B454 Convert Hanger 4
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- FA302224R0009
- Agency
- Air Education and Training Command Air Force, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Z1EB Maintenance Of Maintenance Buildings
- Place of performance
- Columbus, Mississippi 39710, United States
- Points of contact
-
- Willie Common willie.common.1@us.af.mil (662) 434-7780
- Willie Common 14cons.pka.construction@us.af.mil (662) 434-7780
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of the Air Force, Air Education and Training Command is seeking offers for a construction contract to convert Hangar 4 (Building 454) at Columbus Air Force Base in Mississippi into a new Wash Rack facility. The contractor must perform a full renovation according to the Statement of Work, 100% Design, 100% Specifications, and all applicable Air Force, local, and national requirements. The government will use a Lowest Price Technically Acceptable (LPTA) source selection process, evaluating technical acceptability, past performance, and price. Key dates include a site visit on August 13, 2024, a deadline of August 16, 2024 for additional requests for information, and a proposal due date of September 5, 2024.
This is a total small business set-aside contract with an estimated value between $5,000,000 and $10,000,000. The period of performance is 458 calendar days from the notice to proceed. Contractors must complete mandatory Controlled Unclassified Information (CUI) training and sign an acknowledgment form to gain access to the solicitation documents. The place of performance is Columbus, Mississippi.
Notice text
7 versions
Update #7 · Latest ·
Amendment 7: The purpose of this amendment is to post clarification answers to the RFI's and attachments that are in the attachment section.
Amendment 6: The purpose of this amendment is to post answers to the RFI's that was submitted. Answers are in the attachement s/links section.
Amendment 5: The purpose of this modification is to extend the solicitation due date from August 26, 2024 at 12:00 pm to September 5, 2024 at 12:00 pm. The RFI question will be posted with answer within a couple of days. The amendment solicitation is in the attachment section.
Amendment 4: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 3: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 2: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 1: The purpose of this modification is to correct the proposal due date from 12:00 PM CST on Thursday, August 8, 2024 to 12:00 PM CST on Monday, August 26, 2024.
The Government is offering a site visit opportunity on Tuesday, August 13, 2024 at 9:00 AM CST. The site visit is encouraged but not mandatory. In order to attend the site visit, your team must contact the POC to inform them of your intent to attend NLT 1:00 PM CST on Monday, August 12, 2024. If you do not contact the POC by 1:00 PM CST on Monday, August 12, 2024, you will not be able to attend the site visit. All additional RFIs must be submitted NLT 5:00 PM CST on Friday, August 16, 2024. All proposals must be submitted NLT 12:00 PM CST on Monday, August 26, 2024 to the following emails 14cons.pka.construction@us.af.mil and willie.common.1@us.af.mil
IAW FAR 36.204(g) - The range of magnitude for this procurement is between $5,000,000.00 and $10,000,000.00.
Contractors/Offers must complete CUI Training Slides then sign and return the "MFR Contractor CUI Training Acknowledgment for Solicitations" to gain access to drawings and other associated CUI documentation. Send singed MFR to the POC and accesses to the locked documents in SAM.gov will be granted.
The subject requirement must provide all plant, labor, equipment, transportation, and tools required to complete a full renovation of B454 into the new Wash Rack. Perform all work according to this Statement of Work (SOW), the 100% Design, 100% Specifications, and all related AF requirements and other codes and references. Construction must be accomplished in accordance with applicable UFC’s, ETL’s, (UFC’s and ETL’s may be found on-line at www.wbdg.org.) local and national codes, Columbus AFB Installation Facility Standards (IFS) and all Appendices (Special Construction, Mechanical, and Electrical) and other guidance as modified by this SOW.
Update #6 ·
Amendment 6: The purpose of this amendment is to post answers to the RFI's that was submitted. Answers are in the attachement s/links section.
Amendment 5: The purpose of this modification is to extend the solicitation due date from August 26, 2024 at 12:00 pm to September 5, 2024 at 12:00 pm. The RFI question will be posted with answer within a couple of days. The amendment solicitation is in the attachment section.
Amendment 4: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 3: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 2: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 1: The purpose of this modification is to correct the proposal due date from 12:00 PM CST on Thursday, August 8, 2024 to 12:00 PM CST on Monday, August 26, 2024.
The Government is offering a site visit opportunity on Tuesday, August 13, 2024 at 9:00 AM CST. The site visit is encouraged but not mandatory. In order to attend the site visit, your team must contact the POC to inform them of your intent to attend NLT 1:00 PM CST on Monday, August 12, 2024. If you do not contact the POC by 1:00 PM CST on Monday, August 12, 2024, you will not be able to attend the site visit. All additional RFIs must be submitted NLT 5:00 PM CST on Friday, August 16, 2024. All proposals must be submitted NLT 12:00 PM CST on Monday, August 26, 2024 to the following emails 14cons.pka.construction@us.af.mil and willie.common.1@us.af.mil
IAW FAR 36.204(g) - The range of magnitude for this procurement is between $5,000,000.00 and $10,000,000.00.
Contractors/Offers must complete CUI Training Slides then sign and return the "MFR Contractor CUI Training Acknowledgment for Solicitations" to gain access to drawings and other associated CUI documentation. Send singed MFR to the POC and accesses to the locked documents in SAM.gov will be granted.
The subject requirement must provide all plant, labor, equipment, transportation, and tools required to complete a full renovation of B454 into the new Wash Rack. Perform all work according to this Statement of Work (SOW), the 100% Design, 100% Specifications, and all related AF requirements and other codes and references. Construction must be accomplished in accordance with applicable UFC’s, ETL’s, (UFC’s and ETL’s may be found on-line at www.wbdg.org.) local and national codes, Columbus AFB Installation Facility Standards (IFS) and all Appendices (Special Construction, Mechanical, and Electrical) and other guidance as modified by this SOW.
Update #5 ·
Amendment 5: The purpose of this modification is to extend the solicitation due date from August 26, 2024 at 12:00 pm to September 5, 2024 at 12:00 pm. The RFI question will be posted with answer within a couple of days. The amendment solicitation is in the attachment section.
Amendment 4: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 3: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 2: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 1: The purpose of this modification is to correct the proposal due date from 12:00 PM CST on Thursday, August 8, 2024 to 12:00 PM CST on Monday, August 26, 2024.
The Government is offering a site visit opportunity on Tuesday, August 13, 2024 at 9:00 AM CST. The site visit is encouraged but not mandatory. In order to attend the site visit, your team must contact the POC to inform them of your intent to attend NLT 1:00 PM CST on Monday, August 12, 2024. If you do not contact the POC by 1:00 PM CST on Monday, August 12, 2024, you will not be able to attend the site visit. All additional RFIs must be submitted NLT 5:00 PM CST on Friday, August 16, 2024. All proposals must be submitted NLT 12:00 PM CST on Monday, August 26, 2024 to the following emails 14cons.pka.construction@us.af.mil and willie.common.1@us.af.mil
IAW FAR 36.204(g) - The range of magnitude for this procurement is between $5,000,000.00 and $10,000,000.00.
Contractors/Offers must complete CUI Training Slides then sign and return the "MFR Contractor CUI Training Acknowledgment for Solicitations" to gain access to drawings and other associated CUI documentation. Send singed MFR to the POC and accesses to the locked documents in SAM.gov will be granted.
The subject requirement must provide all plant, labor, equipment, transportation, and tools required to complete a full renovation of B454 into the new Wash Rack. Perform all work according to this Statement of Work (SOW), the 100% Design, 100% Specifications, and all related AF requirements and other codes and references. Construction must be accomplished in accordance with applicable UFC’s, ETL’s, (UFC’s and ETL’s may be found on-line at www.wbdg.org.) local and national codes, Columbus AFB Installation Facility Standards (IFS) and all Appendices (Special Construction, Mechanical, and Electrical) and other guidance as modified by this SOW.
Update #4 ·
Amendment 4: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 3: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 2: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 1: The purpose of this modification is to correct the proposal due date from 12:00 PM CST on Thursday, August 8, 2024 to 12:00 PM CST on Monday, August 26, 2024.
The Government is offering a site visit opportunity on Tuesday, August 13, 2024 at 9:00 AM CST. The site visit is encouraged but not mandatory. In order to attend the site visit, your team must contact the POC to inform them of your intent to attend NLT 1:00 PM CST on Monday, August 12, 2024. If you do not contact the POC by 1:00 PM CST on Monday, August 12, 2024, you will not be able to attend the site visit. All additional RFIs must be submitted NLT 5:00 PM CST on Friday, August 16, 2024. All proposals must be submitted NLT 12:00 PM CST on Monday, August 26, 2024 to the following emails 14cons.pka.construction@us.af.mil and willie.common.1@us.af.mil
IAW FAR 36.204(g) - The range of magnitude for this procurement is between $5,000,000.00 and $10,000,000.00.
Contractors/Offers must complete CUI Training Slides then sign and return the "MFR Contractor CUI Training Acknowledgment for Solicitations" to gain access to drawings and other associated CUI documentation. Send singed MFR to the POC and accesses to the locked documents in SAM.gov will be granted.
The subject requirement must provide all plant, labor, equipment, transportation, and tools required to complete a full renovation of B454 into the new Wash Rack. Perform all work according to this Statement of Work (SOW), the 100% Design, 100% Specifications, and all related AF requirements and other codes and references. Construction must be accomplished in accordance with applicable UFC’s, ETL’s, (UFC’s and ETL’s may be found on-line at www.wbdg.org.) local and national codes, Columbus AFB Installation Facility Standards (IFS) and all Appendices (Special Construction, Mechanical, and Electrical) and other guidance as modified by this SOW.
Update #3 ·
Amendment 3: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 2: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 1: The purpose of this modification is to correct the proposal due date from 12:00 PM CST on Thursday, August 8, 2024 to 12:00 PM CST on Monday, August 26, 2024.
The Government is offering a site visit opportunity on Tuesday, August 13, 2024 at 9:00 AM CST. The site visit is encouraged but not mandatory. In order to attend the site visit, your team must contact the POC to inform them of your intent to attend NLT 1:00 PM CST on Monday, August 12, 2024. If you do not contact the POC by 1:00 PM CST on Monday, August 12, 2024, you will not be able to attend the site visit. All additional RFIs must be submitted NLT 5:00 PM CST on Friday, August 16, 2024. All proposals must be submitted NLT 12:00 PM CST on Monday, August 26, 2024 to the following emails 14cons.pka.construction@us.af.mil and willie.common.1@us.af.mil
IAW FAR 36.204(g) - The range of magnitude for this procurement is between $5,000,000.00 and $10,000,000.00.
Contractors/Offers must complete CUI Training Slides then sign and return the "MFR Contractor CUI Training Acknowledgment for Solicitations" to gain access to drawings and other associated CUI documentation. Send singed MFR to the POC and accesses to the locked documents in SAM.gov will be granted.
The subject requirement must provide all plant, labor, equipment, transportation, and tools required to complete a full renovation of B454 into the new Wash Rack. Perform all work according to this Statement of Work (SOW), the 100% Design, 100% Specifications, and all related AF requirements and other codes and references. Construction must be accomplished in accordance with applicable UFC’s, ETL’s, (UFC’s and ETL’s may be found on-line at www.wbdg.org.) local and national codes, Columbus AFB Installation Facility Standards (IFS) and all Appendices (Special Construction, Mechanical, and Electrical) and other guidance as modified by this SOW.
Update #2 ·
Amendment 2: The purpose of this modification is to revised Section M of the solicitation. The amendment solicitation is in the attachment section.
Amendment 1: The purpose of this modification is to correct the proposal due date from 12:00 PM CST on Thursday, August 8, 2024 to 12:00 PM CST on Monday, August 26, 2024.
The Government is offering a site visit opportunity on Tuesday, August 13, 2024 at 9:00 AM CST. The site visit is encouraged but not mandatory. In order to attend the site visit, your team must contact the POC to inform them of your intent to attend NLT 1:00 PM CST on Monday, August 12, 2024. If you do not contact the POC by 1:00 PM CST on Monday, August 12, 2024, you will not be able to attend the site visit. All additional RFIs must be submitted NLT 5:00 PM CST on Friday, August 16, 2024. All proposals must be submitted NLT 12:00 PM CST on Monday, August 26, 2024 to the following emails 14cons.pka.construction@us.af.mil and willie.common.1@us.af.mil
IAW FAR 36.204(g) - The range of magnitude for this procurement is between $5,000,000.00 and $10,000,000.00.
Contractors/Offers must complete CUI Training Slides then sign and return the "MFR Contractor CUI Training Acknowledgment for Solicitations" to gain access to drawings and other associated CUI documentation. Send singed MFR to the POC and accesses to the locked documents in SAM.gov will be granted.
The subject requirement must provide all plant, labor, equipment, transportation, and tools required to complete a full renovation of B454 into the new Wash Rack. Perform all work according to this Statement of Work (SOW), the 100% Design, 100% Specifications, and all related AF requirements and other codes and references. Construction must be accomplished in accordance with applicable UFC’s, ETL’s, (UFC’s and ETL’s may be found on-line at www.wbdg.org.) local and national codes, Columbus AFB Installation Facility Standards (IFS) and all Appendices (Special Construction, Mechanical, and Electrical) and other guidance as modified by this SOW.
Update #1 ·
Amendment 1: The purpose of this modification is to correct the proposal due date from 12:00 PM CST on Thursday, August 8, 2024 to 12:00 PM CST on Monday, August 26, 2024.
The Government is offering a site visit opportunity on Tuesday, August 13, 2024 at 9:00 AM CST. The site visit is encouraged but not mandatory. In order to attend the site visit, your team must contact the POC to inform them of your intent to attend NLT 1:00 PM CST on Monday, August 12, 2024. If you do not contact the POC by 1:00 PM CST on Monday, August 12, 2024, you will not be able to attend the site visit. All additional RFIs must be submitted NLT 5:00 PM CST on Friday, August 16, 2024. All proposals must be submitted NLT 12:00 PM CST on Monday, August 26, 2024 to the following emails 14cons.pka.construction@us.af.mil and willie.common.1@us.af.mil
IAW FAR 36.204(g) - The range of magnitude for this procurement is between $5,000,000.00 and $10,000,000.00.
Contractors/Offers must complete CUI Training Slides then sign and return the "MFR Contractor CUI Training Acknowledgment for Solicitations" to gain access to drawings and other associated CUI documentation. Send singed MFR to the POC and accesses to the locked documents in SAM.gov will be granted.
The subject requirement must provide all plant, labor, equipment, transportation, and tools required to complete a full renovation of B454 into the new Wash Rack. Perform all work according to this Statement of Work (SOW), the 100% Design, 100% Specifications, and all related AF requirements and other codes and references. Construction must be accomplished in accordance with applicable UFC’s, ETL’s, (UFC’s and ETL’s may be found on-line at www.wbdg.org.) local and national codes, Columbus AFB Installation Facility Standards (IFS) and all Appendices (Special Construction, Mechanical, and Electrical) and other guidance as modified by this SOW.
Attachments
| File | Type | Posted |
|---|---|---|
| Geotechnical Report.pdf | ||
| B454 RFIs Answers clarification.docx | DOCX document | |
| B454 RFIs with Answers.pdf | ||
| Solicitation Amendment FA302224R00090004 SF 30.pdf | ||
| Solicitation Amendment FA302224R00090003 SF 30.pdf | ||
| Solicitation Amendment FA302224R00090002 SF 30.pdf | ||
| Solicitation Amendment FA302224R00090001 SF 30.pdf | ||
| B454 - Statement of Work.pdf | ||
| Wage Determination DBA MS20240045.pdf | ||
| Appendix A - Cost Breakdown.xlsx | XLSX spreadsheet | |
| Solicitation - FA302224R0009.pdf | ||
| Contractor CUI Training Slides.pptx | PPTX presentation | |
| Form 66 -- Submittal Register -- B454.pdf | ||
| MFR Contractor CUI Training Acknowledgment for Solicitations.pdf |
Show all 14
Notice history
| Notice | Type | Posted |
|---|---|---|
| B454 Convert Hanger 4 | Award Notice | |
| B454 Convert Hanger 4 | Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity