4_26_23 QA.PDF

PDF 97 KB Posted

Attached to
AK NPS KATM 10(4), Rehabilitate Valley of 10, 000 Smokes Road Phase IV
Solicitation number
69056722B000025
Issued by

About this file

This document contains answers to technical questions regarding solicitation number 69056722B000025 from the Department of Transportation Federal Highway Administration. The solicitation is for an invitation for bid to rehabilitate Valley of 10,000 Smokes Road Phase IV in Alaska. The questions and answers indicate there is no cellular service in the project area or at Brooks Camp, the completion date will not be extended beyond the required date of October 2023, and the available space for contractor housing at Brooks Camp will be addressed in amendment A001.

View the file

Other files

File Type Posted
Bid Tab_AK NPS KATM 10(4).pdf PDF
BidSum_AK NPS KATM 10(4).pdf PDF
5_12_23 QA.PDF PDF
5_11_23 QA.PDF PDF
Amendment A004.pdf PDF
5_10_23 QA.PDF PDF
Amendment A003.pdf PDF
5_09_23 QA.PDF PDF
Amendment A002.pdf PDF
5_08_23 QA.PDF PDF
5_03_23 QA.PDF PDF
Amendment A001.pdf PDF
4_25_23 QA.PDF PDF
WFLHD Construction Contract Administration_2.2.2023.pdf PDF
katm01004_existing-ground-surface.zip ZIP file
AK NPS KATM 10(4)_Katmai_Compiled SWPPP.pdf PDF
katm01004_plans.pdf PDF
IFB_69056722B000025_AK NPS KATM 10(4).pdf PDF
Geo Rpt 06-96 Valley of 10000 Smokes.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No.AK NPS KATM 10(4) Project: Rehabilitate Valley of 10,000 Smokes

# General Technical Question Answer Date

1 X Is there cellular communication coverage at both the Brooks Camp and within the project limits?

Please check with your cellular phone service provider and submit bids according to the solicitation documents.

4/25/23

2 X

Would FHWA consider extending the Completion Date to October 2024? Barging heavy equipment to Brooks Camp is usually not feasible until July 1. Given that NTP is expected on July 7, 2023, most, if not all, of the 2023 construction season will be lost by the time submittals are approved.

The Government will not be extending the fixed completion date. Please bid according to the solicitation documents.

4/26/23

3 X How much space is available at the Brooks Camp for the Contractor designated housing area?

will be addressed under Amendment A001 4/26/23

Check General or Technical