This document summarizes a federal contract solicitation for road reconstruction services. The solicitation involves reconstructing 2.51 miles and potentially an additional 0.68 miles of Fibreboard Road located in Tahoe National Forest, California. Work includes pulverizing existing asphalt, adding aggregate base, and full depth reclamation of some sections. The road would then be paved to match existing width and signed. Estimated costs range from $2.5 to $4 million. The bid schedule includes a base schedule and two options. Significant quantities include full depth reclamation of 29,500 square yards for the base schedule and 5,300 square yards for Option X. The solicitation is set aside for small businesses. Construction is planned from June to October 2021. The soliciting agency is the Federal Highway Administration.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 05/21/21
1 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Contractor Responsive?
Engineer's Estimate
Hat Creek Construction & Materials, Inc.
Meyers Earthwork Inc.
MKD Construction, Inc.
Base Schedule A
$2,460,000.00
$2,051,989.00
$2,088,714.00
$3,106,519.15
Option: X
$457,000.00
$384,000.00
$379,223.00
$592,575.35
Option: Y
$316,875.00
$294,000.00
$263,596.00
$439,682.50
Contractor Responsive?
Engineer's Estimate
Hat Creek Construction & Materials, Inc.
Meyers Earthwork Inc.
MKD Construction, Inc.
Total Base Schedule A and Option(s): X
$2,917,000.00
$2,435,989.00
$2,467,937.00
$3,699,094.50
Total Base Schedule A and Option(s): XY
$3,233,875.00
$2,729,989.00
$2,731,533.00
$4,138,777.00
Total Base Schedule A and Option(s): Y
$2,776,875.00
$2,345,989.00
$2,352,310.00
$3,546,201.65
NO
YES
YES
NO
YES
YES
2 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: A
Schedule Type: Base
Solcitation No: 6982AF21B000009
Division: Central Federal Lands
State: CA County: Sierra
Federal Land: Tahoe National Forest Opened at: Lakewood, CO
Opened by: Leslie Karsten
Date: 05/20/21
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Hat Creek Construction & Materials, Inc. $2,051,989.00 24339 Highway 89 N Burney, CA 96013
Meyers Earthwork Inc. $2,088,714.00 4150 Fig Tree Lane Redding, CA 96002
MKD Construction, Inc. $3,106,519.15 20 Stokes Drive Mound House, NV 89706
Engineer's Estimate $2,460,000.00
Contract Specialist
05/21/2021
3 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0100 15101-0000 MOBILIZATION
Hat Creek Construction & Materials, Inc. Lump Sum $205,000.00 Meyers Earthwork Inc. Lump Sum $200,000.00 MKD Construction, Inc. Lump Sum $307,284.15 Engineer's Estimate ALL LPSM Lump Sum $287,190.00
A0120 15210-3000 CENTERLINE, VERIFICATION AND STAKING
Hat Creek Construction & Materials, Inc. $6,140.35 $14,000.00 Meyers Earthwork Inc. $10,000.00 $22,800.00 MKD Construction, Inc. $26,300.00 $59,964.00 Engineer's Estimate 2.280 MILE $10,000.00 $22,800.00
A0140 15301-0000 CONTRACTOR QUALITY CONTROL
Hat Creek Construction & Materials, Inc. Lump Sum $101,732.00 Meyers Earthwork Inc. Lump Sum $50,000.00 MKD Construction, Inc. Lump Sum $12,900.00 Engineer's Estimate ALL LPSM Lump Sum $64,800.00
A0160 15401-0000 CONTRACTOR TESTING
Hat Creek Construction & Materials, Inc. Lump Sum $225,000.00 Meyers Earthwork Inc. Lump Sum $73,400.00 MKD Construction, Inc. Lump Sum $64,900.00 Engineer's Estimate ALL LPSM Lump Sum $64,800.00
A0180 15501-0000 CONSTRUCTION SCHEDULE
Hat Creek Construction & Materials, Inc. Lump Sum $5,000.00 Meyers Earthwork Inc. Lump Sum $12,000.00 MKD Construction, Inc. Lump Sum $5,300.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00
A0200 15701-0000 SOIL EROSION CONTROL
Hat Creek Construction & Materials, Inc. Lump Sum $47,000.00 Meyers Earthwork Inc. Lump Sum $21,500.00 MKD Construction, Inc. Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $26,400.00
4 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0220 15802-0000 WATERING FOR DUST CONTROL
Hat Creek Construction & Materials, Inc. Lump Sum $40,000.00 Meyers Earthwork Inc. Lump Sum $104,000.00 MKD Construction, Inc. Lump Sum $8,200.00 Engineer's Estimate ALL LPSM Lump Sum $70,000.00
A0240 20202-0000 SELECTIVE CLEARING
Hat Creek Construction & Materials, Inc. $32.00 $3,200.00 Meyers Earthwork Inc. $24.00 $2,400.00 MKD Construction, Inc. $63.00 $6,300.00 Engineer's Estimate 100 SQYD $65.00 $6,500.00
A0260 20301-0700 REMOVAL OF DELINEATOR (OBJECT MARKER)
Hat Creek Construction & Materials, Inc. $25.00 $1,600.00 Meyers Earthwork Inc. $55.00 $3,520.00 MKD Construction, Inc. $30.00 $1,920.00 Engineer's Estimate 64 EACH $30.00 $1,920.00
A0280 20301-2400 REMOVAL OF SIGN
Hat Creek Construction & Materials, Inc. $200.00 $2,000.00 Meyers Earthwork Inc. $155.00 $1,550.00 MKD Construction, Inc. $175.00 $1,750.00 Engineer's Estimate 10 EACH $175.00 $1,750.00
A0300 20402-0000 SUBEXCAVATION
Hat Creek Construction & Materials, Inc. $138.00 $24,840.00 Meyers Earthwork Inc. $68.00 $12,240.00 MKD Construction, Inc. $265.00 $47,700.00 Engineer's Estimate 180 CUYD $175.00 $31,500.00
A0320 30202-2000 ROADWAY AGGREGATE, METHOD 2
Hat Creek Construction & Materials, Inc. $45.00 $124,200.00 Meyers Earthwork Inc. $48.00 $132,480.00 MKD Construction, Inc. $87.00 $240,120.00 Engineer's Estimate 2,760 TON $40.00 $110,400.00
5 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0340 30302-3000 SHOULDER AND DITCH RECONDITIONING
Hat Creek Construction & Materials, Inc. $4.00 $6,000.00 Meyers Earthwork Inc. $9.00 $13,500.00 MKD Construction, Inc. $33.00 $49,500.00 Engineer's Estimate 1,500 LNFT $60.00 $90,000.00
A0360 30502-0600 FULL DEPTH RECLAMATION WITH CEMENT, 6-INCH DEPTH
Hat Creek Construction & Materials, Inc. $5.50 $162,250.00 Meyers Earthwork Inc. $9.00 $265,500.00 MKD Construction, Inc. $18.75 $553,125.00 Engineer's Estimate 29,500 SQYD $6.00 $177,000.00
A0380 30510-0000 CEMENTITIOUS MATERIAL
Hat Creek Construction & Materials, Inc. $199.00 $71,640.00 Meyers Earthwork Inc. $320.00 $115,200.00 MKD Construction, Inc. $234.00 $84,240.00 Engineer's Estimate 360 TON $350.00 $126,000.00
A0400 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
Hat Creek Construction & Materials, Inc. $135.00 $675,000.00 Meyers Earthwork Inc. $144.00 $720,000.00 MKD Construction, Inc. $215.00 $1,075,000.00 Engineer's Estimate 5,000 TON $185.00 $925,000.00
A0420 40601-0000 FOG SEAL
Hat Creek Construction & Materials, Inc. $1,300.00 $16,900.00 Meyers Earthwork Inc. $1,800.00 $23,400.00 MKD Construction, Inc. $1,100.00 $14,300.00 Engineer's Estimate 13.0 TON $1,300.00 $16,900.00
A0440 41102-1000 PRIME COAT, METHOD 1
Hat Creek Construction & Materials, Inc. $1.25 $37,500.00 Meyers Earthwork Inc. $1.45 $43,500.00 MKD Construction, Inc. $2.10 $63,000.00 Engineer's Estimate 30,000 SQYD $1.50 $45,000.00
6 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0460 41105-0000 BLOTTER
Hat Creek Construction & Materials, Inc. $60.00 $3,000.00 Meyers Earthwork Inc. $237.00 $11,850.00 MKD Construction, Inc. $300.00 $15,000.00 Engineer's Estimate 50 TON $115.00 $5,750.00
A0480 41201-0000 TACK COAT
Hat Creek Construction & Materials, Inc. $500.00 $6,250.00 Meyers Earthwork Inc. $1,450.00 $18,125.00 MKD Construction, Inc. $2,300.00 $28,750.00 Engineer's Estimate 12.5 TON $1,300.00 $16,250.00
A0500 60704-0000 CLEANING CULVERT IN PLACE
Hat Creek Construction & Materials, Inc. $4,000.00 $60,000.00 Meyers Earthwork Inc. $973.00 $14,595.00 MKD Construction, Inc. $3,760.00 $56,400.00 Engineer's Estimate 15 EACH $4,000.00 $60,000.00
A0520 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
Hat Creek Construction & Materials, Inc. $125.00 $2,000.00 Meyers Earthwork Inc. $145.00 $2,320.00 MKD Construction, Inc. $210.00 $3,360.00 Engineer's Estimate 16 HOUR $200.00 $3,200.00
A0540 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
Hat Creek Construction & Materials, Inc. $131.00 $2,096.00 Meyers Earthwork Inc. $155.00 $2,480.00 MKD Construction, Inc. $367.00 $5,872.00 Engineer's Estimate 16 HOUR $200.00 $3,200.00
A0560 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
Hat Creek Construction & Materials, Inc. $181.00 $2,896.00 Meyers Earthwork Inc. $185.00 $2,960.00 MKD Construction, Inc. $210.00 $3,360.00 Engineer's Estimate 16 HOUR $225.00 $3,600.00
7 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0580 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
Hat Creek Construction & Materials, Inc. $205.00 $3,280.00 Meyers Earthwork Inc. $195.00 $3,120.00 MKD Construction, Inc. $336.00 $5,376.00 Engineer's Estimate 16 HOUR $240.00 $3,840.00
A0600 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY
Hat Creek Construction & Materials, Inc. $170.00 $2,720.00 Meyers Earthwork Inc. $205.00 $3,280.00 MKD Construction, Inc. $240.00 $3,840.00 Engineer's Estimate 16 HOUR $265.00 $4,240.00
A0620 62301-0000 GENERAL LABOR
Hat Creek Construction & Materials, Inc. $80.00 $1,280.00 Meyers Earthwork Inc. $88.00 $1,408.00 MKD Construction, Inc. $95.00 $1,520.00 Engineer's Estimate 16 HOUR $85.00 $1,360.00
A0640 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
Hat Creek Construction & Materials, Inc. $150.00 $1,200.00 Meyers Earthwork Inc. $220.00 $1,760.00 MKD Construction, Inc. $265.00 $2,120.00 Engineer's Estimate 8 HOUR $180.00 $1,440.00
A0660 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
Hat Creek Construction & Materials, Inc. $460.00 $3,680.00 Meyers Earthwork Inc. $240.00 $1,920.00 MKD Construction, Inc. $250.00 $2,000.00 Engineer's Estimate 8 HOUR $225.00 $1,800.00
A0680 63301-0000 SIGN SYSTEM
Hat Creek Construction & Materials, Inc. $500.00 $5,500.00 Meyers Earthwork Inc. $400.00 $4,400.00 MKD Construction, Inc. $885.00 $9,735.00 Engineer's Estimate 11 EACH $550.00 $6,050.00
8 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0700 63308-2000 OBJECT MARKER, TYPE 2
Hat Creek Construction & Materials, Inc. $100.00 $6,000.00 Meyers Earthwork Inc. $85.00 $5,100.00 MKD Construction, Inc. $100.00 $6,000.00 Engineer's Estimate 60 EACH $150.00 $9,000.00
A0720 63309-0000 DELINEATOR
Hat Creek Construction & Materials, Inc. $100.00 $12,000.00 Meyers Earthwork Inc. $85.00 $10,200.00 MKD Construction, Inc. $90.00 $10,800.00 Engineer's Estimate 120 EACH $85.00 $10,200.00
A0740 63402-0300 PAVEMENT MARKINGS, TYPE B, SOLID
Hat Creek Construction & Materials, Inc. $1,050.00 $24,150.00 Meyers Earthwork Inc. $1,450.00 $33,350.00 MKD Construction, Inc. $1,955.00 $44,965.00 Engineer's Estimate 23.0 MILE $1,500.00 $34,500.00
A0760 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
Hat Creek Construction & Materials, Inc. $75.00 $225.00 Meyers Earthwork Inc. $360.00 $1,080.00 MKD Construction, Inc. $275.00 $825.00 Engineer's Estimate 3 EACH $200.00 $600.00
A0780 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE
Hat Creek Construction & Materials, Inc. $30.00 $3,000.00 Meyers Earthwork Inc. $29.00 $2,900.00 MKD Construction, Inc. $45.00 $4,500.00 Engineer's Estimate 100 EACH $25.00 $2,500.00
A0800 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
Hat Creek Construction & Materials, Inc. $50.00 $5,000.00 Meyers Earthwork Inc. $80.00 $8,000.00 MKD Construction, Inc. $115.00 $11,500.00 Engineer's Estimate 100 EACH $120.00 $12,000.00
9 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0820 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
Hat Creek Construction & Materials, Inc. $150.00 $1,650.00 Meyers Earthwork Inc. $900.00 $9,900.00 MKD Construction, Inc. $205.00 $2,255.00 Engineer's Estimate 11 EACH $200.00 $2,200.00
A0840 63502-3900 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
Hat Creek Construction & Materials, Inc. $250.00 $7,500.00 Meyers Earthwork Inc. $300.00 $9,000.00 MKD Construction, Inc. $475.00 $14,250.00 Engineer's Estimate 30 EACH $325.00 $9,750.00
A0860 63505-1000 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
Hat Creek Construction & Materials, Inc. $2,500.00 $5,700.00 Meyers Earthwork Inc. $4,200.00 $9,576.00 MKD Construction, Inc. $2,100.00 $4,788.00 Engineer's Estimate 2.28 MILE $2,000.00 $4,560.00
A0880 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
Hat Creek Construction & Materials, Inc. $100.00 $80,000.00 Meyers Earthwork Inc. $88.00 $70,400.00 MKD Construction, Inc. $160.00 $128,000.00 Engineer's Estimate 800 HOUR $120.00 $96,000.00
A0900 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR
Hat Creek Construction & Materials, Inc. $125.00 $50,000.00 Meyers Earthwork Inc. $110.00 $44,000.00 MKD Construction, Inc. $177.00 $70,800.00 Engineer's Estimate 400 HOUR $125.00 $50,000.00
Total Schedule - All Items
Hat Creek Construction & Materials, Inc. $2,051,989.00 Meyers Earthwork Inc. $2,088,714.00 MKD Construction, Inc. $3,106,519.15 Engineer's Estimate $2,460,000.00
10 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: X
Schedule Type: Options
Solcitation No: 6982AF21B000009
Division: Central Federal Lands
State: CA County: Sierra
Federal Land: Tahoe National Forest Opened at: Lakewood, CO
Opened by: Leslie Karsten
Date: 05/20/21
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Meyers Earthwork Inc. $379,223.00 4150 Fig Tree Lane Redding, CA 96002
Hat Creek Construction & Materials, Inc. $384,000.00 24339 Highway 89 N Burney, CA 96013
MKD Construction, Inc. $592,575.35 20 Stokes Drive Mound House, NV 89706
Engineer's Estimate $457,000.00
11 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0100 15101-0000 MOBILIZATION
Meyers Earthwork Inc. Lump Sum $20,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $38,000.00 MKD Construction, Inc. Lump Sum $54,000.00 Engineer's Estimate ALL LPSM Lump Sum $53,720.00
X0120 15210-3000 CENTERLINE, VERIFICATION AND STAKING
Meyers Earthwork Inc. $10,000.00 $4,100.00 Hat Creek Construction & Materials, Inc. $7,317.07 $3,000.00 MKD Construction, Inc. $30,235.00 $12,396.35 Engineer's Estimate 0.410 MILE $10,000.00 $4,100.00
X0140 15301-0000 CONTRACTOR QUALITY CONTROL
Meyers Earthwork Inc. Lump Sum $12,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $22,117.00 MKD Construction, Inc. Lump Sum $5,900.00 Engineer's Estimate ALL LPSM Lump Sum $12,300.00
X0160 15401-0000 CONTRACTOR TESTING
Meyers Earthwork Inc. Lump Sum $15,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $39,500.00 MKD Construction, Inc. Lump Sum $14,500.00 Engineer's Estimate ALL LPSM Lump Sum $12,300.00
X0180 15501-0000 CONSTRUCTION SCHEDULE
Meyers Earthwork Inc. Lump Sum $5,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $2,000.00 MKD Construction, Inc. Lump Sum $1,500.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
X0200 15701-0000 SOIL EROSION CONTROL
Meyers Earthwork Inc. Lump Sum $6,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $10,000.00 MKD Construction, Inc. Lump Sum $14,100.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00
12 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0220 15802-0000 WATERING FOR DUST CONTROL
Meyers Earthwork Inc. Lump Sum $15,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $2,500.00 MKD Construction, Inc. Lump Sum $3,000.00 Engineer's Estimate ALL LPSM Lump Sum $13,000.00
X0240 20202-0000 SELECTIVE CLEARING
Meyers Earthwork Inc. $50.00 $1,000.00 Hat Creek Construction & Materials, Inc. $32.00 $640.00 MKD Construction, Inc. $61.00 $1,220.00 Engineer's Estimate 20 SQYD $65.00 $1,300.00
X0260 20301-0700 REMOVAL OF DELINEATOR (OBJECT MARKER)
Meyers Earthwork Inc. $55.00 $550.00 Hat Creek Construction & Materials, Inc. $25.00 $250.00 MKD Construction, Inc. $29.00 $290.00 Engineer's Estimate 10 EACH $30.00 $300.00
X0280 20301-2400 REMOVAL OF SIGN
Meyers Earthwork Inc. $155.00 $930.00 Hat Creek Construction & Materials, Inc. $200.00 $1,200.00 MKD Construction, Inc. $164.00 $984.00 Engineer's Estimate 6 EACH $175.00 $1,050.00
X0300 20402-0000 SUBEXCAVATION
Meyers Earthwork Inc. $68.00 $2,380.00 Hat Creek Construction & Materials, Inc. $138.00 $4,830.00 MKD Construction, Inc. $305.00 $10,675.00 Engineer's Estimate 35 CUYD $175.00 $6,125.00
X0320 30202-2000 ROADWAY AGGREGATE, METHOD 2
Meyers Earthwork Inc. $50.00 $23,500.00 Hat Creek Construction & Materials, Inc. $45.00 $21,150.00 MKD Construction, Inc. $83.00 $39,010.00 Engineer's Estimate 470 TON $40.00 $18,800.00
13 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0340 30302-3000 SHOULDER AND DITCH RECONDITIONING
Meyers Earthwork Inc. $9.00 $1,800.00 Hat Creek Construction & Materials, Inc. $4.00 $800.00 MKD Construction, Inc. $30.00 $6,000.00 Engineer's Estimate 200 LNFT $60.00 $12,000.00
X0360 30502-0600 FULL DEPTH RECLAMATION WITH CEMENT, 6-INCH DEPTH
Meyers Earthwork Inc. $9.00 $47,700.00 Hat Creek Construction & Materials, Inc. $5.50 $29,150.00 MKD Construction, Inc. $24.85 $131,705.00 Engineer's Estimate 5,300 SQYD $6.00 $31,800.00
X0380 30510-0000 CEMENTITIOUS MATERIAL
Meyers Earthwork Inc. $320.00 $20,800.00 Hat Creek Construction & Materials, Inc. $199.00 $12,935.00 MKD Construction, Inc. $234.00 $15,210.00 Engineer's Estimate 65 TON $350.00 $22,750.00
X0400 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
Meyers Earthwork Inc. $144.00 $126,720.00 Hat Creek Construction & Materials, Inc. $135.00 $118,800.00 MKD Construction, Inc. $181.00 $159,280.00 Engineer's Estimate 880 TON $185.00 $162,800.00
X0420 40601-0000 FOG SEAL
Meyers Earthwork Inc. $1,800.00 $3,960.00 Hat Creek Construction & Materials, Inc. $1,300.00 $2,860.00 MKD Construction, Inc. $2,200.00 $4,840.00 Engineer's Estimate 2.2 TON $1,300.00 $2,860.00
X0440 41102-1000 PRIME COAT, METHOD 1
Meyers Earthwork Inc. $1.45 $7,685.00 Hat Creek Construction & Materials, Inc. $1.25 $6,625.00 MKD Construction, Inc. $2.20 $11,660.00 Engineer's Estimate 5,300 SQYD $1.50 $7,950.00
14 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0460 41105-0000 BLOTTER
Meyers Earthwork Inc. $237.00 $2,370.00 Hat Creek Construction & Materials, Inc. $60.00 $600.00 MKD Construction, Inc. $325.00 $3,250.00 Engineer's Estimate 10 TON $115.00 $1,150.00
X0480 41201-0000 TACK COAT
Meyers Earthwork Inc. $1,450.00 $3,045.00 Hat Creek Construction & Materials, Inc. $500.00 $1,050.00 MKD Construction, Inc. $2,250.00 $4,725.00 Engineer's Estimate 2.1 TON $1,300.00 $2,730.00
X0500 60704-0000 CLEANING CULVERT IN PLACE
Meyers Earthwork Inc. $973.00 $2,919.00 Hat Creek Construction & Materials, Inc. $4,000.00 $12,000.00 MKD Construction, Inc. $2,400.00 $7,200.00 Engineer's Estimate 3 EACH $4,000.00 $12,000.00
X0520 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
Meyers Earthwork Inc. $145.00 $580.00 Hat Creek Construction & Materials, Inc. $125.00 $500.00 MKD Construction, Inc. $200.00 $800.00 Engineer's Estimate 4 HOUR $200.00 $800.00
X0540 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
Meyers Earthwork Inc. $155.00 $620.00 Hat Creek Construction & Materials, Inc. $131.00 $524.00 MKD Construction, Inc. $285.00 $1,140.00 Engineer's Estimate 4 HOUR $200.00 $800.00
X0560 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
Meyers Earthwork Inc. $185.00 $740.00 Hat Creek Construction & Materials, Inc. $181.00 $724.00 MKD Construction, Inc. $230.00 $920.00 Engineer's Estimate 4 HOUR $225.00 $900.00
15 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0580 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
Meyers Earthwork Inc. $195.00 $780.00 Hat Creek Construction & Materials, Inc. $205.00 $820.00 MKD Construction, Inc. $325.00 $1,300.00 Engineer's Estimate 4 HOUR $240.00 $960.00
X0600 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY
Meyers Earthwork Inc. $205.00 $820.00 Hat Creek Construction & Materials, Inc. $170.00 $680.00 MKD Construction, Inc. $215.00 $860.00 Engineer's Estimate 4 HOUR $265.00 $1,060.00
X0620 62301-0000 GENERAL LABOR
Meyers Earthwork Inc. $88.00 $352.00 Hat Creek Construction & Materials, Inc. $80.00 $320.00 MKD Construction, Inc. $95.00 $380.00 Engineer's Estimate 4 HOUR $85.00 $340.00
X0640 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
Meyers Earthwork Inc. $220.00 $880.00 Hat Creek Construction & Materials, Inc. $150.00 $600.00 MKD Construction, Inc. $265.00 $1,060.00 Engineer's Estimate 4 HOUR $180.00 $720.00
X0660 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
Meyers Earthwork Inc. $240.00 $960.00 Hat Creek Construction & Materials, Inc. $460.00 $1,840.00 MKD Construction, Inc. $250.00 $1,000.00 Engineer's Estimate 4 HOUR $225.00 $900.00
X0680 63301-0000 SIGN SYSTEM
Meyers Earthwork Inc. $400.00 $2,400.00 Hat Creek Construction & Materials, Inc. $500.00 $3,000.00 MKD Construction, Inc. $885.00 $5,310.00 Engineer's Estimate 6 EACH $550.00 $3,300.00
16 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0700 63308-2000 OBJECT MARKER, TYPE 2
Meyers Earthwork Inc. $85.00 $850.00 Hat Creek Construction & Materials, Inc. $100.00 $1,000.00 MKD Construction, Inc. $100.00 $1,000.00 Engineer's Estimate 10 EACH $150.00 $1,500.00
X0720 63309-0000 DELINEATOR
Meyers Earthwork Inc. $85.00 $2,890.00 Hat Creek Construction & Materials, Inc. $100.00 $3,400.00 MKD Construction, Inc. $90.00 $3,060.00 Engineer's Estimate 34 EACH $85.00 $2,890.00
X0740 63402-0300 PAVEMENT MARKINGS, TYPE B, SOLID
Meyers Earthwork Inc. $1,450.00 $6,090.00 Hat Creek Construction & Materials, Inc. $1,050.00 $4,410.00 MKD Construction, Inc. $2,400.00 $10,080.00 Engineer's Estimate 4.2 MILE $1,500.00 $6,300.00
X0760 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE
Meyers Earthwork Inc. $29.00 $580.00 Hat Creek Construction & Materials, Inc. $30.00 $600.00 MKD Construction, Inc. $45.00 $900.00 Engineer's Estimate 20 EACH $25.00 $500.00
X0780 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
Meyers Earthwork Inc. $80.00 $1,600.00 Hat Creek Construction & Materials, Inc. $50.00 $1,000.00 MKD Construction, Inc. $115.00 $2,300.00 Engineer's Estimate 20 EACH $120.00 $2,400.00
X0800 63502-3900 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
Meyers Earthwork Inc. $900.00 $6,300.00 Hat Creek Construction & Materials, Inc. $150.00 $1,050.00 MKD Construction, Inc. $475.00 $3,325.00 Engineer's Estimate 7 EACH $325.00 $2,275.00
17 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: X
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
X0820 63505-1000 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
Meyers Earthwork Inc. $4,200.00 $1,722.00 Hat Creek Construction & Materials, Inc. $2,500.00 $1,025.00 MKD Construction, Inc. $19,500.00 $7,995.00 Engineer's Estimate 0.41 MILE $2,000.00 $820.00
X0840 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
Meyers Earthwork Inc. $88.00 $17,600.00 Hat Creek Construction & Materials, Inc. $100.00 $20,000.00 MKD Construction, Inc. $160.00 $32,000.00 Engineer's Estimate 200 HOUR $120.00 $24,000.00
X0860 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR
Meyers Earthwork Inc. $110.00 $11,000.00 Hat Creek Construction & Materials, Inc. $125.00 $12,500.00 MKD Construction, Inc. $177.00 $17,700.00 Engineer's Estimate 100 HOUR $125.00 $12,500.00
Total Schedule - All Items
Meyers Earthwork Inc. $379,223.00 Hat Creek Construction & Materials, Inc. $384,000.00 MKD Construction, Inc. $592,575.35 Engineer's Estimate $457,000.00
18 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: Y
Schedule Type: Options
Solcitation No: 6982AF21B000009
Division: Central Federal Lands
State: CA County: Sierra
Federal Land: Tahoe National Forest Opened at: Lakewood, CO
Opened by: Leslie Karsten
Date: 05/20/21
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Meyers Earthwork Inc. $263,596.00 4150 Fig Tree Lane Redding, CA 96002
Hat Creek Construction & Materials, Inc. $294,000.00 24339 Highway 89 N Burney, CA 96013
MKD Construction, Inc. $439,682.50 20 Stokes Drive Mound House, NV 89706
Engineer's Estimate $316,875.00
19 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: Y
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Y0100 15101-0000 MOBILIZATION
Meyers Earthwork Inc. Lump Sum $15,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $29,000.00 MKD Construction, Inc. Lump Sum $43,000.00 Engineer's Estimate ALL LPSM Lump Sum $37,590.00
Y0120 15210-3000 CENTERLINE, VERIFICATION AND STAKING
Meyers Earthwork Inc. $10,000.00 $2,700.00 Hat Creek Construction & Materials, Inc. $7,407.40 $2,000.00 MKD Construction, Inc. $37,150.00 $10,030.50 Engineer's Estimate 0.270 MILE $10,000.00 $2,700.00
Y0140 15301-0000 CONTRACTOR QUALITY CONTROL
Meyers Earthwork Inc. Lump Sum $10,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $26,552.00 MKD Construction, Inc. Lump Sum $5,500.00 Engineer's Estimate ALL LPSM Lump Sum $9,200.00
Y0160 15401-0000 CONTRACTOR TESTING
Meyers Earthwork Inc. Lump Sum $12,500.00 Hat Creek Construction & Materials, Inc. Lump Sum $40,000.00 MKD Construction, Inc. Lump Sum $12,000.00 Engineer's Estimate ALL LPSM Lump Sum $9,200.00
Y0180 15501-0000 CONSTRUCTION SCHEDULE
Meyers Earthwork Inc. Lump Sum $4,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $2,000.00 MKD Construction, Inc. Lump Sum $1,770.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
Y0200 15701-0000 SOIL EROSION CONTROL
Meyers Earthwork Inc. Lump Sum $4,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $10,000.00 MKD Construction, Inc. Lump Sum $10,600.00 Engineer's Estimate ALL LPSM Lump Sum $3,700.00
20 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: Y
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Y0220 15802-0000 WATERING FOR DUST CONTROL
Meyers Earthwork Inc. Lump Sum $10,000.00 Hat Creek Construction & Materials, Inc. Lump Sum $2,500.00 MKD Construction, Inc. Lump Sum $2,575.00 Engineer's Estimate ALL LPSM Lump Sum $9,000.00
Y0240 20202-0000 SELECTIVE CLEARING
Meyers Earthwork Inc. $60.00 $600.00 Hat Creek Construction & Materials, Inc. $60.00 $600.00 MKD Construction, Inc. $82.00 $820.00 Engineer's Estimate 10 SQYD $65.00 $650.00
Y0260 20301-0700 REMOVAL OF DELINEATOR (OBJECT MARKER)
Meyers Earthwork Inc. $55.00 $330.00 Hat Creek Construction & Materials, Inc. $25.00 $150.00 MKD Construction, Inc. $29.00 $174.00 Engineer's Estimate 6 EACH $30.00 $180.00
Y0280 20301-2400 REMOVAL OF SIGN
Meyers Earthwork Inc. $155.00 $310.00 Hat Creek Construction & Materials, Inc. $200.00 $400.00 MKD Construction, Inc. $164.00 $328.00 Engineer's Estimate 2 EACH $175.00 $350.00
Y0300 20402-0000 SUBEXCAVATION
Meyers Earthwork Inc. $68.00 $1,700.00 Hat Creek Construction & Materials, Inc. $138.00 $3,450.00 MKD Construction, Inc. $305.00 $7,625.00 Engineer's Estimate 25 CUYD $175.00 $4,375.00
Y0320 30202-2000 ROADWAY AGGREGATE, METHOD 2
Meyers Earthwork Inc. $50.00 $15,500.00 Hat Creek Construction & Materials, Inc. $45.00 $13,950.00 MKD Construction, Inc. $83.00 $25,730.00 Engineer's Estimate 310 TON $40.00 $12,400.00
21 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: Y
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Y0340 30302-3000 SHOULDER AND DITCH RECONDITIONING
Meyers Earthwork Inc. $9.00 $1,170.00 Hat Creek Construction & Materials, Inc. $4.00 $520.00 MKD Construction, Inc. $34.00 $4,420.00 Engineer's Estimate 130 LNFT $60.00 $7,800.00
Y0360 30502-0600 FULL DEPTH RECLAMATION WITH CEMENT, 6-INCH DEPTH
Meyers Earthwork Inc. $9.00 $31,500.00 Hat Creek Construction & Materials, Inc. $5.50 $19,250.00 MKD Construction, Inc. $31.00 $108,500.00 Engineer's Estimate 3,500 SQYD $6.00 $21,000.00
Y0380 30510-0000 CEMENTITIOUS MATERIAL
Meyers Earthwork Inc. $320.00 $14,400.00 Hat Creek Construction & Materials, Inc. $199.00 $8,955.00 MKD Construction, Inc. $235.00 $10,575.00 Engineer's Estimate 45 TON $350.00 $15,750.00
Y0400 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1
Meyers Earthwork Inc. $144.00 $82,800.00 Hat Creek Construction & Materials, Inc. $135.00 $77,625.00 MKD Construction, Inc. $181.00 $104,075.00 Engineer's Estimate 575 TON $185.00 $106,375.00
Y0420 40601-0000 FOG SEAL
Meyers Earthwork Inc. $1,800.00 $2,880.00 Hat Creek Construction & Materials, Inc. $1,300.00 $2,080.00 MKD Construction, Inc. $1,600.00 $2,560.00 Engineer's Estimate 1.6 TON $1,300.00 $2,080.00
Y0440 41102-1000 PRIME COAT, METHOD 1
Meyers Earthwork Inc. $1.45 $5,075.00 Hat Creek Construction & Materials, Inc. $1.25 $4,375.00 MKD Construction, Inc. $2.50 $8,750.00 Engineer's Estimate 3,500 SQYD $1.50 $5,250.00
22 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: Y
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Y0460 41105-0000 BLOTTER
Meyers Earthwork Inc. $237.00 $1,659.00 Hat Creek Construction & Materials, Inc. $60.00 $420.00 MKD Construction, Inc. $340.00 $2,380.00 Engineer's Estimate 7 TON $115.00 $805.00
Y0480 41201-0000 TACK COAT
Meyers Earthwork Inc. $1,450.00 $2,175.00 Hat Creek Construction & Materials, Inc. $500.00 $750.00 MKD Construction, Inc. $2,850.00 $4,275.00 Engineer's Estimate 1.5 TON $1,300.00 $1,950.00
Y0500 60704-0000 CLEANING CULVERT IN PLACE
Meyers Earthwork Inc. $973.00 $1,946.00 Hat Creek Construction & Materials, Inc. $4,000.00 $8,000.00 MKD Construction, Inc. $2,300.00 $4,600.00 Engineer's Estimate 2 EACH $4,000.00 $8,000.00
Y0520 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY
Meyers Earthwork Inc. $145.00 $580.00 Hat Creek Construction & Materials, Inc. $125.00 $500.00 MKD Construction, Inc. $200.00 $800.00 Engineer's Estimate 4 HOUR $200.00 $800.00
Y0540 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
Meyers Earthwork Inc. $155.00 $620.00 Hat Creek Construction & Materials, Inc. $131.00 $524.00 MKD Construction, Inc. $285.00 $1,140.00 Engineer's Estimate 4 HOUR $200.00 $800.00
Y0560 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
Meyers Earthwork Inc. $185.00 $740.00 Hat Creek Construction & Materials, Inc. $181.00 $724.00 MKD Construction, Inc. $230.00 $920.00 Engineer's Estimate 4 HOUR $225.00 $900.00
23 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: Y
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Y0580 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
Meyers Earthwork Inc. $195.00 $780.00 Hat Creek Construction & Materials, Inc. $205.00 $820.00 MKD Construction, Inc. $325.00 $1,300.00 Engineer's Estimate 4 HOUR $240.00 $960.00
Y0600 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY
Meyers Earthwork Inc. $205.00 $820.00 Hat Creek Construction & Materials, Inc. $170.00 $680.00 MKD Construction, Inc. $215.00 $860.00 Engineer's Estimate 4 HOUR $265.00 $1,060.00
Y0620 62301-0000 GENERAL LABOR
Meyers Earthwork Inc. $88.00 $352.00 Hat Creek Construction & Materials, Inc. $80.00 $320.00 MKD Construction, Inc. $95.00 $380.00 Engineer's Estimate 4 HOUR $85.00 $340.00
Y0640 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
Meyers Earthwork Inc. $220.00 $880.00 Hat Creek Construction & Materials, Inc. $150.00 $600.00 MKD Construction, Inc. $265.00 $1,060.00 Engineer's Estimate 4 HOUR $180.00 $720.00
Y0660 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
Meyers Earthwork Inc. $240.00 $960.00 Hat Creek Construction & Materials, Inc. $460.00 $1,840.00 MKD Construction, Inc. $250.00 $1,000.00 Engineer's Estimate 4 HOUR $225.00 $900.00
Y0680 63301-0000 SIGN SYSTEM
Meyers Earthwork Inc. $400.00 $800.00 Hat Creek Construction & Materials, Inc. $500.00 $1,000.00 MKD Construction, Inc. $885.00 $1,770.00 Engineer's Estimate 2 EACH $550.00 $1,100.00
24 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: Y
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Y0700 63308-2000 OBJECT MARKER, TYPE 2
Meyers Earthwork Inc. $85.00 $510.00 Hat Creek Construction & Materials, Inc. $100.00 $600.00 MKD Construction, Inc. $100.00 $600.00 Engineer's Estimate 6 EACH $150.00 $900.00
Y0720 63309-0000 DELINEATOR
Meyers Earthwork Inc. $85.00 $1,700.00 Hat Creek Construction & Materials, Inc. $100.00 $2,000.00 MKD Construction, Inc. $90.00 $1,800.00 Engineer's Estimate 20 EACH $85.00 $1,700.00
Y0740 63402-0300 PAVEMENT MARKINGS, TYPE B, SOLID
Meyers Earthwork Inc. $1,450.00 $4,060.00 Hat Creek Construction & Materials, Inc. $1,050.00 $2,940.00 MKD Construction, Inc. $2,500.00 $7,000.00 Engineer's Estimate 2.8 MILE $1,500.00 $4,200.00
Y0760 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE
Meyers Earthwork Inc. $29.00 $435.00 Hat Creek Construction & Materials, Inc. $30.00 $450.00 MKD Construction, Inc. $35.00 $525.00 Engineer's Estimate 15 EACH $25.00 $375.00
Y0780 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
Meyers Earthwork Inc. $80.00 $1,600.00 Hat Creek Construction & Materials, Inc. $50.00 $1,000.00 MKD Construction, Inc. $115.00 $2,300.00 Engineer's Estimate 20 EACH $120.00 $2,400.00
Y0800 63502-3900 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
Meyers Earthwork Inc. $900.00 $4,500.00 Hat Creek Construction & Materials, Inc. $150.00 $750.00 MKD Construction, Inc. $475.00 $2,375.00 Engineer's Estimate 5 EACH $325.00 $1,625.00
25 out of 25
Project No: CA FTFS 0007(1)
Project Name: Fibreboard Road
Schedule: Y
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Y0820 63505-1000 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
Meyers Earthwork Inc. $4,200.00 $1,134.00 Hat Creek Construction & Materials, Inc. $2,500.00 $675.00 MKD Construction, Inc. $21,500.00 $5,805.00 Engineer's Estimate 0.27 MILE $2,000.00 $540.00
Y0840 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
Meyers Earthwork Inc. $88.00 $14,080.00 Hat Creek Construction & Materials, Inc. $100.00 $16,000.00 MKD Construction, Inc. $160.00 $25,600.00 Engineer's Estimate 160 HOUR $120.00 $19,200.00
Y0860 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR
Meyers Earthwork Inc. $110.00 $8,800.00 Hat Creek Construction & Materials, Inc. $125.00 $10,000.00 MKD Construction, Inc. $177.00 $14,160.00 Engineer's Estimate 80 HOUR $125.00 $10,000.00
Total Schedule - All Items
Meyers Earthwork Inc. $263,596.00 Hat Creek Construction & Materials, Inc. $294,000.00 MKD Construction, Inc. $439,682.50 Engineer's Estimate $316,875.00