · Latest ·

Amendment 0002 for solicitation SP470326Q0026 is being issued to extend the deadline for quote. The new deadline for quote is COB 04/24/26. See attached document SF30 SP470326Q00260002.pdf for formal SF30 amendment.

Amendment 0001 for solicitation SP470326Q0026 is being issued due to minor SOW revisions. 
The SOW has been revised to specify the option for using precast concrete is allowed, and the underdrain system has been changed to specify 6" PVC, instead of the previously specified 12" RCP. 

All other terms and conditions remain unchanged.

The revised SOW is attached in filename "DSCR - Swale 3 - SOW - Rev 1.pdf"

This is a combined synopsis/solicitation for commercially available services prepared in accordance with the format in FAR Part 12, and supplemented with additional information included in this notice.  The solicitation number SP470326Q0026 is issued as a request for quote(RFQ).  Award will be made to the Lowest Priced Technically Acceptable offeror.   

The resulting contract will be a firm-fixed price award with an expected Period of Performance of 60 days from issuance of notice to proceed. 

Disclosure of magnitude: the estimated magnitude of the award is between $125,000.00 - $175,000.00

This acquisition is set-aside for 100% small business.  

The North American Industry Classification System (NAICS) Code is 238910 (SITE PREPARATION CONTRACTORS).  

The small business size standard is $19M.

 Department of Labor Wage Determination based on location of the service provided (Chesterfield County, VA).  

Partial proposals will not be accepted.  

A site visit will be held on 04/02/2026 @ 10:00. See "Additional Details" below for full text for parties interested in attending the site visit. Please note: Parties interested in attending the site visit MUST be vetted through security prior to the date of the site visit - vetting can take 5 business days, interested parties should plan accordingly. 

Deadline for questions is COB 04/06/2026 - submit questions via email to the contracting officer, Robert Moragues<Robert.Moragues@dla.mil> All Questions and Answers will be publicly posted, as a single attachment, to the same notice id on SAM.gov as the solicitation.  Generally, answers will be posted to SAM.gov within 2 working days of the deadline for questions.  

The revised deadline for quote is COB 04/24/2026.  

Acceptable method of quote: Email to contracting officer Robert Moragues <Robert.Moragues@dla.mil>


******************************Specific Requirements*******************

For an offer to be considered for award, the contractor must own, possess, or otherwise control a bona fide place of business from which mobilization occurs within 125 miles of Defense Supply Center Richmond. A bona fide place of business refers to a location where the offeror regularly maintains an office with at least one full-time employee. The offeror must include the address of this location within the offer submitted.

OBJECTIVES

The objective of this project is to construct the Dry Swale 3 stormwater management facility within the Elk Pasture area on the Defense Supply Center Richmond (DSCR) installation. This work will be executed in accordance with the attached 100% Site Plans dated 09/03/2021. The project aims to provide sediment and nutrient removal for stormwater runoff to ensure compliance with the Virginia Department of Environmental Quality (DEQ) and Environmental Protection Agency (EPA) watershed implementation plans. Components to include excavation, grading, installation of underdrain systems, and geotextile will be completed by the DSCR Maintenance group. The concrete wall, a temporary silt fence, and new chain link fence to protect Dy Swale 3 from the elk are to be constructed by the contractor.

BACKGROUND

DSCR is implementing a comprehensive stormwater management program to protect the local watershed and comply with environmental mandates. The Elk Pasture area, a 26-acre preserve, has been identified for the installation of five dry swales to treat stormwater runoff before it enters Kingsland Creek, which ultimately drains to the Chesapeake Bay. This Statement of Work focuses exclusively on the construction of Dry Swale 3. The existing site consists primarily of grass and trees with variable topography. The construction of this engineered dry swale is essential for meeting sediment and nutrient removal goals established in the Phase II Watershed Implementation Plan.

SPECIFIC REQUIREMENTS

The contractor shall provide all labor, materials, and equipment to complete the construction of Dry Swale 3 listed below as detailed in the attached project plans (2021-09-03 Elk Pasture - 100% Site Plans). The work shall only include the scope for the Dry Swale 3 items. Specific requirements include:


Erosion and Sediment Control:

-Install silt fence (SF) along the perimeter of the Dry Swale 3 work area as shown on sheet CD102 and in accordance with the detail on sheet C-501 coordinate with FRIE Project manager for exact location of silt fence as the project is only for Dry Swale 3, silt fence material to be provided by DSCR Installation.

-Implement all erosion and sediment control measures for Dry Swale 3 detailed in the attached drawings.

-Protect all existing storm drain inlets with inlet protection (IP) as specified.

Dry Swale 3 Construction:

-Construct the concrete weir wall as detailed on sheets CS102, C-302, and C-503. The wall
shall be 12" thick and include all specified concrete and rebar. Wall can be either cast in
place or precast.

-Install the underdrain system, only to include the section under the concrete wall, 6” PVC
underdrain pipe to be provided by DSCR

-Install a new chain link fence around the Dry Swale 3 site. (Note: The type, height, and specific location of the new fence are not detailed in the provided project plans. The contractor shall propose a fence that matches DSCR standards for the existing elk fence, assumed to be an 8-foot chain-link fence (verify in field) to match existing site fencing, for approval by the FRIE Project Manager.


Security Considerations:

-Coordinate access control through FRIE project manager with DSCR Police during construction to maintain site security.


CONTRACTOR QUALIFICATIONS

All contractors submitting proposals must demonstrate a minimum of five (5) years of relevant experience in projects of similar size and scope. They should demonstrate expertise in the construction of stormwater management facilities, including earthwork, grading, installation of underground utilities and underdrain systems, and reinforced concrete construction. Familiarity with Virginia DEQ Stormwater Management Handbook standards, Department of Defense construction standards, and Unified Facilities Criteria (UFC) is essential. All personnel must be OSHA-certified and trained in federal environmental compliance. Contractors must be capable of obtaining base access clearance and adhering to DSCR security protocols as detailed later in this SOW. Must possess valid insurance coverage including general liability, workers’ compensation, and vehicle insurance. Experience must be clearly documented and verifiable, including references from at least three (3) similar projects, project descriptions, and timelines. All contractors submitting proposals must provide contract number in addition to the above qualifications in order to be considered.

PERIOD OF PERFORMANCE

Completion date shall be no later than 60 days after notice to proceed.

SEE SOW FOR FULL PROJECT REQUIREMENT DETAILS


***************ADDITIONAL INFORMATION************************

A site visit will be held 04/02/2026 @ 10:00.  See p.47 of SOW for DSCR map for location of the site visit meeting location and parking location.  Parking/Meeting location is marked with a red dot toward the bottom of the map found of p.47 of the SOW.

In order to attend the site visit interested parties MUST follow the instructions below no less than 5 business days prior to the site visit.  This is to allow time for vetting by base security.  Plan on arriving at DSCR an hour prior to the site visit time, as the processing time through the visitor center fluctuates.  Follow the link below to register through DBIDS, and a QR code should be provided for each visitor.  Visitors(site visit attendees) then MUST email QR codes to the Project Manager, Rob Miller<robert.c.miller@dla.mil> (Work Cell: (804) 239-6891).  The QR code MUST be emailed to the project manager as soon as possible due to the lengthy vetting process of approximately 5 business days. The project manager will also serve as the sponsor for site visit attendees.  

A new system was implemented on 3 January 2023 to screen visitors and contractors for installation access at DSCR.The new system is designed to increase efficiencies, enhance the protection of personal information during the vetting process and eliminate the use of hard copy DLA Form 1815s.  The new screening system will require visitors and contractors to pre-enroll in DBIDS (Defense Biometric Identification System). To begin the process, visitors and contractors will complete registration through the pre-enrollment website: 

https://dbids-global-enroll.dmdc.mil.

Upon entry of their information, visiting personnel will be provided an electronic form to download, which will have an individualized barcode and alpha numeric code. The codes need to be sent to the visiting person’s sponsor. Once in receipt of the barcode, the sponsor will email Security and Emergency Services and provide the barcode and sponsorship information. Once the visitor/contractor is vetted and approved for installation access, Security & Emergency Services will notify the sponsor that the visitor/contractor can go to the DSCR Visitor Center to obtain his/her pass. At the Visitor Center, the visitor provides the barcode and code provided earlier in the process and completes the credentialing process.

See attached SOW for full requirement details. Parties interested in submitting a quote for this project are advised and expected to have reviewed the entire SOW prior to site visit attendance.  

Update #2 ·

Amendment 0001 for solicitation SP470326Q0026 is being issued due to minor SOW revisions. 
The SOW has been revised to specify the option for using precast concrete is allowed, and the underdrain system has been changed to specify 6" PVC, instead of the previously specified 12" RCP. 

All other terms and conditions remain unchanged.

The revised SOW is attached in filename "DSCR - Swale 3 - SOW - Rev 1.pdf"

This is a combined synopsis/solicitation for commercially available services prepared in accordance with the format in FAR Part 12, and supplemented with additional information included in this notice.  The solicitation number SP470326Q0026 is issued as a request for quote(RFQ).  Award will be made to the Lowest Priced Technically Acceptable offeror.   

The resulting contract will be a firm-fixed price award with an expected Period of Performance of 60 days from issuance of notice to proceed. 

Disclosure of magnitude: the estimated magnitude of the award is between $125,000.00 - $175,000.00

This acquisition is set-aside for 100% small business.  

The North American Industry Classification System (NAICS) Code is 238910 (SITE PREPARATION CONTRACTORS).  

The small business size standard is $19M.

 Department of Labor Wage Determination based on location of the service provided (Chesterfield County, VA).  

Partial proposals will not be accepted.  

A site visit will be held on 04/02/2026 @ 10:00. See "Additional Details" below for full text for parties interested in attending the site visit. Please note: Parties interested in attending the site visit MUST be vetted through security prior to the date of the site visit - vetting can take 5 business days, interested parties should plan accordingly. 

Deadline for questions is COB 04/06/2026 - submit questions via email to the contracting officer, Robert Moragues<Robert.Moragues@dla.mil> All Questions and Answers will be publicly posted, as a single attachment, to the same notice id on SAM.gov as the solicitation.  Generally, answers will be posted to SAM.gov within 2 working days of the deadline for questions.  

Deadline for quote is COB 04/17/2026.  

Acceptable method of quote: Email to contracting officer Robert Moragues <Robert.Moragues@dla.mil>


******************************Specific Requirements*******************

For an offer to be considered for award, the contractor must own, possess, or otherwise control a bona fide place of business from which mobilization occurs within 125 miles of Defense Supply Center Richmond. A bona fide place of business refers to a location where the offeror regularly maintains an office with at least one full-time employee. The offeror must include the address of this location within the offer submitted.

OBJECTIVES

The objective of this project is to construct the Dry Swale 3 stormwater management facility within the Elk Pasture area on the Defense Supply Center Richmond (DSCR) installation. This work will be executed in accordance with the attached 100% Site Plans dated 09/03/2021. The project aims to provide sediment and nutrient removal for stormwater runoff to ensure compliance with the Virginia Department of Environmental Quality (DEQ) and Environmental Protection Agency (EPA) watershed implementation plans. Components to include excavation, grading, installation of underdrain systems, and geotextile will be completed by the DSCR Maintenance group. The concrete wall, a temporary silt fence, and new chain link fence to protect Dy Swale 3 from the elk are to be constructed by the contractor.

BACKGROUND

DSCR is implementing a comprehensive stormwater management program to protect the local watershed and comply with environmental mandates. The Elk Pasture area, a 26-acre preserve, has been identified for the installation of five dry swales to treat stormwater runoff before it enters Kingsland Creek, which ultimately drains to the Chesapeake Bay. This Statement of Work focuses exclusively on the construction of Dry Swale 3. The existing site consists primarily of grass and trees with variable topography. The construction of this engineered dry swale is essential for meeting sediment and nutrient removal goals established in the Phase II Watershed Implementation Plan.

SPECIFIC REQUIREMENTS

The contractor shall provide all labor, materials, and equipment to complete the construction of Dry Swale 3 listed below as detailed in the attached project plans (2021-09-03 Elk Pasture - 100% Site Plans). The work shall only include the scope for the Dry Swale 3 items. Specific requirements include:


Erosion and Sediment Control:

-Install silt fence (SF) along the perimeter of the Dry Swale 3 work area as shown on sheet CD102 and in accordance with the detail on sheet C-501 coordinate with FRIE Project manager for exact location of silt fence as the project is only for Dry Swale 3, silt fence material to be provided by DSCR Installation.

-Implement all erosion and sediment control measures for Dry Swale 3 detailed in the attached drawings.

-Protect all existing storm drain inlets with inlet protection (IP) as specified.

Dry Swale 3 Construction:

-Construct the concrete weir wall as detailed on sheets CS102, C-302, and C-503. The wall
shall be 12" thick and include all specified concrete and rebar. Wall can be either cast in
place or precast.

-Install the underdrain system, only to include the section under the concrete wall, 6” PVC
underdrain pipe to be provided by DSCR

-Install a new chain link fence around the Dry Swale 3 site. (Note: The type, height, and specific location of the new fence are not detailed in the provided project plans. The contractor shall propose a fence that matches DSCR standards for the existing elk fence, assumed to be an 8-foot chain-link fence (verify in field) to match existing site fencing, for approval by the FRIE Project Manager.


Security Considerations:

-Coordinate access control through FRIE project manager with DSCR Police during construction to maintain site security.


CONTRACTOR QUALIFICATIONS

All contractors submitting proposals must demonstrate a minimum of five (5) years of relevant experience in projects of similar size and scope. They should demonstrate expertise in the construction of stormwater management facilities, including earthwork, grading, installation of underground utilities and underdrain systems, and reinforced concrete construction. Familiarity with Virginia DEQ Stormwater Management Handbook standards, Department of Defense construction standards, and Unified Facilities Criteria (UFC) is essential. All personnel must be OSHA-certified and trained in federal environmental compliance. Contractors must be capable of obtaining base access clearance and adhering to DSCR security protocols as detailed later in this SOW. Must possess valid insurance coverage including general liability, workers’ compensation, and vehicle insurance. Experience must be clearly documented and verifiable, including references from at least three (3) similar projects, project descriptions, and timelines. All contractors submitting proposals must provide contract number in addition to the above qualifications in order to be considered.

PERIOD OF PERFORMANCE

Completion date shall be no later than 60 days after notice to proceed.

SEE SOW FOR FULL PROJECT REQUIREMENT DETAILS


***************ADDITIONAL INFORMATION************************

A site visit will be held 04/02/2026 @ 10:00.  See p.47 of SOW for DSCR map for location of the site visit meeting location and parking location.  Parking/Meeting location is marked with a red dot toward the bottom of the map found of p.47 of the SOW.

In order to attend the site visit interested parties MUST follow the instructions below no less than 5 business days prior to the site visit.  This is to allow time for vetting by base security.  Plan on arriving at DSCR an hour prior to the site visit time, as the processing time through the visitor center fluctuates.  Follow the link below to register through DBIDS, and a QR code should be provided for each visitor.  Visitors(site visit attendees) then MUST email QR codes to the Project Manager, Rob Miller<robert.c.miller@dla.mil> (Work Cell: (804) 239-6891).  The QR code MUST be emailed to the project manager as soon as possible due to the lengthy vetting process of approximately 5 business days. The project manager will also serve as the sponsor for site visit attendees.  

A new system was implemented on 3 January 2023 to screen visitors and contractors for installation access at DSCR.The new system is designed to increase efficiencies, enhance the protection of personal information during the vetting process and eliminate the use of hard copy DLA Form 1815s.  The new screening system will require visitors and contractors to pre-enroll in DBIDS (Defense Biometric Identification System). To begin the process, visitors and contractors will complete registration through the pre-enrollment website: 

https://dbids-global-enroll.dmdc.mil.

Upon entry of their information, visiting personnel will be provided an electronic form to download, which will have an individualized barcode and alpha numeric code. The codes need to be sent to the visiting person’s sponsor. Once in receipt of the barcode, the sponsor will email Security and Emergency Services and provide the barcode and sponsorship information. Once the visitor/contractor is vetted and approved for installation access, Security & Emergency Services will notify the sponsor that the visitor/contractor can go to the DSCR Visitor Center to obtain his/her pass. At the Visitor Center, the visitor provides the barcode and code provided earlier in the process and completes the credentialing process.

See attached SOW for full requirement details. Parties interested in submitting a quote for this project are advised and expected to have reviewed the entire SOW prior to site visit attendance.  

Update #1 ·

This is a combined synopsis/solicitation for commercially available services prepared in accordance with the format in FAR Part 12, and supplemented with additional information included in this notice.  The solicitation number SP470326Q0026 is issued as a request for quote(RFQ).  Award will be made to the Lowest Priced Technically Acceptable offeror.   

The resulting contract will be a firm-fixed price award with an expected Period of Performance of 60 days from issuance of notice to proceed. 

Disclosure of magnitude: the estimated magnitude of the award is between $125,000.00 - $175,000.00

This acquisition is set-aside for 100% small business.  

The North American Industry Classification System (NAICS) Code is 238910 (SITE PREPARATION CONTRACTORS).  

The small business size standard is $19M.

 Department of Labor Wage Determination based on location of the service provided (Chesterfield County, VA).  

Partial proposals will not be accepted.  

A site visit will be held on 04/02/2026 @ 10:00. See "Additional Details" below for full text for parties interested in attending the site visit. Please note: Parties interested in attending the site visit MUST be vetted through security prior to the date of the site visit - vetting can take 5 business days, interested parties should plan accordingly. 

Deadline for questions is COB 04/06/2026 - submit questions via email to the contracting officer, Robert Moragues<Robert.Moragues@dla.mil> All Questions and Answers will be publicly posted, as a single attachment, to the same notice id on SAM.gov as the solicitation.  Generally, answers will be posted to SAM.gov within 2 working days of the deadline for questions.  

Deadline for quote is COB 04/17/2026.  

Acceptable method of quote: Email to contracting officer Robert Moragues <Robert.Moragues@dla.mil>


******************************Specific Requirements*******************

For an offer to be considered for award, the contractor must own, possess, or otherwise control a bona fide place of business from which mobilization occurs within 125 miles of Defense Supply Center Richmond. A bona fide place of business refers to a location where the offeror regularly maintains an office with at least one full-time employee. The offeror must include the address of this location within the offer submitted.

OBJECTIVES

The objective of this project is to construct the Dry Swale 3 stormwater management facility within the Elk Pasture area on the Defense Supply Center Richmond (DSCR) installation. This work will be executed in accordance with the attached 100% Site Plans dated 09/03/2021. The project aims to provide sediment and nutrient removal for stormwater runoff to ensure compliance with the Virginia Department of Environmental Quality (DEQ) and Environmental Protection Agency (EPA) watershed implementation plans. Components to include excavation, grading, installation of underdrain systems, and geotextile will be completed by the DSCR Maintenance group. The concrete wall, a temporary silt fence, and new chain link fence to protect Dy Swale 3 from the elk are to be constructed by the contractor.

BACKGROUND

DSCR is implementing a comprehensive stormwater management program to protect the local watershed and comply with environmental mandates. The Elk Pasture area, a 26-acre preserve, has been identified for the installation of five dry swales to treat stormwater runoff before it enters Kingsland Creek, which ultimately drains to the Chesapeake Bay. This Statement of Work focuses exclusively on the construction of Dry Swale 3. The existing site consists primarily of grass and trees with variable topography. The construction of this engineered dry swale is essential for meeting sediment and nutrient removal goals established in the Phase II Watershed Implementation Plan.

SPECIFIC REQUIREMENTS

The contractor shall provide all labor, materials, and equipment to complete the construction of Dry Swale 3 listed below as detailed in the attached project plans (2021-09-03 Elk Pasture - 100% Site Plans). The work shall only include the scope for the Dry Swale 3 items. Specific requirements include:


Erosion and Sediment Control:

-Install silt fence (SF) along the perimeter of the Dry Swale 3 work area as shown on sheet CD102 and in accordance with the detail on sheet C-501 coordinate with FRIE Project manager for exact location of silt fence as the project is only for Dry Swale 3, silt fence material to be provided by DSCR Installation.

-Implement all erosion and sediment control measures for Dry Swale 3 detailed in the attached drawings.

-Protect all existing storm drain inlets with inlet protection (IP) as specified.

Dry Swale 3 Construction:

-Construct the concrete weir wall as detailed on sheets CS102, C-302, and C-503. The wall shall be 12" thick and include all specified concrete and rebar.

-Install the underdrain system, only to include the section under the concrete wall, pipe to be provided by DSCR.

-Install a new chain link fence around the Dry Swale 3 site. (Note: The type, height, and specific location of the new fence are not detailed in the provided project plans. The contractor shall propose a fence that matches DSCR standards for the existing elk fence, assumed to be an 8-foot chain-link fence (verify in field) to match existing site fencing, for approval by the FRIE Project Manager.


Security Considerations:

-Coordinate access control through FRIE project manager with DSCR Police during construction to maintain site security.


CONTRACTOR QUALIFICATIONS

All contractors submitting proposals must demonstrate a minimum of five (5) years of relevant experience in projects of similar size and scope. They should demonstrate expertise in the construction of stormwater management facilities, including earthwork, grading, installation of underground utilities and underdrain systems, and reinforced concrete construction. Familiarity with Virginia DEQ Stormwater Management Handbook standards, Department of Defense construction standards, and Unified Facilities Criteria (UFC) is essential. All personnel must be OSHA-certified and trained in federal environmental compliance. Contractors must be capable of obtaining base access clearance and adhering to DSCR security protocols as detailed later in this SOW. Must possess valid insurance coverage including general liability, workers’ compensation, and vehicle insurance. Experience must be clearly documented and verifiable, including references from at least three (3) similar projects, project descriptions, and timelines. All contractors submitting proposals must provide contract number in addition to the above qualifications in order to be considered.

PERIOD OF PERFORMANCE

Completion date shall be no later than 60 days after notice to proceed.

SEE SOW FOR FULL PROJECT REQUIREMENT DETAILS


***************ADDITIONAL INFORMATION************************

A site visit will be held 04/02/2026 @ 10:00.  See p.47 of SOW for DSCR map for location of the site visit meeting location and parking location.  Parking/Meeting location is marked with a red dot toward the bottom of the map found of p.47 of the SOW.

In order to attend the site visit interested parties MUST follow the instructions below no less than 5 business days prior to the site visit.  This is to allow time for vetting by base security.  Plan on arriving at DSCR an hour prior to the site visit time, as the processing time through the visitor center fluctuates.  Follow the link below to register through DBIDS, and a QR code should be provided for each visitor.  Visitors(site visit attendees) then MUST email QR codes to the Project Manager, Rob Miller<robert.c.miller@dla.mil> (Work Cell: (804) 239-6891).  The QR code MUST be emailed to the project manager as soon as possible due to the lengthy vetting process of approximately 5 business days. The project manager will also serve as the sponsor for site visit attendees.  

A new system was implemented on 3 January 2023 to screen visitors and contractors for installation access at DSCR.The new system is designed to increase efficiencies, enhance the protection of personal information during the vetting process and eliminate the use of hard copy DLA Form 1815s.  The new screening system will require visitors and contractors to pre-enroll in DBIDS (Defense Biometric Identification System). To begin the process, visitors and contractors will complete registration through the pre-enrollment website: 

https://dbids-global-enroll.dmdc.mil.

Upon entry of their information, visiting personnel will be provided an electronic form to download, which will have an individualized barcode and alpha numeric code. The codes need to be sent to the visiting person’s sponsor. Once in receipt of the barcode, the sponsor will email Security and Emergency Services and provide the barcode and sponsorship information. Once the visitor/contractor is vetted and approved for installation access, Security & Emergency Services will notify the sponsor that the visitor/contractor can go to the DSCR Visitor Center to obtain his/her pass. At the Visitor Center, the visitor provides the barcode and code provided earlier in the process and completes the credentialing process.

See attached SOW for full requirement details. Parties interested in submitting a quote for this project are advised and expected to have reviewed the entire SOW prior to site visit attendance.  

Files

File Type Posted
SF30 SP470326Q00260002.pdf PDF
Q and A SP470326Q0026.xlsx XLSX spreadsheet
DSCR - Swale 3 - SOW - Rev 1.pdf PDF
Pre-Bid site visit sign in sheet.pdf PDF
SF30 SP470326Q00260001.pdf PDF
SOW_DSCR_Swale 3.pdf PDF
SF1449_SP470326Q0026.pdf PDF
2021 09 03 Elk Pasture Site Plans.pdf PDF
Wage Determination.pdf PDF

Similar open opportunities

Opportunity Agency Set-aside Responses due
DSCR B34 & B42 System Smoke Testing & Hydro Jetting Richmond, Virginia, United States · NAICS 236220 Defense Logistics Agency Total Small Business
Z2NZ-- 658-23-108 Correct Stormwater Drainage Salem, Virginia 24153, United States · NAICS 237110 Veterans Integrated Service Network 6 Service-Disabled Veteran-Owned Small Business
JBMHH Stormwater Management Facility Maintenance and Repair Services Fort Myer, Virginia 22211, United States · NAICS 562998 MICC Fort Sam Houston No set-aside
Fort Eustis Dredge Material Management Area (FEDMMA) Fort Eustis, Virginia, United States · NAICS 237990 ENDIST Norfolk Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity