CA FTFS 0007(1) Fibreboard Road
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 6982AF21B000009
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Truckee, California, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks road reconstruction services for Forest Route 07, also known as Fibreboard Road, located in Tahoe National Forest, California. The Federal Highway Administration is procuring these services to reconstruct approximately 2.51 miles of the roadway beginning at the eastern forest boundary near State Route 89, with an option to improve an additional 0.68 miles if funding permits. Work will include pulverizing existing asphalt and adding aggregate base, with some sections requiring full depth reclamation involving asphalt emulsion or Portland cement. The roadway is to be paved to match existing width. The evaluation criteria will consider price and technical factors. The deadline for questions is May 7th and bids are due by May 20th.
This opportunity is designated as a total small business set-aside. The NAICS code is 237110 and PSC code is R499. The estimated value ranges from $2.5 to $4 million. Key quantities include 29,500 square yards of full depth reclamation and 5,000 tons of asphalt paving. Construction is scheduled to take place from June to October 2021 within Tahoe National Forest, California. The soliciting agency is the Department of Transportation Federal Highway Administration.
Notice text
THIS PROJECT IS ADVERTISED AS A TOTAL SMALL BUSINESS SET-ASIDE.
THIS IS A REQUEST FOR BID - PLANS AND SPECIFICATIONS ARE AVAILABLE.
PROJECT NUMBER: CA FTFS 0007(1)
PROJECT NAME: Fibreboard Road
PROJECT DESCRIPTION: The project is located on Fibreboard Road (Forest Route 07) in Tahoe National Forest, California. Fibreboard Road is located west of State Route 89, approximately 15 miles north of the intersection of State Route 89 with Interstate 80 in Truckee, California.
The Forest Service (Tahoe National Forest) maintains Forest Route 07, also known as Fibreboard Road, in Sierra County, California. The road begins at State Route (SR) 89 just outside the Forest boundary and continues in a southwest-west direction for about 16.3 miles across the Forest to Jackson Meadows Reservoir. The road currently suffers from significant thermal cracking, rutting, and potholing due to severe winter weather and the presence of snowplows on a portion of the route. The purpose of the project is to improve the roadway surface and reduce yearly maintenance costs. Funding for the project is through a combination of FHWA’s Federal Lands Transportation Program and Forest Service funds.
The project includes reconstructing 2.51 miles of Forest Route 07, beginning at the eastern Forest boundary near SR 89. An additional 0.68 miles of the road continuing west may also be improved if funding is available.
Road reconstruction would consist of pulverizing the existing asphalt and adding crushed aggregate base. Some sections of the roadway may require full depth reclamation which involves blending asphalt emulsion or Portland cement with the pulverized material to provide an adequate structural layer. The roadway would then be paved to match the existing roadway width. All work would occur within the existing roadway. In addition, the road would be striped and signs may be replaced, as needed. No drainage improvements or other work is anticipated.
Staging areas would be identified along the road or in previously disturbed areas, such as existing pull-outs, approved for such use by the Forest Service. Construction is planned for summer 2021 and would likely take about 4-6 months. All work would remain on the existing roadway bench, and no vegetation removal or new disturbance beyond the roadway is planned.
Construction equipment anticipated to be used includes: pulverizer, asphalt truck, spreader, compacter, dump truck, skid-steer, backhoe loader, motor grader and excavator.
The contract will be advertised with a Bid Schedule (Schedule A) and 2 Bid Options (Option X and Y).
SIGNIFICANT QUANTITIES:
Schedule A:
- Full Depth Reclamation with Cement, 6-Inch Depth – 29,500 SQYD
- Asphalt Concrete Pavement – 5,000 TON
Option X:
- Full Depth Reclamation with Cement, 6-Inch Depth – 5,300 SQYD
- Asphalt Concrete Pavement – 920 TON
Option Y:
- Full Depth Reclamation with Cement, 6-Inch Depth – 3,430 SQYD
- Asphalt Concrete Pavement –755 TON
COST RANGE: The proposed project is estimated at a cost between $2.5 million and $4 million.
CONSTRUCTION DURATION: Construction is anticipated from June, 2021 thru October, 2021.
Files
Notice history
| Notice | Type | Posted |
|---|---|---|
| CA FTFS 0007(1) Fibreboard Road | Award Notice | |
| This notice | Solicitation | |
| CA FTFS 0007(1) Fibreboard Road | Pre-Solicitation | |
| CA FTFS 0007(1) Fibreboard Road | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Jake Rocks Road Reconstruction | Forest Service | Total Small Business | |
| CO-rocky MTN arsnl NWR-patch hill road | — | No set-aside | |
| Cowboy Hat Stewardship IRSC - Lake Tahoe Basin Management Unit | Forest Service | Total Small Business | |
| Administrative Parking Lot Repairs | Forest Service | Total Small Business | |
| GAOA Pine Creek Vault Toilet HTNF | Forest Service | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity