WFLHD Construction Contract Administration_2.2.2023.pdf
PDF 117 KB Posted
- Solicitation number
- 69056722B000025
About this file
This document provides data on the Federal Highway Administration's past performance regarding the time required to definitize equitable adjustments for change orders under construction contracts. The table contains data on the number of change order proposals definitized by the FHWA from fiscal years 2020 to 2022. It shows that in FY 2020, 0 proposals were definitized within 0 to 30 days and 3 were definitized within 31 to 60 days. In FY 2021, 1 proposal was definitized within 0 to 30 days and 1 within 31 to 60 days. And in FY 2022, 1 proposal was definitized within 0 to 30 days and none within 31 to 60 days. Seven proposals in FY 2022 took between 181 to 365 days to definitize.
The related federal contract opportunity is a solicitation for the project AK NPS KATM 10(4), Rehabilitate Valley of 10,000 Smokes Road Phase IV issued by the Department of Transportation Federal Highway Administration. Bidders can find the invitation for bidders, plans, physical data, and construction contract administration document in the attachments.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Tab_AK NPS KATM 10(4).pdf | ||
| BidSum_AK NPS KATM 10(4).pdf | ||
| 5_12_23 QA.PDF | ||
| 5_11_23 QA.PDF | ||
| Amendment A004.pdf | ||
| 5_10_23 QA.PDF | ||
| Amendment A003.pdf | ||
| 5_09_23 QA.PDF | ||
| Amendment A002.pdf | ||
| 5_08_23 QA.PDF | ||
| 5_03_23 QA.PDF | ||
| Amendment A001.pdf | ||
| 4_26_23 QA.PDF | ||
| 4_25_23 QA.PDF | ||
| katm01004_existing-ground-surface.zip | ZIP file | |
| AK NPS KATM 10(4)_Katmai_Compiled SWPPP.pdf | ||
| katm01004_plans.pdf | ||
| IFB_69056722B000025_AK NPS KATM 10(4).pdf | ||
| Geo Rpt 06-96 Valley of 10000 Smokes.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WFLHD Construction Contract Administration
FAR 36.211 requires a description of the Federal Highway Administration’s (FHWA) procedures that apply to definitization of equitable adjustments for change orders under construction contracts. It also requires that FWHA furnish data on the agency’s past performance, for the prior 3 fiscal years, regarding the time required to definitize equitable adjustments for change orders under construction contracts.
Change orders as defined in FAR 2.101 are changes to the contract work pursuant to FAR 52.243-4, Changes.
There are no agency-specific additional policies and procedures that exist at this time.
The table below contains data regarding the definitization of equitable adjustments for change orders under construction contracts by fiscal year (FY).
Time to definitize after receipt of an adequate change order definitization proposal under construction contracts
Number of change order proposals definitized under construction contracts
FY 2020 FY 2021 FY 2022
0 to 30 days 0 1 1
31 to 60 days 3 1 0
61 to 90 days 0 0 0
91 to 180 days 0 5 1
181 to 365 days 0 0 7
366 or more days 4 2 0
After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance
0 0 0 https://www.acquisition.gov/far/part-52#FAR_52_243_4