This is a solicitation for miscellaneous repairs to the Barksdale Radar Approach Control facility located at Barksdale Air Force Base in Louisiana. The contractor will be required to perform tasks such as replacing sealants, repairing and replacing the roof system, installing a new perimeter railing and access ladder on the roof, replacing exterior doors and frames, installing a new lightning protection system, and removing construction debris from the site. The solicitation number is 697DCK-20-R-00268 and offers are due by June 4, 2021. A site visit will be held on May 13, 2021 for interested offerors to attend. The work is estimated to cost between $300,000 and $500,000 and will be awarded by the Federal Aviation Administration to support repairs at the facility.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 3.pdf | ||
| Amendment 2.pdf | ||
| Amendment 01.pdf | ||
| wage.pdf | ||
| DWG BAD Drawings.pdf | ||
| COVID-19 Contractual Requirement Rev 2 04-28-2021.pdf | ||
| BAD Combined Specs 3-11-2021 rjm.pdf | ||
| PPQ.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of Transportation Federal Aviation Administration
Request for Offers (RFO) Cover Letter
Solicitation Package
Project Name: Miscellaneous repairs to the Barksdale RAPCON. .
Location: Shreveport, LA
Solicitation No.: 697DCK-20-R-00268
Issue Date: May 3, 2021
Submit Offers to: Darren.odegard@faa.gov
Submit Offers by: June 4, 2021 at 1400 local Seattle time.
Special Instructions:
1) Insurance is required (See Contract Clause 3.4.1-12 Insurance (Jul 1996) for required coverage limits).
Employer’s liability coverage of at least $100,000.00 shall be required.
General Liability. Bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000.00 per occurrence.
Automobile liability coverage of at least $200,000.00 per person and $500,000 per occurrence for bodily injury and $200,000.00 per occurrence for property damage
2) Payment and Performance Bonds are required (See Contract Clauses 3.4.1-5 Payment
Bond Requirements, 3.4.1-4 Performance Bond Requirements.
3) Set Aside: This procurement is set aside for ALL Small Business entities.
4) NAICS Code: 236220 Commercial and Institutional Building Construction, which as a small business size standard of $39.5 Million.
5) BADGING, The Contractor is required to acquire ALL necessary FAA and Airport badges.
6) PROJECT START: Work under this contract is anticipated to start in August 2021, COVID dependant.
7) Estimated Price Range: Is between $300,000.00 and $500,000.00.
8) Site Visit: One site visit will be held on May 13, 2021 at 9am. It is optional, but Offerors are highly encouraged to intend. Due to COVID, group size is limited and no Offeror may bring more than one other person (two people total). Should the group size exceed the limit of eight people total, another site visit will be held after the first one for the overflow.
Offerors choosing to attend must provide the name(s) of those who will be attending to darren.odegard@faa.gov, by May 11, 2021 at 1200 PST. Specific instructions for the site visit as well as the local POC will be provided to those who submit an email. If a second group is required, placement will be based on when the email was received, and you will be notified of which group you are in.
mailto:darren.odegard@faa.gov
SOLICITATION, OFFER
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
A. NAME B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder"
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED BID (RFP)
FEDERAL AVIATION ADMINISTRATION
AAQ-500 - REGIONAL ACQUISITIONS
2200 S. 216TH STREET
DES MOINES WA 98198-6547
AAQ530ANM-AFN
Darren Odegard 206-231-3022 x
05/03/2021 59
PURCHASE REQUEST NO.
697DCK-20-R-00268
10. THE CONTRACT AUTHORITY REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Furnish all labor, materials, equipment, transportation, insurance, notifications, licenses, permits, fees and supervision necessary to complete misc. repairs at the
Barksdale TRACON at the Barksdale Air Force Base in Louisiana. Contractor must perform all work in accordance with the specifications, drawings, contract clauses, and wage rates. Work includes:
RAPCON BUILDING (Contractor tasks)
1. ALL FAA specified and Contractor supplied materials must require an approval by the
FAA through the submittal process prior to purchase and installation of such materials.
2. Contractor must use GE Sil Proof 2000 sealant, or an equivalent that meets the specifications in the sealants section (All sealants and all materials listed as brand names are acceptable or an equivalent if the substitute meets the specifications listed in the products specification section). This product will be used to reseal where existing sealant has deteriorated, or sealant was removed (Exterior only).
Continued ...
11. The Contractor shall begin performance within
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award notice to proceed. The performance period is mandatory, negotiable. (See ________________________________________________ .)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and is not required.is, B. An offer guarantee
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers must be publicly opened at that time . Sealed envelopes containing offers shall be marked to show the offeror's name and address. The solicitation number, and the date and time offers are due.
D. Offers providing less than
12B. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in item 12B.)
5 100 calendar days and complete it within ________________ ________________ calendar days after receiving
1 1400
06/04/2021 x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Contract Authority acceptance after the date offers are due will not be considered and will _________________ be rejected.
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Contract Authority in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13D. Failure to insert any number means the offeror accepts the minimum in item 13D.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (MUST BE FULLY COMPLETED BY OFFEROR)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20B. SIGNATURE 20C. OFFER DATE
AWARD (To be completed by Contract Authority)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Contract Authority solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE 30C. DATE 31B. CONTRACT AUTHORITY 31C. AWARD DATE
BY
2PAGE OF
FEDERAL AVIATION ADMINISTRATION
AAQ-500 - REGIONAL ACQUISITIONS
2200 S. 216TH STREET
DES MOINES WA 98198-6547
AAQ530ANM-AFN
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.)
Continued...
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 59
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
697DCK-20-R-00268
(A) (B) (C) (D) (E) (F)
3. Contractor must Furnish and Install (F & I) new GE interior paintable sealant where hollow metal door frames have been replaced with new doors, and frames.
4. Contractor must Repair & Replace (Typ. R & R)
Radar Approach Control facility
(RAPCON): roofing and coping etc. system (Tear off to the deck),
5. F & I new roof top perimeter guard railing system. Railing must meet FAA (drawings and specification sections) and OSHA requirements.
6. F & I fabricated roof top access “ship ladder” per drawing location.
7. Remove (5-6) exterior hollow metal doors and frames.
8. F & I new exterior commercial hollow metal doors and full welded frames.
9. F & I DTM (direct to Metal) primer and paint for new and existing exterior doors.
10. Paint Colors must be chosen at a later date by the occupants ( FAA Personnel that daily maintains and owns the structure) of the facility.
11. Contractor must remove all construction debris from the site, as to maintain a clean and safe working environment.
12. PROVIDE AND INSTALL A NEW ROOF LIGHTNING
PROTECTION SYSTEM FOR
THE RAPCON BLGD LIGHTNING PROTECTION SYSTEM TO
MEET OR EXCEED
THE REQUIREMENTS OF FAA STANDARD, FAA-STD-019F
(THROUGHOUT
THE SPECIFICATIONS, TYP), ORDERS, PROJECT
DRAWINGS, AND THE
FOLLOWING:
13. STANDARDS FOR INSTALLATION OF LIGHTNING
PROTECTION SYSTEMS
(NFPA 780)
14. INSTALLATION REQUIREMENTS FOR LIGHTNING
PROTECTION SYSTEMS
(UL 96A)
15. PROVIDE CLASS II OR LARGER RATED MATERIALS,
AS SPECIFIED IN NFPA
780 FOR AIR TERMINALS, MAIN AND DOWN CONDUCTORS
AND BONDING
CONDUCTORS.
16. NUMBER OF DOWN CONDUCTORS MUST BE BASED ON
Continued ...
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
4 59
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
697DCK-20-R-00268
(A) (B) (C) (D) (E) (F)
FAA-STD-019F. MAKE
SURE DOWN CONDUCTORS FOLLOW THE MOST DIRECT PATH
TO EARTH
AND MAIN AND BONDING CONDUCTORS MAINTAIN A
HORIZONTAL OR
DOWNWARD PATH.
17. AIR TERMINALS MUST BE SOLID COPPER, BRONZE OR
ALUMINUM, 12-IN
HIGH MINIMUM, WITH 1/2 –IN DIAMETER FOR COPPER
AND 5/8-IN DIAMETER
FOR ALUMINUM AND INSTALLED AS PER NFPA 780 AND UL
96A.
18. ALL PRODUCTS MUST BE UL LISTED AND LABELED
WITH THE UL
CERTIFICATION MARK IN ACCORDANCE WITH UL
REQUIREMENTS.
19. PLEASE NOTE THAT INCLUSION OF A UL MASTER
LABEL ALONE MUST NOT
BE SUFFICIENT TO INDICATE COMMPLIANCE WITH
FAA-STD-019F.
Section B - Supplies or Services/Prices Section B - Schedule
B001. PRICES/COSTS: Furnish all labor, materials, equipment, transportation, insurance, notifications, licenses, permits, fees and supervision necessary to complete misc. repairs at the Barksdale TRACON at the Barksdale Air Force Base in Louisiana. Contractor must perform all work in accordance with the Specifications, drawings, contract clauses, and wage rates.
CLIN # Description Quantity Price
Barksdale TRACON Repairs
1 Job
The offered price must encompass all costs related to (a) direct and indirect labor, fringe benefits, overhead, G&A expenses, profit, material, equipment, other direct costs, insurance, freight, handling, transportation, inspection, testing, operation and maintenance manuals, bonds, etc., (b) federal, state, and local taxes, (c) all applicable fees permits, licenses, and (d) any miscellaneous charges.
Effective April 1, 1996, the Federal Aviation Administration (FAA) began operating under the new FAA Acquisition Management System. The 1996 DOT Appropriation Act, Public Law 104-50, mandated that the FAA rewrite its acquisition regulations and granted legislative relief from certain laws. The Federal Acquisition Regulations (FAR), Federal Acquisition Streamlining Act of 1994, Small Business Act, and Competition in Contracting Act, are three of these laws.
Clause List
The remainder of this page has been intentionally left blank.
Section C - Description/Specifications Scope of Work
Summary of work to be performed. Please see the Specification for complete details.
RAPCON BUILDING (Contractor tasks)
1. ALL FAA specified and Contractor supplied materials must require an approval by the FAA through the submittal process prior to purchase and installation of such materials.
2. Contractor must use GE Sil Proof 2000 sealant, or an equivalent that meets the specifications in the sealants section (All sealants and all materials listed as brand names are acceptable or an equivalent if the substitute meets the specifications listed in the products specification section). This product will be used to reseal where existing sealant has deteriorated, or sealant was removed (Exterior only).
3. Contractor must Furnish and Install (F & I) new GE interior paintable sealant where hollow metal door frames have been replaced with new doors, and frames.
4. Contractor must Repair & Replace (Typ. R & R) Radar Approach Control facility (RAPCON): roofing and coping etc. system (Tear off to the deck),
5. F & I new roof top perimeter guard railing system. Railing must meet FAA (drawings and specification sections) and OSHA requirements.
6. F & I fabricated roof top access “ship ladder” per drawing location.
7. Remove (5-6) exterior hollow metal doors and frames.
8. F & I new exterior commercial hollow metal doors and full welded frames.
9. F & I DTM (direct to Metal) primer and paint for new and existing exterior doors.
10. Paint Colors must be chosen at a later date by the occupants ( FAA Personnel that daily maintains and owns the structure) of the facility.
11. Contractor must remove all construction debris from the site, as to maintain a clean and safe working environment.
12. PROVIDE AND INSTALL A NEW ROOF LIGHTNING PROTECTION SYSTEM FOR
THE RAPCON BLGD LIGHTNING PROTECTION SYSTEM TO MEET OR EXCEED
THE REQUIREMENTS OF FAA STANDARD, FAA-STD-019F (THROUGHOUT
THE SPECIFICATIONS, TYP), ORDERS, PROJECT DRAWINGS, AND THE
FOLLOWING:
13. STANDARDS FOR INSTALLATION OF LIGHTNING PROTECTION SYSTEMS
(NFPA 780)
14. INSTALLATION REQUIREMENTS FOR LIGHTNING PROTECTION SYSTEMS
(UL 96A)
15. PROVIDE CLASS II OR LARGER RATED MATERIALS, AS SPECIFIED IN NFPA
780 FOR AIR TERMINALS, MAIN AND DOWN CONDUCTORS AND BONDING
CONDUCTORS.
16. NUMBER OF DOWN CONDUCTORS MUST BE BASED ON FAA-STD-019F. MAKE
SURE DOWN CONDUCTORS FOLLOW THE MOST DIRECT PATH TO EARTH
AND MAIN AND BONDING CONDUCTORS MAINTAIN A HORIZONTAL OR
DOWNWARD PATH.
17. AIR TERMINALS MUST BE SOLID COPPER, BRONZE OR ALUMINUM, 12-IN
HIGH MINIMUM, WITH 1/2 –IN DIAMETER FOR COPPER AND 5/8-IN DIAMETER
FOR ALUMINUM AND INSTALLED AS PER NFPA 780 AND UL 96A.
18. ALL PRODUCTS MUST BE UL LISTED AND LABELED WITH THE UL
CERTIFICATION MARK IN ACCORDANCE WITH UL REQUIREMENTS.
19. PLEASE NOTE THAT INCLUSION OF A UL MASTER LABEL ALONE MUST NOT
BE SUFFICIENT TO INDICATE COMMPLIANCE WITH FAA-STD-019F.
Section D - Packaging and Marking
Section E - Inspection and Acceptance Clause List
3.1-1 CLAUSES AND PROVISIONS INCORPORATED BY REFERENCE (JUL 2019)
This screening information request (SIR) or contract, as applicable, incorporates by reference the provisions or clauses listed below with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make the full text available, or offerors and contractors may obtain the full text via Internet at:
https://fast.faa.gov/contractclauses.cfm.
(End of clause)
3.10.4-10 INSPECTION OF CONSTRUCTION (SEP 2009)
Section F - Deliveries or Performance
Section G - Contract Administration Data Clause List
3.10.1-23 CONTRACTING OFFICER'S REPRESENTATIVE-CONSTRUCTION CONTRACTS (APR
2012)
(a) The Contracting Officer may appoint other Government personnel to accomplish certain contract administration matters. While there shall be various titles and divisions of duties for these individuals, generically they are known as Contracting Officer's Representatives (CORs). The Contracting Officer will provide written notice of COR appointment(s), setting forth the authorities and limitations, to the Contractor within 5 calendar days prior to the notice to proceed. COR duties may include, but are not limited to:
(1) Perform as the authorized representative of the Contracting Officer for technical matters, including interpretation of specifications and drawings, and inspection and review of work performed.
(2) Perform as the authorized representative of the Contracting Officer for administrative matters, including reviewing payments, and updated delivery schedules.
(b) These representatives are authorized to act for the Contracting Officer in all specifically delegated matters pertaining to the contract, except:
(1) contract modifications that change the contract price or cost, technical requirements or time for performance, unless delegated field change order authority;
(2) suspension or termination of the Contractor's right to proceed, either for default or for convenience;
(3) final decisions on any matters subject to appeal, e.g., disputes under the "Contract Disputes" clause; and
(4) final acceptance under the contract.
(End of clause)
Section H - Special Contract Requirements Clause List
3.1.9-1 ELECTRONIC COMMERCE AND SIGNATURE (JUL 2020)
(a) The Electronic Signatures in Global and National Commerce Act (E-SIGN) establishes a legal equivalence between:
(1) Contracts written on paper and contracts in electronic form;
(2) Pen-and-ink signatures and electronic signatures; and
(3) Other legally-required written records and the same information in electronic form.
(b) With the submission of an offer, the offeror acknowledges and accepts the utilization of electronic commerce as part of the requirements of this solicitation and the resultant contract.
(c) Certain documents may need to be provided or maintained in original form, such as large-scale drawings impractical to convert to electronic format or a document with a raised seal signifying authenticity. This clause does not change or affect any other requirements that a document must be in paper format to satisfy legal requirements such as for certain real estate transactions.
(d) The use of electronic signature technology is authorized under this solicitation and the resulting contract.
(e) Contractors must not digitally sign any documents with software that uses the Secure Hash Algorithm 1 (SHA- 1). All digitally signed documents and contracts sent to the FAA must use a SHA-256 or higher hash algorithm. This is based on the National Institute of Standards and Technology (NIST) Policy Statement on Hash Functions dated August 5, 2015. Further guidance on the use of SHA-256 is in NIST Special Publication (SP) 800-57 Part 1, section
5.6.2 as amended and SP 800-131A, Revision 1 dated November 6, 2015. Additional guidance on the use of SHA-3 is in NIST SP 800-185 as amended.
(f) Contractors do not have to update documents previously digitally signed using SHA-1 hash algorithms unless the document requires updating. The FAA and contractors may continue to use SHA-1 for the following applications:
Verifying old digital signatures and time stamps, generating and verifying hash-based message authentication codes (HMACs), key derivation functions (KDFs), and random bit/number generation.
(End of Clause)
3.8.2-17 KEY PERSONNEL AND FACILITIES (JUL 2019)
(a) The personnel and/or facilities as specified below are considered essential to the work being performed hereunder and may, with the consent of the contracting parties, be changed from time to time during the course of the contract.
(b) Prior to removing, replacing, or diverting any of the specified personnel and/or facilities, the Contractor must notify in writing, and receive consent from, the Contracting Officer reasonably in advance of the action and must submit justification (including proposed substitutions) in sufficient detail to permit evaluation of the impact on this contract.
(c) No diversion will be made by the Contractor without the written consent of the Contracting Officer.
(d) The key personnel and/or facilities under this contract are:
[ ] Project Superintendent
(List key personnel and/or facilities)
Section I - Contract Clauses Clause List
3.1-1 CLAUSES AND PROVISIONS INCORPORATED BY REFERENCE (JUL 2019)
This screening information request (SIR) or contract, as applicable, incorporates by reference the provisions or clauses listed below with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make the full text available, or offerors and contractors may obtain the full text via Internet at:
https://fast.faa.gov/contractclauses.cfm.
(End of clause)
3.1.7-2 ORGANIZATIONAL CONFLICTS OF INTEREST (JUL 2018)
3.2.2.3-33 ORDER OF PRECEDENCE (MAR 2009)
3.2.2.3-42 DIFFERING SITE CONDITIONS (JUL 2004)
3.2.2.3-43 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (JUL 2004)
3.2.2.3-45 MATERIAL AND WORKMANSHIP (JUL 2004)
3.2.2.3-46 SUPERVISING THE CONTRACT WORK (JUL 2004)
3.2.2.3-47 PERMITS AND RESPONSIBILITIES (JUL 2004)
3.2.2.3-48 OTHER CONTRACTS (MAR 2009)
3.2.2.3-49 PROTECTING EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,
AND IMPROVEMENTS (JUL 2004)
3.2.2.3-50 PROPERTY PROTECTION (OCT 2014)
3.2.2.3-51 OPERATIONS AND STORAGE AREAS (APR 2012)
3.2.2.3-52 USE AND POSSESSION BEFORE THE PROJECT IS COMPLETE (JUL 2004)
3.2.2.3-53 CLEANING UP AND ROADWAY MAINTENANCE (JUL 2004)
3.2.2.3-54 PREVENTING ACCIDENTS (JUL 2004)
3.2.2.3-55 AVAILABILITY AND USE OF UTILITY SERVICES (JUL 2004)
3.2.2.3-56 SCHEDULES FOR CONSTRUCTION CONTRACTS (JUL 2004)
3.2.2.3-58 LAYOUT OF WORK (MAR 2009)
3.2.2.3-60 SPECIFICATIONS, DRAWINGS, AND MATERIAL OFFERS (MAR 2009)
3.2.2.3-62 PRECONSTRUCTION CONFERENCE (JUL 2004)
3.2.2.3-68 SAFETY AND HEALTH (OCT 2014)
3.2.2.3-83 PROHIBITION AGAINST CONTRACTING WITH INVERTED DOMESTIC
CORPORATIONS (OCT 2015)
3.2.2.7-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH
CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (APR 2011)
3.2.2.7-8 DISCLOSURE OF TEAM ARRANGEMENTS (APR 2008)
3.2.5-1 OFFICIALS NOT TO BENEFIT (APR 2021)
3.2.5-3 GRATUITIES OR GIFTS (OCT 2019)
3.2.5-4 CONTINGENT FEES (OCT 1996)
3.2.5-5 ANTI-KICKBACK PROCEDURES (OCT 2019)
3.2.5-8 WHISTLEBLOWER PROTECTION FOR CONTRACTOR EMPLOYEES (APR 1996)
3.3.1-15 ASSIGNMENT OF CLAIMS (JUL 2018)
3.3.1-19 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2021)
3.3.1-20 PROVIDING ACCELERATED PAYMENT TO SMALL BUSINESS SUBCONTRACTORS
(OCT 2012)
3.3.1-34 PAYMENT BY ELECTRONIC FUNDS TRANSFER- SYSTEM FOR AWARD
MANAGEMENT (JUL 2018)
3.4.1-6 ADDITIONAL BOND SECURITY (APR 1996)
3.4.1-7 NOTICE TO PROCEED (OCT 2019)
3.4.1-10 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (OCT 2020)
3.4.2-6 TAXES - CONTRACTS PERFORMED IN U.S. POSSESSIONS OR PUERTO RICO (OCT
1996)
3.4.2-8 FEDERAL, STATE, AND LOCAL TAXES - FIXED PRICE CONTRACT (JUL 2019)
3.5-1 AUTHORIZATION AND CONSENT (JAN 2019)
3.5-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT
(JAN 2009)
3.5-4 PATENT INDEMNITY - CONSTRUCTION CONTRACTS (JAN 2009)
3.6.1-1 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (OCT 2019)
3.6.1-3 UTILIZATION OF SMALL, SMALL DISADVANTAGED, WOMEN-OWNED, SERVICE-
DISABLED VETERAN OWNED, AND HUBZONE SMALL BUSINESS CONCERNS (JAN 2021)
3.6.1-4 SMALL, SMALL DISADVANTAGED, WOMEN-OWNED, SERVICE-DISABLED VETERAN
OWNED, AND HUBZONE SMALL BUSINESS SUBCONTRACTING PLAN (JAN 2021)
3.6.1-6 LIQUIDATED DAMAGES - SUBCONTRACTING PLAN (JAN 2021)
3.6.1-15 POST-AWARD SMALL BUSINESS PROGRAM RE-REPRESENTATION (JAN 2021)
3.6.2-1 CONTRACT WORK HOURS AND SAFETY STANDARDS ACT-OVERTIME
COMPENSATION (OCT 2018)
3.6.2-2 CONVICT LABOR (APR 1996)
3.6.2-9 EQUAL OPPORTUNITY (JUL 2020)
3.6.2-12 EQUAL OPPORTUNITY FOR VETERANS (JUL 2020)
3.6.2-13 AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES (JUL 2020)
3.6.2-16 NOTICE TO THE GOVERNMENT OF LABOR DISPUTES (OCT 2018)
3.6.2-18 DAVIS BACON ACT (OCT 2018)
3.6.2-19 WITHHOLDING-LABOR VIOLATIONS (JUL 2017)
3.6.2-20 PAYROLLS AND BASIC RECORDS (APR 2017)
3.6.2-21 APPRENTICES, TRAINEES, AND HELPERS (JAN 2019)
3.6.2-22 SUBCONTRACTS (LABOR STANDARDS) (JAN 2019)
3.6.2-23 CERTIFICATION OF ELIGIBILITY (JAN 2019)
3.6.2-35 PREVENTION OF SEXUAL HARASSMENT (OCT 2018)
3.6.2-39 TRAFFICKING IN PERSONS (APR 2019)
3.6.2-44 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS
ACT (JAN 2019)
3.6.3-13 AFFIRMATIVE PROCUREMENT OF RECYCLED CONTENT AND PRODUCTS UNDER
SERVICE AND CONSTRUCTION CONTRACTS (JAN 2020)
3.6.3-14 USE OF ENVIRONMENTALLY PREFERABLE PRODUCTS (JAN 2020)
3.6.3-16 DRUG FREE WORKPLACE (MAR 2009)
3.6.3-23 DELIVERY OF ELECTRONIC AND PAPER DOCUMENTS (JAN 2020)
3.6.3-24 ASBESTOS NESHAP COMPLIANCE (OCT 2015)
3.6.4-5 BUY AMERICAN - STEEL AND MANUFACTURED PRODUCTS (JUL 2010)
3.6.4-10 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JAN 2010)
3.6.4-23 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND
VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (JAN 2021)
3.9.1-1 CONTRACT DISPUTES (JAN 2020)
3.9.1-2 PROTEST AFTER AWARD (AUG 1997)
3.10.1-7 BANKRUPTCY (APR 1996)
3.10.1-8 SUSPENSION OF WORK (SEP 1998)
3.10.1-15 CHANGES-CONSTRUCTION, DISMANTLING, DEMOLITION, OR REMOVAL OF
IMPROVEMENTS (JUL 1996)
3.10.1-16 CHANGES AND CHANGED CONDITIONS (APR 1996)
3.10.1-20 WARRANTY-CONSTRUCTION (JUL 1996)
3.10.1-25 NOVATION AND CHANGE-OF-NAME AGREEMENTS (OCT 2007)
3.10.3-2 GOVERNMENT PROPERTY - BASIC CLAUSE (APR 2019)
3.10.6-1 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) (OCT
1996)
3.10.6-6 DEFAULT (FIXED PRICE CONSTRUCTION) (OCT 1996)
3.13-5 SEAT BELT USE BY CONTRACTOR EMPLOYEES (OCT 2001)
3.13-13 CONTRACTOR POLICY TO BAN TEXT MESSAGING WHILE DRIVING (JAN 2011)
3.13-14 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT
AWARDS (JAN 2018)
3.2.2.3-41 PERFORMING WORK (JUL 2004)
The Contractor (you) must perform, using your own organization, work equivalent to at least 20 percent of the total amount of work under the contract on the site. The CO may modify this contract to reduce this percentage if you request a reduction and the CO determines that it would be to the Government's advantage to do so.
(End of clause)
3.2.2.3-60 SPECIFICATIONS, DRAWINGS, AND MATERIAL OFFERS (MAR 2009) - ALTERNATE
I (MAR 2009)
(a) If either the specifications or the drawings (but not both) mention tasks, the Contractor (you) must assume that the tasks are in both. If the drawings and specifications differ, the specifications govern. If there is a discrepancy in the figures, in the drawings, or in the specifications, submit the matter promptly to the Contracting Officer (CO), who will promptly determine which governs, and notify you in writing. Any adjustment you make without the CO's determination is at your own risk and expense. From time to time the CO will provide necessary detailed drawings and other information, unless otherwise provided.
(b) Wherever in the specifications or the drawings FAA (we, our) uses "directed," "required," "ordered," "designated," "prescribed," or similar words, they refer to the CO's requirements. Similarly, "approved," "acceptable," "satisfactory," or similar words refer to the CO's approval, unless otherwise expressly stated. You must have a complete set of plans and specifications on site and available for our use.
(c) Where we use "as shown," "as indicated," "as detailed," or similar words, they refer to the drawings accompanying this contract, unless stated otherwise. The word "provided" means "provided and installed."
(d) Omissions from the drawings and specifications or the erroneous description of details of work which are necessary to carry out the intent of the drawings and specifications, or which are customarily performed, does not relieve you from performing those omitted or erroneously described details of the work. You must perform them as if fully and correctly set forth and described in the drawings and specifications.
(e) You must check all drawings we provide to you before starting work and must promptly notify the CO of any discrepancies. In general you should follow figures marked on drawings, rather than scale measurements. In general, large scale drawings have precedence over small scale drawings. You must compare all drawings and verify the figures before laying out the work. If you do not verify the figures, you will be responsible for any errors you might have avoided had you verified them.
(f) "Shop drawings" means drawings, you or any subcontractor submit to us under a construction contract, showing in detail the proposed fabrication and assembly of structural elements and the installation (that is, form, fit, and attachment details) of materials or equipment. It includes drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials you provided to explain in detail specific portions of the work the contract requires.
FAA may duplicate, use, and disclose in any manner and for any purpose shop drawings you deliver under this contract.
(g) If this contract requires material offers (for example, shop drawings, catalog cuts, certificates of conformance), you must coordinate all of your offers, and review them for accuracy, completeness, and compliance with contract requirements. You must provide evidence that you approve the submittals. If you submit materials to us without this evidence, we may return them and ask you to resubmit them. The CO will indicate whether he or she approves or disapproves your offer, and if the CO does not approve it as submitted, will indicate our reasons for rejecting it. Any work done before the CO's approval is at your risk. The CO's approval does not relieve you from responsibility for any errors or omissions in the submittals, nor from responsibility for complying with the contract requirements, except as described under (h).
(h) If you submittals vary from the contract requirements, you must describe the variations in writing, separate from the submittal, when you submit them. Send this description, a copy of the offer, and a proposal to incorporate it into the contract directly to the CO. If the CO approves a variation, the CO must issue an appropriate contract modification, unless the variation is minor or does not involve a change in price or in time of performance.
(i) You must submit to the CO for approval four copies (unless otherwise indicated) of all shop drawings as called for under the various headings of these specifications. The CO will keep three sets (unless otherwise indicated) of all offers and will return one set to you.
(j) You must insert this clause, with appropriate changes in the designation of the parties, in all subcontracts.
(k) When you finish the work under this contract, you must provide [CO insert number] complete reproducible sets of all shop drawings as we finally approve them. These drawings must show all changes and revisions made up to the time you finish the work and we accept it.
(End of clause)
3.2.2.3-71 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (JUL 2004)
The Contractor (you) must
(a) begin work under this contract within 5 calendar days after the date you receive the notice to proceed,
(b) perform the work diligently, and
(c) complete the entire work ready for use not later than 100. The time allowed for completion must include final cleanup of the premises.
3.2.2.3-71 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (JUL 2004) -
ALTERNATE I (JUL 2004)
The Contractor (you) must
(a) begin work under this contract within [Contracting Officer (CO) insert number] calendar days after the date you receive the notice to proceed,
(b) perform the work diligently, and
(c) complete the entire work ready for use not later than [CO insert date]. The time allowed for completion must include final cleanup of the premises.
(d) The completion date assumes that the successful offeror will receive the notice to proceed by [Contracting Officer insert date]. The CO will extend the completion date by the number of calendar days after the above date that you receive the notice to proceed, except to the extent that the delay in issuing the notice to proceed results from your failure to execute the contract and give the required performance and payment bonds to FAA within the time specified.
(End of clause)
3.3.1-2 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (JUL 2018)
(a) The FAA will pay the Contractor the contract price as provided in this contract.
(b) The FAA will make financing payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer. The Contractor must furnish a breakdown of the total contract price showing the amount included therein for each principal category of the work, which must substantiate the payment amount requested in order to provide a basis for determining financing payments, in such detail as requested by the Contracting Officer. In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site may also be taken into consideration if --
(1) Consideration is specifically authorized by this contract; and
(2) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.
(c) Along with each request for financing payments, the contractor must furnish the following certification, or payment will not be made:
I hereby certify, to the best of my knowledge and belief, that-
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) Payments to subcontractors and suppliers have been made from previous payments received under the contract, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of chapter 39 of Title 31, United States Code; and
(3) This request for financing payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract.
[enter name] (Name) [enter title] (Title) [enter date] (Date)
(d) If the Contractor, after making a certified request for financing payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the unearned amount), the Contractor must-
(1) Notify the Contracting Officer of such performance deficiency;
(2) Be obligated to pay the FAA an amount (computed by the Contracting Officer in the manner provided in "Interest" clause) equal to interest on the unearned amount from the date of receipt of the unearned amount until-
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for financing payments by an amount equal to the unearned amount.
(e) If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer will authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future financing payments that amount the Contracting Officer considers adequate for protection of the FAA and will release to the Contractor all the remaining withheld funds.
Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment will be made for the completed work without retention of a percentage.
(f) All material and work covered by financing payments made will, at the time of payment, become the sole property of the FAA, but this will not be construed as--
(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the FAA to require the fulfillment of all of the terms of the contract.
(g) In making these financing payments, the FAA will, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) above will not apply to that portion of financing payments attributable to bond premiums.
(h) The FAA will pay the amount due the Contractor under this contract after-
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the FAA arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned.
(i) Notwithstanding any provision of this contract, financing payments will not exceed 80 percent on work accomplished on undefinitized contract actions. A contract action is any action resulting in a contract, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the "Changes" clause, or funding and other administrative changes.
3.3.1-31 PROGRESS PAYMENTS (JUL 2018)
Progress payments will be made to the Contractor when requested as work progresses, but not more frequently than monthly in amounts approved by the Contracting Officer, under the following conditions:
(a) Computation of amounts.
(1) Unless the Contractor requests a smaller amount, each progress payment will be computed as:
(i) 80 percent of the Contractor's cumulative total costs under this contract, whether or not actually paid plus financing payments to subcontractors (see paragraph (j)), as shown by records maintained by the Contractor for the purpose of obtaining payment under Government contracts, plus
(ii) progress or financing payments to subcontractors (see paragraph (j) below), all less the sum of all previous progress payments made by the Government under this contract.
(iii) Cost of money is allowable subject to the requirements of clause 3.3.2-1, "FAA Cost Principles".
(2) The following conditions apply to the timing of including costs in progress payment requests:
(i) The costs of supplies and services purchased by the Contractor from subcontractors directly for this contract may be included whether or not actually paid.
(ii) Costs for the following may be included when incurred, even if before payment, when the Contractor is not delinquent in payment of the costs of contract performance in the ordinary course of business: In support of this, the Contractor must include a certification in its request for progress payment indicating that it is not delinquent in payment of costs of contract performance in the ordinary course of business.
(A) Materials issued from the Contractor's stores and placed in the production process for use on this contract.
(B) Direct labor, direct travel, and other direct in-house costs.
(C) Properly allocable and allowable indirect costs.
(iii) Accrued costs of Contractor contributions under employee pension or other postretirement benefit, profit sharing, and stock ownership plans will be excluded until actually paid unless---
(A) The Contractor's practice is to contribute to the plans quarterly or more frequently; and
(B) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contributions remaining unpaid will be excluded from the Contractor's total costs for progress payments until paid).
(iv) If the contract is subject to the special transition method authorized in Cost Accounting Standard (CAS) 410, Allocation of Business Unit General and Administrative Expense to Final Cost Objective, General and Administrative expenses (G&A) will not be included in progress payment requests until the suspense account prescribed in CAS 410 is less than--
(A) Five million dollars; or
(B) The value of the work-in-process inventories under contracts entered into after the suspense account was established (only a pro rata share of the G&A allocable to the excess of the inventory over the suspense account value is includable in progress payment requests under this contract).
(3) The Contractor must not include the following in total costs for progress payment purposes in subparagraph (a)(1)(i) above:
(i) Costs that are not reasonable, allocable to this contract, and consistent with sound and generally accepted accounting principles and practices.
(ii) Costs incurred by subcontractors or suppliers.
(iii) Costs ordinarily capitalized and subject to depreciation or amortization except for the properly depreciated or amortized portion of such costs.
(iv) Payments made or amounts payable to subcontractors or suppliers, except for--
(A) Completed work, including partial deliveries, to which the Contractor has acquired title; and
(B) Work under cost-reimbursement or time-and-material subcontracts to which the Contractor has acquired title.
(4) The amount of unliquidated progress payments may exceed neither (i) the progress payments made against incomplete work (including allowable unliquidated progress payments to subcontractors) nor (ii) the value, for progress payment purposes, of the incomplete work. Incomplete work will be considered to be the supplies and services required by this contract, for which delivery and invoicing by the Contractor and acceptance by the Government are incomplete.
(5) The total amount of progress payments will not exceed 80 percent of the total contract price.
(6) If a progress payment or the unliquidated progress payments exceed the amounts permitted by subparagraphs (a)(4) or (a)(5) above, the Contractor must repay the amount of such excess to the Government on demand subject to [CO to insert appropriate interest rate] calculated from the time the excess payment was received by the contractor until such time as the reimbursement is received by the Government
(b) Liquidation. Except as provided in termination clauses of the contract, all progress payments will be liquidated by deducting from any payment under this contract, other than advance or progress payments, the unliquidated progress payments, or 80 percent of the amount invoiced, whichever is less. The Contractor must repay to the Government any amounts required by a retroactive price reduction, after computing liquidations and payments on past invoices at the reduced prices and adjusting the unliquidated progress payments accordingly. The Government reserves the right to unilaterally change from the ordinary liquidation rate to an alternate rate when deemed appropriate for proper contract financing.
(c) Reduction or suspension. The Contracting Officer may reduce or suspend progress payments, increase the rate of liquidation, or take a combination of these actions, after finding on substantial evidence any of the following conditions:
(1) The Contractor failed to comply with any material requirement of this contract (which includes paragraphs (f) and (g) below).
(2) Performance of this contract is endangered by the Contractor's (i) failure to make progress or (ii) unsatisfactory financial condition.
(3) Inventory allocated to this contract substantially exceeds reasonable requirements.
(4) The Contractor is delinquent in payment of the costs of performing this contract in the ordinary course of business.
(5) The unliquidated progress payments exceed the fair value of the work accomplished on the undelivered portion of this contract.
(6) The Contractor is realizing less profit than that reflected in the establishment of any alternate liquidation rate in paragraph (b) above, and that rate is less than the progress payment rate stated in subparagraph (a)(1) above.
(d) Title.
(1) Title to the property described in this paragraph (d) will vest in the Government. Vestiture will be immediately upon the date of this contract, for property acquired or produced before that date. Otherwise, vestiture will occur when the property is or should have been allocable or properly chargeable to this contract.
' (2) Property,' as used in this clause, includes all of the below-described items acquired or produced by the Contractor that are or should be allocable or properly chargeable to this contract under sound and generally accepted accounting principles and practices.
(i) Parts, materials, inventories, and work in process;
(ii) Special tooling and special test equipment to which the Government is to acquire title under any other clause of this contract;
(iii) Nondurable (i.e., noncapital) tools, jigs, dies, fixtures, molds, patterns, taps, gauges, test equipment, and other similar manufacturing aids, title to which would not be obtained as special tooling under subparagraph (ii) above;
and
(iv) Drawings and technical data, to the extent the Contractor or subcontractors are required to deliver them to the Government by other clauses of this contract.
(3) Although title to property is in the Government under this clause, other applicable clauses of this contract; e.g., the termination or special tooling clauses, will determine the handling and disposition of the property.
(4) The Contractor may sell any scrap resulting from production under this contract without requesting the Contracting Officer's approval, but the proceeds will be credited against the costs of performance.
(5) To acquire for its own use or dispose of property to which title is vested in the Government under this clause, the Contractor must obtain the Contracting Officer's advance approval of the action and the terms. The Contractor must
(i) exclude the allocable costs of the property from the costs of contract performance, and (ii) repay to the Government any amount of unliquidated progress payments allocable to the property. Repayment may be by cash or credit memorandum.
(6) When the Contractor completes all of the obligations under this contract, including liquidation of all progress payments, title will vest in the Contractor for all property (or the proceeds thereof) not-
(i) Delivered to, and accepted by, the Government under this contract; or
(ii) Incorporated in supplies delivered to, and accepted by, the Government under this contract and to which title is vested in the Government under this clause.
(7) The terms of this contract concerning liability for Government-furnished property will not apply to property to which the Government acquired title solely under this clause.
(e) Risk of loss. Before delivery to and acceptance by the Government, the Contractor must bear the risk of loss for property, the title to which vests in the Government under this clause, except to the extent the Government expressly assumes the risk. The Contractor must repay the Government an amount equal to the unliquidated progress payments that are based on costs allocable to property that is damaged, lost, stolen, or destroyed.
(f) Control of costs and property. The Contractor must maintain an accounting system and controls adequate for the proper administration of this clause.
(g) Reports and access to records. The Contractor must promptly furnish reports, certificates, financial statements, and other pertinent information reasonably requested by the Contracting Officer for the administration of this clause.
Also, the Contractor must give the Government reasonable opportunity to examine and verify the Contractor's books, records, and accounts.
(h) Special terms regarding default. If this contract is terminated under the contract default clause,
(1) The Contractor must, on demand, repay to the Government the amount of unliquidated progress payments and
(2) Title will vest in the Contractor, on full liquidation of progress payments, for all property for which the Government elects not to require delivery under the contract default clause. The Government will be liable for no payment except as provided by the contract default clause.
(i) Reservations of rights.
(1) No payment or vesting of title under this clause will
(i) excuse the Contractor from performance of obligations under this contract or
(ii) constitute a waiver of any of the rights or remedies of the parties under the contract.
(2) The Government's rights and remedies under this clause
(i) Will not be exclusive but rather will be in addition to any other rights and remedies provided by law or this contract and
(ii) Will not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor will such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.
(j) Finance payments to subcontractors. The amounts mentioned in (a)(1)(ii) above will be all financing payments to subcontractors or divisions, if the following conditions are met:
(1) The amounts included are limited to (i) the unliquidated remainder of progress payments made plus (ii) for small business concerns any unpaid subcontractor requests for progress payments that the Contractor has approved for current payment in the ordinary course of business.
(2) The subcontract or interdivisional order is expected to involve a minimum of approximately 6 months between the beginning of work and the first delivery, or, if the subcontractor is a small business concern, 4 months.
(3) If the financing payments are in the form of progress…