Barksdale RAPCON Misc. Repairs
Closed Solicitation Posted
- Solicitation number
- 697DCK-20-R-00268
- Agency
- Southwestern Region Federal Aviation Administration, Department of Transportation
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Place of performance
- Barksdale AFB, Louisiana 71110, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks a contractor to perform miscellaneous repairs at the Barksdale Radar Approach Control facility located on Barksdale Air Force Base in Louisiana. Work will include removing and replacing the roofing system and coping, installing a new roof top guard railing and access ladder, replacing exterior hollow metal doors and frames, installing new sealants and interior paint, repairing and installing a new lightning protection system to meet FAA standards, and removing all construction debris. Offerors must use specified materials and meet all applicable FAA, NFPA, and UL requirements. Proposals are due by June 18, 2021 and will be evaluated based on technical qualifications, past performance, and price.
This is a total small business set-aside. The primary NAICS code is 238210 and PSC code R499 applies. The work is estimated to cost between $300,000 and $500,000 and will be performed at the Barksdale RAPCON facility located at Barksdale Air Force Base in Louisiana. The period of performance is not specified but the solicitation was issued by the Federal Aviation Administration Southwestern Region seeking a contractor to support repairs at the facility.
Notice text
5 versions
Update #5 · Latest ·
Amendment 3: Posted 6/10/21
Amendment 2 posted 6/4/21. Due date extended, answer to received question. There will be another amendment as soon as a response is received regarding a roofing question.
****Clarification**** Due date for questions: The due date for questions is extended to Thursday May 27, 2021 at 1500 PST. Questions received after this date may not be answered.
Amendment 01 posted 5/17/21
The following is a summary of the work to be performed at the Barksdale RAPCON located on the Barksdale Air Force Base.
1. ALL FAA specified and Contractor supplied materials must require an approval by the
FAA through the submittal process prior to purchase and installation of such materials.
2. Contractor must use GE Sil Proof 2000 sealant, or an equivalent that meets the
specifications in the sealants section (All sealants and all materials listed as brand
names are acceptable or an equivalent if the substitute meets the specifications listed
in the products specification section). This product will be used to reseal where existing
sealant has deteriorated, or sealant was removed (Exterior only).
3. Contractor must Furnish and Install (F & I) new GE interior paintable sealant where
hollow metal door frames have been replaced with new doors, and frames.
4. Contractor must Repair & Replace (Typ. R & R) Radar Approach Control facility
(RAPCON): roofing and coping etc. system (Tear off to the deck),
5. F & I new roof top perimeter guard railing system. Railing must meet FAA (drawings
and specification sections) and OSHA
requirements.
6. F & I fabricated roof top access “ship ladder” per drawing location.
7. Remove (5-6) exterior hollow metal doors and frames.
8. F & I new exterior commercial hollow metal doors and full welded frames.
9. F & I DTM (direct to Metal) primer and paint for new and existing exterior doors.
10. Paint Colors must be chosen at a later date by the occupants ( FAA Personnel that daily
maintains and owns the structure) of the facility.
11. Contractor must remove all construction debris from the site, as to maintain a clean and
safe working environment.
12. PROVIDE AND INSTALL A NEW ROOF LIGHTNING PROTECTION SYSTEM FOR
THE RAPCON BLGD LIGHTNING PROTECTION SYSTEM TO MEET OR EXCEED
THE REQUIREMENTS OF FAA STANDARD, FAA-STD-019F (THROUGHOUT
THE SPECIFICATIONS, TYP), ORDERS, PROJECT DRAWINGS, AND THE
FOLLOWING:
13. STANDARDS FOR INSTALLATION OF LIGHTNING PROTECTION SYSTEMS
(NFPA 780)
14. INSTALLATION REQUIREMENTS FOR LIGHTNING PROTECTION SYSTEMS
(UL 96A)
15. PROVIDE CLASS II OR LARGER RATED MATERIALS, AS SPECIFIED IN NFPA
780 FOR AIR TERMINALS, MAIN AND DOWN CONDUCTORS AND BONDING
CONDUCTORS.
16. NUMBER OF DOWN CONDUCTORS MUST BE BASED ON FAA-STD-019F. MAKE
SURE DOWN CONDUCTORS FOLLOW THE MOST DIRECT PATH TO EARTH
AND MAIN AND BONDING CONDUCTORS MAINTAIN A HORIZONTAL OR
DOWNWARD PATH.
17. AIR TERMINALS MUST BE SOLID COPPER, BRONZE OR ALUMINUM, 12-IN
HIGH MINIMUM, WITH 1/2 –IN DIAMETER FOR COPPER AND 5/8-IN DIAMETER
FOR ALUMINUM AND INSTALLED AS PER NFPA 780 AND UL 96A.
18. ALL PRODUCTS MUST BE UL LISTED AND LABELED WITH THE UL
CERTIFICATION MARK IN ACCORDANCE WITH UL REQUIREMENTS.
19. PLEASE NOTE THAT INCLUSION OF A UL MASTER LABEL ALONE MUST NOT
BE SUFFICIENT TO INDICATE COMMPLIANCE WITH FAA-STD-019F.
Update #4 ·
Amendment 2 posted 6/4/21. Due date extended, answer to received question. There will be another amendment as soon as a response is received regarding a roofing question.
****Clarification**** Due date for questions: The due date for questions is extended to Thursday May 27, 2021 at 1500 PST. Questions received after this date may not be answered.
Amendment 01 posted 5/17/21
The following is a summary of the work to be performed at the Barksdale RAPCON located on the Barksdale Air Force Base.
1. ALL FAA specified and Contractor supplied materials must require an approval by the
FAA through the submittal process prior to purchase and installation of such materials.
2. Contractor must use GE Sil Proof 2000 sealant, or an equivalent that meets the
specifications in the sealants section (All sealants and all materials listed as brand
names are acceptable or an equivalent if the substitute meets the specifications listed
in the products specification section). This product will be used to reseal where existing
sealant has deteriorated, or sealant was removed (Exterior only).
3. Contractor must Furnish and Install (F & I) new GE interior paintable sealant where
hollow metal door frames have been replaced with new doors, and frames.
4. Contractor must Repair & Replace (Typ. R & R) Radar Approach Control facility
(RAPCON): roofing and coping etc. system (Tear off to the deck),
5. F & I new roof top perimeter guard railing system. Railing must meet FAA (drawings
and specification sections) and OSHA
requirements.
6. F & I fabricated roof top access “ship ladder” per drawing location.
7. Remove (5-6) exterior hollow metal doors and frames.
8. F & I new exterior commercial hollow metal doors and full welded frames.
9. F & I DTM (direct to Metal) primer and paint for new and existing exterior doors.
10. Paint Colors must be chosen at a later date by the occupants ( FAA Personnel that daily
maintains and owns the structure) of the facility.
11. Contractor must remove all construction debris from the site, as to maintain a clean and
safe working environment.
12. PROVIDE AND INSTALL A NEW ROOF LIGHTNING PROTECTION SYSTEM FOR
THE RAPCON BLGD LIGHTNING PROTECTION SYSTEM TO MEET OR EXCEED
THE REQUIREMENTS OF FAA STANDARD, FAA-STD-019F (THROUGHOUT
THE SPECIFICATIONS, TYP), ORDERS, PROJECT DRAWINGS, AND THE
FOLLOWING:
13. STANDARDS FOR INSTALLATION OF LIGHTNING PROTECTION SYSTEMS
(NFPA 780)
14. INSTALLATION REQUIREMENTS FOR LIGHTNING PROTECTION SYSTEMS
(UL 96A)
15. PROVIDE CLASS II OR LARGER RATED MATERIALS, AS SPECIFIED IN NFPA
780 FOR AIR TERMINALS, MAIN AND DOWN CONDUCTORS AND BONDING
CONDUCTORS.
16. NUMBER OF DOWN CONDUCTORS MUST BE BASED ON FAA-STD-019F. MAKE
SURE DOWN CONDUCTORS FOLLOW THE MOST DIRECT PATH TO EARTH
AND MAIN AND BONDING CONDUCTORS MAINTAIN A HORIZONTAL OR
DOWNWARD PATH.
17. AIR TERMINALS MUST BE SOLID COPPER, BRONZE OR ALUMINUM, 12-IN
HIGH MINIMUM, WITH 1/2 –IN DIAMETER FOR COPPER AND 5/8-IN DIAMETER
FOR ALUMINUM AND INSTALLED AS PER NFPA 780 AND UL 96A.
18. ALL PRODUCTS MUST BE UL LISTED AND LABELED WITH THE UL
CERTIFICATION MARK IN ACCORDANCE WITH UL REQUIREMENTS.
19. PLEASE NOTE THAT INCLUSION OF A UL MASTER LABEL ALONE MUST NOT
BE SUFFICIENT TO INDICATE COMMPLIANCE WITH FAA-STD-019F.
Update #3 ·
****Clarification**** Due date for questions: The due date for questions is extended to Thursday May 27, 2021 at 1500 PST. Questions received after this date may not be answered.
Amendment 01 posted 5/17/21
The following is a summary of the work to be performed at the Barksdale RAPCON located on the Barksdale Air Force Base.
1. ALL FAA specified and Contractor supplied materials must require an approval by the
FAA through the submittal process prior to purchase and installation of such materials.
2. Contractor must use GE Sil Proof 2000 sealant, or an equivalent that meets the
specifications in the sealants section (All sealants and all materials listed as brand
names are acceptable or an equivalent if the substitute meets the specifications listed
in the products specification section). This product will be used to reseal where existing
sealant has deteriorated, or sealant was removed (Exterior only).
3. Contractor must Furnish and Install (F & I) new GE interior paintable sealant where
hollow metal door frames have been replaced with new doors, and frames.
4. Contractor must Repair & Replace (Typ. R & R) Radar Approach Control facility
(RAPCON): roofing and coping etc. system (Tear off to the deck),
5. F & I new roof top perimeter guard railing system. Railing must meet FAA (drawings
and specification sections) and OSHA
requirements.
6. F & I fabricated roof top access “ship ladder” per drawing location.
7. Remove (5-6) exterior hollow metal doors and frames.
8. F & I new exterior commercial hollow metal doors and full welded frames.
9. F & I DTM (direct to Metal) primer and paint for new and existing exterior doors.
10. Paint Colors must be chosen at a later date by the occupants ( FAA Personnel that daily
maintains and owns the structure) of the facility.
11. Contractor must remove all construction debris from the site, as to maintain a clean and
safe working environment.
12. PROVIDE AND INSTALL A NEW ROOF LIGHTNING PROTECTION SYSTEM FOR
THE RAPCON BLGD LIGHTNING PROTECTION SYSTEM TO MEET OR EXCEED
THE REQUIREMENTS OF FAA STANDARD, FAA-STD-019F (THROUGHOUT
THE SPECIFICATIONS, TYP), ORDERS, PROJECT DRAWINGS, AND THE
FOLLOWING:
13. STANDARDS FOR INSTALLATION OF LIGHTNING PROTECTION SYSTEMS
(NFPA 780)
14. INSTALLATION REQUIREMENTS FOR LIGHTNING PROTECTION SYSTEMS
(UL 96A)
15. PROVIDE CLASS II OR LARGER RATED MATERIALS, AS SPECIFIED IN NFPA
780 FOR AIR TERMINALS, MAIN AND DOWN CONDUCTORS AND BONDING
CONDUCTORS.
16. NUMBER OF DOWN CONDUCTORS MUST BE BASED ON FAA-STD-019F. MAKE
SURE DOWN CONDUCTORS FOLLOW THE MOST DIRECT PATH TO EARTH
AND MAIN AND BONDING CONDUCTORS MAINTAIN A HORIZONTAL OR
DOWNWARD PATH.
17. AIR TERMINALS MUST BE SOLID COPPER, BRONZE OR ALUMINUM, 12-IN
HIGH MINIMUM, WITH 1/2 –IN DIAMETER FOR COPPER AND 5/8-IN DIAMETER
FOR ALUMINUM AND INSTALLED AS PER NFPA 780 AND UL 96A.
18. ALL PRODUCTS MUST BE UL LISTED AND LABELED WITH THE UL
CERTIFICATION MARK IN ACCORDANCE WITH UL REQUIREMENTS.
19. PLEASE NOTE THAT INCLUSION OF A UL MASTER LABEL ALONE MUST NOT
BE SUFFICIENT TO INDICATE COMMPLIANCE WITH FAA-STD-019F.
Update #2 ·
Amendment 01 posted 5/17/21
The following is a summary of the work to be performed at the Barksdale RAPCON located on the Barksdale Air Force Base.
1. ALL FAA specified and Contractor supplied materials must require an approval by the
FAA through the submittal process prior to purchase and installation of such materials.
2. Contractor must use GE Sil Proof 2000 sealant, or an equivalent that meets the
specifications in the sealants section (All sealants and all materials listed as brand
names are acceptable or an equivalent if the substitute meets the specifications listed
in the products specification section). This product will be used to reseal where existing
sealant has deteriorated, or sealant was removed (Exterior only).
3. Contractor must Furnish and Install (F & I) new GE interior paintable sealant where
hollow metal door frames have been replaced with new doors, and frames.
4. Contractor must Repair & Replace (Typ. R & R) Radar Approach Control facility
(RAPCON): roofing and coping etc. system (Tear off to the deck),
5. F & I new roof top perimeter guard railing system. Railing must meet FAA (drawings
and specification sections) and OSHA
requirements.
6. F & I fabricated roof top access “ship ladder” per drawing location.
7. Remove (5-6) exterior hollow metal doors and frames.
8. F & I new exterior commercial hollow metal doors and full welded frames.
9. F & I DTM (direct to Metal) primer and paint for new and existing exterior doors.
10. Paint Colors must be chosen at a later date by the occupants ( FAA Personnel that daily
maintains and owns the structure) of the facility.
11. Contractor must remove all construction debris from the site, as to maintain a clean and
safe working environment.
12. PROVIDE AND INSTALL A NEW ROOF LIGHTNING PROTECTION SYSTEM FOR
THE RAPCON BLGD LIGHTNING PROTECTION SYSTEM TO MEET OR EXCEED
THE REQUIREMENTS OF FAA STANDARD, FAA-STD-019F (THROUGHOUT
THE SPECIFICATIONS, TYP), ORDERS, PROJECT DRAWINGS, AND THE
FOLLOWING:
13. STANDARDS FOR INSTALLATION OF LIGHTNING PROTECTION SYSTEMS
(NFPA 780)
14. INSTALLATION REQUIREMENTS FOR LIGHTNING PROTECTION SYSTEMS
(UL 96A)
15. PROVIDE CLASS II OR LARGER RATED MATERIALS, AS SPECIFIED IN NFPA
780 FOR AIR TERMINALS, MAIN AND DOWN CONDUCTORS AND BONDING
CONDUCTORS.
16. NUMBER OF DOWN CONDUCTORS MUST BE BASED ON FAA-STD-019F. MAKE
SURE DOWN CONDUCTORS FOLLOW THE MOST DIRECT PATH TO EARTH
AND MAIN AND BONDING CONDUCTORS MAINTAIN A HORIZONTAL OR
DOWNWARD PATH.
17. AIR TERMINALS MUST BE SOLID COPPER, BRONZE OR ALUMINUM, 12-IN
HIGH MINIMUM, WITH 1/2 –IN DIAMETER FOR COPPER AND 5/8-IN DIAMETER
FOR ALUMINUM AND INSTALLED AS PER NFPA 780 AND UL 96A.
18. ALL PRODUCTS MUST BE UL LISTED AND LABELED WITH THE UL
CERTIFICATION MARK IN ACCORDANCE WITH UL REQUIREMENTS.
19. PLEASE NOTE THAT INCLUSION OF A UL MASTER LABEL ALONE MUST NOT
BE SUFFICIENT TO INDICATE COMMPLIANCE WITH FAA-STD-019F.
Update #1 ·
The following is a summary of the work to be performed at the Barksdale RAPCON located on the Barksdale Air Force Base.
1. ALL FAA specified and Contractor supplied materials must require an approval by the
FAA through the submittal process prior to purchase and installation of such materials.
2. Contractor must use GE Sil Proof 2000 sealant, or an equivalent that meets the
specifications in the sealants section (All sealants and all materials listed as brand
names are acceptable or an equivalent if the substitute meets the specifications listed
in the products specification section). This product will be used to reseal where existing
sealant has deteriorated, or sealant was removed (Exterior only).
3. Contractor must Furnish and Install (F & I) new GE interior paintable sealant where
hollow metal door frames have been replaced with new doors, and frames.
4. Contractor must Repair & Replace (Typ. R & R) Radar Approach Control facility
(RAPCON): roofing and coping etc. system (Tear off to the deck),
5. F & I new roof top perimeter guard railing system. Railing must meet FAA (drawings
and specification sections) and OSHA
requirements.
6. F & I fabricated roof top access “ship ladder” per drawing location.
7. Remove (5-6) exterior hollow metal doors and frames.
8. F & I new exterior commercial hollow metal doors and full welded frames.
9. F & I DTM (direct to Metal) primer and paint for new and existing exterior doors.
10. Paint Colors must be chosen at a later date by the occupants ( FAA Personnel that daily
maintains and owns the structure) of the facility.
11. Contractor must remove all construction debris from the site, as to maintain a clean and
safe working environment.
12. PROVIDE AND INSTALL A NEW ROOF LIGHTNING PROTECTION SYSTEM FOR
THE RAPCON BLGD LIGHTNING PROTECTION SYSTEM TO MEET OR EXCEED
THE REQUIREMENTS OF FAA STANDARD, FAA-STD-019F (THROUGHOUT
THE SPECIFICATIONS, TYP), ORDERS, PROJECT DRAWINGS, AND THE
FOLLOWING:
13. STANDARDS FOR INSTALLATION OF LIGHTNING PROTECTION SYSTEMS
(NFPA 780)
14. INSTALLATION REQUIREMENTS FOR LIGHTNING PROTECTION SYSTEMS
(UL 96A)
15. PROVIDE CLASS II OR LARGER RATED MATERIALS, AS SPECIFIED IN NFPA
780 FOR AIR TERMINALS, MAIN AND DOWN CONDUCTORS AND BONDING
CONDUCTORS.
16. NUMBER OF DOWN CONDUCTORS MUST BE BASED ON FAA-STD-019F. MAKE
SURE DOWN CONDUCTORS FOLLOW THE MOST DIRECT PATH TO EARTH
AND MAIN AND BONDING CONDUCTORS MAINTAIN A HORIZONTAL OR
DOWNWARD PATH.
17. AIR TERMINALS MUST BE SOLID COPPER, BRONZE OR ALUMINUM, 12-IN
HIGH MINIMUM, WITH 1/2 –IN DIAMETER FOR COPPER AND 5/8-IN DIAMETER
FOR ALUMINUM AND INSTALLED AS PER NFPA 780 AND UL 96A.
18. ALL PRODUCTS MUST BE UL LISTED AND LABELED WITH THE UL
CERTIFICATION MARK IN ACCORDANCE WITH UL REQUIREMENTS.
19. PLEASE NOTE THAT INCLUSION OF A UL MASTER LABEL ALONE MUST NOT
BE SUFFICIENT TO INDICATE COMMPLIANCE WITH FAA-STD-019F.
Attachments
| File | Type | Posted |
|---|---|---|
| Amendment 3.pdf | ||
| Amendment 2.pdf | ||
| Amendment 01.pdf | ||
| wage.pdf | ||
| DWG BAD Drawings.pdf | ||
| COVID-19 Contractual Requirement Rev 2 04-28-2021.pdf | ||
| 697DCK-20-R-00268.pdf | ||
| BAD Combined Specs 3-11-2021 rjm.pdf | ||
| PPQ.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Barksdale RAPCON Misc. Repairs | Solicitation | |
| FAA Market Survey: Barksdale AFB RAPCON Building Repairs | Pre-Solicitation |