Bald River Falls Bridge Replacement and NFSR 35 Reconditioning

Closed Solicitation Posted

Solicitation number
12445222B0002
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Tellico Plains, Tennessee 37385, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation involves a bridge replacement and road reconditioning project on National Forest System roads in Monroe County, Tennessee. The USDA Forest Service seeks to replace the existing three-span Bald River Falls Bridge with a new two-span structure and recondition 0.8 miles of NFSR 35 to serve as a detour route. Contractors must complete the road work within 150 days and bridge replacement within 310 days, concluding all activities within 540 days. Proposals were due by September 1, 2022 and evaluated based on technical qualifications, past performance, and price.

This is a total small business set-aside, with a magnitude of construction between $5-10 million. The NAICS code is 237990 and PSC code is R499. Incumbent contractors include Adams Contracting, LLC and Stampede Ventures, INC, who submitted bids of $9,489,652.75 and $10,999,139.06 respectively in response to solicitation 12445222B0002. The work will take place in Tellico Plains, Tennessee and involve clearing, excavation, culvert replacement, guardrail installation, and bridge construction using pre-stressed concrete box beams supported by spread footings and a center pier. The contractor will also maintain the detour routes through the life of the project.

Notice text

5 versions

Update #5 · Latest ·

Bid Verification added to documents/attachments

Bid Abstract added to documents/attachments

Amendment 0002

The purpose of this amendment is:to incorporate attachment J10 - Geotech Exploration.

Amendment 0001

The purpose of this amendment is: a. Update Schedule of Items (SOI), b. Incorporate Request For Information (RFI's), c. Incorporate link for KMZ's instructions/File, d. Incorporate Buy American/Hazardous Materials doc

This contract involves road reconditioning activities on NFSR 35 in the project area. NFSR 35 is a 0.8 mile long single lane paved road that acts as a ‘cutoff’ between NFSR 210 and TN-165. In order for NFSR 35 to be utilized as a Detour Route during bridge construction, the contractor will be responsible for performing reconditioning activities to include clearing, excavation, milling of asphalt, sub-grade stabilization, culvert cleaning/replacement, fill slope armoring and paving. The road reconditioning activities will need to be completed prior to Tellico River Road being closed for bridge construction.

Scope- Bridge Replacement
The Bald River Falls Bridge project will replace the existing 3-span, 200 ft bridge with a new 2-span structure. The existing structure is a two lane, 20 ft wide bridge comprised of concrete abutments, steel girders, concrete deck and 2 concrete piers. The new structure will be 170 ft long two lane structure with sidewalk and observation deck. The structure will be founded on bedrock with shallow foundation spread footings. The abutments/wingwalls will include rock anchors for support. The superstructure will be pre-stressed concrete box beams. A single 3-column concrete pier will be located at center span. Additional work will include clearing, grubbing, bridge rail, guardrail, masonry and paving. Tellico River Road will be closed during construction. The awardee will be responsible for maintaining the detour route (Consisting of NFSRs 216, 217, and 35) through the life of the contract.

Scope- Ongoing Detour Maintenance (NFSR 216,217, 35)
Ongoing maintenance will only occur on the 3 designated detour roads; not the 3 alternate roads. Ongoing Detour Maintenance includes driving the detour route once a week and after storm events to ensure the safety of the road. It will include up to 4 road gradings (inclusive of the final grading) at the discretion of the CO, 2 mowings, cleaning of culverts as needed, removal of downed trees and snow plowing. Snow plowing will be ordered on an as needed basis and is not included in the 001-2 line item. Ongoing Road Maintenance is subject to the 800 series of specifications attached to the Forest Service Supplemental Specifications. It is expected that the Ongoing Road Maintenance will continue through the life of the closure of Tellico River Road. Once Tellico River Road is reopened to public traffic, the contractor will perform a final detour route grading. Grading instances 1-3 will not require compaction, however final grading will require roller compaction and proper moisture content.

2. PROJECT LOCATON
The bridge replacement is located east of Tellico Plains on National Forest System Road (NFSR) 210. From Tellico Plains, TN turn east on TN 165 (Cherohala Skyway) travel 4.5 miles to the junction of NFSR 210 (Tellico River Rd).Turn right onto Tellico River Road and proceed 5.7 miles to project location. Utilize vicinity maps, USGS Maps (included in solicitation), and kmz to locate project roads and work item locations.

Magnitude of Construction Project: In accordance with FAR 36.204 the magnitude of
this construction project is between $5,000,000 and $10,000,000.

Update #4 ·

Bid Abstract added to documents/attachments

Amendment 0002

The purpose of this amendment is:to incorporate attachment J10 - Geotech Exploration.

Amendment 0001

The purpose of this amendment is: a. Update Schedule of Items (SOI), b. Incorporate Request For Information (RFI's), c. Incorporate link for KMZ's instructions/File, d. Incorporate Buy American/Hazardous Materials doc

This contract involves road reconditioning activities on NFSR 35 in the project area. NFSR 35 is a 0.8 mile long single lane paved road that acts as a ‘cutoff’ between NFSR 210 and TN-165. In order for NFSR 35 to be utilized as a Detour Route during bridge construction, the contractor will be responsible for performing reconditioning activities to include clearing, excavation, milling of asphalt, sub-grade stabilization, culvert cleaning/replacement, fill slope armoring and paving. The road reconditioning activities will need to be completed prior to Tellico River Road being closed for bridge construction.

Scope- Bridge Replacement
The Bald River Falls Bridge project will replace the existing 3-span, 200 ft bridge with a new 2-span structure. The existing structure is a two lane, 20 ft wide bridge comprised of concrete abutments, steel girders, concrete deck and 2 concrete piers. The new structure will be 170 ft long two lane structure with sidewalk and observation deck. The structure will be founded on bedrock with shallow foundation spread footings. The abutments/wingwalls will include rock anchors for support. The superstructure will be pre-stressed concrete box beams. A single 3-column concrete pier will be located at center span. Additional work will include clearing, grubbing, bridge rail, guardrail, masonry and paving. Tellico River Road will be closed during construction. The awardee will be responsible for maintaining the detour route (Consisting of NFSRs 216, 217, and 35) through the life of the contract.

Scope- Ongoing Detour Maintenance (NFSR 216,217, 35)
Ongoing maintenance will only occur on the 3 designated detour roads; not the 3 alternate roads. Ongoing Detour Maintenance includes driving the detour route once a week and after storm events to ensure the safety of the road. It will include up to 4 road gradings (inclusive of the final grading) at the discretion of the CO, 2 mowings, cleaning of culverts as needed, removal of downed trees and snow plowing. Snow plowing will be ordered on an as needed basis and is not included in the 001-2 line item. Ongoing Road Maintenance is subject to the 800 series of specifications attached to the Forest Service Supplemental Specifications. It is expected that the Ongoing Road Maintenance will continue through the life of the closure of Tellico River Road. Once Tellico River Road is reopened to public traffic, the contractor will perform a final detour route grading. Grading instances 1-3 will not require compaction, however final grading will require roller compaction and proper moisture content.

2. PROJECT LOCATON
The bridge replacement is located east of Tellico Plains on National Forest System Road (NFSR) 210. From Tellico Plains, TN turn east on TN 165 (Cherohala Skyway) travel 4.5 miles to the junction of NFSR 210 (Tellico River Rd).Turn right onto Tellico River Road and proceed 5.7 miles to project location. Utilize vicinity maps, USGS Maps (included in solicitation), and kmz to locate project roads and work item locations.

Magnitude of Construction Project: In accordance with FAR 36.204 the magnitude of
this construction project is between $5,000,000 and $10,000,000.

Update #3 ·

Amendment 0002

The purpose of this amendment is:to incorporate attachment J10 - Geotech Exploration.

Amendment 0001

The purpose of this amendment is: a. Update Schedule of Items (SOI), b. Incorporate Request For Information (RFI's), c. Incorporate link for KMZ's instructions/File, d. Incorporate Buy American/Hazardous Materials doc

This contract involves road reconditioning activities on NFSR 35 in the project area. NFSR 35 is a 0.8 mile long single lane paved road that acts as a ‘cutoff’ between NFSR 210 and TN-165. In order for NFSR 35 to be utilized as a Detour Route during bridge construction, the contractor will be responsible for performing reconditioning activities to include clearing, excavation, milling of asphalt, sub-grade stabilization, culvert cleaning/replacement, fill slope armoring and paving. The road reconditioning activities will need to be completed prior to Tellico River Road being closed for bridge construction.

Scope- Bridge Replacement
The Bald River Falls Bridge project will replace the existing 3-span, 200 ft bridge with a new 2-span structure. The existing structure is a two lane, 20 ft wide bridge comprised of concrete abutments, steel girders, concrete deck and 2 concrete piers. The new structure will be 170 ft long two lane structure with sidewalk and observation deck. The structure will be founded on bedrock with shallow foundation spread footings. The abutments/wingwalls will include rock anchors for support. The superstructure will be pre-stressed concrete box beams. A single 3-column concrete pier will be located at center span. Additional work will include clearing, grubbing, bridge rail, guardrail, masonry and paving. Tellico River Road will be closed during construction. The awardee will be responsible for maintaining the detour route (Consisting of NFSRs 216, 217, and 35) through the life of the contract.

Scope- Ongoing Detour Maintenance (NFSR 216,217, 35)
Ongoing maintenance will only occur on the 3 designated detour roads; not the 3 alternate roads. Ongoing Detour Maintenance includes driving the detour route once a week and after storm events to ensure the safety of the road. It will include up to 4 road gradings (inclusive of the final grading) at the discretion of the CO, 2 mowings, cleaning of culverts as needed, removal of downed trees and snow plowing. Snow plowing will be ordered on an as needed basis and is not included in the 001-2 line item. Ongoing Road Maintenance is subject to the 800 series of specifications attached to the Forest Service Supplemental Specifications. It is expected that the Ongoing Road Maintenance will continue through the life of the closure of Tellico River Road. Once Tellico River Road is reopened to public traffic, the contractor will perform a final detour route grading. Grading instances 1-3 will not require compaction, however final grading will require roller compaction and proper moisture content.

2. PROJECT LOCATON
The bridge replacement is located east of Tellico Plains on National Forest System Road (NFSR) 210. From Tellico Plains, TN turn east on TN 165 (Cherohala Skyway) travel 4.5 miles to the junction of NFSR 210 (Tellico River Rd).Turn right onto Tellico River Road and proceed 5.7 miles to project location. Utilize vicinity maps, USGS Maps (included in solicitation), and kmz to locate project roads and work item locations.

Magnitude of Construction Project: In accordance with FAR 36.204 the magnitude of
this construction project is between $5,000,000 and $10,000,000.

Update #2 ·

Amendment 0001

The purpose of this amendment is: a. Update Schedule of Items (SOI), b. Incorporate Request For Information (RFI's), c. Incorporate link for KMZ's instructions/File, d. Incorporate Buy American/Hazardous Materials doc

This contract involves road reconditioning activities on NFSR 35 in the project area. NFSR 35 is a 0.8 mile long single lane paved road that acts as a ‘cutoff’ between NFSR 210 and TN-165. In order for NFSR 35 to be utilized as a Detour Route during bridge construction, the contractor will be responsible for performing reconditioning activities to include clearing, excavation, milling of asphalt, sub-grade stabilization, culvert cleaning/replacement, fill slope armoring and paving. The road reconditioning activities will need to be completed prior to Tellico River Road being closed for bridge construction.

Scope- Bridge Replacement
The Bald River Falls Bridge project will replace the existing 3-span, 200 ft bridge with a new 2-span structure. The existing structure is a two lane, 20 ft wide bridge comprised of concrete abutments, steel girders, concrete deck and 2 concrete piers. The new structure will be 170 ft long two lane structure with sidewalk and observation deck. The structure will be founded on bedrock with shallow foundation spread footings. The abutments/wingwalls will include rock anchors for support. The superstructure will be pre-stressed concrete box beams. A single 3-column concrete pier will be located at center span. Additional work will include clearing, grubbing, bridge rail, guardrail, masonry and paving. Tellico River Road will be closed during construction. The awardee will be responsible for maintaining the detour route (Consisting of NFSRs 216, 217, and 35) through the life of the contract.

Scope- Ongoing Detour Maintenance (NFSR 216,217, 35)
Ongoing maintenance will only occur on the 3 designated detour roads; not the 3 alternate roads. Ongoing Detour Maintenance includes driving the detour route once a week and after storm events to ensure the safety of the road. It will include up to 4 road gradings (inclusive of the final grading) at the discretion of the CO, 2 mowings, cleaning of culverts as needed, removal of downed trees and snow plowing. Snow plowing will be ordered on an as needed basis and is not included in the 001-2 line item. Ongoing Road Maintenance is subject to the 800 series of specifications attached to the Forest Service Supplemental Specifications. It is expected that the Ongoing Road Maintenance will continue through the life of the closure of Tellico River Road. Once Tellico River Road is reopened to public traffic, the contractor will perform a final detour route grading. Grading instances 1-3 will not require compaction, however final grading will require roller compaction and proper moisture content.

2. PROJECT LOCATON
The bridge replacement is located east of Tellico Plains on National Forest System Road (NFSR) 210. From Tellico Plains, TN turn east on TN 165 (Cherohala Skyway) travel 4.5 miles to the junction of NFSR 210 (Tellico River Rd).Turn right onto Tellico River Road and proceed 5.7 miles to project location. Utilize vicinity maps, USGS Maps (included in solicitation), and kmz to locate project roads and work item locations.

Magnitude of Construction Project: In accordance with FAR 36.204 the magnitude of
this construction project is between $5,000,000 and $10,000,000.

Update #1 ·

This contract involves road reconditioning activities on NFSR 35 in the project area. NFSR 35 is a 0.8 mile long single lane paved road that acts as a ‘cutoff’ between NFSR 210 and TN-165. In order for NFSR 35 to be utilized as a Detour Route during bridge construction, the contractor will be responsible for performing reconditioning activities to include clearing, excavation, milling of asphalt, sub-grade stabilization, culvert cleaning/replacement, fill slope armoring and paving. The road reconditioning activities will need to be completed prior to Tellico River Road being closed for bridge construction.

Scope- Bridge Replacement
The Bald River Falls Bridge project will replace the existing 3-span, 200 ft bridge with a new 2-span structure. The existing structure is a two lane, 20 ft wide bridge comprised of concrete abutments, steel girders, concrete deck and 2 concrete piers. The new structure will be 170 ft long two lane structure with sidewalk and observation deck. The structure will be founded on bedrock with shallow foundation spread footings. The abutments/wingwalls will include rock anchors for support. The superstructure will be pre-stressed concrete box beams. A single 3-column concrete pier will be located at center span. Additional work will include clearing, grubbing, bridge rail, guardrail, masonry and paving. Tellico River Road will be closed during construction. The awardee will be responsible for maintaining the detour route (Consisting of NFSRs 216, 217, and 35) through the life of the contract.

Scope- Ongoing Detour Maintenance (NFSR 216,217, 35)
Ongoing maintenance will only occur on the 3 designated detour roads; not the 3 alternate roads. Ongoing Detour Maintenance includes driving the detour route once a week and after storm events to ensure the safety of the road. It will include up to 4 road gradings (inclusive of the final grading) at the discretion of the CO, 2 mowings, cleaning of culverts as needed, removal of downed trees and snow plowing. Snow plowing will be ordered on an as needed basis and is not included in the 001-2 line item. Ongoing Road Maintenance is subject to the 800 series of specifications attached to the Forest Service Supplemental Specifications. It is expected that the Ongoing Road Maintenance will continue through the life of the closure of Tellico River Road. Once Tellico River Road is reopened to public traffic, the contractor will perform a final detour route grading. Grading instances 1-3 will not require compaction, however final grading will require roller compaction and proper moisture content.

2. PROJECT LOCATON
The bridge replacement is located east of Tellico Plains on National Forest System Road (NFSR) 210. From Tellico Plains, TN turn east on TN 165 (Cherohala Skyway) travel 4.5 miles to the junction of NFSR 210 (Tellico River Rd).Turn right onto Tellico River Road and proceed 5.7 miles to project location. Utilize vicinity maps, USGS Maps (included in solicitation), and kmz to locate project roads and work item locations.

Magnitude of Construction Project: In accordance with FAR 36.204 the magnitude of
this construction project is between $5,000,000 and $10,000,000.

Files

Show all 19

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Bald River Falls Bridge Replacement and NFSR 35 Reconditioning Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
UT NP ARCH 100(2) Bridges on Delicate Arch Road Moab, Utah 84532, United States · NAICS 237310 Federal Highway Administration No set-aside
Cisco Branch Ontonagon River Bridge Replacement Watersmeet, Michigan 49969, United States · NAICS 237310 Forest Service Total Small Business
Acadia National Park Maine, United States · NAICS 237310 Federal Highway Administration Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity