This document is a Synopsis for an Architect-Engineer (A-E) Indefinite Delivery/Indefinite Quantity (IDIQ) contract for Waterfront Facilities Inspection and Assessment services in the OCONUS (outside continental U.S., Hawaii, and Alaska) region. The contract, solicitation number N39430-25-R-0015, will be awarded on an unrestricted basis with a NAICS code 541330 for Engineering Services. The contract will have a 60-month ordering period with a total fee not to exceed $15,000,000, and a guaranteed minimum of $10,000. The services include underwater and above-water inspections, engineering analysis, structural assessments, design services, geotechnical investigations, and environmental studies for DoD waterfront and ocean facilities worldwide.

Interested firms must submit a completed SF-330 Architect-Engineer Qualifications form by Monday, 06 October 2025 at 1700 PST to Naval Facilities Engineering and Expeditionary Warfare Center (NAVFAC EXWC). The evaluation will be based on seven criteria in descending order of importance: Specialized Experience, Professional Qualifications, Safety, Past Performance, Quality Control, Program Management and Capacity, and Volume of Work. Key requirements include having U.S. state-licensed engineers, registered professional engineer-divers, a comprehensive safety management system, and the ability to simultaneously manage up to three projects. The estimated contract start date is April 2026, and firms must maintain System of Award Management (SAM) registration throughout the solicitation process.

View the file

Other files

File Type Posted
N3943025R0015 -WFI OCONUS RFIs and Answers.docx DOCX document
N3943025R0015 -WFI OCONUS RFI 1.docx DOCX document
Attachment 2 - NAVFAC PPQ Form.doc DOC document
Attachment 1 - SF330.pdf PDF
Attachment 4 - QASP WFI Region OCONUS.docx DOCX document
Attachment 3 - WFI SAES Region OCONUS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AE Synopsis WFI OCONUS/CONUS

Revised AUG 2024

N39430-25-R-0015 INDEFINITE DELIVERY/INDEFINITE QUANTITY CONTRACT

FOR ARCHITECT-ENGINEER SERVICES FOR WATERFRONT FACILITIES

INSPECTION AND ASSESSMENT, OCONUS

Region OCONUS: Region is defined as worldwide (excluding continental U.S., Hawaii and Alaska)

Description: ALL INFORMATION NEEDED FOR INTERESTED PARTIES TO SUBMIT A

STANDARD FORM SF 330, ARCHITECT ENGINEER QUALIFICATIONS IS CONTAINED

HEREIN. THERE IS NO SEPARATE REQUEST FOR PROPOSALS (RFP) PACKAGE TO

DOWNLOAD.

This procurement will result in one (1) Indefinite Delivery/Indefinite Quantity (IDIQ) contract for multi-discipline Architect-Engineer (A-E) services for underwater and above water inspection, material condition assessment, engineering and design services in support of Sustainment, Restoration and Modernization (SRM) and Military Construction (MILCON) projects at DoD waterfront and ocean facilities at various locations worldwide, less areas defined in the associated solicitations for Waterfront Inspection A-E services within Regions 1, 2, 3, and

4. These services will be procured in accordance with 40 USC Chapter 11, Selection of Architects and Engineers, as implemented by FAR Subpart 36.6. The IDIQ contract will be for one (1) 60-month ordering period. The total fee for each contract term shall not exceed $15,000,000. The guaranteed minimum for the contract term is $10,000. The minimum quantity and order value for each task order issued shall not be less than the minimum quantity and order value of $10,000. The maximum quantity and order value for all orders issued shall not exceed the maximum quantity and order value of $15,000,000. Firm-fixed price task orders will be negotiated for each contract. Estimated start date is April 2026.

The proposed Waterfront Facilities Inspection and Assessment OCONUS contract is being solicited on an UNRESTRICTED basis as it will cover work worldwide. The Small Business size standard classification is North American Industrial Classification System (NAICS) Code 541330, Engineering Services. The Government seeks the most highly qualified firm to perform the required services, based on the demonstrated competence and qualifications, in accordance with the selection criteria.

The market research study ACQR59918-19-20-21-22-24-25 conducted by Naval Facilities Engineering and Expeditionary Warfare Center (NAVFAC EXWC) included an assessment of relevant qualifications and capabilities of potentially qualified firms. As a result of the market research analysis, a determination was made to solicit the Waterfront Facilities Inspection and Assessment OCONUS Region procurement on an unrestricted basis inviting full and open competition. The NAVFAC EXWC small business office and Small Business Administration (SBA) concurs with this decision

The type of A-E services expected to be performed under this contract are field investigations, underwater inspections; engineering analysis of waterfront and ocean facility structural, mechanical and electrical systems and component conditions in comparison to design requirements, previous inspection reports and/or existing drawings of the facilities; review of

Revised AUG 2024 construction plans and specifications of engineering features and related work associated with waterfront and ocean facility construction and repair; engineering calculations for structural analysis with or without previous design calculations; failure analysis and forensic engineering;

waterfront and ocean facility engineering feasibility studies; design of facility repairs;

preparation of Design/Build RFPs and Invitation For Bid contract plans and specifications;

environmental studies in support of permit applications to federal, state, and local regulatory agencies; preparation of required permit documentation; design of underwater instrument and cable arrays, associated power and data cable installation and termination, including fiber optic elements; design of underwater instrument support structures and assemblies; design of termination junction boxes and support structures; design of underwater cable installation using horizontal direction drilling technology, including the establishment of directional drilling monitoring and response criteria to minimize environmental effects of directional drilling;

documentation of findings and report preparation; cost estimation for waterfront and ocean facility rehabilitation; construction and installation schedules, development of maintenance action plans, underwater geotechnical and above water surveying.

The types of Task Order submittals may include, but not be limited to, inspection and condition assessment reports, engineering alternatives analyses and basis of repair/design reports, engineering calculations, engineering plans and specifications, construction cost estimates, and technical reviews.

Additional products and services may include construction contract drawings using computer-aided design and drafting (CADD), per the A/E/C CADD Standard, and specifications produced in SPECSINTACT with Standard Generalized Markup Language (SGML) using the Unified Facilities Guide Specifications (UFGS); Building Information Model (BIM) modeling, Waterfront UNIFORMAT II classifications standard; contract bid analyses; post construction award services (PCAS); Title II inspection services; database design, construction and population; procedures and guidelines reports; static and dynamic structural analyses using finite element computer modeling; two and three-dimensional structure modeling and rendering;

seismic vulnerability assessments, including use of finite element models and time history acceleration data for linear and/or nonlinear analyses of critical elements and development of retrofit schemes.

A waterfront facility is defined as any structure located on the waterfront, in connection with, or potentially in contact with, water or the marine environment. This would include inland structures that require underwater investigations. Waterfront facilities include, but are not limited to piers, wharves, bulkheads, quaywalls, offshore towers, dams, levees, water control structures, instrument support structures, dry docks, moorings, underwater cables, or any similar structure.

All waterfront facility assessments, including underwater inspections will be performed under direct control and supervision of registered professional engineer-divers. For each underwater assessment, one registered professional engineer-diver shall be appointed as the engineer-in-charge (EIC). That EIC shall dive at least 50% of the time, supervise the writing of the detailed inspection report, and write at least 50% of the detailed inspection reports.

The other engineers on-site may write the balance of the inspection report. The EIC shall ensure that all field inspection operations, including diving, are performed in accordance with reference

(c) of the Scope of Architect-Engineer Services (SAES), U.S. Army Corps of Engineers Safety

Revised AUG 2024 and Health Requirements EM 385-1-1 (November 2014). US citizenship for all on-site personnel, including the requirement to pass a Federal Law Enforcement Agency Background Screening Process for access to Government sites is required. This contract will set the labor fees and overhead rates for the A-E’s labor positions, and any subcontractor labor positions, for the 60- month period. All fees and rates will be negotiated at the time of issue for the most highly qualified firm. Multiple Task Orders may be awarded with similar delivery schedules requiring the firm to provide services with overlapping work/delivery dates.

Interested firms are advised to ensure System of Award Management (SAM) registration is current at time of offer submission and must remain valid through award. If SAM registration lapses during the solicitation and evaluation period, the offer will no longer be eligible for award.

For instructions on registering with SAM, see the SAM website at https://www.sam.gov/.

The awarded contract will be subject to specific provisions addressing the avoidance of organizational conflicts of interest. The prime firm for this contract will be required to perform throughout the contract term.

Interviews will be scheduled with firms slated as the most highly qualified. Firms slated for interviews may be asked to clarify information contained in the SF330 submittal. Elaborate presentations are not desired.

Security Requirements: Work performed will be at the SENSITIVE BUT UNCLASSIFIED level. The Government does not anticipate the need for a security clearance, however, if clearances are subsequently required the contractor shall comply with SECNAV M5510.30, SECNAV Instruction M-5239.2, and Department of Defense (DoD) 8570.01-M. The contractor shall establish and maintain an access list of those employees working on the contract.

An A-E firm will not be excluded from any other currently solicited region (Regions 2, 3, 4, and OCONUS) based upon an award in any other single region, but will have to prove capacity to complete six inspections at once while being in compliance with the EM-385 (i.e.

24 Engineer Divers, 4 for each individual inspection). As such, multiple regions may be awarded to a single firm who can meet this capacity requirement.

If an awardee has been awarded multiple regions, the three inspections per region requirement remains (6 total concurrent inspections). NAVFAC EXWC’s waterfront inspections will be the awardees priority. Task orders awarded outside of NAVFAC EXWC (Ordering Authorities from other agencies) will be of secondary importance.

SELECTION CRITERIA:

Firms responding to this synopsis will be evaluated to determine the most highly qualified firms to perform the required services in accordance with the published selection criteria. Failure to comply with instructions, or provide complete information may affect the firm’s evaluation or disqualify the firm from further consideration. Selection criteria are listed in descending order of importance. Criteria (7) is of least importance and will be used as a tie-breaker among technically equal firms. Specific selection criteria include:

Revised AUG 2024

1. Specialized Experience

2. Professional Qualifications

3. Safety

4. Past Performance

5. Quality Control

6. Program Management and Capacity and Location

7. Volume of Work

Criterion 1- Specialized Experience (SF330, Part I, Section F):

Firms will be evaluated on specialized experience in performance of services similar to those anticipated under this contract through evaluation of experience in:

1. Both topside and underwater Waterfront Inspections, including an example of performing a waterfront inspection in controlled areas with higher security requirements.

2. Structural condition assessments, including the use of destructive and non-destructive techniques

3. Static and dynamic structural analyses, including seismic vulnerability assessments and vessel/structure interaction analyses of waterfront facilities using computer aided tools

4. Geotechnical investigations related to pile and gravity based foundations

5. Testing and evaluation of structural material samples

6. Evaluation of both impressed current and sacrificial anode type cathodic protection systems on waterfront and submerged structures

7. Preparation of waterfront facilities repair cost estimates, including Form DD1391

8. Design and engineering services associated with underwater instrument and cable arrays, including the use of horizontal directional drilling

9. Applied research and technology to perform engineering services and provide innovative solutions with greater efficiency while maintaining quality. Firms will be evaluated on the strength of their proposed innovations.

10. Leverage experience in conducting Waterfront Inspections to determine the appropriate equipment (i.e. Dive Gear [SSA], Air Cylinders, Survey/Hydrographic Equipment, Boats, etc.) necessary to perform the work. Firms shall provide a list of this associated equipment, as well as indicting if they own or will be renting this equipment.

Submission requirements:

Provide a maximum of six (6) projects completed within the past three (3) years (no later than January 2022) immediately preceding the date of issuance of this notice that best demonstrate specialized experience of the proposed team in the areas outlined above. Sufficient information to determine the date of completion of the project must be included in the project description or the project will not be considered. If more than the maximum number of six (6) projects are submitted, the Government will only evaluate projects up to the maximum number authorized in the order submitted.

Revised AUG 2024

All projects provided in the SF330 must be completed by the actual office/branch/regional office/individual team member proposed to manage and perform work, either as the prime contractor or subcontractor under this contract. Projects not meeting this requirement will be excluded from consideration in the evaluation. To enable verification, firms should include the Unique Entity Identifier (UEI) number along with each firm name in the SF330 Part 1, Section F, block 25, “Firm Name” Include a contract number or project identification number in block 21.

Include an e-mail address and phone number for the point of contact in block 23(c). In block 24, include in the project description the contract period of performance, award contract value, current contract value, and a summary of the work performed that demonstrates relevance to specialized experience as outlined above. For projects performed as a subcontractor or a joint venture involving different members, specifically indicate the value of the work performed as a subcontractor or by those firms proposed for this contract, and identify the specific roles and responsibilities performed as a subcontractor or by those firms on the project rather than the work performed on the project as a whole. If the project description does not clearly delineate the work performed by the entity/entities offering/teaming on this contract, the project could be eliminated from consideration.

NOTE: If the firm is a joint venture, projects performed by the joint venture should be submitted;

however, if there are no projects performed by the joint venture, projects must be submitted for each joint venture member to depict that particular experience pertinent to this solicitation, not to exceed a total of three (3) projects for each joint venture member. Firms failing to provide projects from all joint venture members will be considered to have not met the requirements of the criterion.

Projects shall be submitted on the SF-330 at Part I, Section F and shall be completed projects (within the past three (3) years [no later than January 2022]). Projects not completed will be excluded from evaluation consideration. For submittal purposes, a task order on an IDIQ contract is considered a project, as is a stand-alone contract award. Do not submit an IDIQ contract as an example project. Instead, list relevant task orders or stand-alone contract awards that fit within the definition above. The Government will not evaluate information provided for an IDIQ contract. Examples of project work submitted that do not conform to this requirement will not be evaluated.

All information for Criterion 1 should be submitted in the SF330, Part I, Section F. The Government WILL NOT consider information submitted in addition to Part 1, Section F in evaluation of Criterion 1.

Criterion 2- Professional Qualifications (SF330, Part I, Sections E & G):

Firms will be evaluated on professional qualifications, competence, and experience of the proposed key personnel in providing services to accomplish the tasks required under this contract, including participation in example projects as outlined in the SF330, Part 1, Section G.

Key personnel are individuals who will have major contract or project management responsibilities and/or will provide unusual or unique expertise. Specific disciplines and licenses that must be included in key personnel are:

Revised AUG 2024

Project Manager: U.S. state licensed engineer with one of the following engineering disciplines—ocean, structural, civil, mechanical, electrical or geotechnical.

Senior Engineer: U.S. state licensed engineer with one of the following engineering disciplines—ocean, structural, civil, mechanical, electrical or geotechnical.

Senior Engineer Diver: U.S. state licensed engineer with one of the following engineering disciplines—ocean, structural, civil, mechanical, electrical or geotechnical. Certificate for diver training as required within the current Contract Diving Operations section of the U.S. Army Corps of Engineers EM385-1-1 manual.

Qualifications for all diving personnel proposed for this contract shall include, but not be limited to, training certifications and medical certifications as required within the current Contract Diving Operations section of the U.S. Army Corps of Engineers EM385-1-1 manual.

Joint Ventures shall be Mentor- Protégé agreements. For the proposed dive team, it shall identify which members belong to the small business mentee and large business mentor. Firms with more members of the dive team consisting of small business mentees may be considered more favorably.

Firms that provide letters of commitment for their key personnel may be considered more favorably.

Submission Requirements:

SF330, Part I, Section E. Provide resumes for all proposed key personnel that illustrate experience in the work proposed under this contract. Resumes are limited to one (1) page and should indicate: professional registration, certification, licensure and/or accreditation in appropriate disciplines; cite recent within the past three (3) years’ (from the date of issuance of this Synopsis/Solicitation) project-specific experience in work relevant to the services required under this contract; current level of diver certification and able to accomplish such work in a safe and efficient manner; and indicate proposed role in this contract. Also, indicate in this section (Section E) the participation of key personnel in example projects noted in the SF330, Part 1, Section G.

All information for Criterion 2 should be submitted in the SF330, Part I, Sections E & G.

The Government WILL NOT consider information submitted in addition to Part 1, Sections E & G in evaluation of Criterion 2.

Criterion 3- Safety (SF330, Part I, Section H):

The Government is seeking to determine that the firm has consistently demonstrated a commitment to safety and that the firm plans to properly manage and implement safety

Revised AUG 2024 procedures for itself and its subcontractors. The evaluation will collectively consider the DART rate, TCR, Technical Approach to Safety, and other sources of information available to the Government as part of such collective evaluation. The board will evaluate the DART rates and TCR to determine if the firm has demonstrated a history of safe work practices taking into account any negative trends and extenuating circumstances that impact the rating.

1. DART Rate: The board will evaluate trends over the last five years, as defined below, considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the firm to provide a detailed explanation that includes any corrective actions taken for improvement.

a. Missing data without an explanation is considered a deficiency.

b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or Very Low Risk (VLR) would indicate a strength.

c. An increasing DART rate trend could be considered a weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.

d. This chart correlates the DART rate to the level of risk:

Risk DART Rate Very Low Risk Less Than 1.0 Low Risk From 1.0 to 1.99 Moderate Risk From 2.0 to 2.99 High Risk From 3.0 to 4.0 Extremely High Risk Greater than 4.0

2. TCR Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the firm to provide a detailed explanation that includes any corrective actions taken for improvement.

a. Missing data without an explanation is considered a deficiency.

b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or Very Low Risk (VLR) would indicate a strength.

c. An increasing TCR rate trend could be considered a weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.

d. This chart correlates the TCR rate to the level of risk:

Risk TCR Rate Very Low Risk Less Than 2.49 Low Risk From 2.5 to 3.49

Revised AUG 2024

Moderate Risk From 3.5 to 4.49 High Risk From 4.5 to 5.99 Extremely High Risk Greater than 6.0

3. The Technical Approach to Safety Narrative. To determine the degree to which the firm:

a. Describes a viable SMS that addresses elements; such as Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.

b. Describes a methodical process of evaluating subcontractor’s safety performance in their selection process.

c. Describes a logical management plan to hold themselves and their subcontractors accountable for adhering to the safety requirements of the contract.

d. The Technical Approach to Safety narrative shall be limited to two (2) single-sided pages or one (1) double-sided page. Information on pages beyond this will not be considered.

4. The Government reserves the right to review other available sources (public/Government internal) of information. These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.

Submission Requirements:

The firm shall submit the following information: The Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate; and Total Case Rate (TCR) for the specified five (5) Calendar Years (CY), as well as a safety narrative, as described further below. For a partnership or joint venture, the firm shall submit separate DART rates and TCR for the specified five (5) CY for each contractor who is part of the partnership/joint venture; however, only one safety narrative is required. Any fatalities experienced within this 5-year timeframe must be explained in detail, to include root cause and corrective actions. Firms who fail to provide an explanation for a fatality will be considered “Not Met” for this Criterion.

NOTE: DART and TCR shall not be submitted for subcontractors

1. DART Rate: Submit five (5) previous complete calendar years’ [CY2024, CY2023, CY2022, CY2021, and CY2020] worth of data (not an overall average). If the firm has no DART rate, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required that includes any corrective actions taken for improvement.

a. DART cases include injuries or illnesses resulting in death, days away from work, and/or restricted work or transfer to another job days beyond the day of injury/illness.

Revised AUG 2024

b. Calculation of DART rate: Multiply the total number of DART cases by 200,000, and then divide by the number of employee labor hours worked.

DART RATE =

Number of DART Incidents x 200,000

Total Number of Employee Labor Hours Worked

2. TCR Rate: Submit five (5) previous complete calendar years’ [CY2024, 2023, 2022, 2021, and 2020] worth of data (not an overall average). If the firm has no TCR rate, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required that includes any corrective actions taken for improvement.

a. TCR cases include injuries or illnesses resulting in death, days away from work, restricted work or transfer to another job days beyond the day of injury/illness, medical treatment beyond first aid, or loss of consciousness.

b. Calculation of TCR rate: Multiply the total number of TCR incidents by 200,000, and then divide by the number of employee labor hours worked.

TCR RATE =

Number of TCR Incidents x 200,000

Total Number of Employee Labor Hours Worked

3. Technical Approach to Safety: Submit a narrative that addresses the following:

a. Describe the firm’s approach to implementing and executing a Safety Management System (SMS) including Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.

b. Describe the evaluation process used to select potential subcontractors.

c. Describe the processes of how the firm will oversee safety compliance of subcontractors at all levels throughout performance of the contract (to include the firm’s own in-house workforce).

d. The Technical Approach to Safety narrative shall be limited to two (2) single-sided pages or one (1) double-sided page.

4. The Government reserves the right to review other available sources (public/Government internal) of information. These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.

All information for Criterion 3 should be submitted in the SF330, Part I, Section H. The Government WILL NOT consider information submitted in addition to Part 1, Section H in evaluation of Criterion 3.

Revised AUG 2024

Criterion 4- Past Performance (SF330, Part I, Section H):

Firms will be evaluated on past performance with Government agencies and private industry in terms of work quality, compliance with schedules, cost control, and stakeholder/customer satisfaction. Evaluating past performance and experience will include information provided in Past Performance Questionnaires (PPQs) or CPARS for Criterion 1 projects and may include customer inquiries, Government databases, and other information available to the Government including contacts with points of contact in other criteria. NOTE: Past performance information for projects listed under Criterion 1 will be given greater weight.

Submission Requirements:

SUBMIT A COMPLETED CPARS EVALUATION FOR EACH PROJECT UNDER

CRITERION 1. IF A COMPLETED CPARS EVALUATION IS NOT AVAILABLE, the Past Performance Questionnaire (PPQ) (Attachment (A)) included in this notice is provided for the firm or its team members to submit to the client for each project included under Criterion 1, Specialized Experience. DO NOT SUBMIT A PPQ WHEN A COMPLETED CPARS IS

AVAILABLE.

IF A CPARS EVALUATION IS NOT AVAILABLE, ensure correct phone numbers and email addresses are provided for the client point of contact on the PPQ. Completed PPQs should be submitted with your SF330. If the firm is unable to obtain a completed PPQ from a client for a project(s) before the response date set forth in this notice, firms should complete and submit with their responses the first page of the PPQ (Attachment (A)), which will provide contract and client information for the respective project(s). Firms may submit a PPQ previously submitted under a different Notice/RFP (legible copies are acceptable) as long as it is on the same form as posted with this Synopsis. These may be from the projects submitted as part of Criterion 1. IF A PPQ IS NOT AVAIABLE, firms may provide a PPQ for an equivalent project. Firms should follow up with clients/references to ensure timely submittal of questionnaires. If requested by the client, questionnaires may be submitted directly to the Government's point of contact, Naval Facilities Engineering and Expeditionary Warfare Center (NACFAC EXWC), Code CON74, Attn: Jadon Honour via email at jadon.g.honour.civ@us.navy..mil, prior to the response date. Firms shall not incorporate by reference into their response PPQs or CPARS previously submitted in response to other A-E services procurements. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.

Firms may provide any information on problems encountered and the corrective actions taken on projects submitted under Criterion 1 Specialized Experience. Firms may also address any other adverse past performance issues. Information shall not exceed two double-sided pages (or four single-sided pages) in total.

Awards, letters of commendation, certificates of appreciation, etc. shall not be submitted and will not be considered in the evaluation.

All information for Criterion 4 should be submitted in the SF330, Part I, Section H. The

Revised AUG 2024 in evaluation of Criterion 4.

Criterion 5- Quality Control Program (SF330, Part I, Section H):

Firms will be evaluated on the strength of the quality control program proposed by the firm to ensure quality products and services under this contract, and means of ensuring quality services from their external Subject Matter Experts (SMEs)/subcontractors. The firm’s proposal shall be evaluated in this section for clarity, simplicity and accuracy.

Submission Requirements:

Describe the quality control program that will be utilized for all deliverables of this contract and the management approach for quality control processes and procedures. The description shall:

1. Explain the quality control program including an example of how the plan has worked for one of the projects submitted as part of SF330, Section F or how the plan will work if it has not been used previously.

2. Provide a quality control process chart showing the inter-relationship of the management and team components.

3. Describe specific quality control processes and procedures proposed for this contract A narrative of the firm's quality control methods outlining specific personnel (including their discipline/specialty) and procedures for above- water field inspections and diving operations, technical report preparation, structural assessments, analysis and design services is required. Of special interest are the QC processes in place that minimize the Governments effort to QA the firm's work product for errors, omissions, and quality.

4. Identify the quality control manager and any other key personnel responsible for the quality control program and a description of their roles and responsibilities.

a. Firms who provide a more experienced key personnel to be the quality control manager may be rated more favorably.

5. Describe how the firm’s quality control program extends to management of subcontractors.

6. Describe how the firm will use innovative solutions to provide a high quality control process at a cost effective rate. Firms will be evaluated on the strength of their proposed innovations while still being cost efficient.

All information for Criterion 5 should be submitted in the SF330, Part I, Section H. The in evaluation of Criterion 5.

Criterion 6- Program Management and Capacity and Location (SF330, Part I, Section H):

Revised AUG 2024

Firms will be evaluated on the firm’s ability to plan for and manage work under the contract, the capacity to accomplish up to three (3) separate projects or task orders concurrently in the required timeframe for Region OCONUS, and demonstrated knowledge of the primary geographic areas in which projects could be located. Capacity includes maintaining report submission schedule while simultaneously executing field operations.

Submission Requirements:

1. Provide an organizational chart for the team and discuss the management plan for this contract and personnel roles in the organization. Describe the ability of the firm to manage, coordinate and work effectively with team members (i.e. subcontractors), both internal staff and external SMEs/subcontractors. Discuss the history of working relationships with team members, including joint venture members where applicable.

2. Describe the firm’s present workload and the availability of the project team (including external SMEs/subcontractors) for the specified contract performance period. Describe the workload/availability of the key personnel during the anticipated contract performance period and the ability of the firm to provide qualified backup staffing for key personnel to ensure continuity of services. Detail how key personnel will support the contract, quantifying the time they will dedicate. In addition, discuss specifically how surge workload would be managed to complete three (3) projects at once (one large project and two small projects) within Region OCONUS. A large project would be any project consisting of 30 facilities or more and a small project is less than 10 facilities. General statements of availability/capacity may be considered less favorably.

3. Provide a narrative describing the team’s knowledge of the primary geographic areas in which projects could be located in Region OCONUS. Describe any considerations for higher security waterfront areas.

4. Provide the location of office(s) that will be performing and/or supporting the work, including main offices, branch offices and team member offices.

All information for Criterion 6 should be submitted in the SF330, Part I, Section H. The in evaluation of Criterion 6.

Criterion 7—Volume of Work (SF330, Part 1, Section H)

Firms will be evaluated in accordance with DOD Federal Acquisition Regulation Supplement (DFARS) Procedures, Guidance and Information (PGI) 236.602-1, from data extracted from the Federal Procurement Data System (FPDS). Firms will be evaluated in terms of work previously awarded to the firm by DOD within the past twelve months immediately preceding the date of issuance of this notice (XX Month 2025) with the objective of effecting an equitable distribution of contracts among qualified A-E firms including small, disadvantaged business firms, and firms that have not had prior DOD A-E contracts.

Revised AUG 2024

This Criterion 7 will only be used as a tie-breaker among technically equal firms.

Submission Requirements:

Firms do not submit data for this factor.

Revised AUG 2024

SF-330 SUBMISSION REQUIREMENTS:

Architect-Engineer firms desiring to be considered for this contract must submit a completed SF- 330 package. The SF-330 shall be typed, one sided, at least 11 point Times New Roman or larger. Part I shall not exceed 50 single-sided 8.5 by 11 inch pages (the page limit does not include ISRs, certificates, PPQs, licenses, cover sheets, dividers, or other requested documentation (e.g., joint venture agreement, proof of A-E firm registration) provided that these do not contain any substantive information submitted in response to the synopsis or intended to demonstrate the qualifications of the firm). Part I pages shall be numbered sequentially. The organizational chart may be one-page single sided 11 by 17 foldout, using 11-point font or larger (font limitations do not apply to graphics, captions or tables). Please include your Unique Entity Identifier (UEI) and CAGE numbers in Block 30 of the SF-330.

**In accordance with the FAR 36.601-4(b) contracts for architect-engineer services may only be awarded to firms permitted by law to practice the professions of architecture or engineering.

Firms must submit proof that they are permitted by law as required by FAR 36.601-4(b). If a firm is in a jurisdiction that requires A-E firm registration, the firm must provide proof of registration. If a firm is in a jurisdiction that does not require A-E firm registration, the firm must provide proof eligibility to practice (e.g., a summary explaining eligibility under the laws of that jurisdiction). Failure to submit the required proof could result in a firm’s elimination from consideration.

**Firms who are offering as a joint venture should include with their submission a copy of the joint venture agreement. Failure to include the joint venture agreement may result in the firm’s elimination from further evaluation.

Architect-engineer firms that meet the requirements described in this announcement are invited to submit one (1) electronic copy of the SF-330 to Naval Facilities Engineering and Expeditionary Warfare Center (NAVFAC EXWC), Code CON74, Attn: Jadon Honour, Naval Base Ventura County, 1100 23rd Ave., Bldg. 1100, Port Hueneme, CA 93043-4201. Outside corner of mailing envelope shall be labeled as follows: N39430-25-R-0015. Firms responding to this announcement by Monday 06 October 2025 no later than 1700 PST will be considered.

THIS IS NOT A REQUEST FOR PROPOSAL.

Late responses will be handled in accordance with FAR 52.215-1. The points of contact are either Jadon Honour, Contract Specialist, at 805-982-4807, jadon.g.honour.civ@us.navy.mil or Antonio M. Arias, Contracting Officer, 805-396-9267, antonio.m.arias.civ@us.navy.mil.

If an SF 254/SF 255 is submitted for this solicitation, it will not be reviewed or considered. As required above, provide verifiable evidence that your firm is permitted by law to practice the professions of architecture or engineering (e.g., state registration number).

Facsimile SF-330's submissions are not authorized.

Inquiries concerning this procurement should include solicitation number and title and be forwarded via email to jadon.g.honour.civ@us.navy.mil.