Big Cliff 40 Ton Intake Gantry Crane
Closed Solicitation Posted
- Solicitation number
- W9127N-21-R-0023
- Agency
-
ENDIST Portland
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 333923 Overhead Traveling Crane, Hoist, and Monorail System Manufacturing
- Place of performance
- Gates, Oregon 97346, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers, Portland District seeks to replace the existing 40-ton intake gantry crane at Big Cliff Dam near Gates, Oregon. The selected contractor must design, manufacture, install, test and commission a new 40-ton intake gantry crane including a main hoist trolley and maintenance jib hoist. The contractor must also remove the existing crane and modify the electrical power supply from a 3-wire to a 4-wire system with an emergency stop button. The solicitation will use a best value tradeoff source selection process and responses are due by May 26, 2021.
There is no set-aside designation. The NAICS code is 237990 and PSC code is 4210. The incumbent contractor is unknown. The contractor will be responsible for the full design, manufacture, installation and testing of the new 40-ton crane over an estimated 18 month performance period at Big Cliff Dam in Gates, Oregon. The value is estimated between $3-5 million.
Notice text
12 versions
Update #12 · Latest ·
Amendment 3 for the inclusion of FAR clause 52.232-16 and extension of the proposal due date is posted. As a reminder, all amendments must be acknowledged with the proposal submission.
The U.S. Army Corps of Engineers, Portland District has a new requirement for a New 40 Ton Intake Gantry Crane for Big Cliff Dam, modification of the electrical power supply, and incidental related work.
The work consists of replacing the existing 40 Ton Intake Gantry crane with a New 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The contractor must design, manufacture, install, test, and commissioning of the new Intake Gantry Crane. This crane will include one (1) main hoist trolley, and one (1) maintenance jib hoist. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway. The work includes the removal of the existing Intake Crane and the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons.
This solicitation will use a FAR Part 15.101-1 Best Value Tradeoff Process. This is a hybrid supply with construction installation contract. Acquisition will provide for Full and Open Competition.
PLEASE NOTE: Per Amendment 0001, the organized Site visit has been re-scheduled for- Wednesday, 14 April 2021, between 10:00 a.m. to 12:00 p.m. (PDT). Please contact Melanie. A. Barrett via email at Melanie.A.Barrett@usace.army.mil, if interested in attending.
Amendment 0004 has beeen released to address FAR clause 52.225-10 "Notice to Buy American Requirement - Construction Materials (May 2014)" in Section I, and to check DFAR clause 252.225-7000 within the DFARs clause 204.207-7007 Alt A in Section K.
Amendment 0005 is now in effect, extending the solicitation closing date from 3 May 2021, to 10 May 2021.
Amendment 0006 is now in effect, extending the solicitation closing date from 10 May 2021 to 26 May 2021.
Amendment 0007 is now in effect. The purpose of Amendment 0007 is to adjust work items 01 11 00.00 25 "Summary of Changes," and a revision to Work Specification 41 01 20.74 26 "New Intake Gantry Crane Mechanical and Structural Work."
Attachment 1 - 01 11 00.00 25 Summary of Changes;
Attachment 2 - 41 01 20.74 26 New Intake Gantry Crane Mechanical and Structural Work.
Amendment 0008 is now in effect, extending the validity of proposals by an additional 31 days. All offerors will acknowledge this Amendment by Monday 2 August 2021, by 2:00 p.m. (PDT).
Amendment 0009 is now in effect, extending the validity of proposals by an additional 30 days to 26 September 2021. All offerors will acknowledge this Amendment by Monday 30 August 2021, by 2:00 p.m. (PDT).
Amendment 0010 is now in effect, extending the validity of proposals for discussions to 31 October 2021. All offerors will are requested to acknowledge this Amendment by Monday 27 September 2021, by 2:00 p.m. (PDT).
Update #11 ·
Amendment 3 for the inclusion of FAR clause 52.232-16 and extension of the proposal due date is posted. As a reminder, all amendments must be acknowledged with the proposal submission.
The U.S. Army Corps of Engineers, Portland District has a new requirement for a New 40 Ton Intake Gantry Crane for Big Cliff Dam, modification of the electrical power supply, and incidental related work.
The work consists of replacing the existing 40 Ton Intake Gantry crane with a New 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The contractor must design, manufacture, install, test, and commissioning of the new Intake Gantry Crane. This crane will include one (1) main hoist trolley, and one (1) maintenance jib hoist. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway. The work includes the removal of the existing Intake Crane and the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons.
This solicitation will use a FAR Part 15.101-1 Best Value Tradeoff Process. This is a hybrid supply with construction installation contract. Acquisition will provide for Full and Open Competition.
PLEASE NOTE: Per Amendment 0001, the organized Site visit has been re-scheduled for- Wednesday, 14 April 2021, between 10:00 a.m. to 12:00 p.m. (PDT). Please contact Melanie. A. Barrett via email at Melanie.A.Barrett@usace.army.mil, if interested in attending.
Amendment 0004 has beeen released to address FAR clause 52.225-10 "Notice to Buy American Requirement - Construction Materials (May 2014)" in Section I, and to check DFAR clause 252.225-7000 within the DFARs clause 204.207-7007 Alt A in Section K.
Amendment 0005 is now in effect, extending the solicitation closing date from 3 May 2021, to 10 May 2021.
Amendment 0006 is now in effect, extending the solicitation closing date from 10 May 2021 to 26 May 2021.
Amendment 0007 is now in effect. The purpose of Amendment 0007 is to adjust work items 01 11 00.00 25 "Summary of Changes," and a revision to Work Specification 41 01 20.74 26 "New Intake Gantry Crane Mechanical and Structural Work."
Attachment 1 - 01 11 00.00 25 Summary of Changes;
Attachment 2 - 41 01 20.74 26 New Intake Gantry Crane Mechanical and Structural Work.
Amendment 0008 is now in effect, extending the validity of proposals by an additional 31 days. All offerors will acknowledge this Amendment by Monday 2 August 2021, by 2:00 p.m. (PDT).
Amendment 0009 is now in effect, extending the validity of proposals by an additional 30 days to 26 September 2021. All offerors will acknowledge this Amendment by Monday 30 August 2021, by 2:00 p.m. (PDT).
Update #10 ·
Amendment 3 for the inclusion of FAR clause 52.232-16 and extension of the proposal due date is posted. As a reminder, all amendments must be acknowledged with the proposal submission.
The U.S. Army Corps of Engineers, Portland District has a new requirement for a New 40 Ton Intake Gantry Crane for Big Cliff Dam, modification of the electrical power supply, and incidental related work.
The work consists of replacing the existing 40 Ton Intake Gantry crane with a New 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The contractor must design, manufacture, install, test, and commissioning of the new Intake Gantry Crane. This crane will include one (1) main hoist trolley, and one (1) maintenance jib hoist. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway. The work includes the removal of the existing Intake Crane and the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons.
This solicitation will use a FAR Part 15.101-1 Best Value Tradeoff Process. This is a hybrid supply with construction installation contract. Acquisition will provide for Full and Open Competition.
PLEASE NOTE: Per Amendment 0001, the organized Site visit has been re-scheduled for- Wednesday, 14 April 2021, between 10:00 a.m. to 12:00 p.m. (PDT). Please contact Melanie. A. Barrett via email at Melanie.A.Barrett@usace.army.mil, if interested in attending.
Amendment 0004 has beeen released to address FAR clause 52.225-10 "Notice to Buy American Requirement - Construction Materials (May 2014)" in Section I, and to check DFAR clause 252.225-7000 within the DFARs clause 204.207-7007 Alt A in Section K.
Amendment 0005 is now in effect, extending the solicitation closing date from 3 May 2021, to 10 May 2021.
Amendment 0006 is now in effect, extending the solicitation closing date from 10 May 2021 to 26 May 2021.
Amendment 0007 is now in effect. The purpose of Amendment 0007 is to adjust work items 01 11 00.00 25 "Summary of Changes," and a revision to Work Specification 41 01 20.74 26 "New Intake Gantry Crane Mechanical and Structural Work."
Attachment 1 - 01 11 00.00 25 Summary of Changes;
Attachment 2 - 41 01 20.74 26 New Intake Gantry Crane Mechanical and Structural Work.
Amendment 0008 is now in effect, extending the validity of proposals by an additional 31 days. All offerors will acknowledge this Amendment by Monday 2 August 2021, by 2:00 p.m. (PDT).
Update #9 ·
Amendment 3 for the inclusion of FAR clause 52.232-16 and extension of the proposal due date is posted. As a reminder, all amendments must be acknowledged with the proposal submission.
The U.S. Army Corps of Engineers, Portland District has a new requirement for a New 40 Ton Intake Gantry Crane for Big Cliff Dam, modification of the electrical power supply, and incidental related work.
The work consists of replacing the existing 40 Ton Intake Gantry crane with a New 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The contractor must design, manufacture, install, test, and commissioning of the new Intake Gantry Crane. This crane will include one (1) main hoist trolley, and one (1) maintenance jib hoist. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway. The work includes the removal of the existing Intake Crane and the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons.
This solicitation will use a FAR Part 15.101-1 Best Value Tradeoff Process. This is a hybrid supply with construction installation contract. Acquisition will provide for Full and Open Competition.
PLEASE NOTE: Per Amendment 0001, the organized Site visit has been re-scheduled for- Wednesday, 14 April 2021, between 10:00 a.m. to 12:00 p.m. (PDT). Please contact Melanie. A. Barrett via email at Melanie.A.Barrett@usace.army.mil, if interested in attending.
Amendment 0004 has beeen released to address FAR clause 52.225-10 "Notice to Buy American Requirement - Construction Materials (May 2014)" in Section I, and to check DFAR clause 252.225-7000 within the DFARs clause 204.207-7007 Alt A in Section K.
Amendment 0005 is now in effect, extending the solicitation closing date from 3 May 2021, to 10 May 2021.
Amendment 0006 is now in effect, extending the solicitation closing date from 10 May 2021 to 26 May 2021.
Amendment 0007 is now in effect. The purpose of Amendment 0007 is to adjust work items 01 11 00.00 25 "Summary of Changes," and a revision to Work Specification 41 01 20.74 26 "New Intake Gantry Crane Mechanical and Structural Work."
Attachment 1 - 01 11 00.00 25 Summary of Changes;
Attachment 2 - 41 01 20.74 26 New Intake Gantry Crane Mechanical and Structural Work.
Update #8 ·
Amendment 3 for the inclusion of FAR clause 52.232-16 and extension of the proposal due date is posted. As a reminder, all amendments must be acknowledged with the proposal submission.
The U.S. Army Corps of Engineers, Portland District has a new requirement for a New 40 Ton Intake Gantry Crane for Big Cliff Dam, modification of the electrical power supply, and incidental related work.
The work consists of replacing the existing 40 Ton Intake Gantry crane with a New 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The contractor must design, manufacture, install, test, and commissioning of the new Intake Gantry Crane. This crane will include one (1) main hoist trolley, and one (1) maintenance jib hoist. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway. The work includes the removal of the existing Intake Crane and the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons.
This solicitation will use a FAR Part 15.101-1 Best Value Tradeoff Process. This is a hybrid supply with construction installation contract. Acquisition will provide for Full and Open Competition.
PLEASE NOTE: Per Amendment 0001, the organized Site visit has been re-scheduled for- Wednesday, 14 April 2021, between 10:00 a.m. to 12:00 p.m. (PDT). Please contact Melanie. A. Barrett via email at Melanie.A.Barrett@usace.army.mil, if interested in attending.
Amendment 0004 has beeen released to address FAR clause 52.225-10 "Notice to Buy American Requirement - Construction Materials (May 2014)" in Section I, and to check DFAR clause 252.225-7000 within the DFARs clause 204.207-7007 Alt A in Section K.
Amendment 0005 is now in effect, extending the solicitation closing date from 3 May 2021, to 10 May 2021.
Amendment 0006 is now in effect, extending the solicitation closing date from 10 May 2021 to 26 May 2021.
Update #7 ·
Amendment 3 for the inclusion of FAR clause 52.232-16 and extension of the proposal due date is posted. As a reminder, all amendments must be acknowledged with the proposal submission.
The U.S. Army Corps of Engineers, Portland District has a new requirement for a New 40 Ton Intake Gantry Crane for Big Cliff Dam, modification of the electrical power supply, and incidental related work.
The work consists of replacing the existing 40 Ton Intake Gantry crane with a New 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The contractor must design, manufacture, install, test, and commissioning of the new Intake Gantry Crane. This crane will include one (1) main hoist trolley, and one (1) maintenance jib hoist. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway. The work includes the removal of the existing Intake Crane and the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons.
This solicitation will use a FAR Part 15.101-1 Best Value Tradeoff Process. This is a hybrid supply with construction installation contract. Acquisition will provide for Full and Open Competition.
PLEASE NOTE: Per Amendment 0001, the organized Site visit has been re-scheduled for- Wednesday, 14 April 2021, between 10:00 a.m. to 12:00 p.m. (PDT). Please contact Melanie. A. Barrett via email at Melanie.A.Barrett@usace.army.mil, if interested in attending.
Amendment 0004 has beeen released to address FAR clause 52.225-10 "Notice to Buy American Requirement - Construction Materials (May 2014)" in Section I, and to check DFAR clause 252.225-7000 within the DFARs clause 204.207-7007 Alt A in Section K.
Amendment 0005 is now in effect, extending the solicitation closing date from 3 May 2021, to 10 May 2021.
Update #6 ·
Amendment 3 for the inclusion of FAR clause 52.232-16 and extension of the proposal due date is posted. As a reminder, all amendments must be acknowledged with the proposal submission.
The U.S. Army Corps of Engineers, Portland District has a new requirement for a New 40 Ton Intake Gantry Crane for Big Cliff Dam, modification of the electrical power supply, and incidental related work.
The work consists of replacing the existing 40 Ton Intake Gantry crane with a New 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The contractor must design, manufacture, install, test, and commissioning of the new Intake Gantry Crane. This crane will include one (1) main hoist trolley, and one (1) maintenance jib hoist. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway. The work includes the removal of the existing Intake Crane and the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons.
This solicitation will use a FAR Part 15.101-1 Best Value Tradeoff Process. This is a hybrid supply with construction installation contract. Acquisition will provide for Full and Open Competition.
PLEASE NOTE: Per Amendment 0001, the organized Site visit has been re-scheduled for- Wednesday, 14 April 2021, between 10:00 a.m. to 12:00 p.m. (PDT). Please contact Melanie. A. Barrett via email at Melanie.A.Barrett@usace.army.mil, if interested in attending.
Amendment 0004 has beeen released to address FAR clause 52.225-10 "Notice to Buy American Requirement - Construction Materials (May 2014)" in Section I, and to check DFAR clause 252.225-7000 within the DFARs clause 204.207-7007 Alt A in Section K.
Amendment 0005 will be posted later today, extending the solicitation closing date from 3 May 2021, to 10 May 2021.
Update #5 ·
Amendment 3 for the inclusion of FAR clause 52.232-16 and extension of the proposal due date is posted. As a reminder, all amendments must be acknowledged with the proposal submission.
The U.S. Army Corps of Engineers, Portland District has a new requirement for a New 40 Ton Intake Gantry Crane for Big Cliff Dam, modification of the electrical power supply, and incidental related work.
The work consists of replacing the existing 40 Ton Intake Gantry crane with a New 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The contractor must design, manufacture, install, test, and commissioning of the new Intake Gantry Crane. This crane will include one (1) main hoist trolley, and one (1) maintenance jib hoist. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway. The work includes the removal of the existing Intake Crane and the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons.
This solicitation will use a FAR Part 15.101-1 Best Value Tradeoff Process. This is a hybrid supply with construction installation contract. Acquisition will provide for Full and Open Competition.
PLEASE NOTE: Per Amendment 0001, the organized Site visit has been re-scheduled for- Wednesday, 14 April 2021, between 10:00 a.m. to 12:00 p.m. (PDT). Please contact Melanie. A. Barrett via email at Melanie.A.Barrett@usace.army.mil, if interested in attending.
Amendment 0004 has beeen released to address FAR clause 52.225-10 "Notice to Buy American Requirement - Construction Materials (May 2014)" in Section I, and to check DFAR clause 252.225-7000 within the DFARs clause 204.207-7007 Alt A in Section K.
Update #4 ·
Amendment 3 for the inclusion of FAR clause 52.232-16 and extension of the proposal due date is posted. As a reminder, all amendments must be acknowledged with the proposal submission.
The U.S. Army Corps of Engineers, Portland District has a new requirement for a New 40 Ton Intake Gantry Crane for Big Cliff Dam, modification of the electrical power supply, and incidental related work.
The work consists of replacing the existing 40 Ton Intake Gantry crane with a New 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The contractor must design, manufacture, install, test, and commissioning of the new Intake Gantry Crane. This crane will include one (1) main hoist trolley, and one (1) maintenance jib hoist. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway. The work includes the removal of the existing Intake Crane and the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons.
This solicitation will use a FAR Part 15.101-1 Best Value Tradeoff Process. This is a hybrid supply with construction installation contract. Acquisition will provide for Full and Open Competition.
PLEASE NOTE: Per Amendment 0001, the organized Site visit has been re-scheduled for- Wednesday, 14 April 2021, between 10:00 a.m. to 12:00 p.m. (PDT). Please contact Melanie. A. Barrett via email at Melanie.A.Barrett@usace.army.mil, if interested in attending.
Update #3 ·
The U.S. Army Corps of Engineers, Portland District has a new requirement for a New 40 Ton Intake Gantry Crane for Big Cliff Dam, modification of the electrical power supply, and incidental related work.
The work consists of replacing the existing 40 Ton Intake Gantry crane with a New 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The contractor must design, manufacture, install, test, and commissioning of the new Intake Gantry Crane. This crane will include one (1) main hoist trolley, and one (1) maintenance jib hoist. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway. The work includes the removal of the existing Intake Crane and the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons.
This solicitation will use a FAR Part 15.101-1 Best Value Tradeoff Process. This is a hybrid supply with construction installation contract. Acquisition will provide for Full and Open Competition.
PLEASE NOTE: Per Amendment 0001, the organized Site visit has been re-scheduled for- Wednesday, 14 April 2021, between 10:00 a.m. to 12:00 p.m. (PDT). Please contact Melanie. A. Barrett via email at Melanie.A.Barrett@usace.army.mil, if interested in attending.
Update #2 ·
The U.S. Army Corps of Engineers, Portland District has a new requirement for a New 40 Ton Intake Gantry Crane for Big Cliff Dam, modification of the electrical power supply, and incidental related work.
The work consists of replacing the existing 40 Ton Intake Gantry crane with a New 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The contractor must design, manufacture, install, test, and commissioning of the new Intake Gantry Crane. This crane will include one (1) main hoist trolley, and one (1) maintenance jib hoist. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway. The work includes the removal of the existing Intake Crane and the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons.
This solicitation will use a FAR Part 15.101-1 Best Value Tradeoff Process. This is a hybrid supply with construction installation contract. Acquisition will provide for Full and Open Competition.
PLEASE NOTE: Per Amendment 0001, the organized Site visit has been re-scheduled for- Wednesday, 7 April 2021, between 10:00 a.m. to 12:00 p.m. (PDT). Please contact Melanie. A. Barrett via email at Melanie.A.Barrett@usace.army.mil, if interested in attending.
Update #1 ·
The U.S. Army Corps of Engineers, Portland District has a new requirement for a New 40 Ton Intake Gantry Crane for Big Cliff Dam, modification of the electrical power supply, and incidental related work.
The work consists of replacing the existing 40 Ton Intake Gantry crane with a New 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The contractor must design, manufacture, install, test, and commissioning of the new Intake Gantry Crane. This crane will include one (1) main hoist trolley, and one (1) maintenance jib hoist. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway. The work includes the removal of the existing Intake Crane and the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons.
This solicitation will use a FAR Part 15.101-1 Best Value Tradeoff Process. This is a hybrid supply with construction installation contract. Acquisition will provide for Full and Open Competition.
Files
Show all 25
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Solicitation | |
| Big Cliff 40 Ton Intake Gantry Crane | Pre-Solicitation |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity