Work Specification 01 11 00.00 25.pdf

PDF 555 KB Posted

Attached to
Big Cliff 40 Ton Intake Gantry Crane
Solicitation number
W9127N-21-R-0023
Issued by

About this file

This document includes a work specification and related federal contract opportunity for replacing an existing 40 ton intake gantry crane at Big Cliff Dam in Oregon. The work specification provides project details such as replacing the existing 40 ton intake gantry crane with a new crane designed to meet the same requirements, modifying the electrical power supply from cable reel to conductor rail, converting from a three-wire to four-wire feed, and installing emergency stop buttons. The contractor must design, manufacture, test, commission, install and remove the existing crane. The related federal contract opportunity is solicitation number W9127N-21-R-0023 issued by the U.S. Army Corps of Engineers, Portland District to procure the crane replacement and modernization project using a best value tradeoff source selection process and providing for full and open competition.

View the file

Other files

File Type Posted
Amendment 0010 - Extend Proposal Validity for Discussions.pdf PDF
Amendment 0009 - Extend Proposal Validity.pdf PDF
Amendment 0008 - Ext of Proposals.pdf PDF
Amendment 0007 - Spec Revision.pdf PDF
BCD_M-501 - 5 May 21.pdf PDF
Work Specification 41 01 20.74 26.pdf PDF
Amendment 0006 - Extension of Closing Date.pdf PDF
Moffett Drawing 546-S2 - BC-20125-7.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003 - Add 52.232-16 & Extension to Due Date.pdf PDF
Amendment 0002 - Site Visit Adjustment.pdf PDF
Amendment 0001 - Site Visit Adjustment.pdf PDF
Attachment C - Small Business Commitment - BC.docx DOCX document
Attachment A - Offeror Experience Form.docx DOCX document
Big Cliff Work Specificatins and Solicitation. - W9127N21R0023.pdf PDF
E1_BCL_IGC_Contract Drawings_FINAL.pdf PDF
E3_BCL_IGC_Reference_Drawings_Vendor.pdf PDF
Enclosure 1- Small Business Subcontracting Plan.docx DOCX document
Big Cliff Gantry Crane Solicitation - W9127N21R0023.pdf PDF
E4_BCL_IGC_Reference_Drawings_ODOT.pdf PDF
Attachment B - USACE Past Performance Questionnaire.docx DOCX document
Attachment D - Ltr Notice to Large Business.pdf PDF
E2_BCL_IGC_Reference_Drawings_USACE.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 11 00.00 25

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY

This Section provides a summary of the various Contract work elements and their relationship to each other. This summary describes work activities within interim construction completion date. This Section does not provide the technical detail for particular work activities, but describes the work as a whole, providing overall perspective to the separate tasks and their interrelationships. Use this Section in conjunction with all the Specification Sections and the Drawings to establish the total work requirements.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

a. The work consists of replacing the existing 40 Ton Intake Gantry crane with a new 40 Ton Intake Gantry Crane at the Big Cliff Dam located near Gates, Oregon. The Intake Gantry Crane provides for placement of the spillway stoplogs, the penstock stoplogs, and for general servicing of the deck of the spillway.

b. If possible, the new intake crane should be fully commissioned, tested and operational prior to demolition of the existing intake crane. This may not be possible due to the limited space availability at Big Cliff Dam. If construction methods do not allow maintaining an operable intake gantry crane at all times, efforts should be made to minimize the amount of crane outage time and coordinate the outage schedule with the Contracting Officer (KO)The new crane must be fully designed, manufactured, tested, and commissioned prior to acceptance by the government. The work must include the removal of the existing intake crane which is known to have asbestos containing material and lead based paint. Demolition of the existing crane must occur after Factory Acceptance Testing of the new crane and must be coordinated with the Resident Office and Operations staff.

c. Included in this work is the replacement of the existing cable reel power supply to a conductor rail and collector system, conversion from a 3-wire to 4-wire power feed, and installation of emergency stop buttons

1.2.2 Location

The work is located at Big Cliff Dam, 44 miles east of Salem Oregon.

Contractor access to the work site will be from highway 22 on the north side of Big Cliff Dam. The exact location will be shown by the Contracting Officer (KO).

1.3 CONTRACT DRAWINGS

01 11 00.00 25-1

a. The Drawings that accompany these Specifications are a part thereof.

Sheet

ID

Drawing File No. Title

G-001 BCD-9-0/1 Location and Vicinity Map

G-002 BCD-9-0/2 Drawing Index

M-101 BCD-3-1/1 Dam Mechanical Plan

M-102 BCD-3-1/2 Crane Mechanical Plan

M-201 BCD-3-1/3 Dam Mechanical Elevation

M-202 BCD-3-1/4 Crane Mechanical Elevation

M-203 BCD-3-1/5 Crane Elevation at Spillway

M-501 BCD-3-1/6 Machinery Layout

M-502 BCD-3-1/7 Operator Cab Layout and View Angles

E-201 BCD-9-6-0A0/1 Lighting Arrangement

E-202 BCD-9-6-0A0/2 Electrical General Equipment Arrangement

E-401 BCD-9-6-0A0/3 Conductor Rail Installation

E-402 BCD-9-6-0A0/4 Cab Arrangement

E-501 BCD-9-6-0A0/5 Control Arrangement

E-601 BCD-9-6-0A0/6 One-Line Diagram

b. Contract drawings, maps, and Specifications will be furnished to the Contractor without charge per Section H Contract Clause 252.236-7001, CONTRACT DRAWINGS AND SPECIFICATIONS. Reference publications will not be furnished.

c. Immediately check furnished drawings, maps, and specifications and notify the Government of any discrepancies.

1.4 OCCUPANCY OF PREMISES

a. Big Cliff Dam is an unmanned facility and occasional access to the work area will be required. Government access will be coordinated with the Contractor on an as needed basis. Contractor's work must be temporarily suspended whenever required by the Government to accommodate required maintenance and operations activities.

b. Before work is started, arrange with the KO a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.5 EXISTING WORK

01 11 00.00 25-2

In addition to Section H Contract Clause 52.236-9, PROTECTION OF EXISTING

VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portion of the existing work to remain.

b. Upon completion of the work, repair or replace portions of existing work, which have been damaged by Contractor's operations, to preconstruction conditions at the expense of the Contractor.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section --