About this opportunity

This solicitation requests offers to provide mechanical fuels reduction services on approximately 1,908 acres of the Mt. Hood National Forest in Oregon. Mandatory work includes machine piling of existing slash on 1,406 acres and mastication of live vegetation on 502 acres, with optional additions of piling 922 acres and masticating 1,473 acres. Equipment is required that can reach 10 feet high and climb 30% slopes to complete the work between July 2021 and December 2022. The solicitation is issued by the USDA Forest Service Pacific Northwest Region. Offers are due by June 7, 2021.

The opportunity is set aside for total small business concerns. The primary NAICS code is 561110, with PSC code D304. Work will be performed in Dufur, Oregon, with a period of performance from July 15, 2021 through December 31, 2022 for mandatory items and to be negotiated for optional items. Equipment must be capable of piling debris ranging from 1 inch to 18 inches by 20 feet and operating on slopes up to 30 percent. No operations are allowed from March 1 to July 15.

Notice text

3 versions

Update #3 · Latest ·

Amendments Issued

01: Add Geo-Referenced Maps (see attachments).

02: Add Pre-Quote Site Visit Attendee Roster, Q&A, and Unit Locations Map (see attachments).

Important Notice

This solicitation will be processed IAW the Simplified Acquisition Procedures (SAP) outlined in FAR 13.5 – Simplified Procedures for Certain Commercial Items. The contracting officer reasonably expects, based on the nature of these services sought, and on market research, that offers will only include commercial services.

Project Location (refer to Solicitation's maps)

Mt. Hood National Forest

Barlow Ranger District

Oregon, U.S.A.

Pre-Quote Site Visit

Date:               May 19, 2021

Time:               0900-1200

Location:         Barlow Ranger District Office, 780 NE Court St., Dufur, OR 97021

RSVP:             On or before May 17 at 1300 to Rick Lancaster, richard.lancaster@usda.gov, (541) 340-4285

Summary Scope of Work

Mandatory (Item 1) Machine Piling = 1,406 Acres

Mandatory (Item 2) Mastication = 502 Acres

Optional (Item 3) Machine Piling = 922 Acres

Optional (Item 4) Mastication = 1,473 Acres

Period of Performance

For the “Mandatory” items stated above, the estimated start date for the for this project is July 15, 2021. The start date for the Option items shall be negotiated between the USDA Forest Service and the company awarded the project. The overall completion date, including the Option items, is December 31, 2022.

Overall Project Objectives

  1. The slash layer to a depth of 2 to 6 inches and to eliminate vegetative competition of brush and small diameter saplings through grapple piling and mastication. Logs greater than 18 inches in diameter will be left in place.

This portion of the solicitation requires reduction of fuel loading on approximately 1,908 acres by piling existing and created slash (1,406 acres) and mastication of live vegetative materials (502 acres). Piling will occur with a “lift and pile” mechanism rather than a “push and pile” mechanism. Work shall be performed on slopes up to 30 percent.

Equipment Requirements

Equipment shall be furnished on a fully operational basis and in good operating condition, with a competent, qualified operator. The Contractor shall provide operators that have sufficient skill and experience to perform properly and efficiently the work assigned to them. The Contractor, upon written request from the Contracting Officer (CO), shall immediately remove any operator, who in the opinion of the Contracting Officer does not perform their work in a proper and skillful manner.

  1. Can be rubber tired or track-mounted, capable of piling logging slash and masticating live vegetation, and meet the following specifications:
  2. Capable of reaching 10 feet from center of machine.
  3. Ground pressure not to exceed 10 pounds per square inch (psi).
  4. Climbing ability up to 30 percent slope.
  5. Piling machine shall be equipped with a bucket and thumb or articulating brush grapple mechanism.
  6. Piling machine shall be capable of picking up woody debris from 1 inch by 3 feet to 18 inches by 20 feet.
  7. Equipment shall be free of fluid leaks and have hoses and hydraulics in good operating condition.
  8. The cab/canopy shall be firmly secured to the machine and free of broken glass.

Special Requirements

There are no operations from March 1 through July 15.

Water baring and/or other erosion control devices removed or altered for the convenience of the Contractor shall be rebuilt and inspected prior to the final closing of this contract.

Berms and/or guard rails removed or altered for the convenience of the Contractor shall be rebuilt and inspected prior to the final closing of this contract.

Equipment Operating Restrictions: Equipment shall operate on logging debris where it exists when possible. Should no slash exist, equipment may operate on other surface litter, duff, or approved skid trails if no additional soil is exposed by operations. The objective is to not add additional soil disturbance or compaction than already exists in the area.

All refueling, maintenance, and repairs will be done at landings or on skid trails.

Project work may be done at any time during the term of the contract, except under the following conditions: (a) Weather predictions indicate a hazardous fire condition warranting curtailment of operations, as specified elsewhere in this contract; and (b) When soil moisture conditions create excessive risk of damage to the soil.

Technical Point of Contact

Rick Lancaster, C: (541) 340-4285 O: 541-467-5130, richard.lancaster@usda.gov 

Update #2 ·

Amendments Issued

01: Add Geo-Referenced Maps (see attachments).

Important Notice

This solicitation will be processed IAW the Simplified Acquisition Procedures (SAP) outlined in FAR 13.5 – Simplified Procedures for Certain Commercial Items. The contracting officer reasonably expects, based on the nature of these services sought, and on market research, that offers will only include commercial services.

Project Location (refer to Solicitation's maps)

Mt. Hood National Forest

Barlow Ranger District

Oregon, U.S.A.

Pre-Quote Site Visit

Date:               May 19, 2021

Time:               0900-1200

Location:         Barlow Ranger District Office, 780 NE Court St., Dufur, OR 97021

RSVP:             On or before May 17 at 1300 to Rick Lancaster, richard.lancaster@usda.gov, (541) 340-4285

Summary Scope of Work

Mandatory (Item 1) Machine Piling = 1,406 Acres

Mandatory (Item 2) Mastication = 502 Acres

Optional (Item 3) Machine Piling = 922 Acres

Optional (Item 4) Mastication = 1,473 Acres

Period of Performance

For the “Mandatory” items stated above, the estimated start date for the for this project is July 15, 2021. The start date for the Option items shall be negotiated between the USDA Forest Service and the company awarded the project. The overall completion date, including the Option items, is December 31, 2022.

Overall Project Objectives

  1. The slash layer to a depth of 2 to 6 inches and to eliminate vegetative competition of brush and small diameter saplings through grapple piling and mastication. Logs greater than 18 inches in diameter will be left in place.

This portion of the solicitation requires reduction of fuel loading on approximately 1,908 acres by piling existing and created slash (1,406 acres) and mastication of live vegetative materials (502 acres). Piling will occur with a “lift and pile” mechanism rather than a “push and pile” mechanism. Work shall be performed on slopes up to 30 percent.

Equipment Requirements

Equipment shall be furnished on a fully operational basis and in good operating condition, with a competent, qualified operator. The Contractor shall provide operators that have sufficient skill and experience to perform properly and efficiently the work assigned to them. The Contractor, upon written request from the Contracting Officer (CO), shall immediately remove any operator, who in the opinion of the Contracting Officer does not perform their work in a proper and skillful manner.

  1. Can be rubber tired or track-mounted, capable of piling logging slash and masticating live vegetation, and meet the following specifications:
  2. Capable of reaching 10 feet from center of machine.
  3. Ground pressure not to exceed 10 pounds per square inch (psi).
  4. Climbing ability up to 30 percent slope.
  5. Piling machine shall be equipped with a bucket and thumb or articulating brush grapple mechanism.
  6. Piling machine shall be capable of picking up woody debris from 1 inch by 3 feet to 18 inches by 20 feet.
  7. Equipment shall be free of fluid leaks and have hoses and hydraulics in good operating condition.
  8. The cab/canopy shall be firmly secured to the machine and free of broken glass.

Special Requirements

There are no operations from March 1 through July 15.

Water baring and/or other erosion control devices removed or altered for the convenience of the Contractor shall be rebuilt and inspected prior to the final closing of this contract.

Berms and/or guard rails removed or altered for the convenience of the Contractor shall be rebuilt and inspected prior to the final closing of this contract.

Equipment Operating Restrictions: Equipment shall operate on logging debris where it exists when possible. Should no slash exist, equipment may operate on other surface litter, duff, or approved skid trails if no additional soil is exposed by operations. The objective is to not add additional soil disturbance or compaction than already exists in the area.

All refueling, maintenance, and repairs will be done at landings or on skid trails.

Project work may be done at any time during the term of the contract, except under the following conditions: (a) Weather predictions indicate a hazardous fire condition warranting curtailment of operations, as specified elsewhere in this contract; and (b) When soil moisture conditions create excessive risk of damage to the soil.

Technical Point of Contact

Rick Lancaster, C: (541) 340-4285 O: 541-467-5130, richard.lancaster@usda.gov 

Update #1 ·

Important Notice

This solicitation will be processed IAW the Simplified Acquisition Procedures (SAP) outlined in FAR 13.5 – Simplified Procedures for Certain Commercial Items. The contracting officer reasonably expects, based on the nature of these services sought, and on market research, that offers will only include commercial services.

Project Location (refer to Solicitation's maps)

Mt. Hood National Forest

Barlow Ranger District

Oregon, U.S.A.

Pre-Quote Site Visit

Date:               May 19, 2021

Time:               0900-1200

Location:         Barlow Ranger District Office, 780 NE Court St., Dufur, OR 97021

RSVP:             On or before May 17 at 1300 to Rick Lancaster, richard.lancaster@usda.gov, (541) 340-4285

Summary Scope of Work

Mandatory (Item 1) Machine Piling = 1,406 Acres

Mandatory (Item 2) Mastication = 502 Acres

Optional (Item 3) Machine Piling = 922 Acres

Optional (Item 4) Mastication = 1,473 Acres

Period of Performance

For the “Mandatory” items stated above, the estimated start date for the for this project is July 15, 2021. The start date for the Option items shall be negotiated between the USDA Forest Service and the company awarded the project. The overall completion date, including the Option items, is December 31, 2022.

Overall Project Objectives

  1. The slash layer to a depth of 2 to 6 inches and to eliminate vegetative competition of brush and small diameter saplings through grapple piling and mastication. Logs greater than 18 inches in diameter will be left in place.

This portion of the solicitation requires reduction of fuel loading on approximately 1,908 acres by piling existing and created slash (1,406 acres) and mastication of live vegetative materials (502 acres). Piling will occur with a “lift and pile” mechanism rather than a “push and pile” mechanism. Work shall be performed on slopes up to 30 percent.

Equipment Requirements

Equipment shall be furnished on a fully operational basis and in good operating condition, with a competent, qualified operator. The Contractor shall provide operators that have sufficient skill and experience to perform properly and efficiently the work assigned to them. The Contractor, upon written request from the Contracting Officer (CO), shall immediately remove any operator, who in the opinion of the Contracting Officer does not perform their work in a proper and skillful manner.

  1. Can be rubber tired or track-mounted, capable of piling logging slash and masticating live vegetation, and meet the following specifications:
  2. Capable of reaching 10 feet from center of machine.
  3. Ground pressure not to exceed 10 pounds per square inch (psi).
  4. Climbing ability up to 30 percent slope.
  5. Piling machine shall be equipped with a bucket and thumb or articulating brush grapple mechanism.
  6. Piling machine shall be capable of picking up woody debris from 1 inch by 3 feet to 18 inches by 20 feet.
  7. Equipment shall be free of fluid leaks and have hoses and hydraulics in good operating condition.
  8. The cab/canopy shall be firmly secured to the machine and free of broken glass.

Special Requirements

There are no operations from March 1 through July 15.

Water baring and/or other erosion control devices removed or altered for the convenience of the Contractor shall be rebuilt and inspected prior to the final closing of this contract.

Berms and/or guard rails removed or altered for the convenience of the Contractor shall be rebuilt and inspected prior to the final closing of this contract.

Equipment Operating Restrictions: Equipment shall operate on logging debris where it exists when possible. Should no slash exist, equipment may operate on other surface litter, duff, or approved skid trails if no additional soil is exposed by operations. The objective is to not add additional soil disturbance or compaction than already exists in the area.

All refueling, maintenance, and repairs will be done at landings or on skid trails.

Project work may be done at any time during the term of the contract, except under the following conditions: (a) Weather predictions indicate a hazardous fire condition warranting curtailment of operations, as specified elsewhere in this contract; and (b) When soil moisture conditions create excessive risk of damage to the soil.

Technical Point of Contact

Rick Lancaster, C: (541) 340-4285 O: 541-467-5130, richard.lancaster@usda.gov 

Files

File Type Posted
Amendment 02.pdf PDF
Amendment 01.pdf PDF
RFQ No 1240BD21Q0078.pdf PDF

Notice history

Notice Type Posted
2021 Mechanical Fuels Reduction, Mt. Hood National Forest, Barlow Ranger District Award Award Notice
This notice Latest solicitation Solicitation
2021 Mechanical Fuels Reduction, Mt. Hood National Forest, Barlow Ranger District Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Pacific Northwest (PNW) Stewardship BPA- Region 6 (OR & WA) - OPEN/CONTINUOUS Portland, Oregon 97204, United States · NAICS 115310 Forest Service No set-aside
West zone MT hood national forest parent BPA Oregon 97049, United States · NAICS 562991 Forest Service Total Small Business
Corral G-Z Stewardship IRSC, Region 6, Fremont-Winema National Forest, Bly Ranger District, Bly , Oregon Bly, Oregon 97622, United States · NAICS 113310 Forest Service Total Small Business
Intermountain Stewardship BPA Ogden, Utah 84401, United States · NAICS 115310 Forest Service No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors