SOW - Conduit Install MOD 12 South_20JUN24.pdf

PDF 771 KB Posted

Attached to
4 SOPS B400 Mod 12 Conduit Install- AMENDMENT 4 Federal contract opportunity
Solicitation number
FA255024Q0022
Issued by
Department of the Air Force Space Command

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to install new plenum-rated conduit within the MOD 12 South area of Building 400 at Schriever Space Force Base.

The key requirements include:

  • Installing new conduit from the second floor cable vault to the MOD 12 South server room, including new wall and floor penetrations
  • Running plenum-rated conduit for black and red cables from server racks 006 and 011 to Seat 52
  • Installing two new 3-inch floor penetrations at Seat 52 for the black and red conduits, plus one additional 3-inch penetration for cabling outside the conduit
  • Adhering to all relevant installation standards, codes, and security requirements
  • Providing a one-year warranty on the work
  • Completing the work within a 90-day period of performance

The related federal contract opportunity, Solicitation Number FA255024Q0022, is being issued by the Department of the Air Force Space Command for this conduit installation project in the MOD 12 South area.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

UNITED STATES SPACE FORCE

SPACE DELTA 8

Statement of Work Mod 12s Conduit Install

Contents 1.0

1.0 Statement of Work

1.1 Mod 12 South Conduit installation

1.2 Install Standards

1.3 Period of Performance

1.4 Quality Assurance

1.4.1 Contracting Quality Control

1.4.2 Government Quality Assurance Plan

1.4.3 Post Award Conference/Periodic Progress Meetings:

1.4.4 Warranty

1.5 General Information

1.5.1 Recognized Holidays: [The contractor is not required to perform services on holidays.]

1.5.2 Hours of Operation

1.5.3 Place of Performance

1.5.4 Security Requirements

1.5.5 Contractor Travel

1.5.6 Data Rights

1.5.7 Subcontracting

Figure 1 …………………………………………………………………………………………………………………………………………………..6

Figure 2 …………………………………………………………………………………………………………………………………………………. 7

Figure 3 …………………………………………………………………………………………………………………………………………………. 8

1.0 Statement of Work

One mission system has custom cables without a fire rating, and per NFPA-70, it is required to have conduit installed in any plenum areas that will house the cables. Delta 8 needs to have 2in diameter conduit installed within MOD 12 South starting from a wall penetration (commonly referred to as a window) into the bldg 400, second floor cable chase and ending at two racks (FAB-T racks) within the MOD 12 South server room.

1.1 Mod 12 South Conduit installation

• The contractor will install new plenum rated conduit in the MOD 12 South sub floor between the bldg. 400, second floor cable vault and the MOD 12 South server room (room 17). See Figures 1 and 2.

• The contractor will install new wall penetration (also referred to as a window) from the cable vault in the sub floor between MOD 12 South and the cable vault. This penetration can go along the MOD 12 South East perimeter wall. See Figures 2 and 3.

• The contractor will install two new floor penetrations within the server room where the conduit exits the sub floor at racks 006 and 011. These penetrations should be big enough for the conduit (or flex tube) and additional server rack cabling outside the conduit. Approximately 4inx4in is needed for the cables outside the conduit. See Figures 1 and 3.

• The contractor will install plenum rated conduit for BLACK cables from racks 006 and 011 in the MOD 12 South server room to seat 52. See Figures 1 and 3.

• The contractor will install plenum rated conduit for RED cables from racks 006 and 011 in the MOD 12 South server room to seat 52. See Figures 1 and 3.

• The contractor will install two new 3-inch floor penetrations at seat 52 for the BLACK and RED conduits.

• The contractor will install one new 3-inch floor penetration at seat 52 for cabling outside of the conduit (or flex tubing).

1.2 Install Standards

• Contractor is responsible for all trash management and disposal.

• All installs will be installed according to all appropriate codes, IAW SSFB 17-201, NFPA-70, and

ICD-705

• Contractor is responsible for creating all wall and/or floor penetrations as necessary

• All wall and/or floor penetrations will be properly sealed and/or covered (i.e. sealants, grommets, koldloks)

• Contractor to supply all materials, equipment, and labor for a complete installation

1.3 Period of Performance

The period of performance shall be for 90 days to start at the time the contract has been officially awarded.

1.4 Quality Assurance

1.4.1 Contracting Quality Control

The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this SOW. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which the contractor verifies that their work complies with the requirement of the contract. The QCP is to be delivered within 30 days after contract award or with the contractors proposal if it is an evaluation factor, three copies of a comprehensive written QCP shall be submitted to the KO and COR within 5 working days when changes are made thereafter. After acceptance of the quality control plan the contractor shall receive the contracting officer’s acceptance in writing of any proposed change to their QC system.

1.4.2 Government Quality Assurance Plan

The government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied and the frequency of surveillance.

1.4.3 Post Award Conference/Periodic Progress Meetings:

The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The contracting officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government.

1.4.4 Warranty

The contractor shall honor a one year warranty period in which the contractor agrees to resolve any malfunctions caused due to errors during manufacturing of materials, poor quality construction/installation, or poor quality materials that did not meet Government requirements as defined in this statement of work.

1.5 General Information

1.5.1 Recognized Holidays: [The contractor is not required to perform services on holidays.]

New Year’s Day Juneteenth Veteran’s Day Martin Luther King Jr.’s Birthday Independence Day Thanksgiving Day President’s Day Labor Day Christmas Day Memorial Day Columbus Day

1.5.2 Hours of Operation

The contractor is responsible for conducting business, between the hours of [0700-1600] Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.

1.5.3 Place of Performance

The work to be performed under this contract will be performed at Schriever SFB; bldg. 400, MOD 12 South; Rooms 13, 14, 15, 16, and 17; and, in bldg. 400, second floor, cable vault as necessary.

1.5.4 Security Requirements

The Contractor personnel performing work under this contract must have access to Schriever SFB and the ability to get (“T-badges”) for Restricted Area (RA) access. If any personnel do not have the ability to have a T-badge, then the contractor must have at least one person with RA access who also has escort privileges.

1.5.5 Contractor Travel

The Contractor will be authorized travel expenses consistent with the substantive provisions of the Joint Travel Regulation (JTR) and the limitation of funds specified in this contract. All travel requires Government approval/authorization and notification to the COR. Overall travel costs shall not exceed 5% of the total bid.

1.5.6 Data Rights

The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.

1.5.7 Subcontracting

If the contractor chooses to subcontract the scheduled work, the prime contractor is solely responsible to ensure that the subcontractor has the necessary insurance, licenses, ability to provide the contracted services and shall adhere to all requirements stated herein.

Figure 1

Approximate area for floor penetrations where conduit exits sub floor

Seat 52

Figure 2

East perimeter wall /

Conduit start point

Figure 3 East perimeter wall

Rack 006, FAB-T 2 Rack 011, FAB-T 1

E

N

S

W Seat 52

1.0 Statement of Work
1.1 Mod 12 South Conduit installation
1.2 Install Standards
1.3 Period of Performance
1.4 Quality Assurance
1.4.1 Contracting Quality Control
1.4.2 Government Quality Assurance Plan
1.4.3 Post Award Conference/Periodic Progress Meetings:
1.4.4 Warranty
1.5 General Information
1.5.1 Recognized Holidays: [The contractor is not required to perform services on holidays.]
1.5.2 Hours of Operation
1.5.3 Place of Performance
1.5.4 Security Requirements
1.5.5 Contractor Travel
1.5.6 Data Rights
1.5.7 Subcontracting