4 SOPS B400 Mod 12 Conduit Install- AMENDMENT 4

Closed Solicitation Posted

Solicitation number
FA255024Q0022
Agency
Air Force Space Command Air Force, Department of Defense
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
238210 Electrical Contractors and Other Wiring Installation Contractors
PSC
5975 Electrical Hardware And Supplies
Place of performance
Colorado Springs, Colorado 80912, United States
Points of contact

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of the Air Force Space Command is seeking quotes for the installation of new plenum-rated conduit within Modification 12 South of Building 400 at Schriever Space Force Base in Colorado. The contractor will be required to install new conduit between the building's second-floor cable vault and server room, including necessary wall and floor penetrations. They will also install plenum-rated conduit for black and red cables from server racks to seat 52, with additional floor penetrations. The Government will award a firm-fixed-price contract to the lowest priced, technically acceptable offeror. Quotes are due by August 30, 2024 at 1:00 PM Mountain Time, and the Government reserves the right to award without discussions.

This solicitation is a total small business set-aside under NAICS code 238210, with a $19M size standard. The place of performance is at Schriever Space Force Base in Colorado Springs, Colorado. The Government has not identified any incumbent contractors for this requirement. The total value of the contract is unknown, but the focus is on the installation of the required conduit and cabling within a 90-day period of performance.

Notice text

6 versions

Update #6 · Latest ·

AMENDMENT 4

**New SOW with visual aid and New Dates**

1. Questions to new SOW due Monday, 19 August 2024 at 1300 Mountain Time.

Note- there are 2 new attachments: SOW  (Attach 2) and Visual Aid (Attach 3)

2. Quotes Due: Friday, 30 August 2024 at 1300 Mountain Time.

3. Be sure to add your Technical Approach and Lead Time/POP in your quote.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

AMENDMENT 3

Questions and answers have been uploaded. Quote due date reamins unchanged at Friday, 9 August 2024 at 1300 Mountain Time.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

AMENDMENT 2

**New Dates**

1. Answers to questions will be posted Friday, 2 August 2024

2. Quotes Due: Friday, 9 August 2024 at 1300 Mountain Time.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

AMENDMENT 1

**New Dates**

1. Answers to questions will be posted Wednesday, July 24, 2024

2. Quotes Due: Wednesday, July 31, 2024 at 1300 Mountain Time.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

*****************************************************************************************************************************

4 SOPS needs to have 2in diameter conduit installed within MOD 12 South, building 400.
 The contractor will install new plenum rated conduit in the MOD 12 South sub floor between the bldg. 400, second floor cable vault and the MOD 12 South server room (room 17). They will install new wall penetration (also referred to as a window) from the cable vault in the sub floor between MOD 12 South and the cable vault. This penetration can go along the MOD 12 South East perimeter wall. There is a potential to use an existing window within room 14. The contractor will install two new floor penetrations within the server room where the conduit exits the sub floor at racks 006 and 011. These penetrations should be big enough for the conduit (or flex tube) and additional server rack cabling outside the conduit. Approximately 4inx4in is needed for the cables outside the conduit. They will install plenum rated conduit for BLACK cables from racks 006 and 011 in the MOD 12 South server room to seat 52. The contractor will install plenum rated conduit for RED cables from racks 006 and 011 in the MOD 12 South server room to seat 52. They will install two new 3-inch floor penetrations at seat 52 for the BLACK and RED conduits. The contractor will install one new 3-inch floor penetration at seat 52 for cabling outside of the conduit (or flex tubing). 

Update #5 ·

AMENDMENT 4

**New SOW with visial aid and New Dates**

1. Questions to new SOW due Monday, 19 August 2024 at 1300 Mountain Time.

Note- there are 2 new attachments: SOW  (Attach 2) and Visial Aid (Attach 3)

2. Quotes Due: Friday, 30 August 2024 at 1300 Mountain Time.

3. Be sure to add your Technical Approach and Lead Time/POP in your quote.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

AMENDMENT 3

Questions and answers have been uploaded. Quote due date reamins unchanged at Friday, 9 August 2024 at 1300 Mountain Time.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

AMENDMENT 2

**New Dates**

1. Answers to questions will be posted Friday, 2 August 2024

2. Quotes Due: Friday, 9 August 2024 at 1300 Mountain Time.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

AMENDMENT 1

**New Dates**

1. Answers to questions will be posted Wednesday, July 24, 2024

2. Quotes Due: Wednesday, July 31, 2024 at 1300 Mountain Time.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

*****************************************************************************************************************************

4 SOPS needs to have 2in diameter conduit installed within MOD 12 South, building 400.
 The contractor will install new plenum rated conduit in the MOD 12 South sub floor between the bldg. 400, second floor cable vault and the MOD 12 South server room (room 17). They will install new wall penetration (also referred to as a window) from the cable vault in the sub floor between MOD 12 South and the cable vault. This penetration can go along the MOD 12 South East perimeter wall. There is a potential to use an existing window within room 14. The contractor will install two new floor penetrations within the server room where the conduit exits the sub floor at racks 006 and 011. These penetrations should be big enough for the conduit (or flex tube) and additional server rack cabling outside the conduit. Approximately 4inx4in is needed for the cables outside the conduit. They will install plenum rated conduit for BLACK cables from racks 006 and 011 in the MOD 12 South server room to seat 52. The contractor will install plenum rated conduit for RED cables from racks 006 and 011 in the MOD 12 South server room to seat 52. They will install two new 3-inch floor penetrations at seat 52 for the BLACK and RED conduits. The contractor will install one new 3-inch floor penetration at seat 52 for cabling outside of the conduit (or flex tubing). 

Update #4 ·

AMENDMENT 3

Questions and answers have been uploaded. Quote due date reamins unchanged at Friday, 9 August 2024 at 1300 Mountain Time.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

AMENDMENT 2

**New Dates**

1. Answers to questions will be posted Friday, 2 August 2024

2. Quotes Due: Friday, 9 August 2024 at 1300 Mountain Time.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

AMENDMENT 1

**New Dates**

1. Answers to questions will be posted Wednesday, July 24, 2024

2. Quotes Due: Wednesday, July 31, 2024 at 1300 Mountain Time.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

*****************************************************************************************************************************

4 SOPS needs to have 2in diameter conduit installed within MOD 12 South, building 400.
 The contractor will install new plenum rated conduit in the MOD 12 South sub floor between the bldg. 400, second floor cable vault and the MOD 12 South server room (room 17). They will install new wall penetration (also referred to as a window) from the cable vault in the sub floor between MOD 12 South and the cable vault. This penetration can go along the MOD 12 South East perimeter wall. There is a potential to use an existing window within room 14. The contractor will install two new floor penetrations within the server room where the conduit exits the sub floor at racks 006 and 011. These penetrations should be big enough for the conduit (or flex tube) and additional server rack cabling outside the conduit. Approximately 4inx4in is needed for the cables outside the conduit. They will install plenum rated conduit for BLACK cables from racks 006 and 011 in the MOD 12 South server room to seat 52. The contractor will install plenum rated conduit for RED cables from racks 006 and 011 in the MOD 12 South server room to seat 52. They will install two new 3-inch floor penetrations at seat 52 for the BLACK and RED conduits. The contractor will install one new 3-inch floor penetration at seat 52 for cabling outside of the conduit (or flex tubing). 

Update #3 ·

AMENDMENT 2

**New Dates**

1. Answers to questions will be posted Friday, 2 August 2024

2. Quotes Due: Friday, 9 August 2024 at 1300 Mountain Time.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

AMENDMENT 1

**New Dates**

1. Answers to questions will be posted Wednesday, July 24, 2024

2. Quotes Due: Wednesday, July 31, 2024 at 1300 Mountain Time.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

*****************************************************************************************************************************

4 SOPS needs to have 2in diameter conduit installed within MOD 12 South, building 400.
 The contractor will install new plenum rated conduit in the MOD 12 South sub floor between the bldg. 400, second floor cable vault and the MOD 12 South server room (room 17). They will install new wall penetration (also referred to as a window) from the cable vault in the sub floor between MOD 12 South and the cable vault. This penetration can go along the MOD 12 South East perimeter wall. There is a potential to use an existing window within room 14. The contractor will install two new floor penetrations within the server room where the conduit exits the sub floor at racks 006 and 011. These penetrations should be big enough for the conduit (or flex tube) and additional server rack cabling outside the conduit. Approximately 4inx4in is needed for the cables outside the conduit. They will install plenum rated conduit for BLACK cables from racks 006 and 011 in the MOD 12 South server room to seat 52. The contractor will install plenum rated conduit for RED cables from racks 006 and 011 in the MOD 12 South server room to seat 52. They will install two new 3-inch floor penetrations at seat 52 for the BLACK and RED conduits. The contractor will install one new 3-inch floor penetration at seat 52 for cabling outside of the conduit (or flex tubing). 

Update #2 ·

AMENDMENT 1

**New Dates**

1. Answers to questions will be posted Wednesday, July 24, 2024

2. Quotes Due: Wednesday, July 31, 2024 at 1300 Mountain Time.

Send Quotes to both TSgt Alejandro Castellanos alejandro.castellanos@spaceforce.mil and Melanie Briggs melanie.briggs.2@spaceforce.mil

*****************************************************************************************************************************

4 SOPS needs to have 2in diameter conduit installed within MOD 12 South, building 400.
 The contractor will install new plenum rated conduit in the MOD 12 South sub floor between the bldg. 400, second floor cable vault and the MOD 12 South server room (room 17). They will install new wall penetration (also referred to as a window) from the cable vault in the sub floor between MOD 12 South and the cable vault. This penetration can go along the MOD 12 South East perimeter wall. There is a potential to use an existing window within room 14. The contractor will install two new floor penetrations within the server room where the conduit exits the sub floor at racks 006 and 011. These penetrations should be big enough for the conduit (or flex tube) and additional server rack cabling outside the conduit. Approximately 4inx4in is needed for the cables outside the conduit. They will install plenum rated conduit for BLACK cables from racks 006 and 011 in the MOD 12 South server room to seat 52. The contractor will install plenum rated conduit for RED cables from racks 006 and 011 in the MOD 12 South server room to seat 52. They will install two new 3-inch floor penetrations at seat 52 for the BLACK and RED conduits. The contractor will install one new 3-inch floor penetration at seat 52 for cabling outside of the conduit (or flex tubing). 

Update #1 ·

4 SOPS needs to have 2in diameter conduit installed within MOD 12 South, building 400.
 The contractor will install new plenum rated conduit in the MOD 12 South sub floor between the bldg. 400, second floor cable vault and the MOD 12 South server room (room 17). They will install new wall penetration (also referred to as a window) from the cable vault in the sub floor between MOD 12 South and the cable vault. This penetration can go along the MOD 12 South East perimeter wall. There is a potential to use an existing window within room 14. The contractor will install two new floor penetrations within the server room where the conduit exits the sub floor at racks 006 and 011. These penetrations should be big enough for the conduit (or flex tube) and additional server rack cabling outside the conduit. Approximately 4inx4in is needed for the cables outside the conduit. They will install plenum rated conduit for BLACK cables from racks 006 and 011 in the MOD 12 South server room to seat 52. The contractor will install plenum rated conduit for RED cables from racks 006 and 011 in the MOD 12 South server room to seat 52. They will install two new 3-inch floor penetrations at seat 52 for the BLACK and RED conduits. The contractor will install one new 3-inch floor penetration at seat 52 for cabling outside of the conduit (or flex tubing). 

Attachments

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
4 SOPS B400 Mod 12 Conduit Install- AMENDMENT 4 This notice · Latest solicitation Solicitation
62 CYS SANS Training Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity